SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health...

92
Scottish Health Technical Memorandum 2023 (Part 2 of 2) Good practice guide Access and accommodation for engineering services NHSScotland, P&EFEx, June 2001 Disclaimer The contents of this document are provided by way of guidance only. Any party making any use thereof or placing any reliance thereon shall do so only upon exercise of that party’s own judgement as to the adequacy of the contents in the particular circumstances of its use and application. No warranty is given as to the accuracy of the contents and the Property and Environment Forum Executive, which produced this document on behalf of NHSScotland Property and Environment Forum, will have no responsibility for any errors in or omissions therefrom. The production of this document was jointly funded by the Scottish Executive Health Department and the NHSScotland Property and Environment Forum. ARCHIVE

Transcript of SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health...

Page 1: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

Scottish Health TechnicalMemorandum 2023

(Part 2 of 2)

Good practice guide

Access and accommodation forengineering services

NHSScotland, P&EFEx, June 2001

Disclaimer

The contents of this document are provided by way of guidance only. Any party making anyuse thereof or placing any reliance thereon shall do so only upon exercise of that party’sown judgement as to the adequacy of the contents in the particular circumstances of itsuse and application. No warranty is given as to the accuracy of the contents and theProperty and Environment Forum Executive, which produced this document on behalf ofNHSScotland Property and Environment Forum, will have no responsibility for any errors inor omissions therefrom.

The production of this document was jointly funded by the Scottish Executive HealthDepartment and the NHSScotland Property and Environment Forum.

ARCHIVE

Page 2: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 2 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Contents

1. Introduction page 6

2. General considerations page 72.2 Development planning2.11 Working in confined spaces2.15 Fire

3. Preliminary plan areas for engineering plantrooms page 103.1 General3.3 Total engineering plan area (Figure 1)3.6 Calorifier room plan area (Figure 2)3.7 Ventilation plantroom plan area (Figure 3)3.9 Lift wells and motor rooms plan area (Figures 4 and 5)3.10 Vertical plan area (Figure 6)3.11 Water storage plan area (Figure 7)3.12 Switchroom plan area (Figure 8)

4. Engineering distribution principles page 12

5. Common distribution requirements page 135.1 General5.2 Distribution5.3 Distribution to plantroom5.9 General access5.10 Frequent access5.11 Intermittent access5.13 Renewal of services

6. Site primary service distribution space requirements page 156.1 General6.7 Ducts showing accommodation space for services, access and

working space6.12 Subways6.14 Crawlways6.16 Walkways6.18 Pipeworkdimensions6.20 Electrical tray and cabling trunking6.22 Ventilation ducts6.23 Method of spacing services6.27 Vertical ducts6.31 Ha-ha and low-level piperuns – typical arrangement6.32 Trenches

ARCHIVE

Page 3: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 3 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

6.36 Chases

7. Plantrooms page 207.1 General7.2 Ventilation plantrooms7.8 Clean and dirty extract plant7.12 High voltage sub-stations7.13 Layout7.18 Ducts7.20 Low voltage switchrooms

7.20 Sitings7.21 Layout

7.22 Electrical switchgear7.22 Located within roof level plantrooms7.23 Access and maintenance

7.24 Calorfier plantrooms7.24 Size7.25 Site7.26 Shape7.27 Height7.28 Construction7.29 Other services in the calorfier plantroom

7.30 Water storage rooms7.31 Site7.32 Shape7.33 Height7.34 Construction7.35 Other services in cistern rooms

7.36 Storage of medical pathology and industrial gas cylinders7.38 Operation considerations7.40 Cylinder store design7.42 General principles of cylinder storage

7.42 Key points7.55 Location of main cylinder storage7.62 Design and construction of main cylinder stores7.65 Security7.66 Requirements for manifolds for non-medical gases7.69 Ready use stores7.70 Medical air compression

7.70 Size7.71 Site

7.72 Medical vacuum plant7.72 Size7.73 Site

ARCHIVE

Page 4: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 4 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

7.74 Liquid Oxygen storage7.74 Safety distances7.75 Sterilizers

8. The zoning and routing of primary services in the hospitalstreet vertical shafts page 34

8.1 General8.4 Standard shaft arrangement8.5 Alternative shaft arrangement8.6 Drawings

9. Service distribution within departments page 369.1 General9.12 Structure9.14 Drainage zones9.17 Routing Drainage Systems

9.17 Main collection drains (ground level)9.19 Vertical drainage stacks9.20 Drainage vents9.23 Interfloor drainage9.26 Ground floor damage9.28 Pipework service zone

9.28 Pipe main zones9.29 Combined duct and pipe branch zone9.31 Pipe branches

9.32 Low pressure hot water9.32 Compensated temperature circuit9.35 Constant temperature circuit

9.36 Hot and cold water services9.36 Hot water service9.37 Cold water service9.39 Fire-fighting services9.41 Medical gases

9.42 Electrical sub-main9.42 Sub-main feeder cables9.43 Trunking and conduit

9.44 Ceiling zone9.47 Ventilation zones

9.48 Duct main zones9.50 Fire dampers

9.52 Electrical zones9.52 Electrical main zone9.53 Departments with 3m high ceilings9.55 Departments with 2.4m high ceilings

ARCHIVE

Page 5: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 5 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

10. Definitions page 44

Figures page 46

References page 89

ARCHIVE

Page 6: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 6 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

1. Introduction

1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 givesgeneral guidance on the space requirements for mechanical, electrical andpublic health engineering services in hospitals and provides data to assist inthe planning of those requirements. It relates services areas to hospital totalfloor areas, and assesses the space requirements and clearances of pipeworkand ventilation ductwork. Zoning principles are illustrated for a typical hospitalservices installation.

1.2 Maintenance of building services can only be carried out satisfactorily ifadequate space for access is provided. This document establishes somebasic rules and principles for the allocation of space and engineering servicedistribution in a hospital, and illustrates how a systematic approach canimprove design coordination and service installation on site.

1.3 The data given is intended to assist in ensuring that space provision for futureschemes is adequate to enable easy installation and allow convenient accessand sufficient working space for maintenance, renewal and possible extensionof the services.

1.4 The guidance in this SHTM is based on information obtained from engineersin the NHS, NHS Estates and consulting engineers, and is specially intendedfor use during the initial stages of design when specific dimensional details ofplant may not be available.

1.5 Variations in the structural system, department layout and engineeringservices provision will influence the extent to which this guidance can beapplied. Individual project solutions may differ, although most should be ableto adopt the principles of zoning and spacing for the services outlined in thisdocument. ARCHIV

E

Page 7: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 7 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

2. General considerations

2.1 A modern hospital may require 50 or more different engineering services, andothers may be added later as new techniques are developed. Hospitalbuildings can be expected to have a useful life of at least 60 years and duringthis period engineering services will have to be renewed. Unless adequatespace is provided initially, the cost of renewing services will be excessive andtheir extension may be impossible.

Development planning

2.2 With the increasing complexity of modern hospital services, it is more thanever essential that the engineering and architectural aspects of a project aredeveloped simultaneously from its inception.

2.3 The purpose of early collaboration is to ensure that the planning of medicalrequirements and communications is properly integrated with the followingengineering aspects:

a. services distribution;b. plant location;c. future development.

2.4 At the earliest stages of planning, designs should be based on an overallconception of the complete scheme. It is essential to foresee as far aspossible what provisions should be made for the passage of services, throughdifferent parts of the structure, not only for present requirements but also forpossible future developments. It is important to ensure that any constructiondoes not preclude the accommodation of further services in the future.

2.5 Engineering services are necessarily continuous, and must not be obstructedby structural design which might restrict such continuity. The effect of anysuch obstruction will be felt far beyond its own locality, and may effectivelyisolate large areas of buildings from services.

2.6 It is therefore most important that the basic structural design should permitsufficient space for the services, and all such space must be regarded asinviolable. Difficulties in this area will be minimised if the services engineer isresponsible for public health engineering.

2.7 The provision of extra space for future plant and services should be related tothe probable requirements. If there is little likelihood of an increase the extraspace allowed should be minimal, but a margin of up to one third above thenet basic requirement may well be justified. Possible developments in theremote future should be dealt with at the time of their design.

ARCHIVE

Page 8: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 8 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

2.8 The development of detailed engineering drawings will produce accurateinformation on service space requirements, but these will not be available untila later stage. If a satisfactory estimate of space requirements can be madeduring the preparation of the sketch plans, serious and costly revisions will beavoided.

2.9 Component data is not included in this document due to the wide variation insizes between manufacturers. The designer should make reference to actualmanufacturers’ data including drawings of the specific components orassembly of components, for example air handling units, boilers, switchgear.Reference may also be made to British Standards for specific componentsand BSRIA technical note TN10/02 which provides space requirements for anumber of common service components.

2.10 Plant requirements will depend upon the design solution for the type, designand function of the building. Consideration should be given to the followingpoints:

a. services and plant to be accommodated;b. optimum siting, in terms of distribution and the effect on adjacent

accommodation;c. optimum size;d. floor loading when plant is fixed and during installation;e. space and access requirements for installation and possible subsequent

renewal;f. space and access requirements for proper and safe operation and

maintenance;g. ventilation and combustion air;h. adequate lighting and heating;i. fire precautions;j. safety requirements;k. the possibility of noise nuisance;l. heat insulation;m. minimum heights;n. drainage;o. surface finishes.

Working in confined spaces

2.11 Working within confined spaces should be covered by a “permit-to-worksystem” covering safe working practices in accordance with the “permit-to-work”. Reference should be made to Health and Safety Guidance Note GS5,‘Entry to Confined Spaces’. The guidance note covers spaces where there is

ARCHIVE

Page 9: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 9 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

a possibility of a build-up of gas or vapour, or where there is likely to be adeficiency of oxygen.

2.12 The presence of asbestos products within a site will require implementation offollowing approved codes of practice: ‘The Control of Asbestos at WorkRegulations 1987’ and ‘Work with asbestos insulation, asbestos coating andasbestos insulating board, 1988’.

2.13 Where no “permit-to-work” system is in operation, it is important to ensure thework is undertaken only after a full investigation and resolution of the followingmatters has been completed, and the engineer has been informed in writing ofthe proposals:

a. assessment of the task to be undertaken;b. identification of the hazards of the task;c. decision on methods of working to avoid hazards;d. implementation of a system of work to incorporate these methods;e. monitoring of the operation of the system of work.

2.14 Prior to the entry of personnel into the space and the commencement of work,the space must be demonstrated to be safe by testing that no toxic orasphyxiant gases are present and that oxygen levels are adequate.

Fire

2.15 Guidance on fire precautions is contained in NHS in Scotland Fire SafetyManagement. Fire safety requirements should be established prior tocommencement of any services design work as the particular disposition ofsub-compartment walls, cavity barriers and other physical fire precautionsmay influence the service distribution and routing.ARCHIV

E

Page 10: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 10 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

3. Preliminary plan areas for engineering platforms

General

3.1 This section provides guidance on initial plan areas for engineering services.

3.2 The information is based on data obtained from existing sites and newhospital schemes. Measured service areas have been discussed with thedesign engineers and confirmed or revised in the light of experience, andwhere possible an inspection of the accommodation was made. The datagiven is intended to be used during the early planning stages in conjunctionwith schedules of accommodation. Figure 1 may be used before drawings areavailable, and Figures 2 to 8 will assist during more detailed planning.

Total engineering plan area (Figure 1)

3.3 The plan areas shown are for complete hospitals and the point of selectionwithin the band should be related to:

a. the number and complexity of services;b. the shape and layout of buildings, which largely determines the amount of

ventilation required;c. the basic design of services, for example central or decentralised

calorifiers; electrical HV or MV distribution.

3.4 The gross area referred to on Figure 1 is the sum of basic and additionalaccommodation plus the circulation and communication areas, but does notinclude engineering service areas.

3.5 Selection within the band will depend on the number of services to beprovided, and any special requirements for each service. The value obtainedfrom the graph should be checked against the sum of the areas required bythe separate services.

Calorifier room plan area (Figure 2)

3.6 It should be noted that several decentralised plantrooms require considerablymore space than one central room (but there may be some savings indistribution services). The most appropriate policy for a particular hospital canbe determined by a financial appraisal of each option.

ARCHIVE

Page 11: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 11 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Ventilation plantroom plan area (Figure 3)

3.7 Ventilation requirements will depend upon the type of building, for examplethe number of internal rooms and the extent to which full air conditioning is tobe provided.

3.8 The plan area for low level buildings with little mechanical ventilation will fallwell below the band shown on Figure 3, and the area required for a hospitalwholly or largely air conditioned will be well above it. An individual assessmentwill be necessary in such instances.

Lift wells and motor rooms plan area (Figures 4 and 5)

3.9 The area required for lift wells and motor rooms is related to the number offloors served. The band width indicates the variation due to servicerequirements. For example, office accommodation does not require a bed lift,but a block with a number of operating theatres may require several.Reference should be made to SHTM 2024; Lifts for further details on thedesign of lifts.

Vertical ducts plan area (Figure 6)

3.10 The requirement for vertical ducts will depend upon the number and size ofventilation ducts and piped services to be accommodated, but shows noappreciable relationship to building height.

Water storage plan area (Figure 7)

3.11 Figure 7 is based on examples where nearly all of the storage is internal. Theband width is attributable to variation in cistern depth and the estimated dailyconsumption.

