Spindle2.ppt
-
Upload
vishukirthi -
Category
Documents
-
view
218 -
download
0
Transcript of Spindle2.ppt
-
7/29/2019 Spindle2.ppt
1/9
Six Sigma Project Case Study:
Improved Productivity of Fans
through Reduction of
Defects/Defectives at Spindlemanufacturing
-
7/29/2019 Spindle2.ppt
2/9
Preamble/Project Selection
High Loss of Production of Fans due to short
supply of Critical Components Spindle was an important component. It was
not possible to augment the production of
However, it was observed that, rejection ofspindles was very high (6.5%)
If rejection is brought down, it will have greatimpact on business in the form of higher
productivity of fans and reduced losses atspindle manufacturing
Hence, management initiated a Six Sigmaproject at spindle manufacturing
-
7/29/2019 Spindle2.ppt
3/9
Define Phase : The Project Charter
Problem StatementHigh rejection of spindles due to various dimensions
was causing heavy losses and loss of production of
fans due to short supply of the component.
The TeamSponsor: GM, components Manufacturing
Leader : Manager (QC), a Black Belt
Team Members: Two Green Belts and one supervisorTrainer & Guide : Consultant
Scope:
All types of Spindles manufactured
-
7/29/2019 Spindle2.ppt
4/9
Define Phase : The Project Charter
The process and CTQsThe entire manufacturing process for spindle. Various
dimensions of the spindle which may lead to rejections
A high level process map was drawn
Schedule for the project milestones was drawn
using a Gantt diagram.
Target
It was decided to achieve a five-fold improvement in
rejections. The current level being 6.5%, the target was
set at 1.3%
-
7/29/2019 Spindle2.ppt
5/9
Define Phase : The Project Charter
DefectiveAny spindle which cannot be used in the assembly due
to one or more of the dimensions being high or low is a
defective product.
DefectAny dimension which is high or low is considered as a
defect. There were as many as 19 dimensions. Hence
number of opportunities is 19
-
7/29/2019 Spindle2.ppt
6/9
Measure Phase
Base line Data
Past 1 months go-no-go inspection data wasconsidered. The number of spindles inspected, the totalnumber of defective spindles and the number of defectsdue to each dimension were noted down.
Total no. inspected : 17,000
Number of defectives : 1130Total no. of defects : 1350
P = 0.065
Yield = 93.5%
dpmo = 4180
Sigma Rating for product: 3.01 (Z= 1.51 for p=0.065)Sigma for defects: 4.13 (based on dpmo)
Target p = 0.013
Target sigma rating for product: 3.72
-
7/29/2019 Spindle2.ppt
7/9
Analyze Phase
Pareto analysis was carried out with the Data on defects.
Four dimensions accounted for over 90% of the defects(A group). These were selected for further study. There
were 8 dimensions with negligible defects (C group).
Remaining 7 dimensions (B group) were average.
For each of the selected dimensions, data on actualmeasurement were collected for 150 components.
Histograms were drawn
The histograms suggested that the process capabilities
were good. However, there was severe lack of control in2 cases, improper setting in one case and shift in
average dimension due to tool wear out in the fourth
case.
-
7/29/2019 Spindle2.ppt
8/9
Improve Phase
1. Improvement suggestions for A group items:
For cases where lack of control was evident,control chart was recommended. ( )
For the case where there was improper setting, first
off inspection (approval inspection) was
recommended For the case where there was tool wear out,
statistical analysis (regression analysis) was carried
out and optimum tool grinding/ tool replacement
were recommended2. For B group items maintenance of p/np chart shift
wise were recommended
RX
-
7/29/2019 Spindle2.ppt
9/9
ControlPhase : Sustain the Gain
The control charts were designed and implemented for
all the 11 dimensions.
The manager of the spindle shop was assigned the task
of routine follow and feedback as a process owner.
1 month after implementation, the status was as under:
Overall rejection level: 2.1%dpmo : 1200
Sigma Rating for product: 3.54
Sigma Rating for defects: 4.54
The expected annual savings from increased productionand reduced losses is 35 lakhs of rupees.