SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first...

29
1 KAOMBO Project 19 March 2019 Willy Gauttier – TechnipFMC Aymeric Lépinay – Total E&P Angola

Transcript of SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first...

Page 1: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

1

KAOMBO Project

19 March 2019

Willy Gauttier – TechnipFMCAymeric Lépinay – Total E&P Angola

Page 2: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

2

KAOMBO : An « Iconic » Subsea Project

I – Introduction

II – Challenging Development

III – Approach & Relationship

IV – Kaombo Take Away

Page 3: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

3

I - INTRODUCTION

Willy Gauttier – TechnipFMC – TechnipFMC/Heerema Consortium Director Aymeric Lépinay – Total E&P Angola – Kaombo SURF Project Control Manager

CONFIDENTIAL

Page 4: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

4

KAOMBO : An « Iconic » Subsea Project

I – Introduction

II – Challenging Development

III – Approach & Relationship

IV – Kaombo Take Away

Page 5: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

5

KAOMBO – A FRONTIER PROJECT

CONFIDENTIAL

II - A challenging development

Page 6: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

6

II - A challenging development

CONFIDENTIAL

• 1999 PSA signed• 2003-08 Discoveries of the 6 fields:

Gindungo, Canela,Gengibre, Mostarda, Caril and Louro

• 2008-11 Pre-Project studies• 2011-12 Basic Engineering & CFTs• 2013 Project Value Enhancement• 2014 April 14th = FID• 2018 July 27th = First oil

A long journey towards FID, then 4 years to first oil

30%

20%15%

5%

30%

Manjericao

Gengibre Canela

Louro

Salsa

Mostarda

GindungoCaril

Colorau

Alho

Cominhos

Cola

20 km

Kaombo658 Mb

5090 km²

Page 7: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

7

II - A challenging development

CONFIDENTIAL

GGR uncertainties and drilling challenges Dispersed reserves: 6 fields, 9 reservoirs Complex structural & sedimentological environment Presence of salt layers Huge subsea layout on a complex seabed 800 km2 Numerous pockmarks and geohazards A first as FPSO Built & Operate model with one

of biggest turret & schedule challenges Over 50 main activity centers in 23 different

countries Scope in Angola: 14 MMhours commitment

140 km2200 kb/d 230 km2

240 kb/d

600 km2200 kb/d

381 km2160 kb/d

800 km2230 kb/d

110 km2250 kb/d

180 km2250 kb/d

400 km2240 kb/d

100 km2100 kb/d

450 km2150 kb/d

0

500

1000

1500

2000

2500

1998 2003 2008 2013 2018

Water dep

th (m

)

First oil date

GIRASSOLDALIA

PAZFLOR

CLOV

KAOMBO

KIZOMBA C

KIZOMBA B

KIZOMBA A

KUITO

PSVM

TOTALPROJECTS

TOTALKAOMBO

OTHER OPERATORS

Page 8: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

8

Louro

Mostarda

GengibreCanela

GindungoCaril

SURF290 km of line pipe115 km umbilical6 hybrid production loops5 water injection lines1 gas export line

HSENo permanent flaring(gas export to ALNG)Oily drilling cuttings  brought to shore (new law)100+ million man‐hours

2 FPSOs operated – D1B2Converted VLCCsTurret moored/Tandem offloading2 x 115 kbpd  oil  yearly average1650 m water depth

SPS59 (+6) Vertical Xmas trees19 Production manifoldsSubsea prod. ctrl. systems

Drilling59 wells (23 sub‐salt, 33 OP + 26 WI)Average : 63.5 days / well (with 2 rigs dual derricks x 5 years each)1400 to 1950 m water depth

Geosciences9 dispersed and complex reservoirs of limited volume Limited upsides658 Mb