Switchroom plan area (Figure 8)

3.12 Figure 8 does not include accommodation for HV switch gear andtransformers (for which SHTM 2007; Electrical services: supply anddistribution shows dimensioned layouts). The graph shows the approximatearea required when space is specifically allocated for switchrooms.

ARCHIVE

Page 12: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 12 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

4. Engineering distribution principles

4.1 The main engineering distribution principles, which are illustrated on theexemplar hospital layout in Figures 9 and 10, are as follows:

a. each block may be serviced from the hospital street/corridor unlessinternal ducts are appropriate for a specialist department, for examplepathology or operating theatres;

b. services (except drainage) will be contained within the particular floor theyserve, to minimise penetrations of the building structure between floors;

c. services to each department floor will have the means of isolation at thehospital street interface;

d. the routing of the main engineering services to the departments andplantrooms will be within or above the hospital street;

e. major items of plant may be located:(i) as a separate enclosure off the hospital street or service street (but

not part of, or combine with, a life risk department);(ii) in a discreet enclosure remote from the main building block;(iii) above the hospital street;(iv) at roof level above a block;

f. access to plantrooms will be achieved via general access stairways and acovered walkway above the hospital street.

ARCHIVE

Page 13: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 13 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

5. Common distribution requirements

General

5.1 The assessment of requirements must be considered with respect tocommunication, areas, plant and distribution, and be related to the site, sizeand shape of buildings. Accommodation for vertical services will be decidedduring the preparation of the development plan. This information will be in theform of total areas required, to be sub-divided later as design work proceeds.

Distribution

5.2 As far as is practicable, departments that impose a heavy load on theengineering services should be grouped and located near to the maindistribution centres to avoid long runs of large capacity mains. It will generallybe found advantageous for services to follow the main communication routes.

Distribution to plantrooms

5.3 Generally, the first plantroom to be sited is the energy centre, so that the mainservices routes can be determined. Energy centres are usually sited in aservice centre complex for the hospital, located centrally to the primary energyusers, although consideration may be given to siting at roof level.

5.4 The next step will be to decide the areas required for other plantrooms.

5.5 Consideration should be given to the degree of flexibility that is necessary toallow for possible changes in the use of hospital departments.

5.6 In multi-storey buildings, a smaller number of large vertical ducts withadequate provision for horizontal distribution above ceiling level and belowstructural members may give the most flexible arrangement. A large numberof smaller vertical ducts with ceiling spaces for horizontal distribution asnecessary, will generally be less flexible.

5.7 The omission of space above ceilings produces the least flexiblearrangement.

5.8 Convenient access should be provided to all service spaces.

General access

5.9 Access to services, excluding requirements for initial installation, should beconsidered for operation, maintenance and replacement.

ARCHIVE

Page 14: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 14 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Frequent access

5.10 Plant, valves, switchgear, and all equipment requiring frequent attention foroperation of the system or for maintenance, need immediate access. Ifenclosed, access should be by hinged doors and adequate clearance shouldbe provided for ease of working on the equipment.

Intermittent access

5.11 Items not in frequent use or requiring maintenance only at intervals of somemonths, need ready access, which may be by means of floor traps orremovable panels in walls, partitions and false ceilings. It is recommendedthat access panels be fixed by means of quick-release fasteners, such ascarriage locks, rather than by screws and cups.

5.12 Access should be arranged, as far as possible, to enable work to be carriedout without affecting hospital routine. Access points should be convenient toitems requiring attention, and in the case of rodding eyes sufficient spaceprovided to facilitate rodding of the pipework.

Renewal of services

5.13 Some services may have to be renewed once or twice during the useful life ofa building. Accommodation should be planned to allow for this and take intoaccount both weight and size of major items. Where emergency renewals arenot envisaged the removal of door frames, windows, and even partitions andnon structural walls may be considered. The renewal of minor items does notusually create problems, except for pipe lengths and allowance should bemade for passing pipe lengths into the ducts at a later date.

5.14 The destruction of finishes to open up a trench or vertical duct or to increasethe size of an existing means of access could be more economical than theprovision of expensive, rarely used permanent access. The saving must beconsidered with regard to the cost and inconvenience incurred at the time ofreplacement.

ARCHIVE

Page 15: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 15 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

6. Site primary service distribution spacerequirements

General

6.1 This section presents, in tabular and diagrammatic form, information on thespace requirements for the distribution of site services, with suggestedarrangements.

6.2 Dimensions given will allow sufficient access to services for inspection,adjustment or replacement. Where applicable, British Standards or BritishStandard Codes of Practice should be complied with.

6.3 Dimensional allowances for lighting, drainage, wash down, ventilation, powersupply, access points and finishes are to be made as additions to the spacesrequired for the services.

6.4 Detailed dimensions of access traps, doors, etc. are not given as these willvary considerably with circumstances, but access clearances should not beless than 450 mm square.

6.5 The main requirements are:

a. adequate space to operate valve controls;b. unobstructed access to rodding eyes, etc;c. easy access for inspection and maintenance;d. sufficient space to enable repairs and replacements to be carried out;e. entry points large enough for the passage of equipment, materials and

tools likely to be required during replacement and extension work, forexample pipes, valves, pumps, welding equipment, etc.

6.6 Where pipes, ducts, etc, are placed behind fully demountable ceilings, walls,partitions etc, the provision for working space given here need not be allowed.However, services in such positions should have access doors or traps forvalves, rodding eyes, etc.

Ducts showing accommodation space for services, accessand working space

6.7 Figure 11 illustrates four possible arrangements for installing services inhorizontal ducts. Dimensions will depend on the number and size of pipes andfittings to be accommodated, and on ease of access for jointing, installation,branches and maintenance.

ARCHIVE

Page 16: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 16 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

6.8 All four spaces may be combined in any permutation conducive to economy,good engineering practice, efficient distribution and access. The sizes of theservice areas can be calculated from Figures 15 to 20.

6.9 Consideration should be given to leaving a space or part of a space free toallow for future increases in service loadings.

6.10 The clear space should allow convenient access to install and maintainservices (see Figures 12 to 14).

6.11 The above arrangements are suitable for service corridors. It is preferable tolocate services to sides rather than overhead to allow access to the pipeworkand cables.

Subways

6.12 Figure 12 shows engineering services accommodated on either side oroverhead as required. Figures 15 to 20 give the dimensions of service spaceswhich are additional to the clearance space values listed in Table 1.

Table 1: Clear space dimensionsDimensions of free

spacePedestrian use only Pedestrians and

trolleysPedestrians andpowered vehicles

A 2.0 m 2.0 m *2.0 m

B 1.1 m 1.2 m *1.4 m

* These dimensions and turning radii to suit type of powered vehicles.

6.13 Allowances must be made for any services which cross the subway. Extrawidth in lay-bys must be included when the subway has to provide for two-waytraffic.

Crawlways

6.14 Figure 13 shows engineering services provided on either or both sides of aduct, allowing minimum working space. Reference should be made to Figures15 to 20 for the dimensions of service spaces, which should be added to thedimensions shown.

6.15 Access should be provided at each end of the crawlway, for example fromplantrooms, and access openings with removable covers provided at intervals.The distance between access points should be decided by consideration ofthe particular circumstances and the installed services. When makingprovision for access, consideration should be given to the removal andreplacement of lengths of pipe where this is practicable. The crawlway shouldbe ventilated to provide fresh air and prevent possible toxic gas build up orexcessive ambient temperatures.

ARCHIVE

Page 17: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 17 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Walkways

6.16 Figure 14 shows engineering services accommodated on either or both sidesof a walkway allowing clear space dimensions for movement and working.Reference should be made to Figures 15 to 20 for the dimensions of servicespaces which should be added to the dimensions shown.

6.17 Access through removable covers should be provided at intervals to allow forventilation as well as the entry for materials, etc.

Pipework dimensions

6.18 Figure 13 indicates the clearances for pipes and valves to allow foraccommodation, servicing or renewal.

6.19 Table 2 lists the values of A and B (see Figures 15 to 19) for a series of pipesand valves whether insulated (I) or uninsulated (U).

Table 2: Pipes and valves, clearance dimensionsPipe

diameter(d)

Dimension A (mm) Dimension B (mm)

mm Welded orscrewed

Flanged Cast iron Gas Water Steam

I U I U I U

80 350 300 350 350 350 300 475 600 650

100 375 325 400 375 375 325 550 700 800

150 475 425 475 425 425 400 700 800 950

225 600 _ 600 550 550 475 750 1050 1325

Electrical tray and cable trunking

6.20 Figure 16 shows cable trays and trunking of nominal dimensions A and B, andTable 3 indicates the minimum access space required for installation orreplacement of cables over the top, C, and at either or both sides, D.

Table 3: Dimensions of space requirements for trays and trunkingTrays (mm) Trunking

(mm)

A *B C D A B C D

100 12 225 225 75 50 225 225

150 12 225 225 100 100 225 225

300 18 300 450 150 150 225 225

450 18 300 450 225 100 225 225

* B is a nominal dimension and will vary according to manufacturer

ARCHIVE

Page 18: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 18 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

6.21 For installation and replacement cable trays and trunking installed verticallyrequire front access of no less than dimension C. These minimum dimensionsare applicable only where a crawlway or walkway access is available.

Ventilation ducts

6.22 Figure 17 shows minimum areas required around ducts for access to dampersand for making slip or flanged joints. See Figure 18 for clearance dimensionsC and D, for appropriate duct dimensions A and B.

Method of spacing services

6.23 Figure 19 shows a recommended arrangement for services in ducts.

6.24 Installation areas (taken from Figure 15) may overlap provided there isreasonable access to services. The overlap should not exceed (A - d)/2 whereA is the clearance distance and d the diameter of the smaller pipe.

6.25 Double banking should be avoided as it will create difficulties withmaintenance or renewal of services.

6.26 If double banking is unavoidable, banked services should be paired (forexample flow and return) and the method of support should be such as tofacilitate access.

Vertical ducts

6.27 Figure 20 shows typical vertical ducts of dimensions A x B with frontal accessfor installation, maintenance and replacement of services.

6.28 The dimensions A and B will depend on the number and size of services to beaccommodated (allowing the clearance indicated in Figures 15 to 19).

6.29 Dimensions C and D will vary as follows:

a. with arrangement I, C will be equal to the full opening A and no clearancedepth D will be required as there is free access from outside the duct;

b. with arrangement II, C should ensure convenient access, and be not lessthan 0.5 m. D can be the minimum necessary to clear valve projections;

c. with arrangement Ill, C and D should be at least 1.1 m and 0.75 mrespectively, and the access opening should have a minimal clearancewidth E of 0.75 m and a clearance height of 1.8 m.

6.30 Rodding eyes should be easily accessible.

ARCHIVE

Page 19: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 19 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Ha-ha and low-level piperuns - typical arrangement

6.31 Figures 21 and 22 show services carried on supports or hung from crossmembers. Provision should be made for movement of pipework due toexpansion and contraction. The accommodation should allow for originalinstallation, maintenance and replacement of services. Provision should bemade for drainage of the ha-ha and for the clearing of fallen leaves, etc.

Trenches

6.32 Figures 23 and 24 show services in trenches. The arrangement of servicesaccommodated in trenches will be dictated by the fact that installation canonly be carried out from above.

6.33 Trenches can be finished with cast in-situ concrete covers, or preformedcovers bedded in sealant and finished, for example, with screed or tarmac.The exposure of the trench may require destruction of the finish (such asearth and grass) to obtain access and renewal on completion of servicing.

6.34 If there is need for frequent access after installation the covers should bereadily removable precast units or filled metal trays.

6.35 When detailing trench runs, special attention should be given to the depth ofthe trench to allow for cross-over points, falls in pipework and for drainage ofthe trench floor. The strength of the covers should relate to their span andanticipated traffic loadings.

Chases

6.36 Figure 25 shows services in chases. Chases are mainly used foraccommodating electrical conduits and smaller sized piped services, etc.

6.37 The maximum depth of chases will be governed by the thickness andproperties of the material being chased. The width of chases will be limited bythe need to prevent cracking of plaster cover, etc, and should be mutuallyagreed by architect and engineer.

6.38 An alternative is to use a trunking with removable covers which allowsconvenient access for servicing and installing additional services.

ARCHIVE

Page 20: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 20 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

7. Plantrooms

General

7.1 The space requirements for the engineering plant and equipment must beidentified early in the design planning stage. For guidance on escape routesand escape route lighting, reference should be made to BS 5266:Part 1:1988:‘Code of practice for emergency lighting’ with European amendment asintroduced; BS 5499: ‘Fire safety signs, notices and graphic symbols; NHS inScotland Firecode – Fire precautions in NHS Premises and BuildingStandards (Scotland) Regulations.

Ventilation plantrooms

7.2 Ventilation plant can best be accommodated at roof level. The spaceallocation will depend on the extent to which ventilation is provided in thedepartments which interface with the particular hospital street section. In theexemplars, the ventilation plant serves only the department interfacing withthe hospital street above which it is located.

7.3 As the combinations of departments change to suit project needs so will thespace requirements for ventilation plant. It is therefore consideredinappropriate to prepare standard detailed plantroom layouts. General spaceprovision for various ventilation plant requirements have therefore beenprepared in block diagram format to provide basic planning advice.

7.4 Due consideration needs to be given to those departments which are almosttotally air conditioned or mechanically ventilated, and those which have 24-hour or day (9 am to 5 pm) operation. The combinations of these will greatlyinfluence the number and size of the ventilation plants and therefore thespace requirements.

