Spindle2.ppt

download Spindle2.ppt

of 9

Transcript of Spindle2.ppt

  • 7/29/2019 Spindle2.ppt

    1/9

    Six Sigma Project Case Study:

    Improved Productivity of Fans

    through Reduction of

    Defects/Defectives at Spindlemanufacturing

  • 7/29/2019 Spindle2.ppt

    2/9

    Preamble/Project Selection

    High Loss of Production of Fans due to short

    supply of Critical Components Spindle was an important component. It was

    not possible to augment the production of

    However, it was observed that, rejection ofspindles was very high (6.5%)

    If rejection is brought down, it will have greatimpact on business in the form of higher

    productivity of fans and reduced losses atspindle manufacturing

    Hence, management initiated a Six Sigmaproject at spindle manufacturing

  • 7/29/2019 Spindle2.ppt

    3/9

    Define Phase : The Project Charter

    Problem StatementHigh rejection of spindles due to various dimensions

    was causing heavy losses and loss of production of

    fans due to short supply of the component.

    The TeamSponsor: GM, components Manufacturing

    Leader : Manager (QC), a Black Belt

    Team Members: Two Green Belts and one supervisorTrainer & Guide : Consultant

    Scope:

    All types of Spindles manufactured

  • 7/29/2019 Spindle2.ppt

    4/9

    Define Phase : The Project Charter

    The process and CTQsThe entire manufacturing process for spindle. Various

    dimensions of the spindle which may lead to rejections

    A high level process map was drawn

    Schedule for the project milestones was drawn

    using a Gantt diagram.

    Target

    It was decided to achieve a five-fold improvement in

    rejections. The current level being 6.5%, the target was

    set at 1.3%

  • 7/29/2019 Spindle2.ppt

    5/9

    Define Phase : The Project Charter

    DefectiveAny spindle which cannot be used in the assembly due

    to one or more of the dimensions being high or low is a

    defective product.

    DefectAny dimension which is high or low is considered as a

    defect. There were as many as 19 dimensions. Hence

    number of opportunities is 19

  • 7/29/2019 Spindle2.ppt

    6/9

    Measure Phase

    Base line Data

    Past 1 months go-no-go inspection data wasconsidered. The number of spindles inspected, the totalnumber of defective spindles and the number of defectsdue to each dimension were noted down.

    Total no. inspected : 17,000

    Number of defectives : 1130Total no. of defects : 1350

    P = 0.065

    Yield = 93.5%

    dpmo = 4180

    Sigma Rating for product: 3.01 (Z= 1.51 for p=0.065)Sigma for defects: 4.13 (based on dpmo)

    Target p = 0.013

    Target sigma rating for product: 3.72

  • 7/29/2019 Spindle2.ppt

    7/9

    Analyze Phase

    Pareto analysis was carried out with the Data on defects.

    Four dimensions accounted for over 90% of the defects(A group). These were selected for further study. There

    were 8 dimensions with negligible defects (C group).

    Remaining 7 dimensions (B group) were average.

    For each of the selected dimensions, data on actualmeasurement were collected for 150 components.

    Histograms were drawn

    The histograms suggested that the process capabilities

    were good. However, there was severe lack of control in2 cases, improper setting in one case and shift in

    average dimension due to tool wear out in the fourth

    case.

  • 7/29/2019 Spindle2.ppt

    8/9

    Improve Phase

    1. Improvement suggestions for A group items:

    For cases where lack of control was evident,control chart was recommended. ( )

    For the case where there was improper setting, first

    off inspection (approval inspection) was

    recommended For the case where there was tool wear out,

    statistical analysis (regression analysis) was carried

    out and optimum tool grinding/ tool replacement

    were recommended2. For B group items maintenance of p/np chart shift

    wise were recommended

    RX

  • 7/29/2019 Spindle2.ppt

    9/9

    ControlPhase : Sustain the Gain

    The control charts were designed and implemented for

    all the 11 dimensions.

    The manager of the spindle shop was assigned the task

    of routine follow and feedback as a process owner.

    1 month after implementation, the status was as under:

    Overall rejection level: 2.1%dpmo : 1200

    Sigma Rating for product: 3.54

    Sigma Rating for defects: 4.54

    The expected annual savings from increased productionand reduced losses is 35 lakhs of rupees.