Some electrical connection design issues for offshore wind farms Paul Gardner, Helen Snodin, & Nigel...
-
Upload
spencer-wells -
Category
Documents
-
view
217 -
download
5
Transcript of Some electrical connection design issues for offshore wind farms Paul Gardner, Helen Snodin, & Nigel...
Some electrical connection design issues for offshore
wind farms
Paul Gardner, Helen Snodin, & Nigel Scott
Garrad Hassan and Partners
Presentation Rationale
Most UK projects quite advanced Grid connections and costs known
Issues of design choices Unknowns ?
Electrical Design
Can be split into 3 key areas:
Offshore array Transmission to shore Grid connection
will concentrate on the latter two.
Some Electrical Design Issues
Subsea vs land cable 33kV vs 132kV transmission to shore Export security
Parallel 132/33kV transformers Teed vs looped vs busbar connections
Grid Code changes
Electrical Design Diagram
Wind turbine
Other wind turbines
33kV cableonshore
33kV cableto shore
132/33kVtransformer132kV switch
circuit breaker
Offshore transformationto 132kV or continue at33kV ?
Arrangement ofoffshore array ?
Onshore Offshore
Continue withsubmarine cableonshore ?
Single or doubletransformerarrangement ?
Tee or loopconnection ?
Existing 132kVgrid line
132kV cable
33kV submarine cablewithin array
Wind turbinetransformer
Subsea vs Land Cables Offshore
33kV - use either EPR submarine cables or XLPE cable with additional waterproofing
132kV - use XLPE cables Better electrical insulator Sealed in watertight lead sheath - not land cable !
OnshoreSubsea cables can be used but only worth considering
for short and simple routes.Key issues are costs and practicability
33kV vs 132kV Transmission to Shore
Highest CostItem 132kV 33kVCable £Cable installation £Power losses £Substation £Power factor correction £O&M £Other costs / risks £
Export Security Teed vs Loop vs Busbar connections
Capital cost vs improved export security against grid faults, operations and maintenance outages
E.g. 100MW at £0.035/kWh and 35% load factor
Cost of Lost Production Time£1.2k 1 hour£29k 1 day
£206k 1 week£412k 2 weeks
Export Security - Tee & Loop
Wind farm
Circuitbreaker/switch
Existing grid line
Tee connectionarrangement
Loop connectionarrangement
Export Security Single or double 132/33kV transformers One transformer = all eggs in one basket Two transformers
Extra capital cost Improved security against transformer failure
new transformer or repairs could take months failure rates are low reduced export depending on transformer rating
Higher O&M costs
Grid Code Changes
Compliance in full or in part mandatory New Grid Code due in 2002 Possible requirements
Control of real and reactive power Frequency response Voltage regulation Stability
Implications - more cost ?
Summary
Impossible to cover all the issues, design choices and best practices
Hopefully raised awareness of one or two issues
The answers are often project specific