SOFTWARE PACKAGES Status and commissioning plans
description
Transcript of SOFTWARE PACKAGES Status and commissioning plans
![Page 1: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/1.jpg)
1
SOFTWARE PACKAGES
Status and commissioning plansD.Jacquet with input from : V.Baggiolini, J.C.Bau,
M.Buttner, S.Deghaye, G.Kruk, C.Roderick, K.Sigerud, W.Sliwinski, J.Wenninger, J.Wozniak, M.Zerlauth
![Page 2: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/2.jpg)
2
Software during LS1 : a large working site
3 years of LHC operation– issues or limitations discovered– new requirements from operational experience– Short technical stops : Issues and requests addressed not
necessary in the cleanest way• Short time for the implementation• Only non-breaking changes allowed
– Outside CERN the software world is moving fast
Long shut-down: enough time for major upgrade – Catch-up on major third party libraries– Non backward compatible modifications are allowed
• Clean-up, implementation of new functionality• Implementation of the necessary adaption from the users
Evian 2012: beam based systems, what we want.
![Page 3: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/3.jpg)
3
Scope
What is happening in the control side during LS1– Major upgrade of core systems– Ameliorations, new functionality of operational applications– New projects– No time to mention in detail all the LS1 controls activities
![Page 4: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/4.jpg)
4
User written
Middleware
Central services
Physical Devices (BI, BT, CRYO, COLL, QPS, PC, RF, VAC, …)
Java Control Programs
RDA Client API (C++/Java)Device/Property Model
DirectoryService
ConfigurationDatabase
CCDB
VB, Excel, LabView
ServersClients
Virtual Devices(Java)
PS-GMServer
FESAServer
FGCServer
PVSSGateway
C++ Programs
MoreServers
Administrationconsole
Passerelle C++
CMW InfrastructureZeroMQ
RDA Server API (C++/Java)Device/Property Model
RBAC A1Service
DirectoryService
RBAC Service
JAPC API
CMW integr. CMW int. CMW int.CMW int.CMW int. CMW int.
Upgrade in LS1
CMW upgrade
![Page 5: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/5.jpg)
5
User written
Middleware
Central services
Physical Devices (BI, BT, CRYO, COLL, QPS, PC, RF, VAC, …)
Java Control Programs
RDA Client API (C++/Java)Device/Property Model
DirectoryService
ConfigurationDatabase
CCDB
VB, Excel, LabView
ServersClients
Virtual Devices(Java)
PS-GMServer
FESAServer
FGCServer
PVSSGateway
C++ Programs
MoreServers
Administrationconsole
Passerelle C++
CMW InfrastructureZeroMQ
RDA Server API (C++/Java)Device/Property Model
RBAC A1Service
DirectoryService
RBAC Service
JAPC API
CMW integr. CMW int. CMW int.CMW int.CMW int. CMW int.
Upgrade in LS1
RDA renovation (RDA2 RDA3):• Functional limitations seen during operation : impossible to improve with
current implementation (management of bad clients, client number scalability, lack of flexibility for new development)
• RDA3 include new requirements: -priority system for the clients - improvement of the subscription
mechanism- new data structure supported (i.e. nDim
array)
![Page 6: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/6.jpg)
6
CMW upgrade: current status
• RDA3 deployed in operation for FGCD gateway in PSB & Linac2, soon in CPS
• June 2014: release of FESA3 v. 2.0.0 with RDA3
• RDA2 will be maintained until LS2
Responsible : W.Sliwinskiweb site https://wikis.cern.ch/display/MW/CMW+-+Controls+Middleware
![Page 7: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/7.jpg)
7
FESA 3• Main technical motivation: FESA3 supports
multicore CPU. First version was available on 07/2013
• All known important issues solved• Status
– Many critical systems are planned to restart with FESA3 (i.e. QPS, Cryo, Collimators, kickers, power converters…) and have started the migration
– Some stay with FESA 2 and will do the migration later (i.e BIS, most of the BI and RF systems)
• FESA2 will be supported until end of 2015
Responsible : S.Deghayeweb site https://wikis.cern.ch/display/FESA3/Home
![Page 8: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/8.jpg)
8
• With operational experience, many new requirements and fixes have been implemented on top of the first design
• LSA extended (INCA) to PS complex to renovate their control system
LSA refactoring : Motivations
• API complexity increased, difficult to stay flexible and add new functionality
• Clean-up and refactoring needed!
