SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009

Transcript of SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop...

Page 1: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

SCE Solar PV Program

California Public Utilities Commission Workshop

July 31, 2009

Page 2: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 2SCE Solar PV Program – CPUC Workshop

Agenda• Background and Introduction

• Reverse Auction / RFO Process and Criteria

• Lunch Break

• PPA Terms & Conditions

Page 3: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 3SCE Solar PV Program – CPUC Workshop

Background

• In Decision (D.) 09-06-049, the Commission adopted a Solar PV Program for SCE that will result in 500 MW of new renewable energy generating capacity in SCE’s service territory over five years

• SCE’s Solar PV Program consists of the following:– 250 MW DC owned and maintained by SCE (UOG), plus

– 250 MW DC owned and maintained by Independent Power Producers (IPPs)

• Pursuant to D.09-06-049, on July 20, 2009 SCE filed Advice Letter 2364-E requesting approval of a competitive solicitation process and criteria, and a standard contract

Page 4: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 4SCE Solar PV Program – CPUC Workshop

Introduction and Program Summary

• Today’s workshop will focus on the competitive solicitation process and criteria, and standard contract for the IPP portion of SCE’s Solar PV Program

• Reverse Auction • SCE to provide guidance on preferred locations• Clearly defined short-listing criteria• Standard 20-year contract based on AB 1969 • Minimum of one auction per year the course of five years

Solicitation Process

• Primarily 1-2 MW rooftop installations• Up to 10% of capacity ground mounted• All within SCE service territory

Market Niche

Page 5: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 5SCE Solar PV Program – CPUC Workshop

SCE Procurement Background• SCE will rely upon its experience procuring power

through competitive solicitation– Balances needs of all stakeholders (customers,

counterparties, and SCE)

• The proposed Solar PV Program process and criteria are modeled after the All Source RFO, a reverse auction in which SCE procures several hundred million dollars worth of energy and capacity every year

Page 6: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 6SCE Solar PV Program – CPUC Workshop

Agenda• Background and Introduction

• Reverse Auction / RFO Process and Criteria

• Lunch Break

• PPA Terms & Conditions

Page 7: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 7SCE Solar PV Program – CPUC Workshop

Reverse Auction / RFO Process Overview

1) Develop Reverse Auction / RFO package

2) Launch Reverse Auction / RFO

3) Receive indicative offers

4) Evaluate indicative offers, create short list

5) Finalize terms, interconnection studies

6) Receive binding price offers

7) Evaluate offers and select projects

8) Accept offers, execute PPAs, CPUC approval

Page 8: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 8SCE Solar PV Program – CPUC Workshop

1) Develop Reverse Auction / RFO Package• All documents will be specified in the Procurement

Protocol, including:– Complete Reverse Auction / RFO instructions and timeline

– Procedures and templates for submitting indicative offers

– Conforming criteria for evaluation and selection

– Interconnection applications and forms

– Instructions for submitting Binding Price Offers

Step 1

Page 9: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 9SCE Solar PV Program – CPUC Workshop

Desirable Locations• SCE is required to “identify locations where distributed

solar PV will be desirable, thereby optimizing the locational value of the project sites.”*

• A list of zip codes will be posted online– Will be updated as new information becomes available

– Will include SCE’s approximation of available capacity for new solar PV generation within each zip code

• By providing this data, SCE does not warrant economic project viability or the ability of proposals to pass the interconnection screens or studies without upgrades

*See D.09-06-049, p. 42.

Step 1

Page 10: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 10SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Step 1

Page 11: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 11SCE Solar PV Program – CPUC Workshop

2) Launch Reverse Auction / RFO• Upon the Reverse Auction / RFO launch, information

including a complete timeline of the procurement process will be made public through a dedicated website and other outreach

• Q&A information will be updated subsequent to a Reverse Auction / RFO participants’ conference

Update Website

Post Q&A results

RFO Launch

Website information becomes public

RFO Publicized

Press release

SCE emails its renewable energy

mailing lists

RFO Conference

Q&A Session

Step 2

Page 12: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 12SCE Solar PV Program – CPUC Workshop

3) Receive Indicative Offers• The proposal template for indicative offers will include:

– A non-binding price in dollars per megawatt hour ($/MWh)• Including estimated interconnection costs and all tax incentives