KAOMBO PROJECT SCOPE

8

Page 9: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

9CONFIDENTIAL

II - A challenging developmentUK

SPS engineeringWellheads

Control systemsUmbilicals engineering

SURF FlexjointsSURF multi-jointing

URA/LRA fabrication

AngolaGeosciences, Drilling managementManifolds fabricationXmas trees and wellheads assembliesFlowlines spooling, risers prefabricationUmbilicals fabrication FPSO piles fabrication2 FPSO modules fabricationOperations onshore baseSURF offshore installation vessels

JapanRiser pipes

Conductor pipes

MexicoSURF linepipes

Italy Subsea valves and forgingsSURF linepipes

NetherlandsSURF engineering

Conductor pipesTurret engineering

FPSO pumps

Czech Republic Umbilicals tubes

NorwaySPS engineering

Manifolds Xmas trees

MPFMFPSO Turbines

USASURF engineeringUmbilicals fabricationDrilling completion, subsea test tree

SingaporeFPSO NORTE conversionand integration

IndonesiaFPSO modules fabrication Pipe coating

ChinaConductor pipes

FranceProject managementEngineering (SURF, FPSO/FOSC)TubingFlexible jumpers

IndiaEngineering (SPS, SURF, FPSO)

GermanyTurret bearings and swivel stack

FinlandXmas trees blocks

MalaysiaControl systems

SPS tubing hangers,Xmas trees

Xmas trees flat packSCMs

MSMs, connectors

BrazilSURF welded linepipes

SpainSURF structures fabrication

United Arab EmiratesLower turret fabrication

Riser piles and buoyancy tanks fabrication

South KoreaDS-8 rig

construction

ChiliLower bearing

CanadaTurret controls

Activities completed

SURFSPS FPSO / FOSCUMBILICALS WELLS & DRILLING

KAOMBO Worldwide sites

FPSO SUL conversion and integration

Page 10: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

10CONFIDENTIAL

II - A challenging development

Cut off date: 20 Oct 18

402%

PETROMAR  Ambriz2 modules fabrication, suction piles, boat landing

SONILS  LuandaAssembly of 21 wellheads  &x‐mas trees

ANGOFLEX Lobito Fabrication of dynamic  umbilicals

SONAMET LobitoFabrication of 21 PGBs, 19 manifold foundations, 9 manifolds, 35 production jumpers

PAENAL Porto Amboim2 modules integration FPSO South (cancelled)3 SURF riser foundations Structures installation aidsWater injection jumpers

HEEREMA  Porto AmboimRiser foundations,  multijointing,  spool & jumpers,  seafastening

TECHNIP  DandePipe stalking: 10”/ 16” PIP production, WI, Sl & GE flowlines

145%

148%

139%

137%

111%

59%

152%

Block32

230%

SAIPEM Onshore logistics base133%

TECHNIP ‐ HEEREMASURF offshore installation

SAIPEMFPSO/FOPS offshore works

19.4 M143%

13.5 M manhours

Still active

Still active

All still active

Excellent safety and quality records to date

ANGOLAN CONTENT – MANHOURS STATUS AS OF 20 OCT 18% = EXPENDED HOURS VS. ESTIMATED HOURS

Page 11: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

1111

CLOV Kaombo

Duration 46 months 47 months 42 months

Production 220 KBOE/d 160 KBOE/d 230 KBOE/d

# subsea wells 49 34 59

Lines kms 180 180 300

Investment $9b $8b $16b

Larger and quicker

Our core Business BUTbut with a good mix of Organization, Method and Agility !!

II - A challenging development

Page 12: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

12CONFIDENTIAL

II - A challenging development

KAOMBO SULKAOMBO NORTE

Page 13: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

13CONFIDENTIAL

The Team

II - A challenging development

Page 14: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

14CONFIDENTIAL

II - A challenging development

Page 15: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

15

Doing twice the same thing with the same level of performance is a challenge.

HSE an interesting journey: when you are halfway you feel as if you've not yet started.It's only when you reach the finish line that you've really achieved anything.