7.5 Where 24-hour-a-day departments are located together, and turn down ratiosare reasonable, a single ventilation plant may be the best choice. If turn downis impracticable then separate plants will be necessary (see Figures 28, 29and 31).

7.6 The ventilation plant space requirements for the operating department, whereindividual plants per theatre suite are necessary and a separate plant isrequired for the ancillary accommodation, are shown in Figures 34 to 37inclusive.

7.7 Optional designs of plantrooms may accommodate boilers, calorifiers andother plant (see Figure 42).

ARCHIVE

Page 21: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 21 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Clean and dirty extract plant

7.8 Ventilation plantrooms will also need to house the clean and dirty extract fanunits, and these may be floor or duct mounted. Exhausts from these unitsmust be positioned to discharge clear of air intake louvre and departmentopenable windows (see Figures 35 to 37).

7.9 Consideration should be given to the possibility of installing run-around coilsand associated equipment where heat recovery from these items is feasible.

7.10 Fans for special extract systems conveying hazardous or toxic products mayneed to be sited in ventilation plantrooms. The discharge from these systemsshould be at high level to atmosphere - the height and location is to bedetermined in consultation with the appropriate authority (EnvironmentalHealth Officer, Health and Safety Executive).

7.11 Extract fans for the smoke extract hood systems are also located in theseplantrooms and they should discharge to atmosphere above the plantroomroof level (see Figure 29).

High voltage sub-stations

7.12 Sub-stations should be accessible from a road to allow easy access fortransformer changing, fire appliances, maintenance vehicles, etc. There aresafety restrictions for personnel access to high voltage sub-stations, andemergency exit doors of the approved “crash bar” type must be provided atregular 20 m intervals, and be located in suitable places to prevententrapment of personnel.

Layout

7.13 The cable trench layout should allow adequate space for pulling in andterminating cables, and wall clearances for servicing switchgear or cubicles.The size of the sub-station should be related to the anticipated totaldevelopment, either by building an unequipped extension for future additionsor by locating and designing the sub-station so that future building extensionis possible.

7.14 Headroom should be sufficient to ensure adequate natural cooling and spacefor luminaires and fire protection equipment; typical layouts are shown inFigures 44 to 47. A work space should be provided at the end of theswitchboard for maintenance work on at least one circuit breaker. In the eventof an equipment fault it must be possible for the transformer to be moved intothe open air and a crane used.

7.15 Ring anchor fixing should be available for hauling transformers into position orout to the open air.

ARCHIVE

Page 22: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 22 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

7.16 The cable entries and ducts should be routed to avoid obstructing theinstallation or removal of the transformer.

7.17 The following minimum clearances are recommended:

a. between transformer and wall – 1.0 m;b. headroom above transformer tank – 1.6 m;c. headroom above switchboard – 0.9 m;d. between rear of HV and LV switchgear wall – 0.8 m;e. at front of LV switchboard – 1 m vertically, and to the wall 2 m, for

horizontally isolated switching devices.

Ducts

7.18 Cable trenches and ducts should be constructed to avoid paths along whichsurface water, leaking mineral oil or synthetic fluid will flow. If this isunavoidable, or if cable entries or exits occur at or below ground level, thenoutside cover edges should be sealed with a suitable weather sealant. Alloutside cable trench covers should be sealed against water penetration.

7.19 Cable trenches and ducts should have fire-resistant barriers provided inaccordance with NHS in Scotland Firecode.

Low voltage switchrooms

Siting

7.20 Switchrooms other than those associated with sub-stations should be sited asclose as possible to the load centre and arranged to allow convenient directentry to rising ducts, horizontal ducts, crawlways etc.

Layout

7.21 The layout should allow adequate space around the switchboard for servicingpurposes. Suggested minimum clearances between the switchboard andwalls are 0.8 m minimum at the rear and 1 m in front, plus additional spacerecommended by the manufacturer for withdrawing switchgear. Whereprovision is made for bus-bars to be extended, adequate space should beallowed at one end of the switchboard for this purpose.

ARCHIVE

Page 23: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 23 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Electrical switchgear

Located within roof level plantrooms

7.22 The distribution strategy proposed in Chapter 6 for the routing of the mainelectrical cables suggests the optimum position of the sub-main switchgear tobe within the roof level ventilation plantrooms (see Figures 28 to 39). In thislocation, good access for maintenance and repair can be provided withoutdisturbing staff or patients. The option to position the switchgear within thehospital street area or another selected location is, however, not ruled out.

Access and maintenance

7.23 Sufficient space should be provided for normal operating access,maintenance and plant inspection and removal. Provision should also bemade for the lifting and removal of large or heavy items of plant or equipment.Wherever possible the “line” of the rooftop walkway should continue throughthe plantroom to ease plant movement and general access.

Calorifier plantrooms

Size

7.24 Figures 48 and 49 show minimum plantroom areas required for theaccommodation of calorifiers, associated plant and equipment.

Site

7.25 Calorifier rooms should be located as near as practicable to the load centresor between the load centres and the source of heat supply. They shouldpreferably have direct access to the outer air. Consideration should be givento the effect on adjacent rooms of heat transfer through walls and ceiling.

Shape

7.26 In general the room shape should vary between a square and rectangle with amaximum ratio of 3:1.

Height

7.27 A minimum room height of 2.7 m is recommended for the accommodation ofhorizontal calorifiers. Vertical calorifiers may require a height of more than onestorey to achieve the necessary headroom.

Construction

7.28 The calorifier base should be designed to carry the weight of the calorifier andits contents. The walls and ceiling may be required to support pipework andminor items of plant. Bases for pumps should be designed to minimise

ARCHIVE

Page 24: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 24 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

vibration from the pump and motor. It may be necessary to provide sufficientspace to allow for lifting equipment to be used during the installation orrenewal of the larger items of plant.

Other services in the calorifier plantroom

7.29 Space for general lighting will be required, with suitable electric power points.Adequate provision should be made for the removal of heat losses from plantto prevent an excessive rise in temperature in the plantroom. This should beachieved by natural ventilation wherever possible. Drains will be required fornormal drainage and emptying down. If the plantroom is below drain level,space for a sump and sump pumps will be necessary.

Water storage rooms

7.30 The area required to accommodate water storage cisterns is readilycalculated from the required storage capacity and the available room height.Additional space may be required for pressurisation plant or circulatingpumps. Figure 50 shows the minimum clearance that should be providedaround cisterns.

Site

7.31 The most suitable location for internal storage is either the roof or thebasement, except in very tall buildings where cisterns may be required onintermediate floors. Water towers or concrete underground reservoirs may beconsidered for external storage with the capacity of the high level cisterns inbuildings reduced accordingly. Siting cisterns over vertical shafts such asstaircases may facilitate supporting the weight of the cisterns.

Shape

7.32 The proportions of the cistern may have to suit the available site. Thecost/capacity ratio of the cistern increases as its shape departs from square,therefore cisterns should be designed to be as close to square as ispracticable.

Height

7.33 The height will generally be governed by standard plate sizes and a clearancespace of approximately 1000 mm above and 450 mm below the sectionalcisterns.

Construction

7.34 Sectional cisterns using standard flanged pressed plates are most commonlyused for water storage. Adequate supports and supporting structure should beprovided. Curbs of adequate height should be provided around descendingducts and at doorways to prevent the spread of spilled or leaking water. A tell-tale overflow should be provided from the floor.

ARCHIVE

Page 25: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 25 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Other services in cistern rooms

7.35 Space for adequate lighting will be required around the tanks. A suitablepower point may be required in the cistern room. Adequate ventilation isrequired for internal cistern rooms. Heating for frost protection should beconsidered.

Storage of medical pathology and industrial gas cylinders

7.36 The following sections provide guidance on the storage of medical pathologyand industrial gas cylinders. Figure 51 shows typical layouts of manifoldrooms.

7.37 In respect of liquefied petroleum gas storage (LPG), it should be noted thatthe principles of ‘The Highly Flammable Liquids and Liquefied PetroleumGases Regulations 1972’, should be followed as appropriate. Detailedguidance on the storage of LPG is given in the Health and Safety ExecutiveGuidance Notes CS4 and CS5, and the advice which follows is given withoutprejudice to that contained in these documents.

Operational considerations

7.38 This guidance represents the minimum standard applicable to all newinstallations, and the general principles should be followed on existinginstallations so far as is reasonably practicable. Normally, existing installationswill have been designed to comply with the recommendations of NHS inScotland Firecode and/or SHTM 2022; Medical gas pipeline systems asappropriate, that is gas cylinders will have been stored either in a storeroomwhich is part of a health building or in a separate, specially constructedbuilding, both areas being used exclusively for medical gas cylinders. Theseinstallations will usually be satisfactory if adequate ventilation is provided.

7.39 In cases where there are difficulties in meeting the requirements contained inthis document for either new or existing installations, for example on arestricted site, the advice of the gas supplier or Property and EnvironmentForum Executive) should be sought as appropriate. Where significantproblems exist, the local inspector of the Health and Safety Executive shouldbe consulted. Overall, the principles contained in this document should befollowed as far as is reasonably practicable.

ARCHIVE

Page 26: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 26 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Cylinder store design

7.40 Cylinders should ideally be stored in the open air, but where this is notpracticable, the store should be adequately ventilated to minimise thepossibility of gas accumulating in the event of a leak. Details of suitableconstruction for a store are given in paragraphs 7.62 to 7.64.

7.41 Within the storage area, cylinders whose contents are incompatible, thosecontaining flammable and oxidising gases should not be stored togetherunless there is adequate separation. Details of the storage area layout aregiven in paragraph 7.62 to 7.64.

General principles of cylinder storage

Key points

7.42 The cylinder storage area should be:

a. well ventilated;b. clearly labelled;c. secure (but with clear access);d. used exclusively for cylinders;e. for flammable and oxidising gases, free from naked flames and all

sources of ignition, and in a “no smoking” area;f. provided with barriers for cylinder segregation and to prevent cylinders

falling.

7.43 Storage of cylinders containing compressed, liquefied or dissolved gaseswithin unsuitable buildings may increase the risk of fire or explosion. All fulland empty cylinders, apart from those in use or required for immediate use,should be kept in specially designed stores, which should be sited away fromoccupied premises, and used exclusively for the storage of cylinders.

7.44 Wherever possible, cylinders should be stored in the open air.

7.45 Where storerooms have to be used, they should be specially designed andused solely for this purpose. A high standard of natural ventilation to the openair should be provided at high and low level. If used for flammable gases,adequate explosion relief should be incorporated, for example by provision ofa roof of lightweight, friable material (see paragraph 6.4 of the BritishCompressed Gases Association Code of Practice CP8, ‘The safe storage ofgaseous hydrogen in seamless cylinders and similar containers’. Automaticfire detection should be installed if appropriate as required by SHTM 82;Alarm and detection systems).

7.46 Sources of ignition should be eliminated from all areas where gas cylindersare kept. Smoking and naked lights should be prohibited, and suitable notices

ARCHIVE

Page 27: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 27 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

should be posted in prominent positions to this effect in accordance with theEEC directive which came into effect on 1 January 1981. For further guidancesee the Health and Safety Sign and Signals Regulations 1996; BS 5499 ‘FireSafety Signs, Notices and Graphic Symbols’; and BS 5378 ‘Safety Signs andColours’.

7.47 The store should be clearly labelled to indicate the type of cylinders itcontains, action to be taken in an emergency and the location of the key(s).The graphic symbols in BS 5499 and BS 5378 may also be used asappropriate.

7.48 If the store contains more than one section, each should be clearly labelled toshow which types or classification of cylinders may and may not be stored.

7.49 The store should have adequate means of access to facilitate movement ofcylinders on trolleys. The cylinder bays should similarly be arranged to allowthe safe loading and manoeuvring of trolleys.

7.50 Industrial and medical gases recognition charts should be displayed, inaccordance with BS EN 1089-3 and BS EN 850.

7.51 Cylinders should not be stored in bulk except in specially designated stores.However operational policy may require small quantities of gases to be heldoutside the main store in ready for use stores. The general considerationsoutlined in this section will also apply to ready use stores.

7.52 Full cylinders should be stored separately from empty ones in a clearlyidentified area. Empty cylinders should be stored in the same way as fullcylinders.

7.53 The store should normally be locked and access restricted to authorisedpersonnel – see paragraph 7.65.

7.54 Cylinders should be properly secured to prevent toppling or rolling. Verticalstorage is recommended for cylinders containing dissolved or liquefied gasesand is essential for cylinders fitted with dip tubes.

Location of main cylinder stores

7.55 For guidance on the fire hazards associated with inappropriately locatedcylinder stores and in buildings adjoining stores, reference should be made toNHS in Scotland Firecode.

7.56 Main cylinder stores should be located at ground level; never underground, forexample in basements.

7.57 Where necessary, protection from vehicular damage should be provided forexample by a low wall, crash barriers or bollards. This should not significantlyrestrict the ventilation, and should not create a ‘tank’ in which gases couldaccumulate.

ARCHIVE

Page 28: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 28 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

7.58 Adequate access should be provided to stores to allow safe delivery andmanipulation of cylinders.

7.59 Stores should be located close to the delivery point. Wherever possible, thereshould be only one delivery supply point on each site.

7.60 No parking should be permitted within the delivery and storage areas, otherthan for loading and unloading.

7.61 Stores should be located in the shade wherever possible (cylinders of liquidammonia require special protection from direct sunlight).