![Page 9: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/9.jpg)
9
LSA refactoring : what has changed?
• Simplification of the software structure reduction of the number of modules
• Services API : organized in a more coherent way, less exposed methods
• Common concepts have been factored out to a generic package, to facilitate reuse (i.e. Introduction of common domain objects)
![Page 10: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/10.jpg)
10
LSA will be easier to maintain and to extend
All software using LSA needs to be adapted to the new API – not a trivial and simple task, quite time consuming– Wiki provided by LSA team with full documentation
• https://wikis/display/LSA/LS1+refactoring+of+client+controllers+and+Domain+objects
LSA refactoring : consequences
![Page 11: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/11.jpg)
11
New LSA version released as pro in March 2014
Most of the operational applications have been released with new LSA version
LSA core is now being tested and debugged with the injector start-up and the LHC dry runs
LSA refactoring : status
Responsible : G.Krukweb site https://wikis.cern.ch/display/LSA/Home
![Page 12: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/12.jpg)
12
The same team supports LSA/INCA on 8 machines (support for operation and for developers)
Requests are addressed in order of priority as all requests cannot be satisfied at once
OP has to help define the priorities
LSA/INCA support
![Page 13: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/13.jpg)
13
LSA Database Performance problems in 2011/2012 with
access of LSA settings
Actions during LS1– Replacement of the hardware : new CPU, new disk,
much bigger DB cache: faster access to the data– Cleaning of the data
• Keep only the last operational settings (p/p, Pb/Pb and Pb/p)
• Read only LSA database with frozen settings on April 2013. Not converted to the new LSA design, old version of LSA software available to access the data.
Evian 2012: « beam based systems, what we want »
![Page 14: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/14.jpg)
14
Devices and properties configuration
CCDBNew classesNew, renamed devicesNew renamed propertiesMigration FESA2 FESA3
LSA DBConfiguration to be updated
New devices or backward compatible changes :• straight-forward, automatic process
under developmentNon backward compatible changes with setting to keep:• Migration map needed• Not immediate process, several
iteration may be needed
Procedures: https://wikis/display/config/User+info
![Page 15: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/15.jpg)
Renovation of LHC central timing
Hardware and software upgrade (simpler design with a single front-end, Linux SLC5, FESA3)
Status– New protocol ready in CBCM, to be implemented in LHC
CT– The deployment of the LHC central timing is foreseen
the 27th of October to be ready for the LHC dry run scheduled the first week of November.
LHC Central Timing
New protocol for injection request• Solves the dynamic destination issue• Simpler, secure and more flexible, allows to inject
later in the SPS
CBCM
15Responsible : J.C. Bauweb site https://wikis.cern.ch/display/HT/Timing+Software
![Page 16: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/16.jpg)
16
Logging : SDDS eradication
For simplification and maintainability reasons: SDDS logging replaced by full Parameter Logging in the Measurement & Logging databasesSTATUS• Parameter Logging is fully operational : configured for
~8000 devices• SDDS based logging service disabled
Old SDDS data can be transferred to Logging database on requestResponsible : J. Wozniak
web site https://wikis.cern.ch/display/CALS/CERN+Accelerator+Logging+Service
![Page 17: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/17.jpg)
17
DiamonRecurrent complaint: difficult to get the real
status of a process or front-endSoftware improved during LS1, but
configuration effort needed (OP, front end resp in equ. groups)– Limits adjustment now possible from the GUI (CPU
load, memory, temperature)– Any problem has to be reported by OP for correction– Missing detection and control points to be added by
developers– During cold check out : make sure the configuration
is correct for all servers before the start-upResponsible : M.Buttnerweb site https://wikis.cern.ch/display/ADM/Home
![Page 18: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/18.jpg)
18
Connection viewer
New application that complements diamon information – Dynamically retrieve and
visualize dependencies between CO processes
– Great help for diagnostic– Web site with demo:
https://wikis/display/ACET/ACET+Connections+ViewerCo
nsol
eM
iddl
e Ti
erFr
ont-e
nd
Courtesy Gergo Horanyi
![Page 19: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/19.jpg)
19
Alarms Not usable mainly due to configuration problem– To many alarms sent from the equipment– Configuration by beam mode available but not used
Strategy for the start-up‒ Remove all alarms from LHC OP configuration‒ OP with the equipment's responsible and the LASER team :
select useful alarms and add them to the configuration
![Page 20: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/20.jpg)
20
New QPS software kit
QPS software kit for operators and piquet teams to perform basic and safe operations, i.e.