HSEhighest standard

Everyone SAFE at homeNo material damage

Upgrading our leadership…

… and our assets

Up to 1200 POB Block 32 / 18 marine assets

II - A challenging development

Page 16: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

16

II - A challenging development

Massive logistics for a flawless 600+ days Offshore Campaign

55.000 tons of material installed by TechnipFMC

Massive Offshore work 5000 vessel days for TechnipFMC with:

1200 Construction + 3800 Third Party15000

Meet & Greet

500 Containers

180 Cargo Barge Approaches

2000 Supply Boat runs

Page 17: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

17

II - A challenging development

But simple tools to enable alignment…

Visual time-location chart to spot potential Clash ahead 1000

Offshore Interface Dossierswith CPY

1000Vessels/Rigs moves

24 monthsRIG/vessel clash free

Campaign

De-coupling Deep Blue &Balder upon progress

Page 18: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

18

Main Installation Campaign :

De-risking of Rigid Spools installation (Project Risk #1)

Breaking installation timing50 large rigid spools 900Te Crane Upgrade

Lifting weight: Up to 310Te 100% of operability over the year resulting to no stand-by

II - A challenging development

Page 19: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

19CONFIDENTIAL

II - A challenging developmentA Unique Technology: 900Te Crane – Constant Tension Pick Up mode

Page 20: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

20FPSO heading control ≤ ±30˚ to 15%

when handling

Hook-up Campaign :

De-risking Flexible Jumper Connection to the STTR Upper Riser Assembly

Better than expected since the first one

Stack-up testsFull scale test Connection with

TMOS personnel

Offshore Operations

II - A challenging development

Page 21: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

21CONFIDENTIAL

II - A challenging developmentA Unique Technology: EHS (End Handling System)

EHSVideo

Page 22: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

22CONFIDENTIAL

Operations

II - A challenging development

Page 23: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

23

KAOMBO : An « Iconic » Subsea Project

I – Introduction

II – Challenging Development

III – Approach & Relationship

IV – Kaombo Take Away

Page 24: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

24

II – Approach and RelationshipKaombo Frontier Project :

Necessity to establish a proper collaborative working environment

CONFIDENTIAL

5 years14 Sponsors

Page 25: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

25

II – Approach and RelationshipFPSO North Campaign :

Alignment on an optimized First Oil sequence with the « Time location chart »

Slot 1 Slot 2 Slot 3 Slot 4 Slot 5 Slot 6 Slot 7 Slot 8 Slot 9 Slot 10 Slot 11 Slot 12 Slot 13 Slot 14 Slot 15 Slot 16 Slot 17 Slot 18

CAN PROD Priority 2

CAN GL Priority 2

CAN WI Priority 6

CAN SERV Priority 2

LOU/MOS WI Priority 7/8 Future Riser

MOS PROD Priority 1

MOS GL Priority 1

MOS SERV Priority 1

LOU SERV Priority 5

LOU GL Priority 5

LOU PROD Priority 5

MOS DPU Priority 1

LOU DPU Priority 5 Future Riser

GE Priority 4

SSIV CC Priority 4

CAN DPU Priority 2

KEY MILESTONES Mooring Sequence (simplified)F F Deploy chainstoppersF F 1 Line SURF SURF hook‐up (Skandi  Africa)F F 2 Lines SURF SURF hook‐up (FPSO) Turret Critical Path to Mostarda startupF F 3 Lines ( storm moored) SURF SURF Pre‐commissioning activity F F 4 Lines SURF SURF Subsea Operation  FPSO Commissioning   ‐ Leak tests during night shif tF F 5 Lines SURF SURF GEP Dewatering / Packing F F 6 Lines No activities in turret due to SURF activity / hydrotest  / leak test / well  opening / mooring retensioningF F 7 Lines FPSO FPSO hook‐up /Tie‐in activity F F 8 Lines (*) Activity performed during hook ‐up (no tension)  phase. Timing subjected to site adjustementsF F 9 Lines SUBSEA Subsea CommissioningF F ROV l ine integrity surveyF F F F ROV l ine integrity survey Dive support