Design and construction of main cylinder stores

7.62 Stores should be constructed so as to provide maximum ventilation.

7.63 Where practicable, cylinders should be stored in the open air, with open meshfences for security. Protection against weather, debris etc. should not reducethe provision for natural ventilation below that given in Table 4 which shouldbe regarded as a minimum standard.

Table 4: Design of main cylinder storesClassification Sides Roof

Medical and non – medicalinert and oxidising gases only.

At least one major side openwire mesh (see notes).Remaining sides brick orother non – combustiblematerial. Where the sides arenot required to be “ fire –resisting” they shouldincorporate suitably distributedopening (for example airbricks) at high and low level topromote cross – ventilation.

Light, non – combustiblematerial, designed to preventaccumulation of gases inevent of leak.

Non – medical includingcylinders of flammable, toxicand / or corrosive gases.

At least 2 – sides open wiremesh (wherever possibleopposite rather than adjacentsides). Remaining sides asabove.

As above.

Notes:1. The sides should be at least 2 m high.2. The open wire mesh should be industrial quality, chain link fence or similar material to

provide security and free ventilation.

ARCHIVE

Page 29: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 29 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

7.64 The floor and hard standing should be level and constructed of concrete orother non-combustible, non-porous material. A concrete finish is preferred andis likely to have a longer life.

NOTE: Bituminous or other similar carbonaceous materials should not beused for surfacing in the vicinity of cryogenic storage installations (especiallyliquid oxygen), and in any area where spillage of cryogenic liquid may occur(for example tanker delivery areas). (See SHTM 2022; Medical gas pipelinesystems.) The floor should be laid to a fall, to avoid the accumulation of waterin any undrained area of the storeroom.

Security

7.65 Unauthorised access to the store should be prevented. A perimeter fence ofindustrial quality chain-link or equivalent, at least 2 m high, should beadequate unless protection is otherwise provided (see also Chapter 6).

Requirements for manifolds for non-medical gases

7.66 Wherever possible, manifolds for gases other than medical gases should belocated in the open air. If this is not possible, the above guidelines on manifoldrooms should be followed, with particular emphasis on good ventilation.

7.67 Explosion relief for flammable gas manifold rooms should be incorporated intothe exterior walls or roof of the manifold room. It should be designed so that ifan explosion occurs, the pressure would be relieved safely. The area ofexplosion relief should be equivalent to the area of one of the largest sides orthe roof and relief may be achieved by using a roof of lightweight, friablematerial or via openings in the walls/roof of the store (see also BCGA Code ofPractice CP8).

7.68 Manifold control panels for open air service should be suitably constructedand protected against the weather for such a location. Such weatherprotection should incorporate adequate natural ventilation to prevent theaccumulation of any gas leakage.

Ready use stores

7.69 In some areas it will be essential to hold small numbers of spare cylinders forimmediate use, for connection to anaesthetic machines, and for suddenunanticipated demands. Such areas would include: operating department,accident and emergency department, coronary care unit, central delivery suiteof maternity department, special care baby unit, intensive therapy unitsterilizing and disinfecting unit, etc.

ARCHIVE

Page 30: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 30 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Medical air compressor

Size

7.70 The area required to accommodate a medical air compressor set is shown inFigure 52. Reference should also be made to SHTM 2022; Medical gaspipeline systems.

Site

7.71 Ground level or roof level are suitable locations for medical air compressors.Allowance should be made for isolating the noise generated by the plantduring operation from adjacent areas. Adequate fresh air intake will berequired to the plantroom.

Medical vacuum plant

Size

7.72 The area required to accommodate the medical vacuum plant is shown inFigure 53. Reference should also be made to SHTM 2022; Medical gaspipeline system.

Site

7.73 Ground level or roof level are suitable locations for medical vacuum plant.Allowance should be made for isolating noise generated by the plant duringoperation from adjacent areas.

Liquid oxygen storage

Safety distances

7.74 The area required to accommodate the liquid oxygen storage unit is related tothe surrounding buildings. Figures 54 and 55 and Table 5, 6 and 7 show therequired clearance for various situations. Reference should be also be madeto SHTM 2022; Medical gas pipeline systems.

Sterilizers

7.75 The area required for sterilizers is provided in Table 8 and typical layouts forthe plant are given in Figure 56. Reference should be made to SHTM 2010;Sterilization.

ARCHIVE

Page 31: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 31 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Table 5: Separation distances: liquefied flammable gases, flammableliquids and oxygen storage

a) LPG storage

Size of storageLiquid oxygen vessel(tonnes)

LPG vessels

Weight capacity(tonnes)

Equivalent liquidcapacity (m3) 15°C

Separation distancemetres

Up to 200 0 – 1.1 0 – 2.2 6.0

1.1 – 4.0 2.2 – 7.8 7.5

4.0 – 60.0 7.8 – 117.0 15.0

60.0 – 150.0 117.0 – 124.0 22.5

150.0 & above 294.0 & above 30.0

LPG cylinders and other liquefied flammablegas* cylinders above 50 kg total capacity

7.5

See also HS(G)34 ‘Storage of LPG at Fixed Installations’ and LPGITA COP 1 ‘Code ofPractice - Installation and Maintenance of Bulk LPG at Customer Premises’.

b) Other bulk flammable liquids and liquefied flammable gases

The separation distances listed above for LPG should be applied to thesame stored volumes (m3) of other bulk liquefied flammable gases andmay be used for the same stored volumes (m3) of bulk flammableliquids (+). These distances may be reduced depending on the natureof the flammable liquid and any protective measure and in these casesan individual assessment of the proposed location should be carriedout.

* Common examples of liquefied flammable gases supplied in cylinders include ammonia,hydrogen sulphide and ethylene oxide.+ Common examples of bulk flammable liquids include acetone, methanol, diesel, petrol.

Table 6: Separation distances: compressed flammable gases andoxygen storage

Compressed flammable gas cylinders (m3)

(gas volume measured as Nm3 at 1013 mbarand 15°C)

Liquid oxygen storage up to 200 tonnesseparation distance (metres)

Up to 70 5.0

Above 70 8.0

Notes:1. For liquefied flammable gas cylinders, see Table 12. Distances in Table 2 are based on hydrogen cylinders. Reference: BCGA CP8 (1986).

For separation distance for Acetylene, BCGA CP 6 (1986) should be referred to.

ARCHIVE

Page 32: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 32 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Table 7: Separation distances: flammable liquid or gas lines with unionflanges etc and oxygen storage.

Flammable liquid or gas line size (nominal) Liquid oxygen storage up to 200 tonnesseparation distance (metres)

mm bore inches bore metres

Up to 25 1 6.0

Up to 50 2 10.0

Above 50 2 15.0

Notes:

1. The above separation distances are intended to provide protection for the LOXstorage tank against jet flame impingement from an ignited release from theflammable liquid/gas line.

2. The distances are based on LPG as the contents of the flammable liquid/gas line andare given as a “worst case”.

3. For flammable liquids or gases other than LPG in the line, the above distances shouldbe used, unless it can be shown that smaller distances are adequate to avoid jet flameimpingement.

4. If some means of protection from jet flame impingement (such as shielding of the jointby fire resistive material) can be provided between the union/flange on the flammableliquid/gas line and the LOX storage, and this can be shown to provide an equal orgreater degree of protection than the separation distances shown, the separationdistances may be reduced.

ARCHIVE

Page 33: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 33 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Table 8: Planning Dimensions for preferred sizes of sterilizer

Wei

ght

kgm

axim

um

1400

1600

1400

1600

1800

Porta

ge fo

rIn

stal

latio

n an

d re

mov

al (b

)

mm

H x

W x

Dm

axim

um

2000

x105

0x17

50

2000

x105

0x21

00

2000

x105

0x17

50

2000

x105

0x21

00

2000

x105

0x24

20

Fully

load

ed

1740

2070

1970

2340

2500

Wei

ght (

a)Kg

Max

imum

Inst

alle

d

1550

1850

1550

1850

1950

Hei

ght

2060

2060

2060

2060

2060

C

1750

1950

1750

1950

2200

B

1200

1200

1200

1200

1200

Dim

ensi

ons

as F

igur

e 56

mm

max

imum

A

Verti

cal c

ham

ber m

achi

ne –

refe

r to

man

ufac

ture

r

1000

1000

1000

1000

1000

Nom

inal

vess

elca

paci

tym

3

0.28 0.4

0.6

0.4

0.6

0.8

Usa

ble

Cha

mbe

rSp

ace

mm

H x

W x

DM

inim

um (c

)

780x

635x

635

780x

635x

935

780x

635x

635

780x

635x

935

780x

635x

1250

Wei

ght s

houl

d be

dis

tribu

ted

usin

g a

min

imum

of 4

pad

s ea

ch m

easu

ring

a m

inim

um o

f 150

mm

x 1

50 m

m.

Whe

re p

ossi

ble

ster

ilizer

s sh

ould

be

trans

porte

d as

a w

hole

and

not

par

tially

stri

pped

.

Cha

mbe

r ope

ning

sho

uld

not b

e le

ss th

an 9

15 m

m x

660

mm

.

Labo

rato

ry a

nd E

O s

teril

izer

s sh

ould

be

size

d to

sui

t the

ir pa

rticu

lar a

pplic

atio

n. W

here

a m

ulti-

purp

ose

labo

rato

ry s

teril

izer

is to

be

inst

alle

d it

shou

ld c

ompl

y w

ith th

e da

ta g

iven

for t

he p

orou

s lo

ad.

Type

of

ster

ilizer

Poro

us lo

ad a

nd L

TS

LTS

and

F

Flui

ds

a. b. c. d.

ARCHIVE

Page 34: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 34 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

8. The zoning and routing of primary services in thehospital street vertical shafts

General

8.1 Engineering services may be distributed to departments via service shaftslocated within the hospital street. As well as facilitating verticalcommunication and distribution of services between plantrooms anddepartments, these shafts form the main vertical distribution zone. It isimportant, therefore, that sufficient space should be provided within theseshafts to accommodate the services provisions for the whole building.

8.2 Where possible, services should be positioned to interface directly with thedepartmental zoning and spacing principles set down in Chapter 9. Figures57 and 58 illustrate how space is allocated within the shaft to allow smokecanopy extract ducts on each floor level to be taken up to roof levelplantrooms in a separate fire-rated enclosure. A similar enclosure is includedfor the distribution of the departmental electrical feeder cables and isolators.At each floor level, direct access from the hospital street to the electricalenclosures is recommended. Engineering shafts, apart from thosecontaining electrical services, generally need not be carried below theground floor ceiling zone down through to the ground floor slab. Access tothese shafts for the isolation of services to ground floor and first floor may beaccomplished at first floor level (see Figures 57 and 58).

8.3 The space provision for ventilation ductwork in each shaft will be determinedby the functional, clinical and fire requirement of particular departments, andalso the limitations imposed by the available service void heights inside thebuilding. Piped water services are generally grouped in one shaft, whilemedical gas services are contained in another.

Standard shaft arrangement

8.4 The standard arrangement shown consists of two rectangular shaftsinterfacing directly with a department which does not contain a lift orstairway.

Alternative shaft arrangement

8.5 This arrangement is only appropriate where a lift and/or stairway isincorporated within the department entrance. The services provision issimilar to the standard arrangement but the shafts are contained within thezone by the lift or stairway.

ARCHIVE

Page 35: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 35 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Drawings

8.6 The drawings depict basic zoning principles for typical departmentalaccommodation and show how they may be interpreted for typical servicesrouting into engineering shafts positioned at the hospital street interface.These drawings are illustrative only and teams will need to consider localproject requirements when designing structural variations and other optionsfor accommodating services not included within this guidance.

ARCHIVE

Page 36: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 36 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

9. Service distribution within departments

General

9.1 This chapter provides guidance for all floor levels where a full width ceilingvoid can be utilised for the distribution of engineering services.

9.2 All the engineering services principles referred to in this section apply to atypical departmental layout. The zoning principles developed and describedbelow have been based on the maximum expected service requirements fora hospital complex containing various departments, each approximately1400 m2 in area, and with a minimum ceiling height of 2.7 m (excludingcorridors and WCs). For areas requiring a ceiling height of 3 m, such asoperating theatres and X-ray departments, these rules may need to bemodified accordingly.

9.3 In some departments on the top floor, roof lights may be provided and therouting of the services will need to be coordinated to suit the particular typeand application.

9.4 The services provision to each department will dictate the extent to whichindividual service zones will be utilised. Flexibility is not allowed in the pipeor duct mains zone where services have pre-determined routes dimensionedin the horizontal plane. Branch pipes and ducts should be grouped within theparticular zone to provide good access and supports arrangement.

9.5 Figures 57 and 58 illustrate typical department services layouts. These plansindicate the routing of services within the department zone and show howservices are connected to:

a. the mains distribution system located in the hospital street;b. rooftop plantrooms via the vertical services shafts.

9.6 Individual services have been allocated a zone or zones through which theymay be routed and, apart from vertical penetration by other services, eachzone is generally reserved for the assigned service or services. By zoningthe services in this manner the difficulties of coordination between them arekept to an absolute minimum. The final design solution for individualservices is left to the planning team.

9.7 When dealing with a Whole Hospital design the collection of departments isvaried in size and functions and service requirements. A standardarrangement for the services at the hospital street/development interface istherefore essential if the design of the hospital street is not to be over-complicated by different solutions at every interface. This does not meanthat a standard arrangement at the interface will solve all problems, but it will

ARCHIVE

Page 37: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 37 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

enable standard zoning and spacing arrangements within the hospital streetto be workable and easier to apply.