– Forecasted initial operation date

– Project sponsors and reference projects

– Completed Project Viability Calculator• With adequate information for SCE and the IE to populate a Project Viability

Calculator

– Physical details of the proposed project• Site location and ownership• Gross and net power ratings• PV technology, mounting and installation area• Single line diagram

• SCE may follow up to clarify or obtain any necessary information

• See following section for Conforming Criteria

Step 3

Page 13: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 13SCE Solar PV Program – CPUC Workshop

4) Evaluate Indicative Offers, Create Short List• Select projects will be placed on a short list

– Based on Indicative Offers and Conforming Criteria specified in Procurement Protocol

– Subject to review by PRG

• Complete interconnection application (fast track or otherwise) must be filed and deemed complete within ten business days of short list notification

Filed interconnection

applications must be deemed

complete within 10 days

Indicative Offers submitted

Indicative Offers which conform to criteria are placed

on the short list

Short-listed parties are notified of their

status

Step 4

Page 14: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 14SCE Solar PV Program – CPUC Workshop

Conforming Criteria• Capacity should be primarily in the 1 to 2 MW range

(DC) and built on rooftops

• Levelized indicative offer must be below $260/MWh

• Within SCE’s service territory and subject to a FERC jurisdictional interconnection agreement

• Demonstrated site control by either:– Providing a roof lease

– Providing a firm option to lease demonstrating the owner’s agreement that the PV system will be and can be installed

Step 4

Page 15: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 15SCE Solar PV Program – CPUC Workshop

Conforming Criteria (Cont.)• Project must not participate in the California Solar

Initiative (CSI) program or net energy metering (NEM)– Signed statement by roof owner acknowledging familiarity with

CSI and NEM, committing not to apply for either program with respect to a Solar PV Program project

• Must be scheduled to begin operation within 18 months of contract execution

• Seller must have sufficient experience with large commercial and industrial roof-mounted PV installations

• The system must be a commercially proven PV system and use UL-rated components

Step 4

Page 16: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 16SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Step 4

Page 17: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 17SCE Solar PV Program – CPUC Workshop

5) Finalize Terms, Interconnection Studies• To the extent that any variations to the PPA terms are

necessary, they will be finalized at this stage– Terms and conditions of the standard 20-year PPA are not

intended to be subject to negotiation, but changes will be considered for unique circumstances and within time and resource constraints

• Projects must complete an interconnection application and pass nine of ten screens or a completed System Impact Study

SCE will only continue past step 5 with proposals that are complete in all respects except for an agreement on price

Step 5

Page 18: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 18SCE Solar PV Program – CPUC Workshop

6) Receive Binding Price Offers• Eligible parties will submit a Binding Price Offer in

response to the SCE reverse auction– One flat price, in $ per MWh (no escalation permitted)

– Time-Of-Delivery periods and energy payment allocation factors will be incorporated into payment calculations

• SCE reserves the right (but is not obligated) to accept any Binding Price Offer according to the terms presented

Step 6

Page 19: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 19SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Step 6

Page 20: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 20SCE Solar PV Program – CPUC Workshop

7) Evaluate Offers and Select Projects• SCE will select the lowest Binding Price Offers,

subject to:– Local interconnection constraints

– Maximum 10% of program capacity can be ground mounted

– 250 MW total program target

– Costs including time-of-use factors are not to exceed SCE’s utility owned Solar PV Program’s levelized cost of electricity (LCOE) ($260/MWh)

• SCE is considering a multi-round reverse auction– Would give offerors an opportunity to improve prices to

acceptable levels by submitting new Binding Price Offers

– Offerors would be informed at time of Reverse Auction / RFO launch, through the Procurement Protocol and RFO conference, on exactly how this would operate

Step 7

Page 21: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 21SCE Solar PV Program – CPUC Workshop

8) Accept Offers, Execute PPAs, CPUC Approval

• SCE will execute PPAs with selected projects

• SCE will submit all executed PPAs to the CPUC for approval under a single Tier 2 Advice Letter

Step 8

Page 22: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 22SCE Solar PV Program – CPUC Workshop

Timeline• Finalized timeline and dates will be released upon the

Reverse Auction / RFO Launch

Process Steps and Relative Timeline (approximate)Launch Reverse Auction / RFO T = 0