F F F F ROV l ine integrity survey Dive support I tube cover rem I tube cover remF F F F RFHU I tube cover rem I tube cover rem Riser prep

F F F I tube cover rem I tube cover rem I tube cover remF F FF F FF F F I tube cover rem I tube cover rem I tube cover rem Riser prepF F F I tube cover rem I tube cover rem I tube cover remF F FF F FF F F I tube cover rem I tube cover rem I tube cover rem Riser prepF F F I tube cover rem I tube cover remF F F SSIV tub precom (*)F F FF F F Riser prep Removal Umb headF F FF F FF F F  F F F Umb E&I precom (*) Umb E&I precom (*)F F FF F F Riser prepF F FF F FF F FF F F Install  Frame (*)F F FF F F Riser prep Pulling head removeF F FF F F 1F F FF F F 2F F FF F F Riser prep Gauging prep Gauging prep JB + TUB RTMS precom Umb E&I precom 3F F F E&I G&T  + TUBF F F FO + TUB RTMS precom Umb E&I precom 1F F F E&I G&T  + TUBF F F 2F F FF F F Riser prep FO + TUB RTMS precom 3F F F E&I G&T  + TUBF F F FO + TUB PTMS network test F F F E&I G&T  + TUBF F FF F FF F F Gauging prep Gauging  prep Riser prepF F F E&I G&T  + TUB INSTALL FRAME INSTALL FRAMEF F FF F FF F F Riser prep FO + TUB Removal Umb head JB INTALL JB INSTALLF F F TUBING E&I G&T  + TUBF F F Note :F F F TopsidesF F F only F F F LTPsF F F Riser prep not shownF F FF F F Flushing FO + TUB E&I G&T +TUB 1F F F TUBING E&I G&T+ TUBF F F INSTALL FRAME (*) 2F F F

F FF F Flushing TUBING JB INTALL FO + TUB 1F F   SURFF F SURF 2F F  Global LT prep ESDV installation TUB HYDROTEST (Exclusion zone apply during the pressure test)F F SURF 3

F F F SURFF F F LTP 4F F F Spool installation Spool installation Riser prepF F F LTP 5F F F Spool installation Spool installation Spool installation TUB HYDROTEST (Exclusion zone apply during the pressure test)F F F LTP 6F F F E&I and tub conn(*)F F F 1F F F Spool installation Spool installation Riser prep TUBING RTMS E&I G&T FO + TUBF F F LTP 2F F F Spool installation Spool installation Torqueing Torqueing Torqueing TUB + FLUSHING RTMS E&I G&T FO + TUBF F F LTP 3F F F AVT (*) AVT (*) AVT  (*) AVT (*)F F F 4F F FF F F LTP 5F F F AVT AVT AVT Riser prep TUB + FLUSHING RTMS E&I G&T FO + TUBF F F LTP 6F F F AVT  (*) AVT  (*)F F FF F F Riser prep Spool trial fit TUB HYDROTEST (Exclusion zone apply during the pressure test)F F F LTPF F F Torqueing ESDV installation Torqueing Spool trial fit Spool trial fit TUBING RTMS E&I G&T FO + TUBF F F LTPF F F E&I and tub conn(*)F F FF F F Gauging prep Riser prep TUB HYDROTEST (Exclusion zone apply during the pressure test)F F F LTPF F F E&I and tub conn. FLUSHING FO + PCS E&I G&T E&I G&T  + TUBF F F LTPF F F AVT (*) E&I and tub conn(*)F F F

F F Spool installation AVT AVT FLUSHING FO + PCS E&I G&T E&I G&T  + TUBF F LTPF F Torqueing Spool trial fit Spool trial Fit Flushing TUBING SUPPORTS FO + PCS E&I G&T E&I G&T  + TUBF F LTPF F Spool trial fit Spool trial Fit Spool trial fit TUBING FINAL CON FO + PCS E&I G&T E&I RFC Insp. + TUBF F LTPF F E&I and tub conn. RACS tubing TUBING FINAL CON Gauging prep 1F F LTPF F E&I and tub conn. RACS tubing 2 1F F LTP