9.8 Drainage has more significant constraints than any other service and, as aconsequence, it is more important that its zones are not penetrated by otherservices. Moreover the services void for a particular department will containthe drainage zone for the department located on the floor above. It istherefore essential that no intrusions into the drainage zone above the falseceiling are made. It is permissible, however, for a department’s services topass through its own drainage zone, that is, below floor level. Such anarrangement should be avoided, however, since it increases costs and theneed for coordination.

9.9 The physical integration between services and the components of thebuilding, such as structure, partitions and ceiling support system, aredetermined in such a way as to suit individual departmental arrangementsand service requirements.

9.10 Each department floor may be serviced independently, from its interface withthe hospital street. The following basic rules relate to the overall routing ofservices within the department and should be applied during the earlyplanning stages of the engineering design. The rules aim to simplify thedesign and routing of services, keep the service loads and therefore sizes toa minimum at departmental entrances, minimise coordination, and lead tothe better preparation of engineering drawings.

9.11 Although each block can accommodate a part of one, or a number ofindividual departments, the basic service routing, illustrated in Figures 57and 58, remains the same.

Structure

9.12 The zoning and routing of mechanical and electrical engineering services inthis document has been set out according to a notional departmentstructural grid. The structural grid may be modified to accommodate thestructural variations within hospital developments and the designer will berequired to modify the zoning as appropriate. The suggested minimumbeam/floor slab depths are assumed to be as illustrated by Figure 59.

9.13 Mechanical and electrical vertical shafts or ducts are located at thedepartment and hospital street interface. These allow verticalcommunication of services between plantrooms and the main horizontaldistribution system into each floor.

ARCHIVE

Page 38: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 38 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Drainage zones

9.14 The drainage branch zone and the perimeter drainage zone contain alldrainage pipework. Where a department is single storey or where itconstitutes the top floor of a block, this zone may be utilised for rain-waterpipework.

9.15 The drainage vent pipe may be routed within the combined pipe and ductbranch zone, and will need to be coordinated with the other services usingthis zone.

9.16 The drainage system should be contained fully within the drainage zonesand should not impinge on any other zone. Similarly no other service shouldimpinge on the drainage zone unless it is related to the department to whichthe drainage design is associated.

Routing drainage systems

Main collection drains (ground level)

9.17 The route of each main collection drain is either towards the hospital streetor preferably towards the periphery of the building for connection into themain hospital drain.

9.18 Separate main collection drains convey the soil and waste and surface waterdrainage from each departmental department into the main hospital drain.

Vertical drainage stacks

9.19 Vertical drainage stacks may rise at the corners of each module of thedepartmental unit for a vertical drainage duct to accommodate the soil andwaste vent stacks, the surface water stack and the drainage vent pipes.

Drainage vents

9.20 Drainage ventilation pipework should be kept to a minimum.

9.21 A 50 mm diameter vent pipe may be required at the high point of all heavilyloaded main drains and spine or branch drains of exceptional length.

9.22 For top floor locations having a pitched roof, the drainage vent pipe may becontained solely within the combined duct and pipe branch zone, and routedtowards a corner stack location. The connection to the stack may not bepossible within the building and in this situation the vent may terminatethrough the roof adjacent to this position. The service branches will bepositioned and routed, and then the vent pipe(s) coordinated with them.

ARCHIVE

Page 39: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 39 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Interfloor drainage

9.23 The drainage system employed for above-ground templates is basicallyhorizontal in concept (shallow gradient). The zones through which thedrainage pipework from above-ground floor departments is routed arelocated in the service void of the department below, and are reserved fordrainage systems only.

9.24 Outlets from sanitary appliances may drop vertically through the structuralslab into the drainage branch zone below, and connect into collecting spinedrains to discharge into the perimeter drainage zone at each side of themodule.

9.25 The design should allow blockages to be cleared from above floor level viaan access point located either at or adjacent to each sanitary appliance orfitting. Rodding eyes at floor level and access to pipework below the floorslab are not generally acceptable.

Ground floor drainage

9.26 The ground floor does not impose the same restrictions on the penetrationand zoning of the drainage pipework. A similar concept may, however, befollowed.

9.27 Internal manholes should be provided at the junction between spine andmain drains only in areas where they are clinically acceptable.

Pipework service zone

Pipe main zones

9.28 The pipe mains are contained in zones within the services void as follows:

a. Central pipe main zones – these zones contain all piped distributionservices with the exception of the drainage pipework and thecompensated low pressure hot water (LPHW) heating mains (see Figure60);

b. Perimeter pipe mains zones – these zones, which run down theperimeter of each side of the block, contain only the compensatedLPHW heating mains. The positions shown should be adhered to sincethey generally allow for the most economic runs of the services.

ARCHIVE

Page 40: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 40 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Combined duct and pipe branch zone

9.29 To fully utilise the total space requirements of the engineering services void,the duct and pipe branch zones are combined. This will entail a greaterdegree of coordination of services and therefore will necessitateidentification of the ventilation requirements at an early stage.

9.30 When routing the branch ducts in this zone an overall dimensional allowanceof 50 mm should be made for flanges, supports and insulation.

Pipe branches

9.31 Branch pipes do not have prescribed routes within the branch zone. Theyneed, therefore, to be coordinated with the branch ventilation ductwork andthe electrical services where they pass through the crossover zone orelectrical zone.

Low pressure hot water heating

Compensated temperature circuit

9.32 The general pipework arrangement within the service void of eachdepartment unit for radiator and convector systems is shown in Figure 60.

9.33 The branch pipework to local low level circuits at the perimeter should dropwithin a vertical (100 mm min) engineering zone at the perimeter of theblock.

9.34 Terminal emitters sited internally within the department can be served vialocal partitions. In this instance, isolating and regulating valves should not bepositioned within the partitioning unless suitable access to them can bearranged.

Constant temperature circuit

9.35 Ceiling mounted fan convectors, and duct mounted heating coils requiringconstant temperature low pressure hot water, may have control valveslocated within the false ceiling. As no alternative is available to the siting ofthese valves, every effort should be made to ensure that good access to andaround these fittings is made available.

ARCHIVE

Page 41: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 41 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Hot and cold water services

Hot water service

9.36 Each department may be served separately from the hospital street by aconventional two-pipe flow and return system. The pipework is routedhorizontally in a predetermined position through the service void to dropperpositions adjacent to the draw-off points. Careful consideration must begiven to the routing of branch flow and return pipework to draw-off pointsparticularly to avoid venting problems.

Cold water service

9.37 Provision has been made within the rules for a single potable cold waterservice (CWS) pipe. The main enters the department from the hospital streetand runs in a predetermined position within the service void. The systemdesign must observe all the necessary precautions against back siphonageas outlined in SHTM 2027; Hot and cold water supply, storage and mainservices.

9.38 The CWS pipework to draw-off points will drop from the high leveldistribution pipework to draw-off points either within the thickness of thepartition or via vertical pipe ducts adjacent to a fitting or range of fittings.

Fire-fighting services

9.39 Reference should be made to NHS in Scotland Firecode.

9.40 Where a sprinkler system is installed, the distribution pipes may be run inthe combined duct and pipe branch zones and coordination will be requiredwhere the branch pipes pass through the electrical and ceiling zones toconnect to the sprinkler heads.

Medical gases

9.41 Consideration should be given to the siting of the main isolation valves atdepartment entrances and nurses' station. The valves will need to beaccessed in an emergency and for maintenance; they should therefore belocated in a site that is readily accessible and unlikely to be obstructed byequipment. See SHTM 2022 for specific requirements.

ARCHIVE

Page 42: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 42 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Electrical sub-main

Sub-main feeder cables

9.42 The main feeder tray which carries the essential and non-essential sub-mainfeeder cables to the departmental switchcupboard should have apredetermined route dimensioned in the horizontal plane within the hospitalstreet.

Trunking and conduit

9.43 There is no predetermined horizontal position for the distribution trunkingand fire conduit. However, it is recommended these be routed within themain services zone in a readily accessible position above corridor areas,where practical, or in areas where normal departmental routines will not beinterrupted.

Ceiling zone

9.44 This zone provides the spatial requirements necessary to accommodate theceiling and the support members.

9.45 Access will be required through the ceiling zone into the space above for theinspection and maintenance of all plant and equipment located in the ceilingzone.

9.46 Items of equipment which require regular attention should be positioned inareas which will cause minimum disruption to department routines.

Ventilation zones

9.47 An allowance of 50 mm is included in the depth of the ventilation zone forflanges, supports and insulation, and to provide a clearance betweenadjacent zones.

Duct mains zones

9.48 Supply, clean and dirty extract air ducts may enter the department from thevertical engineering services shafts at the hospital street interface. Theythen may run horizontally within the duct mains zones which run down eachside of the block.

9.49 Duct mains, to serve the side areas of the department, are routed initiallyinto the combined duct and pipe branch zone. Once the perimeter drainagezone within the side module has been cleared, the ducts may then rise backinto the main ventilation zone of the side module.

ARCHIVE

Page 43: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 43 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Fire dampers

9.50 Fire dampers are required in ducts which pass through fire compartmentfloors and walls. Regular access will be required to check and reset all fireand smoke dampers. Adequate space for access to the fire damper shouldbe provided to allow service personnel access to service and reset thedamper.

9.51 Further advice and information on the provision of fire dampers is containedin NHS in Scotland Firecode.

Electrical zone

Electrical main zone

9.52 This zone contains both the essential and non-essential sub-main feedercables which run from the electrical riser switchroom in the hospital street tothe department switchcupboard. The department switchcupboard should belocated centrally within the department.

Departments with 3 m high ceilings

9.53 Basic spacing and zoning principles can be applied to departments, such asX-ray and operating theatres, which have a ceiling height of 3 m.

9.54 In all cases the drainage zone related to such a department should not bepenetrated unless the precise routing of these drains is known.

Departments with 2.4 m high ceilings

9.55 A 2.4 m high ceiling will not normally involve any major engineering routingproblems. It will also be possible to maintain the basic zoning and spacingprinciples for the main through services within the department and wherethese interface with the hospital street.

9.56 The drawings in this chapter depict, for ground, intermediate and top floorlocations, basic zoning principles and how they may be interpreted for typicalservices provision. These drawings are illustrative only and design teamsmay need to include local project variations to suit particular needs. In thisrespect roof profiles, structural systems and roof lights can often imposezoning and routing constraints not included within this guidance.

ARCHIVE

Page 44: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 44 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

10. Definitions

10.1 Chase: An accommodation for small services cut or formed in the buildingfabric and covered by the normal finish. Subsequent access is usuallyobtained by destroying the finish.

10.2 Crawlway: An enclosed horizontal space for services large enough to permita person to crawl along for a reasonable distance or work in crampedconditions for a reasonable period according to circumstances and installedservices, when all services have been installed.

10.3 Duct (horizontal): A general term referring to an enclosed space used forthe distribution of horizontal services.

10.4 Duct (vertical): An enclosure specifically designed for the controlledmovement of air.

10.5 Ha-ha: An open trench with one or both sides sloped in which services arerun to avoid spoiling the general appearance of the landscape.

10.6 Lift well: A vertical space through a building in which lifts will be installed.

10.7 Plant: Equipment supplying or served by the engineering services or usedfor their maintenance.

10.8 Public health engineering: The drainage system within the building,including waters, overflows, soil pipes, and rainwater pipes.

10.9 Service corridor: A passageway at or above ground level, primarilyintended for the use of hospital personnel. Part of such a passageway maybe suitably separated for the accommodation of services.

10.10 Services: The mechanical, electrical and public health engineering servicesdistributed throughout the hospital.

10.11 Subway: An underground traffic route between buildings through oralongside which provision may be made for the installation of services.

10.12 Trench: A covered horizontal services space in the floor or ground withaccess from above.

10.13 Void: A space formed in the construction of a building, which can be usedfor the installation of services, but is not necessarily constructed for thatpurpose.

10.14 Walkway: An enclosed space for horizontal services, large enough to permita person to walk freely and work comfortably when all services have beeninstalled.

ARCHIVE

Page 45: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 45 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

10.15 Department: the building envelope containing a department which may beon a single floor or multi-floors.

10.16 Template: the floor of a block which can be isolated as a single entry withina hospital development and may contain more than one department.

10.17 Ready use store: a local store within a particular department for a limitednumber of medical gas cylinders - usually one day’s supply for reservepurposes, and cylinders for immediate use.

10.18 Fire Safety Officer: as defined in NHS in Scotland Firecode.

10.19 Flammable: capable of burning with a flame.

10.20 Main cylinder storage area: the main area where all cylinders on a site arestored, excluding only those cylinders in use in manifold rooms or in readyuse stores.

10.21 Manifold rooms: a purpose built room designed to accommodate a cylindermanifold installation, and reserve cylinders as appropriate.

10.22 Medical gases: gases used for clinical purposes.

10.23 Non-medical gases: all other gases including those used for industrialpurposes and in laboratories and pathology departments.

ARCHIVE

Page 46: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 46 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

From top:

Figure 1: Total engineering area per gross floor area

Figure 2: Calorifier plantroom/gross floor area

Figure 3: Ventilation plantroom/gross floor area

E N G IN E E R IN G A R E A C O M P R IS E S :

C A L O R IF IE R P L A N T R O O M SV E N T IL A T IO N P L A N T R O O M SL IF T W E L L S A N D M O T O R R O O M SV E R T IC A L D U C T SW A T E R S T O R A G ES W IT C H R O O M S

U P P E R

L O W E R

G R O S S F L O O R A R E A ( E X C L U D IN G E N G IN E E R IN G A R E A S ) 1 0 0 0 S Q . M .

