Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU...

21
Solenoid Status Paul Brindza Dec. 12, 2003

description

Status of work at IUCF Solenoid R&R is based on a MOU between JLAB and IUCF The MOU divides the work into three Phases and a pause. Phase zero is measurement and investigation. This includes electrical measurements on each coil, instrumentation checkout, leak testing and pressure testing and mechanical measurements of the shields in coils 1 and 4.

Transcript of Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU...

Page 1: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Solenoid Status

Paul Brindza Dec. 12, 2003

Page 2: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…
Page 3: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Status of work at IUCF

 • Solenoid R&R is based on a MOU between JLAB and IUCF

• The MOU divides the work into three Phases and a pause. • Phase zero is measurement and investigation.

• This includes electrical measurements on each coil, instrumentation checkout, leak testing and pressure testing and mechanical measurements of the shields in coils 1 and 4.

Page 4: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Status of work at IUCF

• Phase one includes the rework of all four coils and final testing and evacuation.• This includes replacement of the LN2 shields, repair of instrumentation and other

internal work • The pause is to allow time for getting the Model 2800 Helium refrigerator

operational • Phase two includes the replacement of "puffing billy" and the reassembly of the

solenoid, new controls and instrumentaion and mating with the new power supply. • At present Phase zero is near completion.

Page 5: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Phase zero measurements and results 

Coil electrical measurementsCoil # Across

CoilLH Lead - Ground

RH Lead - Ground

1 4.9 O 2.2 O 6.4 O

2 3.2 O OPEN OPEN

3 2.7 O 2.6 O 0.2 O

4 5.2 O OPEN OPEN

Page 6: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Coil Inductances

•  • Coil 1 Coil 2 Coil 3 Coil 4•  • 372 mH 244 mH 172 mH 763 mH

Page 7: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Internal instrumentation and voltage taps

• Each coil has voltage taps (VT) and Carbon Resistance Thermometers (CRT) in the Helium vessel and Thermalcouples (TC) on the N2 shield and strain gauges (SG) on the support posts.

Coil 1 Coil 2 Coil 3 Coil 4  VT OK OK OK OK  CRT 7 of 8 OK OK OK 4 of 7 OK  TC OK OK OK OK  SG 3 of 6 OK 2 of 6 OK OK 3 of 6 OK

Note: coil 4 has some extra CRT’s in unknown locations.

Page 8: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Leak testing and pressure testing

 

N2 Shield He Vessel External Pressure tests Coil one 5 x 10 ^ -5 OK 12 inch bellows OK Coil two OK 2 x 10 ^ -6 OK OK Coil three 4 x 10 ^ -5 OK 12 inch bellows OK Coil four 4 x 10 ^ -6 OK OK OK

Leak rates in torr-liter per second

Page 9: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…
Page 10: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…
Page 11: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…
Page 12: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Ongoing work for Phase zero

 • Coils 1, 3 and 4 have been evacuated , backfilled dry and sealed. • A search is on for the Helium leak in coil 2

• The N2 shield has been removed to provide access• The He vessel has been pumped to reduce background• The He vessel will also be pressurized and "sniffed"• The leak will be repaired by welding when found• During the leak investigation further tests to locate the probblems with

the strain gauges have been performed

Page 13: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Ongoing work for Phase zero

• All four coils have had conflat flanges added to all internal connections to permit high quality leak testing and to permit future connections without "cut and weld".

 • The two damaged and leaky 12 inch bellows will be replaced. • Attempts to repair have proven to be temporary • The model 2800 helium refrigerator is indoors and is being prepped for shipment to JLAB• The JLAB cryo group will perofrm a thorough checkout , some updating and a dry run• To test the turbines. • The new N2 shield design based on field measurements of coils 1 and 4 and original drawings is

being finalized at JLAB in consultation with the manufacturer.• The N2 coolant flow for the new shields has been evaluated.• Potential modification to the "cake pan" coil covers is being evaluated with IUCF to provide

better clearance for assembly and insulation

Page 14: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Cake Pan ModificationsCake Pan Modifications

Cross section of coil 2,3,4

Page 15: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Status of Phase one

 • A Scope of Work (SOW) and Purchase Requisition (PR) have been prepared• The SOW and PR have been circulated at JLAB for signature• Final approval is awaiting CD-0• The SOW has been sent to IUCF for comment. • The Scope of Work includes the complete R&R of all four coils.• This includes replacement of the LN2 shields, repair of any leaks, repair (if

possible) of instrumentation, final evacuation and leak test, pressure test and dry storage until Phase two

Page 16: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Magnetic simulations of the upstream hole and an iron plug with varying gaps

• .

Page 17: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Bmod over a patch (-5 < Z < 80 , 10 < R < 80 inches)4 inch gap , max field .208 T , Integral B.dA = 132 Tesla inch^2

Page 18: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Bmod max on patch upstreamBmod max on an upstream patch

0

500

1000

1500

2000

2500

3000

3500

0 1 2 3 4 5 6 7 8

gap inches

gaus

s Bmod max thick plug

Bmod max Big Hole

Bmod max Thin plug

Page 19: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Integral Bmod over patch upstream

Integral Bmod.dA over an upstreampacth

0

50

100

150

200

250

0 1 2 3 4 5 6 7 8

gapinches

Tesl

a in

ch^2 Int Bmod.da thick plug

Bmod.dA Big hole

Int Bmod thin plug

Page 20: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Bmod on patch with big hole

Page 21: Solenoid Status Paul Brindza Dec. 12, 2003. Status of work at IUCF Solenoid R&R is based on a MOU between…

Bmod on upstream patch 4 inch gap with thin plug