F Annulus vent tubing leak test prep 3 2F SURFF SURF 3

LTPE&I and tub conn. Gauging prep Gauging prep JB + TUB FO + PCS E&I G&T TUBING 4

LTPE&I and tub conn. DOP INSTALL FO + PCS E&I G&T TUBING 5

LTPLeak  test  prep ESDV + Actuator  6

Leak test (incl. Subsea  network) LTP

ESDV + Actuator  7SURFSURFSURF

RACS tubing ESDV installation DOP REMOVE ScaffoldingLTP

1LTP

Leak test prep Spool installation Spool installation Spool Installation 2SURFSURF 3LTP

Gauging prep Spool installation Support install. Spool installation ESDV Panel Install Spool Installation 4LTP

Spool installation Torqueing TUB HYDROTEST 5LTP

LTPLeak test prep Torqueing Torqueing Torqueing TUB HYDROTEST

LTP

LTPSpool installation Spool installation E&I and tub conn. PFP ESDV Tub + E&I  TUB + FLUSHING

LTPSpool installation Spool installation E&I and tub conn. PFP ESDV Tub + E&I  TUB + FLUSHING

LTP

Torqueing Torqueing E&I G&T + TUB ESDV Tub + E&I  TUBING 1 1LTP

RACS tubing E&I and tub conn. TUB HYDROTEST 2 2LTP

Annulus vent tubing E&I and tub conn. ESDV Tub + E&I  PCS E&I G&T  FLUSHING 3 3LTP

PFP E&I G&T + TUB PCS E&I G&T  FLUSHING 4 4LTP

5 5LTP

PFP RACS tubing E&I G&T + TUB Leak test prep PCS E&I G&T TUB SUPPORTS 6 6LT ( incl. Subsea network) SURF

