Solar Power Plant Development
By Mr. Phongsakorn Damnoen
Gunkul Powergen Co., Ltd.
November 04 , 2010
1. VSPP Privilege
VSPP Program for Solar Energy
Supplied to PEA incase of power output
lower than 10 MW
45 days approval period after
completion of application
PPA automatically extend 5 years unless
breach or power producer decided to
terminate PPA
Adder fixed but tariff subject to change
Adder program : +8 baht/kWh @ 10 yrs
Other Privilege
BOI privilege for investment:
BOI defines a focused industry for PV industry so then…..
8 years full income tax exemption
Another 5 years of 50% income tax exemption
No import tax for machine
No import tax for material
BOI document must be submitted & register before Dec 31,2012
THB/KWh On Peak Off Peak
Base Tariff 2.93 1.12
Fuel Tariff 0.92 (as of Jan, 09) 0.92 (as of Jan, 09)
Adder (fixed) 8.0 (10 years from COD) 8.0 (10 years from COD)
Total Baht/kWh 11.85 (0.359 USD/kWh) 10.04 (0.304 USD/kWh)
2. Site Selection
Main Concern
Radiation: > 5 kWh/m2/day
Price: < 100,000 THB/rai
No back fill required
Near by 22 kV, 33 kV line
Near by main road
Not locate in the green zone
Not in flood area
Not far from the water resource
3. Module Selection
Photovoltaic
Thin FilmCrystalline Silicon
Compound
(CIS)
A-SiliconMonoPoly
Degradation
Temperature Co-effi.
Module Efficiency
Shadow Tolerance
Performance Ratio
Investment Cost
Note: Very good Fair
3. Module Selection
Source: ̀ Information f rom manufacturer
-35.0%
-30.0%
-25.0%
-20.0%
-15.0%
-10.0%
-5.0%
0.0%
5.0%
10.0%
15.0%
20.0%
-5℃ 5℃ 15℃ 25℃ 35℃ 45℃ 55℃ 65℃ 75℃ 85℃
CIS
Polycrystalline
a-Silicon
Frigid Zones
Tropical Zones
Change in Efficiency
Temperature
3. Module Selection
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
a- Sil icon
Polycrystalline
Compound (CIS)
Output (MWh)
Years
Source: ̀ Information f rom manufacturer
3. Module Selection
0
50
100
150
200
250
300
350
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29
Crystalline Silicon Compound (CIS)
8.8%
Accumulated Output (kW-h)
Source: EGAT
4. Inverter Selection
Main Concern
Type: String, Central
Capacity: 10 kW – 1 MW
Performance: > 98%
Reference
Warranty Guaranty
Price
Monitoring System
Comply with PEA grid code
Others function LVRT
5. Simulation
Software simulation: PVSYST
Put coordinate
Put PV Module
Put Inverter
Put others parameter
6. Risk Management
Thailand is a good location for solar
farm given intensive solar radiation
and should be able to yield good
solar output
50% of the total area receives an
annual average solar radiation of 18
-19 MJ/m2 – day, which are
considered relatively high
GUNKUL has carefully selected proven
technology and manufacturers f rom
Solar Frontier which has an established
record
Solar Frontier as a supplier for solar
modules, and Schneider, as a
manufacturers for equipment relating to
the transformation of electric current,
provides 5 years bond guaranteeing the
performance of their equipment
GUNKUL has already secured PPA
contract f rom PEA
PPA defines a series of operating
characteristics in terms of start up
and shut down times, loading and
deloading rates
PEA guarantees that it will
purchase all electricity generated
from the farm under the contract
1. Raw Material 2. Technology 3. Offtaker
7. Contract agreement
ElectricityDebt Funding
• Total financing of THB 315
mn with interest rate of MOR – 1.5%, repayment 93 months
• Collateral: Land and
equipment of project
• Guaranteed by GUNKUL
• Key Covenant: GUNKUL maintain stake at least 75%
VSPP Non-firm PPA
with PEA Loan Agreement
• Tenor 5 years with automatic
extension of 5 years, which can only be terminated by
seller, GPG
• COD within 2 years of signing
of PPA, which in practice can
be extended if the seller can prove that they are committed
to investing in the project
• Non – firm contract because
seller cannot control sun light therefore cannot determine
when to generate electricity to
grid