Solar Power Plant Development - tesia-thailand.com · Solar Power Plant Development By Mr....

23
Solar Power Plant Development By Mr. Phongsakorn Damnoen Gunkul Powergen Co., Ltd. November 04 , 2010

Transcript of Solar Power Plant Development - tesia-thailand.com · Solar Power Plant Development By Mr....

Solar Power Plant Development

By Mr. Phongsakorn Damnoen

Gunkul Powergen Co., Ltd.

November 04 , 2010

1. VSPP Privilege

VSPP Program for Solar Energy

Supplied to PEA incase of power output

lower than 10 MW

45 days approval period after

completion of application

PPA automatically extend 5 years unless

breach or power producer decided to

terminate PPA

Adder fixed but tariff subject to change

Adder program : +8 baht/kWh @ 10 yrs

Other Privilege

BOI privilege for investment:

BOI defines a focused industry for PV industry so then…..

8 years full income tax exemption

Another 5 years of 50% income tax exemption

No import tax for machine

No import tax for material

BOI document must be submitted & register before Dec 31,2012

THB/KWh On Peak Off Peak

Base Tariff 2.93 1.12

Fuel Tariff 0.92 (as of Jan, 09) 0.92 (as of Jan, 09)

Adder (fixed) 8.0 (10 years from COD) 8.0 (10 years from COD)

Total Baht/kWh 11.85 (0.359 USD/kWh) 10.04 (0.304 USD/kWh)

2. Site Selection

Main Concern

Radiation: > 5 kWh/m2/day

Price: < 100,000 THB/rai

No back fill required

Near by 22 kV, 33 kV line

Near by main road

Not locate in the green zone

Not in flood area

Not far from the water resource

2. Site SelectionChondan Petchaboon

3. Module Selection

Photovoltaic

Thin FilmCrystalline Silicon

Compound

(CIS)

A-SiliconMonoPoly

Degradation

Temperature Co-effi.

Module Efficiency

Shadow Tolerance

Performance Ratio

Investment Cost

Note: Very good Fair

3. Module Selection

Source: ̀ Information f rom manufacturer

-35.0%

-30.0%

-25.0%

-20.0%

-15.0%

-10.0%

-5.0%

0.0%

5.0%

10.0%

15.0%

20.0%

-5℃ 5℃ 15℃ 25℃ 35℃ 45℃ 55℃ 65℃ 75℃ 85℃

CIS

Polycrystalline

a-Silicon

Frigid Zones

Tropical Zones

Change in Efficiency

Temperature

3. Module Selection

2,000

2,500

3,000

3,500

4,000

4,500

5,000

5,500

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

a- Sil icon

Polycrystalline

Compound (CIS)

Output (MWh)

Years

Source: ̀ Information f rom manufacturer

3. Module Selection

0

50

100

150

200

250

300

350

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29

Crystalline Silicon Compound (CIS)

8.8%

Accumulated Output (kW-h)

Source: EGAT

4. Inverter Selection

Main Concern

Type: String, Central

Capacity: 10 kW – 1 MW

Performance: > 98%

Reference

Warranty Guaranty

Price

Monitoring System

Comply with PEA grid code

Others function LVRT

5. Simulation

Software simulation: PVSYST

Put coordinate

Put PV Module

Put Inverter

Put others parameter

6. Risk Management

Thailand is a good location for solar

farm given intensive solar radiation

and should be able to yield good

solar output

50% of the total area receives an

annual average solar radiation of 18

-19 MJ/m2 – day, which are

considered relatively high

GUNKUL has carefully selected proven

technology and manufacturers f rom

Solar Frontier which has an established

record

Solar Frontier as a supplier for solar

modules, and Schneider, as a

manufacturers for equipment relating to

the transformation of electric current,

provides 5 years bond guaranteeing the

performance of their equipment

GUNKUL has already secured PPA

contract f rom PEA

PPA defines a series of operating

characteristics in terms of start up

and shut down times, loading and

deloading rates

PEA guarantees that it will

purchase all electricity generated

from the farm under the contract

1. Raw Material 2. Technology 3. Offtaker

7. Contract agreement

ElectricityDebt Funding

• Total financing of THB 315

mn with interest rate of MOR – 1.5%, repayment 93 months

• Collateral: Land and

equipment of project

• Guaranteed by GUNKUL

• Key Covenant: GUNKUL maintain stake at least 75%

VSPP Non-firm PPA

with PEA Loan Agreement

• Tenor 5 years with automatic

extension of 5 years, which can only be terminated by

seller, GPG

• COD within 2 years of signing

of PPA, which in practice can

be extended if the seller can prove that they are committed

to investing in the project

• Non – firm contract because

seller cannot control sun light therefore cannot determine

when to generate electricity to

grid

Annex

Public Hearing

Annex

Public Hearing

Annex

Site Preparation

Annex

Site Preparation

Annex

Foundation and Supporting Structure

Annex

Foundation and Supporting Structure

Annex

Solar Module Installation

Annex

Solar Module Installation

Annex

Solar Module Installation

Annex

Solar Module Installation