PFP RACS tubing E&I G&T + TUB TUBING TUB FINAL CON. SURF 7LTP

PFP Annulus vent tubing E&I G&T + TUB TUBING TUB FINAL CON. 8LTP

PFP PFP E&I G&T + TUB TUBING 9LTP

PFP PFP FO + TUB TUB HYDROTEST 10LTP

PFP FO + TUB FLUSHING 1 11LTP

PFP FO + TUB FLUSHING 2 12LTP

PFP FO + TUB 3 13LTP

PFP FO + TUB PFP 4 14LTP

PFP E&I RFC Insp.+ TUB PFP 5 15LTP

PFP TUB PFP 6 16LTP

1 17LTP

PFP TUB PFP 2 18LTP

PFP TUB HYDROTEST 19LTP

PFP TUB HYDROTEST 4 20LTP

PFP TUB HYDROTEST 5 21LTP

22TUB HYDROTEST

23

24

25

TUB + FLUSHING 1TUB + FLUSHING

TUB 2TUB TEST FLUSHING PFP 3 FLUSHING

TUB SUPPORTS PFP 4TUB FINAL CON.TUB FINAL CON. 5

PFP 6PFP

7

1 8

2 9

3 10

4 11

5 12

6 13

14

15

16

D+71

CAN M

anifo

lds 

Commiss

ionn

ing

Chem

ical lines dew

atering

Hybrid loop thermal performance test

Hybrid loop warm up

MOSTARDA Well opening

CANELA SU

BSEA

 X‐TRE

E SO

FTWAR

E TEST

S

TIMELIN

E

D+108

D+109

D+110

D+111

D+112

D+113

D 114

D+97

D+98

D+99

D+100

D+101

D+102

D+103

D+104

D+89

D+90

D+91

D+92

D+105

D+96

D+79

METHANOLBUNKERING 

Circulation

MOS SU

BSES X‐TRE

E SO

FTWARE

 TESTS

D+106

D+107

D+87

D+70

Circulation

D+72

D+73

D+74

D+75

D+76

D+77

D+78

D+93

D+94

D+95

D+80

D+81

D+82

D+83

D+84

D+85

D+86

D+88

MeOH Dewat

Diesel

Hybrid loop thermal performance test

Hybrid loop warm up

CANELA Well opening

X TR

EE COMMISSIONNING

D+61

D+62

D+63

D+64

D+65

D+66

D+67

D+68

D+69

D+52

D+53

D+54

D+55

D+56

D+57

D+58

D+59

D+60

D+43

D+44

D+45

D+46

D+47

D+48

D+49

D+50

D+51

D+34

D+35

D+36

D+37

D+38

D+39

D+40

D+41

D+42

D+25

D+26

D+27

D+28

D+29

D+30

D+31

D+32

D+33

D+16

D+17

D+18

D+19

D+20

D+21

D+22

D+23

D+24

D+7

D+8

D+9

D+10

D+11

D+12

D+13

D+14

D+15

D+0

D+1

D+2

D+3

D+4

D+5

D+6

D+63

D+64

MOS Man

ifolds 

EFL conn

ection

Diving  

Hook up (#15) Downline

Downline Hook up (#16)

D+8

Hook up (#9)

Diving  

Diving  

Diving  

D+9

D+10

MOORINGFINAL SURVEY

(INCL. H LINKS)  

MOORINGLINES 

RE‐TENSION(RISK ON PLANNING ‐3 

DAYS)

MeOH Dewat

Chem

ical lines dew

atering

Gauging

Spool trial fitSpool trial fit

Diving  

D+62

MOS X TR

EE 

CAPS & EFLs

MOS Man

ifolds 

Commiss

ionn

ing

D+47

D+48

D+49

D+50

D+51

D+52

Downline Hook up (#10)

Gauging

Umb tub precom

Moor. Installatio

n Ve

ssel

Surf IV

 ‐ Scan

di Africa

DSV ‐ XXX

X

Subsea FOPS

 Com

LCV BO101 

SURF LCV

 ops 

BE80

5

Tug ‐ m

oorin

g

Tug ‐ h

eading

GaugingGaugingD+23

D+14

D+15

D+16

D+17

D+18

D+19

D+20

D+21

D+22

D+1

D+2

D+3

D+4

DSV MOORING  & DIVING PREPARATION

INTE

RIM

MOB

Umb E&I precom

SSIV M

odule 

EFL SS con

nection

D+99

D+100

D+101

D+102

D+103

D+104

D+105

D+106

D+107

D+90

D+91

D+92

D+93

D+94

D+95

D+79

D+72

D+46

TOPSIDES COMMISSIONNING

METHAN

OL

DEAD

 OIL

FLAR

E SYSTEM

OIL TREATM

ENT

SEA WATER 

TREA

TMEN

T an

d WAT

ER IN

JECT

ION

GAS COMPR

ESSION

GAS

 DEH

YDRA

TION & 

TEG REG

EN.Leak Test Slots 

in Turret

SURF / SUBSEA / STARTUP

EFL CO

NNEC

TIONS

SOFTWAR

E TE

STS

SUBS

EA M

ANIFOLD

S CO

MM

CHEM

ICAL LINES 

DEW

ATER

ING

MET

HANO

L LINES

 DEW

ATER

ING

PROD LO

OP 

DEW

ATER

ING W

ITH 

DIESEL

D+44

D+65

SUBSEA

 X‐ TRE

ES 

COMM

D+5

D+6

D+7

Umb tub precom

DSV MOORING  & DIVING PREPARATION

Hook up (#3) Downline

Umb tub precom

Hook up (#6) Downline

MOS+LOU  WI lines dewatering

WI service test

Gauging

Dewatering

PLR Removal SS

OPEN PLEM valves  

 Global leak test

Leak test

Gauging

Leak test preparation

 Global leak test prep

PLR Removal SS

Gauging Gauging

Downline

D+30

D+34

D+35

D+36

D+37

D+38

D+39

D+40

Downline

Downline

D+73

D+74

D+75

D+76

D+77

D+66

D+67

D+43

Gauging

Leak testD+54

D+55

D+56

D+57

Diving  

Leak test  (incl. Subsea network)