Hold RFO Conference T + 2 weeks

Post Q&A Results T + 3 weeks

Receive Indicative Non-Binding Offers T + 4 weeks

Evaluate Conforming Criteria T + 5 weeks

Notify Short List T + 7 weeks

Receive Completed WDAT Interconnection Applications

T + 9 weeks

Complete Interconnection Screens T + 16 weeks

Receive Binding Offers T + 17 weeks

Complete Price Improvement Period T + 17 weeks

Execute PPAs T + 18 weeks

Submit Tier 2 Advice Letter T + 25 weeks

Step 1

Step 2

Step 3

Step 4

Step 5

Step 6

Step 7

Step 8

Page 23: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 23SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Page 24: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 24SCE Solar PV Program – CPUC Workshop

Agenda• Background and Introduction

• Reverse Auction / RFO Process and Criteria

• Lunch Break

• PPA Terms & Conditions

Page 25: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 25SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Page 26: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 26SCE Solar PV Program – CPUC Workshop

Agenda• Background and Introduction

• Reverse Auction / RFO Process and Criteria

• Lunch Break

• PPA Terms & Conditions

Page 27: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 27SCE Solar PV Program – CPUC Workshop

Solar Photovoltaic (“PV”) Standard PPA• This presentation will address key terms only, not all of the terms and conditions

in the Solar Photovoltaic Power Purchase and Sale Agreement (“PPA”)

• Based on CREST tariff (AB 1969) approach with modifications to maintain consistency with objectives of SCE’s Utility Owned Generation (“UOG”) Program

• The Commission will adopt the final Standard PPA by Resolution

• This presentation assumes projects within the expected norms of 1-2 MW, primarily on rooftops

– In no instance will SCE review offers for projects greater than 10 MW

– Additional contract terms may be required for projects greater than 2 MW

Page 28: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 28SCE Solar PV Program – CPUC Workshop

Terms, Interconnections, and Obligations

• 20-year Term

• Term must start within 18 months of CPUC Approval

• Producer to comply with California Independent System Operator Tariff (“CAISO”)

• Interconnection in SCE’s service territory

• No performance assurance obligations

• No annual delivery obligations

• No energy replacement damage amount

• SCE is the Scheduling Coordinator

Page 29: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 29SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Page 30: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 30SCE Solar PV Program – CPUC Workshop

Product, Price, and Payments

• SCE buys Product (energy, Green Attributes, Capacity Attributes and Resource Adequacy Benefits)

• Product Price is based on competitive offer

• SCE makes monthly payment based on metered amounts

• Payments adjusted by SCE’s Time-of-Delivery Periods and Energy Payment Allocation Factors

• SCE sends payments by the last Business Day of the calendar month following the energy production

• Payment made by check unless Parties otherwise agree

Page 31: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 31SCE Solar PV Program – CPUC Workshop

Interconnection and Delivery• Producer must obtain and maintain all interconnection

rights and interconnection agreements

– Pursuant to the Procurement Protocol, producers will generally file a WDAT application (fast track or otherwise) with SCE

– However, projects connecting to the CAISO-controlled grid will apply directly to the CAISO

• Delivery Point is first point of interconnection with CAISO controlled transmission system (aka “PNode”)

Page 32: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 32SCE Solar PV Program – CPUC Workshop

SCE Responsibilities

• SCE will be responsible for turning the Forecast information into Schedules or accept the CAISO’s PIRP Schedules

• SCE will handle reporting renewable energy credits to Western Renewable Energy Generation Information System (“WREGIS”)

Page 33: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 33SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Page 34: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 34SCE Solar PV Program – CPUC Workshop

Development Security

• $20 per kW of Gross Power Rating

• Due within thirty (30) days of the PPA Effective Date

• In the form of cash deposit or Letter of Credit

• Refunded in whole, or on a prorated basis, based upon Producer installing the Gross Power Rating, or only a portion, before the Term Start Date

• Forfeited for failure of Producer to commence Operation by the Term Start Date

Page 35: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 35SCE Solar PV Program – CPUC Workshop

• Starting on the Effective Date and continuing until the Term ends, Producer shall maintain in force at its sole expense, valid and collectible insurance