QPS ‘Swiss knife’, to display & verify config parameters(Coutersy M.Zerlauth)
Power cycling of QPS crates (replacing existing LabView application)
QPS configuration management• using standard LSA settings
management + RBAC• New sequencer tasks for
systematic settings consistency checks is needed
![Page 21: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/21.jpg)
21
Online model project
Taken over by ABP – Aperture measurement application will be reviewed
for November– Many ideas of different tools useful for machine
setup and model improvements– Requirement, needs and priorities have to be
reviewed, and resources gathered
Knob and optic upload part are taken over by OP
![Page 22: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/22.jpg)
22
Knobs and optics upload
The optics uploader have been rewritten : – PERL script replaced by a java API for optic and
elements upload in LSA– user Interfaces to compare MADX and LSA optics and
elements– Same application can be used in injectors
New Knob application– based on the two existing applications– Include new functionality to facilitate the management
of knobs (i.e. add or remove components from a knob)
![Page 23: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/23.jpg)
23
Heat load display Heat load : concern for operation at 25ns
Heat load monitoring will help maximising the scrubbing efficiency
New cryo heat load display is under development– Data extracted from the logging DB and heat load computed– Timber used for the display for the moment– Fixed display in the control room based on timber data will
be developed for the start-up
bu/bu energy loss measurement from RF phase : development to start soon
![Page 24: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/24.jpg)
24
New features on ACCTEST (Accelerator Test framework) –HWC tests
Automatic test analysis based on Java DSL directly in Acctesting– All sequence + analysis steps for
HWC of 60A and120A circuits will be fully automated (need expert only in case of doubt or problem)
– Gradually automated analysis will be extended to more complex circuits
– Time + dependability gained for HW commissioning
Output of automated test for 60A orbit corrector
New analysis modules are conceived in generic way to run systematically after any circuit failure, not only on predefined current cycles as used for HWC • Circuits checked regularly during beam operation• Higher chance of timely discovery of problems!
![Page 25: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/25.jpg)
25
Logging Data Extraction API renovation
API used by Timber application (+115 custom user apps)
Refactoring and cleaning done during LS1(previous API had evolved over 10 years)
Paving the way for adding new functionality, particularly in the area of data analysis:– Extraction from multiple sources : logging, LSA settings,
logbook, post mortem, new PVSS DBs…– Possibility to store analysis results related to events in the past– Increased data aggregation and alignment options– Extracting data based on other signals– Data value distribution analysis and histograms– Extraction of vector elements over time as time series
![Page 26: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/26.jpg)
26
Accelerator Statistics & Data Analysis
Coherent and maintainable solution for accelerator statistics– Common implementation for all accelerators– new interactive Web interface with accelerator statistics
displays (replacing current statistic web pages for LHC, SPS, and PS Complex)
Status– Accelerator Statistics are on track
• PSB data is being collected• Data specifications are on-going for other machines• Web interface development will start in July
– General Data analysis:• Requirements are foreseen to be integrated into Logging
Extraction API (previous slide), further input is welcomeResponsible : C.Roderickweb site: https://wikis.cern.ch/display/DAS
![Page 27: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/27.jpg)
27
Actual system (mainly logbook and PM)– Tools allow only partial fault tracking (first fault and dump only)– No commons rules inside OP and in equipment
groups for the fault definition– Fault analysis difficult and incomplete
New Accelerator Fault Tracking project– Common solution for all accelerators– Automate as much as possible (link with Post mortem, logging
and logbook)– Functionality to highlight inconsistencies or missing information– Will greatly facilitate fault follow-up, update, and analysis– Someone still needs to take responsibility for data completion