D+41

D+42

PLR Removal SS

D+111

D+112

D+113

Leak test (incl. Subsea network)

WI service test

CAN  WI lines dewatering

D+78

D+80

D+96

D+97

D+98

D+81

D+82

D+83

D+84

D+85

D+86

D+87

D+88

D+89

D+110

CdFWorking Draft 

revision 211 Oct 2018

Canela Cluster Mostarda Louro Cluster East Cluster

Hook up (#2)

Diving  

Diving  

Hook up (#1)Downline

Dummy Spool Removal

Dummy Spool Removal

Dummy Spool Removal

Downline

D+0Dummy Spool 

RemovalDummy Spool 

RemovalDummy Spool 

RemovalDummy Spool 

Removal

SURF / FPSO Coordination for Turret activities

TIMELIN

E

 Global leak test prep

DELUGE (TBC) DELUGE (TBC)

BLACK START BLACK START BLACK START

Umb tub precom

Downline Hook up (#4)

Diving  

Marine Coordination

D+70

D+71

Leak test  preparationLeak test (incl. Subsea network)

Downline Hook up (#8)

PLR Removal SS

Leak test

 Global leak test prep

Hook up (#11)

 Global leak test  Global leak test

Diving  D+32

D+33

D+45

D+68

D+53

D+59

D+60

D+61

D+24

D+25

D+26

D+58

Diving  

Downline

Umb tub precom

Leak test preparation

Hook up (#13)

Diving  

DELUGE (TBC)

Umb E&I precomDiving  

Hook up (#5) Downline

D+13

Diving  

Hook up (#7)

D+12

D+27

D+31

D+28

D+29

D+11

D+69

Downline

Diving  

 Global leak test

Diving  

Downline

Hook up (#12)

Spool trial fitSpool trial fit

Diesel

CANELA X TR

EE 

CAPS & EFLs

LOURO

 X TRE

E CA

PS & EFLs

D+109

Umb E&I precom

Hook up (#14)

X TR

EE COMMISSIONNING

LOURO

 Man

ifolds 

EFL conn

ectio

nCA

N  M

anifo

lds 

EFL conn

ectio

n

MOS SU

BSEA

 MANIFOLD

S SO

FTWAR

E TEST

SCA

NELA SU

BSEA

 MANIFO

LDS 

SOFTWAR

E TEST

SLO

URO

 SUBS

EA M

ANIFOLD

S SO

FTWARE

 TESTS

Mobilisation of Dewatering Equipment

(on P1 and S1)

Final Rig‐up(on P1 and S1)

+functional testing 

equipement(on P1 and S1)

Packing

Load and launch Pig Train

GEP inerting

LOURO

 SUB

SEA X‐TR

EE 

SOFTWARE

 TESTS

LOU M

anifo

lds 

Commission

ning

Chem

ical line

s de

watering

C irculation

NG

MeOH Dewat

Di lD 114

D+108

RFC

RFC

RFC

RFC

DSV MooringAlongside + Turret Prep

PSV AlongsideUnloading SURF material

RFC Partial E&I

MOORING 9 LINES

Ready forMethanol bunkering

Ready forFirst Oil

Ready forDiesel Circulation

No activities during MeOH first circulationNo activities during MeOH first circulationNo  activities during MeOH first circulation

No activities during Diesel first circulationNo activities during Diesel first circulationNo activities during Diesel f irst circulation

MOSTARDA HOOK‐UP START UP MIN REQUIREMENTS COMPLETEDDiving Final Survey

Tug Demobilisation

No activity in the turret during Mostarda startup activities  No activity in the turret during Mostarda startup activities  No activity in the turret during Mostarda startup activities  