0 5 1 0 1 5 2 0 2 5 3 0 3 5 4 0 4 5 5 0

F IG U R E 1 T O T A L E N G IN E E R IN G A R E A P E R G R O S S F L O O R A R E A

5 0 0 0

4 0 0 0

3 0 0 0

2 0 0 0

1 0 0 0

TO

TA

L E

NG

INE

ER

ING

AR

EA

SQ

. M

.

G R O S S F L O O R A R E A ( E X C L U D IN G E N G IN E E R IN G A R E A S ) 1 0 0 0 S Q . M .

F IG U R E 2 C A L O R IF IE R P L A N T R O O M /G R O S S F L O O R A R E A

AR

EA

OF

CA

LO

RIF

IER

PL

AN

T R

OO

M (

SQ

. M

.)

3 0 0

0 5

2 0 0

1 0 0

5 0 0

4 0 0

1 51 0 2 0 3 02 5 3 5

L O W E R

U P P E R

4 54 0 5 0

G R O S S F L O O R A R E A ( E X C L U D IN G E N G IN E E R IN G A R E A S ) 1 0 0 0 S Q . M .

AR

EA

OF

VE

NT

ILA

TIO

N P

LA

NT

RO

OM

(S

Q.

M.)

0

2 5 0

5

5 0 0

7 5 0

1 0 0 0

1 2 5 0

1 51 0 2 0 3 02 5 3 5

L O W E R

U P P E R

4 54 0 5 0

ARCHIVE

Page 47: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 47 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

From top:Figure 4: Lift wells and motor rooms/gross floor area.Figure 5: Lift wells and motor rooms/gross floor area.Figure 6: Vertical duct area/gross floor area.

AREA COMPRISES: LIFT WELL(S)SIZE x NUMBER OF FLOORSSERVED + AREA OF MOTOR ROOMS

SIX TO TEN FLOORS

THREE TO SIX FLOORS

GROSS FLOOR AREA (EXCLUDING ENGINEERING), 1000 SQ. M.

0 5 10 15 20 25 30 35 40 45 50

1250

1000

750

500

250

AR

EA

OF

LIFT

WEL

LS A

ND

MO

TOR

RO

OM

S S

Q. M

.

GROSS FLOOR AREA (EXCLUDING ENGINEERING), 1000 SQ. M.

AR

EA

OF

LIFT

WEL

LS A

ND

MO

TOR

RO

OM

S S

Q. M

.

300

0 2

200

100

500

400

64 8 1210 14 1816 20

GROSS FLOOR AREA (EXCLUDING ENGINEERING), 1000 SQ. M.

AR

EA

OF

VER

TIC

AL

DU

CTS

SQ

. M.

0

200

5

400

600

800

1000

1510 20 3025 35 4540 50

THREE TO SIX FLOORS

SIX TO TEN FLOORS

AREA COMPRISES: LIFT WELL(S)SIZE x NUMBER OF FLOORSSERVED + AREA OF MOTOR ROOM(S)

ARCHIVE

Page 48: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 48 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

From top:Figure 7: Water storage room/gross floor areaFigure 8: Switchroom/gross floor area

5

5

AREA

OF

SWIT

CH

RO

OM

S, S

Q. M

.

100

0

AREA

OF

WAT

ER S

TOR

AGE

RO

OM

S, S

Q. M

.

500

400

200

300

100

0

200

300

400

500

GROSS FLOOR AREA (EXCLUDING ENGINEERING), 1000 SQ. M.

10 15 20 25 30 35 40 45 50

GROSS FLOOR AREA (EXCLUDING ENGINEERING), 1000 SQ. M.

2010 15 25 3530 40 5045

ARCHIVE

Page 49: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 49 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 9: Main engineering distribution within hospital

Internal Duct serving Specialist Dept. i.e. Pathology Operating Theatre.

Detached plant area at ground level in close proximity to energy centre housing the high voltage electrical intake standby generator transformers, medical gas stores and flammable liquids store.

Mains Distribution to Development.

An energy centre may be integrated with the hospital and located close to the primary energy consumers to ensure short distribution routes for mains.

Energy Dept.

Horizontal Distribution at High or Low level to Departments.

Roof Level Plant room.Horizontal service distribution zones

Ceiling Void

Department

First floor

Ground floor

Ceiling Void

Department

Ceiling VoidCeiling VoidHorizontal Service Distribution into Dept.

Vertical Service Distribution Ducts.

Hospital Street

Hospital Street

Main Engineering Distribution Principles Hospital Street - Department Interface.

Floor or Basement Duct for Horizontal Distribution.

Figure 9: Main Engineering Distribution within HospitalFigure 10

Internal Ductserving SpecialistDept. e.g.PathologyOperating Theatre

ARCHIVE

Page 50: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 50 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 11: Composite of duct and service spares

Figure 13: Typical cross-section of crawlway

Figure 14: Typical cross-sectionof walkway

Figure 12: Typical cross-section

ARCHIVE

Page 51: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 51 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 15: Clearance areas around pipes and valves

Figure 16: Typical cross-sections

Figure 17: Typical cross-section of ventilation duct areas

ARCHIVE

Page 52: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 52 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 18: Clearance dimension around duct

WIDTH (OR DIAMETER) A OR DEPTH B OF DUCT (mm)

CLEA

RANC

E SP

ACE

(mm

)

100

0 5

200

300

400

500

10 15 20 25 30 35 40 45 50

TOP AND BOTTOM CLEARANCE C

SIDE CLEARANCE D

ARCHIVE

Page 53: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 53 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 19: Typical cross-section showing spacing of services

Figure 20: Typical cross-sections of vertical ducts.

ARCHIVE

Page 54: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Figure 21: Typical cross-section of ha-ha

10 mm clearance toInsulation

Roller

Cement Plinthl

D

Drain Channe

Version 2.0: June 2001 Page 54 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Roller Guide

Walkway

rain Channel

ARCHIVE

Page 55: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 55 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 22: Typical cross-section of ha-ha

ARCHIVE

Page 56: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 56 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 24: Typical cross-section of service trench – external.

Figure 23: Typical cross section of service trench - internal

Figure 25: Typical cross-section showingchases in brickwork or concrete

ARCHIVE

Page 57: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 57 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 26: Anthropometric data – body dimensions

KNEELPRONE

CRAWL

MAINTENANCE REACH LEVELS

SQUAT

STOOP

GENERAL

Passageway

ARCHIVE

Page 58: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 58 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 27: Anthropometric data – climbing dimensions

ARCHIVE

Page 59: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 59 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 28: Typical plantroom 1 serving a combination of 24 hr and 9-5accommodation departments. End location

CONTROL PANELS

SMOKE EXTRACT FAN

AIR HANDLING UNIT(AHU)

(AIR HANDLING UNIT)

AHU FOR 9-5 ACCOMMODATION

1.5 m

DIRTY EXTRACT

(D / EXT)PLANTTWIN

SHAFT

SMOKE EXTRACTS

SHAFT

MECHANICAL SERVICES CONTROL PANEL

( C / EXT )PLANT

CLEAN EXTRACTFRESH AIR

INLET LOUVRES

SECTION

AHU FOR 24 HR ACCOMMODATION

15.6m

HEATING & CH WATER MAINS SERVING AHU BATTERIES

ELECTRICAL DISTRIBUTION PANEL

FIRE MAIN CONN.

11.6

m2.

6 m

1.5 m

SHAFT SHAFT

³/S

³/S

ARCHIVE

Page 60: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 60 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 29: Typical plantroom 2 serving a combination of 24 hr and 9-5accommodation departments

SHAFT

CONTROL PANELS

SMOKEEXTRACTFAN

SECTION

SPECIAL EXTRACT PLANT /FANS

A H U

SPECIAL EXTRACT PLANT FANS AT HIGH LEVEL

A H U

FRESHAIRINLET LOUVRES

FIREMAINCONN

SMOKE EXTRACTS

SMOKE EXTRACTS

MEC

H

ELEC

D / EXTPLANT(TWIN)

C / EXTPLANT

A H U FOR 24hrACCOMMODATION 0.6m³/S

HEATING & CH WATERMAINS SERVINGA H U BATTERIES

A H U FOR DAYACCOMMODATION5.0m³/S

SHAFT

SHAFTSHAFT

3.3m

11.6

m

15.6m

ARCHIVE

Page 61: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 61 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 30: Typical plantroom 3 serving a combination of 24 hr and 9-5accommodation departments

A H U

CONTROLPANELS

SMOKE EXTRACT

FAN

3.3m

SECTION

A H U FOR 9-5 ACCOMODATION

3.5m³/s

SHAFT

ELEC.

MEC

H.

C / EXTPLANT

D / EXTPLANT(TWIN)

FIRE MAIN CONN.

HEATING AND C H WATERMAINS SERVING A H U

BATTERIES

11.6

m

15.6m

FRESH AIR INLET LOUVRES

SMOKEEXTRACTS

SHAFT

SHAFT SHAFT

A H U

SMOKE EXTRACTSA H U FOR 24HR ACCOMODATION

0.6 m³/s

ARCHIVE

Page 62: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 62 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 31: Typical plantroom 4 serving combined 24 hr and 9-5accommodation

ELEC. MECH.

SMOKE EXTRACTS

SMOKE EXTRACTS

FIREMAINCONN

15.6m

SHAFT SHAFT

AHU AT HIGH LEVEL 1.0m³/S

MAINS PIPE WORK AT HIGH LEVEL

CABLE ROUTE FROM LV SW RM TO FEED L.H. SIDE OF

HOSPITALCABLE ROUTE TO

SERVE R.H SIDE OF HOSPITAL

HEATING & CH WATER MAINS FROM ENERGY

CENTRE TO AHU BATTERIES IN PLANT ROOM

LV SWITCH ROOM

6.1m

CONTROL PANELS AHU FOR 24HR 9-5 ACCOMMODATION

3.7m

SECTION

ARCHIVE

Page 63: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 63 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 32: Typical plantroom 5 serving a combination of 24 hr and 9-5accommodation departments

AHU

CONTROL PANEL

SMOKE EXTRACT

FAN

3.3m

SECTION

SHAFT SHAFT

SMOKE EXTRACTS

ELEC.

MEC

H.

SPECIAL EXTRACTSFROM 9-5 DEPT

FIRE MAIN CONN.

SMOKE EXTRACTS

11.6

m

15.6m

FRESH AIRINLET LOUVRES

HEATING AND CH WATER

MAINS SERVINGAHU BATTERIES

AHU

SPECIAL AHU to 9-5 DEPT 0.25m³/s

D/EXTPLANT(TWIN)AT H/L

C/EXTPLANT

HEATING & CH WATER MAINS

SERVICING A H UBATTERIES

AHU FOR 9-5ACCOMMODATION

4.0-4.3m³/s

SHAFT SHAFT

AHU FOR 24 hr ACCOMMODATION 0.6m³/s

ARCHIVE

Page 64: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 64 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 33: Typical plantroom 6 serving 24 hr accommodationdepartment

AHU CONTROL PANELS

SMOKE EXTRACTS

3.3m

SECTION

AHU FOR 24Hr ACCOMMODATION 5.2m³/s

SHAFT

ELEC.

MEC

H.

SPECIAL EXTRACTS

C/EXTPLANT

D/EXTPLANT(TWIN)

FIRE MAIN CONN.

HEATING AND CH WATERMAINS SERVING AHU

BATTERIES

SMOKE EXTRACTS

11.6

m

15.6m

FRESH AIR INLET LOUVRES

SMOKE EXTRACTS

SHAFT

SHAFT SHAFT

ARCHIVE

Page 65: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 65 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 34: Arrangement ‘A’ of plantroom 7 serving a combination of 24hr operating theatres (4) and 9-5 accommodation

AHU FOR 24 HR ACCOMMODATION 5.5m³/S

ELEC.

MEC

H.

HEATING AND CH WATERMAINS SERVING AHU BATTERIES

FRESH AIR INLET LOUVRES

SMOKE EXTRACTS

SHAFT

SHAFT

SMOKE EXTRACTS

AHU FOR OP. TH. ABOVE AHU FOR OP. TH. BELOW

1.3m³/s

FIRE MAINCONN

17.1

m

SHAFT

15.6m

C/EXTRACT FROM OTHER

DEPTS

D/EXT PLANT (TWIN)

C/EXTRACT FROM OTHER DEPTS

AHU FOR OP.TH., ANCIL. AREAS & 9-5

DEPTS. 2.3m ³/s

C/EXTRACT FROM OP.THEATRES

C/EXTRACT FROM OP.THEATRES

C/EXTRACT FANS MOUNTED AT MEZZ LEVEL

AHU FOR OP. TH. ABOVE AHU FOR OP. TH. BELOW

1.3m³/s

ACCESS TO MEZZANINE FLOOR

C/EXTRACT FANS AT HIGH LEVEL IN PLANT ROOM

ARCHIVE

Page 66: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 66 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 35: Section through arrangement (plantroom 7)

OP. TH 1 AHU

OP. TH 2 AHU

OP. TH 4 AHU

OP. TH 3 AHU

A H U FOR 24 HRACCOMMODATION

CONTROLPANELS(ELEC & MECH)

C/EXTRACT

SMOKE EXTRACTC/EXTRACT

HEATING & CH WATERMAINS TO AHU BATTERIES

D/EXTPLANT

ARCHIVE

Page 67: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 67 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 36: Typical plantroom serving a combination of 24 hr operatingtheatres (4) and 9-5 accommodation

AHU FOR 24 HR ACCOMMODATION 5.5m³/S

ELEC.