– Workers’ compensation insurance

– Employer’s liability insurance

– Commercial general liability insurance must bear a minimum limit per occurrence of not less than $1,000,000

– Commercial automobile liability insurance covering bodily injury and property damage with a combined single limit of not less than $1,000,000 per occurrence

– Excess liability insurance on a following form basis with limits of not less than $4,000,000 per occurrence

Insurance

Page 36: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 36SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Page 37: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 37SCE Solar PV Program – CPUC Workshop

Other Requirements• Producer responsible for Forecasting Capacity or

Energy, including: – 30-day rolling forecast

– Weekly updates

– Updates 20 minutes before the operating hour

• Producer to use commercially reasonable efforts to Operate so production conforms with Forecasts

• Producer will comply with NERC reliability standards, as applicable

• Producer will provide monthly reports during development period

• With limited exceptions, neither Party may disclose Confidential Information

Page 38: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 38SCE Solar PV Program – CPUC Workshop

• Waive claims for eligibility for California Solar Initiative (“CSI”) funds and net energy metering for the Generating Facility while the PPA is in effect

• Producer required to pay prevailing wage

• Producer required to use Electricians with class C-10 licenses and who employ apprentice electricians who have been enrolled in apprentice training programs meeting specified criteria

• SCE Buyout Option

– At SCE’s sole discretion

– At end of the Term

– $100/MW of Gross Power Rating

Provisions to Match the Benefits of the UOG Program

Page 39: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 39SCE Solar PV Program – CPUC Workshop

• Interconnection study determines system upgrades are required

• Term does not begin within 18 months of CPUC approval

• Producer fails to take corrective actions specified in Notice

• Producer abandons Generating Facility

• Electrical output ceases for 12 consecutive months

• Producer or owner of the Site applies for or participates in California Solar Initiative or net metering program with respect to the Generating Facility

Termination Rights

• Any obligation to make payment when due

• Force Majeure, which extends for more than 365 consecutive days, or for more than 365 days in a consecutive 540-day period

SCE

Mutual

Page 40: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 40SCE Solar PV Program – CPUC Workshop

Check In -- Discussion

Page 41: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 41SCE Solar PV Program – CPUC Workshop

Back-Up Slides

SCE Solar PV Program

Page 42: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 42SCE Solar PV Program – CPUC Workshop

Payment Calculation

TOD PERIOD PAYMENT = A x B x C

Where:

A = Product Price (in $/kWh)

B = Energy Payment Allocation Factor for the TOD Period

C = Sum of Metered Amounts for the TOD Period

“Holiday” is defined as New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, or Christmas Day. When any Holiday falls on a Sunday, the following Monday will be recognized as a Holiday. No change will be made for Holidays falling on Saturday.

TOD Periods

TOD PeriodSummer

Jun 1st – Sep 30th

WinterOct 1st – May 31st Applicable Days

On-Peak Noon – 6:00 P.M. Not Applicable Weekdays except Holidays

Mid-Peak

8:00 A.M. – Noon8:00 A.M. – 9:00 P.M.

Weekdays except Holidays

6:00 P.M. – 11:00 P.M.

Weekdays except Holidays

Off-Peak

11:00 P.M. – 8:00 A.M.

6:00 A.M. – 8:00 A.M.

Weekdays except Holidays

9:00 P.M. – Midnight Weekdays except Holidays

Midnight – Midnight 6:00 A.M. – Midnight Weekends and Holidays

Super-Off-Peak

Not Applicable Midnight – 6:00 A.M.Weekdays, Weekends & Holidays

Page 43: SOUTHERN CALIFORNIA EDISON SM SCE Solar PV Program California Public Utilities Commission Workshop July 31, 2009.

SOUTHERN CALIFORNIA EDISON

SM

Page 43SCE Solar PV Program – CPUC Workshop

Payment Calculation (Cont.)

Energy Payment Allocation Factors

Season TOU PeriodCalculation

MethodEnergy Payment Allocation Factor

Summer

On-Peak Fixed Value 3.13

Mid-Peak Fixed Value 1.35

Off-Peak Fixed Value 0.75

Winter

Mid-Peak Fixed Value 1.00

Off-Peak Fixed Value 0.83

Super-Off-Peak

Fixed Value 0.61