RFC Partial E&I

No activity in the turret during Canela startup activities  No activity in the turret during Canela startup activities  No activity in the turret during Canela startup activities  

No  activities during MeOH first circulationNo  activities during MeOH first circulationNo  activities during MeOH first circulation

No activities during Diesel first circulationNo  activities during Diesel first circulationNo activities during Diesel f irst circulation

RFC Partial E&I

Topsides ready forWater Injection

WARNINGTHE TOPSIDES READINESS DATES  ARE GIVEN IN LINE WITH THE "TOPSIDES  COMMISSIONNING ROAD MAP" . DATES / DURATIONS  ARE TO BE 

CONFIRMED

WARNING !!THE METHANOL

BUNKERING WINDOW IS TO BE CONFIRMED 

WARNING !!SHALL MOORING LINE RETENSIONNING BE 

REQUIRED IT WILL IMPACT ALL TURRET ACTIVITIES

FOR SURF : PLEASE COMMENT ON THE DURATION OF  DEWATERING AND PACKING ACTIVITIES KNOWING THAT THE GAS EXPORT TIE‐ IN IS  ~ 5 KM AWAY AS  COMPARED TO ~50 KM ON NORTE

NOTE : DECK SPACE STUDY TO BE PERFORMED TO CONFIM  THEFEASEABILITY OF  THE EARLY MOBILISATION OF  THE DEWATERING SPREAD.

DATE TBC

SUBSEA  HPUto be ready (AKER)

LINK TO SUBSEA SCOPE

Mob FPSO Leak Test Spread 

No activities during Diesel first circulationNo activities during Diesel first circulationNo activities during Diesel first circulation

No activities during MeOH first circulationNo activities during MeOH first circulationNo  activities during MeOH first circulation

!

SURF / SUBSEA  COM TO REVIEW THE EFLs  SCOPE DESCRIPTION / 

DURATION 

!IN CASE OF ANTICIPATEDDIESEL CIRCULATION THE CASE OF LIFTING THE LOURO SPOOLS ABOVE THE MOSTARDA ONES FULL OF HYDROCARBON WILL HAVE TO BE ADRESSED FROM HSE POINT OF VIEW 

Level 1Safest de-riskedsequence

Quickest Hook-Up ever for TOTAL

0,8 0,80,4 0,4 0,5 0,3

0,90,3

1,0

4,13,5

2,5

3,92,9

3,9

4,1

3,5 2,4

0,0 months

1,0 months

2,0 months

3,0 months

4,0 months

5,0 months

Project #1 Project #2 Project #3 Project #4 Project #5 Project #6 Project #7 Project #8 KAOMBO N

FPSO/FPU offshore timing comparison

Hookup & Commissioning

Mooring

Page 26: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

26

II – Approach and Relationship

FPSO moving target : « give a chance to chance » with no pressure !!unlocking L2 critical path to enable earlier FPSO Access

100% strike with the “Plan B”!

Optimistic scenario achieved !

FPSO Access 26th Jan. 2019

25.000 Fruit Trees

CO2 Offset initiative 50/50 funding with CPY Negative Float in Sept 2018

Page 27: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

27

KAOMBO : An « Iconic » Subsea Project

I – Introduction

II – Challenging Development

III – Approach & Relationship

IV – Kaombo Take Away

Page 28: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

28

Kaombo Take Away: a part of the recipe!

Interfaces

Digitalisation for Material Management

Agility for Plan « B »

Governanceand mindset…

Amongst other 1.000.000 Lessons Learned…

EngineeringProcurement

Fabrication

Installation

SPS

Page 29: SPE presentation 19 March 2019...2019/03/19  · A long journey towards FID, then 4 years to first oil 30% 20% 15% 5% 30% Manjericao Gengibre Canela Louro Salsa Mostarda Gindungo Caril

29CONFIDENTIAL