MEC

H.

HEATING AND CH WATERMAINS SERVING AHU BATTERIES

FRESH AIR INLET LOUVRES

SMOKE EXTRACTS

SHAFT

SHAFT

SMOKE EXTRACTS

AHU FOR OP. TH. ABOVE AHU FOR OP. TH. BELOW

1.3m³/s

FIRE MAINCONN

17.1

m

SHAFT

15.6m

C/EXTRACT FROM OTHER

DEPTS

D/EXT PLANT (TWIN)

C/EXTRACT FROM OTHER DEPTS

AHU FOR OP.TH., ANCIL. AREAS & 9-5

DEPTS. 2.3m³/s

C/EXTRACT FROM OP.THEATRES

C/EXTRACT FROM OP.THEATRES

C/EXTRACT FANS MOUNTED AT MEZZ LEVEL

AHU FOR OP. TH. ABOVE AHU FOR OP. TH. BELOW

1.3m³/s

ACCESS TO MEZZANINE FLOOR

C/EXTRACT FANS AT HIGH LEVEL IN PLANT ROOM

ARCHIVE

Page 68: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 68 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 37: Section through arrangement (plantroom from Figure 36)

AHU FOR 24HRACCOMMODATION

C/EXTPLANT D/EXT

PLANT

AHU FOR OP. TH.1 AHU FOR OP. TH.2

CLEAN EXTRACT FROM 2 OP. TH.

CLEAN EXTRACT FROM 2 OP. TH.

4.5m

ARCHIVE

Page 69: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 69 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 38: Typical plantroom serving a combination of 24 hr operatingtheatres (2) and 9-5 accommodation. End location.

AHU FOR 24hr ACCOMMODATION

5.2m³/s

ELEC

.

MECH.

C/EXTPLANT

D/EXTPLANT(TWIN)

HEATING AND CH WATERMAINS SERVING AHU

BATTERIES

FRESH AIR INLET LOUVRES

SMOKE EXTRACTS

SHAFT

SHAFT SHAFT

SMOKE EXTRACTS

AHU TO OP TH 1.3m³/S

AHU TO OP TH 1.3m³/S

FIRE MAINCONN

17.1

m

SHAFT

15.6m

ARCHIVE

Page 70: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 70 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 39: Section through plantroom from Figure 38

CONTROL PANELS

SMOKE EXTRACT FAN

AHU 5.2m ≥/ σ³/s

3.3m

HEATING & CH WATERMAINS TO A H U

BATTERIES

ARCHIVE

Page 71: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 71 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 40: Typical plantroom. End location

CONTROL PANEL

SMOKE EXTRACT

CLEAN EXTRACT FAN

DIRTY EXTRACT

SMOKE EXTRACT FAN

SMOKE EXTRACTSCONTROL PANEL

AIR HANDLING UNIT

SECTION

DIRTY EXTRACT

CLEAN EXTRACT

WALKWAY

SHAFTS

AIR HANDLING PLANT3.0m³/s TO 3.5m³/s

CONST. TEMP. HEATING & CHILLED WATER F & R TO HEATER AND COOLER BATTERIES

PLAN

2.6m

16.3m

2.6m

ARCHIVE

Page 72: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 72 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 41: Typical plantroom serving a combination of 24 hr and 9-5accommodation

SMOKE EXTRACTS

WALKWAY

FRESH AIR INLET PLENUM

AIR HANDLING PLANT2.5m³ /S

2 O

PER

ATIN

G T

HEA

TRES

AIR

H

AND

LIN

G P

LAN

T 2.

3m³/s

CONTROL PANEL

SHAFTS

16.30

DIRTY EXTRACT

WALKWAY

TO CLEAN EXTRACT FANS

CLEAN EXTRACT

FRESHAIRINLET

2 O

PER

ATIN

G T

HEA

TRES

AIR

H

AND

LIN

G P

LAN

T 2.

3m³/s

NOTE

PLAN

SMOKE EXTRACT FAN

FRESH AIR INLET

FROM DIRTY EXTRACT FANS

FROM CLEAN EXTRACT FAN

AccessDoor

2 OperatingTheatresA/H Plant

CONTROLPANEL

SECTION

FRESH AIR SUPPLY PLENUM

CONST. TEMP. HEATING AND CHILLED WATER CONNECTIONS TO HEATER & COOLER BATTERIES OMITTED FOR CLARITY

2 OperatingTheatresA/H Plant

16.3m

16.3

m2.

6m

ARCHIVE

Page 73: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 73 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 42: Typical plantroom including hot water boilers and HWScalorifiers

2.6m

CLEAN EXTRACT FAN

AIR HANDLING PLANT

WALKWAY

AIR HANDLING PLANT5.0m³/s

AIR GRILLE

CONTROL PANEL SHAFTS

CLEAN EXTRACT

SMOKE EXTRACTS

WALKWAY

DIRTY EXTRACT

COMPENSATED TEMP. HEATING

PUMPS

CONSTANT TEMP

HEATING PUMPS

BOILERS2 x 900Kw

HWS PUMPS

H.W.S. CALORIFIERS

CONST. TEMP. HEATING AND CHILLED WATER CONNECTIONS TO HEATER AND COOLER BATTERIES OMITTED FOR CLARITY

NOTE

PLAN

16.3m

SMOKE EXTRACT

PUMPS

FROM DIRTY EXTRACT FANS

BOILERSBOILERSH.W.S.PUMPS

CALORIFIER

SECTION

16.3

mARCHIVE

Page 74: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 74 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 43: Typical segregated routes for services not to scale

LUM

INAI

RE

FIN

ISH

ED F

LOO

R L

EVEL

MIN

IMU

M

DIS

TAN

CE

ELEC

TRIC

AL

SER

VIC

ES

CR

AWLW

AY S

ERVI

CES

TUN

NEL

OR

TR

ENC

H

MIN

IMU

M

DIS

TAN

CE

MEC

HAN

ICAL

AN

D

BUIL

DIN

G S

ERVI

CES

TEM

POR

ARY

LIG

HTI

NG

/PO

WER

SOC

KETS

DR

AIN

AGE

CH

ANN

EL

DU

CTS

TO

BE

WAT

ERPR

OO

FED

SUBW

AY O

R W

ALKW

AYSE

RVI

CES

TU

NN

EL

DR

AIN

AGE

CH

ANN

EL

1.0m

2.0m

TYPI

CAL

CEI

LIN

G V

OID

SER

VIC

ES IN

A C

OR

RID

OR

CO

RR

IDO

R

ACC

ESS

PAN

ELS

IN

SUSP

END

EDC

EILI

NG

VEN

TILA

TIO

N

DU

CT

0.6m

MIN

IMU

M

ELEC

TRIC

ALSE

RVI

CES

MEC

HAN

ICAL

SER

VIC

ES

1.1m

MIN

IMU

MD

ISTA

NC

E

TEM

POR

ARY

LIG

HTI

NG

/PO

WER

SO

CKE

TS

MEC

HAN

ICAL

SER

VIC

ES

ELEC

TRIC

ALSE

RVI

CES

0.9m N

OT

TO S

CAL

E

ARCHIVE

Page 75: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 75 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 44: Sub-station with HV ring main switchboard, twotransformers and low voltage switchboard cubicle type

D RY T RA NS FO RM E R C UB ICLE

S TE E L S CRE E N(RE M O V A B LE )

W ITH DRA W A LS P A CE

E S C A P E DOOR

D U CT

H VS W ITC H

D U C T ORT R E NCH

C A B LE T RE NCH

D O O RD UC TS

D O O RS

L.V .S W ITCHB OA RD

R E A R A C CE S S

D UC TSF IR E S C RE E N FLOOR T O CE IL ING

P LA N

F ig ure 44 S u b-stat io n wi th H V ring m ain sw it ch bo ard, two t ra ns fo rm ers an d lo w vo lt age switchboard cubicle type

C OV ER ED C ABLE T R EN C H

D U C TS D U C TS

C OV ER ED C ABLE T R EN C H

T RA NS FO RME R

T RA NS FO RME R

C BW IT H D R A W AL S PAC E

D OO R P LAC ED O P P O S ITE E N D T O E SC A PE D O OR

H V SW IT C H T R IP AN D C LO SE B AT TE R Y C H AR GER

HV

SW

ITC

HB

OA

RD

LOU VR ED D OORE SC APED O OR

S PA C E F OR F U TU R E E XT EN SION

W IT H D R A W AL S PAC E

D OO R S

A

B

A

B

A

B

F IR E BA R R IE R S IN C AB LE T R EN C H

LV

SW

ITC

HB

OA

RD

Figure 45: Sub-station with single HV switch, dry transformer andlow voltage switchboard

DRY TRANSFORMER CUBICLE

ARCHIVE

Page 76: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 76 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 46: Typical diesel generator installation (100kW)Lo

w le

vel a

irin

let v

entil

ator

sw

ith a

djus

tabl

elo

uver

s.E

xhau

st p

ipe

wal

l cle

aran

ce

Exh

aust

si

lenc

er

Lagg

ed e

xhau

stpi

pe a

t hig

h le

vel

Eng

ine

radi

ator

Flex

ible

se

ctio

n

Bat

tery

door

door

door

Tem

pera

ture

cont

rolle

rs

Bat

tery

char

ger

Hig

h an

d lo

wro

om te

mpe

ratu

real

arm

ther

mos

tat

Ele

ctric

room

heat

ing

ther

mos

tat

3.6m approx.

7.0m

app

rox.

Rol

ler d

oor

NO

TE: T

ypic

al o

pera

ting

valu

es fo

r eng

ine

room

tem

pera

ture

ala

rms:

hig

h te

mpe

ratu

re

35°C

low

tem

pera

ture

7°C

Rem

ote

indi

cato

r lam

ps a

nd a

udib

le a

larm

pos

ition

ed a

t a p

erm

anen

tly

man

ned

stat

ion,

for e

xam

ple

in th

e bo

iler h

ouse

.

T

TT

415v

sw

itchb

oard

and

cont

rol p

anel

T

Ant

i-vib

ratio

nm

ount

ings

Ben

ch

CP

Dai

lyS

ervi

ceFu

elTa

nk

ARCHIVE

Page 77: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 77 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 47: Typical layout for two 300 kW diesel generator sets

Note: Layout not to scale.

Battery

T

TT

T

Adjustable louvred ventilators at low level

for air inlet

Roller doors

door

doors

door

1.8m

7.5m

app

rox.

Space heatingcontrols

Switchgearand controlequipment

Acoustic wall and window

Battery

1.2m

fitters bench

240v socket outlet

Bulk fuel oil storagetank

Fire resistingenclosure

Oil retainingwall

Rotor draw out clearance

Engine starting battery charger

Roller doors

Ventilating fan at high level

Engine starting battery charger

Duct betweenengine radiator

and louvred air outlet

cable trench

2.5m

0.6m

300kW DIESELGENERATOR

Dailyservice

fuel tank

ARCHIVE

Page 78: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 78 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 48: Plantroom areas for HWS storage calorifiers

Figure 49: Plantroom areas for heating calorifiers

ARCHIVE

Page 79: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001

Figure 50: Sectional elevation on cistern

800mm

1000mm clearance

450mm min belowsectional tanks

Minimum clearance around cistern excluding allowance for access to valves and other equipment

NOTE: Clearancemanufacturers’ re

s

600mm min belowsectional cisterns

A

500mm min for access800mm min for acces

Page 79 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

800mm

below sectional cisterns to be in accordance withquirements which may be greater than 600 mm.

RCHIVE

Page 80: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 80 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 51: Typical arrangement of combined manifold and gas cylinderstorage rooms

P ressu re regu la to rsgaug es and C on tro l U n it

E m ergencyM an ifo ld

P ressu re R egu la torsgauges andC on tro l U n it.

2 x 4 M an ifo ld

S pare cylinde rson rack a roundw a ll.

27

00 m

m

2 300 m m

2300 m m

27

00 m

m

3 960 m m

30

50 m

m

2 x 6 M an ifo ldS pare cylinde rson W a ll R ack and cen tra l doub le support rack .

2 x 8 M an ifo ldM axim um E xterna lD iam e te r o fC ylin de rs 200m m

S pare C y linde rs a rranged ve rtica llyon racks a nd a t 225m m cen tres

C ylin de rs onM an ifo lds a t250m m cen tres

ARCHIVE

Page 81: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 81 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 52: Typical plan of medical air compressor plantroom

F .A .D . 7 .2 ba r (litre s)

Len g th 'A 'm in im um (m m )

Len g th 'B 'm in im um (m m )

R oo f H e igh t m in im um (m m )

C apac ity a t m inus 500 H g (L itres /m in )

Len g th 'A 'm in im um (m m )

Len g th 'B 'm in im um (m m )

R oo f H e igh t m in im um (m m )

180 38 00 37 00 24 0014 0038 00

47 0057 00

49 0059 00

32 0038 00

180 42 00 39 00 26 0014 0038 00

43 0058 00

41 0047 00

26 0026 00

50 00 61 00 79 00 26 00

W all m o un ted C on tro l P ane lR ece ive r

T w in co m p ressor

un it

Dry

ers

an

d F

ilte r

s

W a ll m o un ted C on tro l P ane l

T raps

&

F ilte rs

Va

cuum

P

um

p

no

.1

Va

cuum

P

um

p

no

.2

R ece ive r

F igu re 52 T yp ica l p lan o f m e d ica l a ir com presso r p lan troomFigure 53: Typical plan of medical vacuum plantroom.

