Transcript of Snapshot of achieved work within the GREDOR project.
Sunday 30 June 13
GREDOR Gestion des Réseaux Electriques de
Distribution Ouverts aux Renouvelables
Presentation and snapshot of achieved work
FLEXIPAC meeting Bertrand Cornélusse, University of Liège
December 2014
1
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables2
P L A N I N V E S T M E N T S
P L A N O P E R A T I O N S
REAL-TIME CONTROL
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables3
DSO Consumer TSO
Retailer BRP ProducerBSP
P L A N I N V E S T M E N T S
P L A N O P E R A T I O N S
REAL-TIME CONTROL
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Main GREDOR aims
Study investment planning, operational planning and real-time control strategies from a functional perspective - what do we want to aid? - from a computational perspective - how do we optimise the decisions? - and from an organisational perspective - how do system actors interact?
We build IT tools to do so. These tools plugged into a simulation framework provide quantified recommendations for system evolution.
4
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Project partners
5
Sunday 30 June 13
Funded by
Started in January 2013
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
General process
6
Prequalification
Global Capacity ANnouncement
Investment
Flexibility procurement
Flexibility notification
Flexibility Activation
Operational planning
Real-time control
Settlement
Long term
Short term
Very short term
ex post
DSO & TSO All stakeholders
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Global Capacity Announcement
7
Prequalification
Global Capacity ANnouncement
Investment
Flexibility procurement
Long term
DSO & TSO All stakeholders
Questions •What to publish, who to?•is base case actual system or with foreseen investment?
Goals:•estimate & communicate capacity of network through a set of indicators•incentivise connections in good locations from network’s perspective•incentivise flexibility service in good locations
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux RenouvelablesGREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
GCAN example: generation connection
8
New connections
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
GCAN computation results
9
Active Network Management aspect not considered:
Flexible connectionFirm connection
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Operational planning
10
Prequalification
Flexibility notification
Operational planning
Real-time control
Short term
Very short term
Long term
Available controls:•reconfiguration•flexibility contracts•storage•regulation devices
Goals:•take preventive actions to have the system in a
secure state in real time, •with sufficient controls to maintain it there in RT• Trade off preventive versus corrective actions.
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Operational planning example
11
Voltage magnitude
Power injection
Power off take
Curtailed
Modulated
Now24h ahead
Current magnitude
Instantaneous cost
Now24h ahead
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Operational planning = Active Network Management
12
31/10/14 17:42Active Network Management Benchmark
Page 1 of 4http://www.montefiore.ulg.ac.be/~anm/
ANM Benchmark.In order to promote the development of computational techniques
for Active Network Management (ANM), we propose a test
instance of a generic ANM problem. It can be used as a test bed for
comparing existing computational techniques, as well as for
developing new ones.
3
Intro Material Team
http://www.montefiore.ulg.ac.be/~anm/
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
X
GREDOR - Distribution Network SimulatorGREDOR - Distribution Network SimulatorEngine for the Quantitative Analysis of Regulatory Frameworks in Distribution Networks
Instance Server
Parameters
Simulate
Additional parameters
58f44b10 - day 167
Date Tue, 21 Oct 2014 15:30:40 GMT
Title Day 167
Network bus75
Production 25 MW mean
50 MW max
100 % of flexibility
-55 €/MWh cost
Consumption 5 MW mean
9.2 MW max
20 % of flexibility
60.5 €/MWh benefits
Energy prices 47.45 €/MWh mean
82.3 €/MWh max
Day 167 to 167
.
. . . . . . . .
.
.
.
.
.
.
.
. .
.
.
. .
.
. .
. .
.
.
.
. .
.
. .
. .
.
.
.
. .
.
. .
. .
.
. .
.
.
.
. .
.
. .
. .
.
. .
.
. .
.
. .
. .
.
. .
.
.
1000
1100
1101
1102
1103
1104
1105
1106
1107
1108
1109
1110
1111
1112 1113
1114
1115
1116
1117
1118
1119
1120
1121
1122
1123
1124
1125
1126
1127
1128
1129
1130
1131
1132
1133
1134
1135
1136
1137
1138
1139
1140
1141
1142
1143
1144
1145
1146
1147
1148
1149
1150
1151
1152
1153
1154
1155
1156
1157
1158
1159
1160
1161
1162
1163
1164
1165
1166
1167
1168
1169
1170
1171
1172
1173
1174
1175
~ ~ ~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Quantitative analysis
13
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Simulation process (just an overview)
14
Sunday 30 June 13
Figure: General view of the future implementation. 5/5
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
Example of results
15
Model 0 Model 1 Model 2 Model 3
min mean max min mean max min mean max min mean max
Welfare Euro -6697 30400 67922 5697 31462 67922 5697 31438 67922 5697 31559 67974
Shedding costs Euro 0 1108 32524 0 132 9702 0 151 9702 0 12 2532
DSO costs Euro 0 0 0 0 59 3218 -52 159 8613 -0 202 8541
TSO surplus Euro 573 2284 4129 573 2284 4129 573 2284 4129 387 2266 4129
Producers surplus
Euro -10935 27521 67497 -10929 27664 67497 -10906 27760 10906 -10906 27803 67459
Retailers surplus Euro -3081 1704 15579 -3081 1704 15579 -3081 1704 15579 -3081 1704 15579
Total shed quantity
MWh 0,0 11,1 325,2 0,0 1,3 97,0 0,0 1,5 97,0 0,0 0,1 25,3
Max. imbalance MW -0,8 -3,6 -16,6 -0,8 -3,0 -15,0 -0,8 -3,2 -15,0 -0,8 -3,0 -11,0
Total imbalance MWh 5,8 36,3 348,8 5,3 30,8 194,6 5,3 31,5 194,6 5,3 30,6 196,0
Total flexibility usage
MWh 0,0 0,8 207,0 0,0 5,2 207,5 0,0 5,6 207,5 0,0 6,2 207,5
Sunday 30 June 13
GREDOR - Gestion des Réseaux Electriques de Distribution Ouverts aux Renouvelables
And many more activities
16
Investment planning☞ Tractebel engineering
Real time control☞ ULg, Pr. T. Vancutsem
Statistical models☞ UMons, Pr. J. Lobry
System data collection☞ RESAInteraction models and
qualitative analysis ☞ORES
See www.gredor.be Follow us on Twitter @GredorProject