Accelerator Fault Tracking
EVIAN 2012 : 2012 AVAILABILITY (B.TODD)
![Page 28: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/28.jpg)
28
Fault Tracking : StatusPrototype databaseData from previous years uploaded from the logbook
Courtesy Chris Roderick
![Page 29: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/29.jpg)
29
Fault Tracking : Status
Persistence API under development
Courtesy Chris Roderick
![Page 30: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/30.jpg)
30
Fault Tracking : Status
User interfaces mock-upsUse cases definition
Courtesy Chris RoderickWeb site : https://wikis.cern.ch/display/AFT
![Page 31: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/31.jpg)
31
Other useful information• Post mortem : New version of PM client library based on RDA3 is
ready• BIS: refactoring & cleaning + new cycle GUI for fast cycling
machines, will include gradually functionalities from Jorg’s applications + new requests (hidden interlocks, …)
Power converter interlock GUI : new reference system with tolerances based on functions
New orbit reference system: automatic configuration will be implemented
Console manager : new GUI for menu configuration, mode dependent display of the applications for the start-up
Sequencer : cleaning of the sequences and tasks, sub-sequence with parameters implemented
A process for automatic start of the abort gap cleaning will be developed
![Page 32: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/32.jpg)
32
Conclusion Developers have been very busy during LS1,
a lot has changed at every software layer The core software that is common to the
accelerator complex will be largely tested and debugged with the injector start-up
LHC dry-run that already started will track as much bugs and issues as possible well before the start-up
Still a lot to do in the coming months, but no major problem anticipated!
![Page 33: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/33.jpg)
Reserved slides
![Page 34: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/34.jpg)
34
Interlocks• BIS
– Refactoring mainly for code cleaning– BIS GUI will be extended to include the views developed by
Jorg and little by little all their functionality like group masking, hidden interlocks etc…
• SIS– RBAC protection added– New simpler language for the configuration (DSL), but xml
can still be used– Development of the user documentation (https://
wikis/display/SIS/User+Manual)– New hardware more powerful for LHC&SPS instances.
![Page 35: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/35.jpg)
35
Power converter interlock GUI
LHC correctors current
REF +/- Fixed Tolerance
SIS interlock
Fixed tolerance not flexible enough• Replace by tolerance function parameters• Makerules and value generator to be defined
Later extend to other power converters.
![Page 36: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/36.jpg)
36
Console manager: new features• New easy tool for menu configuration will be
developed for end of 2014
• Automatic update of the console manager in all consoles will be ready this summer
• Hide or show fixed display according to beam mode: will be ready for next start-up
![Page 37: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/37.jpg)
37
• base reference orbit0
YASP: reference orbit management
Reference orbit
base reference orbit from measurements and corrections with all separation and crossing bumps to 0
Overlaystheoretical beam position calculated by JMAD from active optic and crossing and separation bumps value
![Page 38: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/38.jpg)
38
YASP: reference orbit management
• For each beam process : manual preparation of the reference orbits
• Will become laborious if we have ramp and squeeze or collide and squeeze beam processes
• New reference system will be implemented– Automatic reference generation using LSA settings
(separation and crossing bump, optics) and JMAD– Should be ready for the start-up
![Page 39: SOFTWARE PACKAGES Status and commissioning plans](https://reader035.fdocuments.in/reader035/viewer/2022062812/568163e4550346895dd543ef/html5/thumbnails/39.jpg)
39
Post Mortem• New version is ready, adapted for RDA3. Old
version still available. Transparent for users.
• Adaptation of the analysis modules to the new format of data sent by some equipment (BLM + QPS that goes to standard PM format instead of binary files).