ARCHIVE

Page 82: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 82 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 54: Safety distances: distances between oxygen storage andtypical exposure for storage tanks up to 20 tonnes net liquid capacity(in metres)

ARCHIVE

Page 83: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 83 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 55: Distance between oxygen storage and typical exposure forstorage tanks of 20 tonnes to 200 tonnes net liquid capacity (in metres)

ARCHIVE

Page 84: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 84 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 56: Typical layouts not to scale

1.Sliding doors are illustrated.2.Lighting fittings should be installed between and not over sterilizers.3.Refer to Table 8.5 for dimensions.4.For temperature sensor access a 50mm aperture with a swing single fixing cover should be fitted on the fascia at a low level and between each sterilizer.5.An electrical isolator for each sterilizer should be located in the plantroom.6.In the working area the distance between the fascia and the oppositewall should be 3m or twice the length of the loading carriage.7.Ventilation air to the plant room may be taken in at a low level from the working area or from an independent source.

FasciaEmergency Power Isolation

Air outlet

SINGLE STERILIZER

Emergency Power Isolation

STERILIZER GROUP Access for maintenance and testing

Piped services at high levelA B CA

C

A

AC

B B

A

B

A A

A

ARCHIVE

Page 85: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 85 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 57: Standard arrangement – engineering shafts level plan

ARCHIVE

Page 86: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 86 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 58: Standard arrangement – engineering shafts section at streetinterface

ARCHIVE

Page 87: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 87 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 59: Typical sectional elevation through a multi-storey departmentshowing suggested minimum service zones

Floor slabBeam Depth use for Drainage

Main Service Zone 350mm

Crossover zone 200mm

Electrical 100mmCeiling grid 100mm

Activity Space

Finished Floor Level

2700mm typical floor to ceiling height

1200mm

Zone 250mm

ARCHIVE

Page 88: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 88 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

Figure 60: Standard arrangement – flat slab section at departmentinterface

PLA

NT

RO

OM

FLO

OR

VE

NTI

LATI

ON

ZO

NE

PLA

NT

RO

OM

FLO

OR

400

x35

0 P

ER

IME

TER

H

EA

TIN

G

MA

INS

ZO

NE

850

300

900

650

x35

0M

ED

ICA

LG

AS

ES

ZON

E

200

900

400

900

200

2750

x 3

50 P

IPE

MA

INS

ZO

NE

FOR

FIR

ST

2.05

M F

RO

M H

OS

PIT

AL

STR

EE

T26

00 x

350

40

0 x

350

PE

RIM

ETE

RP

IPE

M

AIN

S

ZON

E

850

VE

NTI

LATI

ON

ZO

NE

1200

AT

INTE

RFA

CE

EX

IT F

RO

M S

HA

FT

175

250

350

200

75 100

400

100

ZON

ING

PR

INC

IPLE

S

600

1200

1200

1200

850

850

CE

NTR

ES

OF

CE

ILIN

G S

UP

PO

RT

GR

ID

EN

GIN

EE

RIN

G Z

ON

E(B

ELO

W F

/CE

ILIN

G)

STR

UC

TUR

AL

ZON

E

27001150

STRUCTURAL ZONE OPTION 'B'

STRUCTURAL ZONE OPTION 'A'

STRUCTURAL ZONE OPTION 'B'

ELECTRICAL MAINS ZONE

7900

SA

NIT

ATI

ON

V

EN

TC

OM

P. T

EM

P. L

.P.H

.W. F

LOW

CLE

AN

E

XTR

AC

TS

UP

PLY

A

IRS

UP

PLY

A

IRCO

RE

ZON

E S

UP

PLY

AIR

DIR

TY

EX

TRA

CT

H.W

.S. F

LOW

H.W

.S. R

ETU

RN

FIR

E M

AIN

C.W

.S.

OP

TIO

NA

L P

OS

ITIO

N F

OR

A

LTE

RN

ATI

VE

S

ER

VIC

ES

P

RO

VIS

ION

SM

ALL

PO

WD

ER

&

LIG

HTI

NG

CA

BLE

TR

UN

KIN

G, F

IRE

ALA

RM

C

ON

DU

IT &

C

OM

MU

NIC

ATI

ON

S C

AB

LE

TRU

NK

ING

LO

CA

TED

A

BO

VE

CO

RR

IDO

R

CO

MP

. TE

MP

. L.P

.H.W

. R

ETU

RN

OX

YG

EN

ME

DIC

AL

VA

CU

UM

OP

TIO

NA

L M

ED

ICA

L G

AS

S

ER

VIC

ES

MA

IN C

AB

LE

TRA

Y

DIR

TY

EX

TRA

CT

CO

RE

ZON

E S

UP

PLY

AIR

SU

PP

LY A

IR SU

PP

LY A

IR

CLE

AN

E

XTR

AC

T

CO

MP

. TE

MP

.L.

P.H

.W. F

LOW S

AN

ITA

TIO

N

VE

NT

CO

MP

. TE

MP

.L.

P.H

.W. R

ETU

RN

7900

950

1300

4000

550

325

500

600

400

200

150

300

150 15

0150

VE

NT

PIP

E F

RO

MS

TAFF

W.C

.'S

1400

100

PR

IMA

RY

CE

ILIN

G

SU

PP

OR

T M

EM

BE

RS

400

600

500

275

600

1300

950

200

VE

NT

PIP

E F

RO

M

CLE

ANER

S S

INK

PLA

NT

RO

OM

FLO

OR

TYP

ICA

L S

ER

VIC

ES

PR

OV

ISIO

N

2700

ARCHIVE

Page 89: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 89 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

References

NOTE:Where there is a requirement to address a listed reference, care should be taken to ensurethat all amendments following the date of issue are included.

PublicationID

Title Publisher Date Notes

Acts and Regulations

The Building (Scotland) Act HMSO 1959

Clean Air Act HMSO 1993

Electricity Act HMSO 1989

Health and Safety at Work etc Act HMSO 1974

Registered Establishments (Scotland)Act

HMSO 1998

The Water (Scotland) Act HMSO 1980

SI 2179 &187

The Building Standards (Scotland)Regulations (as amended)

HMSO 1990

The Building Standards (Scotland)Regulations: Technical StandardsGuidance

HMSO 1998

SI 1460 Chemicals (Hazard Information andPackaging for Supply) Regulations(CHIP2)

HMSO 1997

SI 3140 Construction (Design and Management)Regulations

HMSO 1994

SI 437 Control of Substances Hazardous toHealth Regulations (COSHH)

HMSO 1999

SI 635 Electricity at Work Regulations HMSO 1989

SI 1057 Electricity Supply Regulations (asamended)

HMSO 1988(amd1994)

SI 2372 Electromagnetic CompatibilityRegulations (as amended)

HMSO 1992

SI 2451 Gas Safety (Installation and Use)Regulations

HMSO 1998

SI 917 Health & Safety (First Aid) Regulations HMSO 1981

SI 682 Health & Safety (Information forEmployees) Regulations

HMSO 1989

SI 2115 Control of Asbestos at Work Regulations(as amended)

HMSO 1987

SI 1713 Confined Space Regulations HMSO 1997

ARCHIVE

Page 90: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 90 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

PublicationID

Title Publisher Date Notes

SI 2792 Health and Safety (Display ScreenEquipment) Regulations

HMSO 1992

SI 341 Health and Safety (Safety Signs andSignals) Regulations

HMSO 1996

SI 1380 Health and Safety (Training forEmployment) Regulations

HMSO 1990

Highly Flammable Liquids and LiquefiedPetroleum Gases Regulations

HMSO 1972

SI 2307 Lifting Operations and Lifting EquipmentRegulations (LOLER)

HMSO 1998

SI 3242 Management of Health and Safety atWork Regulations

HMSO 1999

SI 2793 Manual Handling OperationsRegulations

HMSO 1992

SI 1790 Noise at Work Regulations HMSO 1989

SI 3139 Personal Protective Equipment (ECDirective) Regulations (as amended)

HMSO 1992

SI 2966 Personal Protective Equipment at Work(PPE) Regulations

HMSO 1992

SI 2306 Provision and Use of Work EquipmentRegulations (PUWER)

HMSO 1998

SI 3163 Reporting of Injuries, Diseases andDangerous Occurrences Regulations(RIDDOR)

HMSO 1995

SI 3004 Workplace (Health, Safety and Welfare)Regulations

HMSO 1992

British Standards

BS 349 Specification for identification of thecontents of industrial gas containers(AMD 6132, 5189)

BSIStandards

1973

BS 1319 Specification for medical gascylinders, valves and yokeconnections (AMD 3029, 6179, 4603,6184)

BSIStandards

1976

BS 5378 Safety signs and colours BSIStandards

BS 5499 Fire safety signs and graphicsymbols

BSIStandards

BS 5266 Code of practice for emergencylightning

BSIStandards

1988

BS 8313 Code of practice for accommodationsof building services in duct

BSIStandards

1997

ARCHIVE

Page 91: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 91 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

PublicationID

Title Publisher Date Notes

Scottish Health Technical Guidance

SHTM 2007 Electrical services supply anddistribution

P&EFEx 2001 CD-ROM

SHTM 2010 Sterilization P&EFEx 2001 CD-ROM

SHTM 2011 Emergency electrical services P&EFEx 2001 CD-ROM

SHTM 2014 Abatement of electrical interference P&EFEx 2001 CD-ROM

SHTM 2020 Electrical safety code for low voltagesystems (Escode – LV)

P&EFEx 2001 CD-ROM

SHTM 2021 Electrical safety code for high voltagesystems (Escode – HV)

P&EFEx 2001 CD-ROM

SHTM 2022 Medical gas pipeline systems P&EFEx 2001 CD-ROM

SHTM 2024 Lifts P&EFEx 2001 CD-ROM

SHTM 2025 Ventilation in healthcare premises P&EFEx 2001 CD-ROM

SHTM 2027 Hot and cold water supply, storage andmain services

P&EFEx 2001 CD-ROM

SHTM 2045 Acoustics P&EFEx 2001 CD-ROM

SHPN 1 Health service building in Scotland HMSO 1991

SHPN 2 Hospital briefing and operational policy HMSO 1993

SHTN 1 Post commissioning documentation forhealth buildings in Scotland

HMSO 1993

SHTN 4 General Purposes Estates andFunctions Model Safety Permit-to-WorkSystems

EEF 1997

NHS in Scotland – PROCODE P&EFEx 2001 Version1.1

NHS in Scotland Firecode

SHTM 81 Fire precautions in new hospitals P&EFEx 1999 CD-ROM

SHTM 82 Alarm and detection systems P&EFEx 1999 CD-ROM

SHTM 83 Fire safety in healthcare premises:general fire precautions

P&EFEx 1999 CD-ROM

SHTM 84 Fire safety in NHS residential careproperties

P&EFEx 1999 CD-ROM

SHTM 85 Fire precautions in existing hospitals P&EFEx 1999 CD-ROM

SHTM 86 Fire risk assessment in hospitals P&EFEx 1999 CD-ROM

SHTM 87 Textiles and furniture P&EFEx 1999 CD-ROM

SFPN 3 Escape bed lifts P&EFEx 1999 CD-ROM

SFPN 4 Hospital main kitchens P&EFEx 1999 CD-ROM

ARCHIVE

Page 92: SHTM 2023 Part 2 - Health Facilities Scotland (HFS) Part 2.pdf · 1.1 This part of Scottish Health Technical Memorandum (SHTM) 2023 gives general guidance on the space requirements

SHTM 2023 (Pt 2): Access and accommodation for engineering services

Version 2.0: June 2001 Page 92 of 92© Borders General Hospital NHS Trust on behalf of

NHSScotland Property and Environment Forum

PublicationID

Title Publisher Date Notes

SFPN 5 Commercial enterprises on hospitalpremises

P&EFEx 1999 CD-ROM

SFPN 6 Arson prevention and control in NHShealthcare premises

P&EFEx 1999 CD-ROM

SFPN 7 Fire precautions in patient hotels P&EFEx 1999 CD-ROM

SFPN 10 Laboratories on hospital premises P&EFEx 1999 CD-ROM

UK Health Technical Guidance

EH 40 HSE Occupational Exposure limits HSE Annual

MES Model Engineering Specifications NHS Estates 1997 Asrequired

Approvedcode ofpractice

The Control of Asbestos at WorkRegulations

HMSO 1987

Approvedcode ofpractice

Work with Asbestos Insulation, AsbestosCoating and Asbestos Insulating Board

HMSO 1988

HSE Publications

CS 4 Keeping of LPG in cylinders and similarcontainers

HMSO 1986

CS 5 Part 1: Entry into confined spacesPart 2: Cleaning and gas freeing of tankscontaining flammable residues

HMSO 1977

Miscellaneous References

Space allowances for building servicesdistribution systems: detail design stage(TN 10/92)

BuildingServicesResearchandInformationAssociation(BSRIA)

1992

The safe storage of gaseous hydrogenin seamless cylinders and similarcontainers (CP 8)

BritishCompressedGasesAssociation

1986ARCHIVE