Shore Station UPS Requirements for the
NEPTUNE Power System
Tim McGinnis
UW/APL
![Page 2: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/2.jpg)
Background
• 2 Shore Stations – each able to individually power to the network, although with possible reduced capability
• West Coast of Vancouver Island– Planned visitor center at Victoria– Existing cable stations at Port Alberni,
Bamfield
• Oregon Coast– Existing cable stations at Nedonna Beach,
Rockaway, Pacific City, Bandon
![Page 3: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/3.jpg)
Local Utility Power Reliability
• 2 Substations, each located about 8 miles away
• Station currently served by 1, possibility of connecting to both substations with a switch
• Several outages of 30-60 minutes per year can be expected – mostly from trees/branches
![Page 4: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/4.jpg)
Cable Station
Public UtilitySub-StationLocations
Nedonna Beach
5 mi
![Page 5: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/5.jpg)
UPS Alternatives
• DC System– Typical for Telecom Systems– Most equipment requires 48 VDC – AC-DC rectifiers supply power to batteries
and equipment – If utility power fails, batteries are always on-
line– 3-8 hour battery life typical, generator optional– DC-AC inverter for critical AC loads (minimal)
![Page 6: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/6.jpg)
Traditional Telecom Power Feed Equipment (PFE)
DieselGenerator480 VAC
DC/DCConverter
48VDC:10kVDC
Ground Bed
480VACControl andSwitching
Step DownTransformer480VAC:240/
120VAC
Utility480VAC
Rectifier/BatteryCharger
48VDCBattery Bank
BackboneCable
DC/DC Convertersand
DC/AC Inverters
Non-Essential
Loads
EssentialLoads
![Page 7: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/7.jpg)
UPS Alternatives
• AC System– Typical for Information Technology, Network,
Hospital, Commercial and similar facilities– Most equipment requires 120VAC– If utility fails, run on battery until generator
starts– 10 minute battery life, typical– One or more generators for AC backup
![Page 8: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/8.jpg)
Typical IT UPS System with a backup generator
DieselGenerator480 VAC
AC/DCConverter
480VAC:10kVDC
Ground Bed
Power Module480VAC
Control andSwitching
Step DownTransformer480VAC:240/
120VAC
Battery Bank
Utility480VAC
BackboneCable
Other Loads
![Page 9: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/9.jpg)
Selection Criteria
• Reliability
• Load Voltage and Power Requirements
• Cost
![Page 10: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/10.jpg)
Reliability - DC
dc system 1
commercialac power
enginegenerator
switchrectifier
N+1
battery3 hours
boostconverter
N+1
commercialac power
rectifierN+1
battery8 hours
dc system 2
W = 9 x 10-10
W = 3.45 x 10-7
![Page 11: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/11.jpg)
Reliability - AC
commercialac power
enginegenerator
transferswitch
ac/dc
battery10 min
ac system
commercialac power
enginegenerator
transferswitch
bypassswitch
dc/ac
W = 3.5 x 10-10
![Page 12: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/12.jpg)
Load Power Requirements
• Expected NEPTUNE Shore Station Load is mostly AC equipment
• Power Estimate – 120 kW total– 100 kW seafloor cable load– 20 kW terrestrial load
• Current Estimates– 48 VDC → 2500 A– 480 VAC, 3Ф → 144 A
![Page 13: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/13.jpg)
Cost
• For Loads < 25 kW– Batteries cost less– Batteries have smaller footprint
• For Loads > 25 kW– Generator costs less– Generator has smaller footprint
![Page 14: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/14.jpg)
Item AC DC
Simplicity X
Reliability X X
Majority of Load Voltage - 120AC X
Load Power Requirement – 200 kW
X
Foot Print Size X
Cost X
Criteria for selecting a UPS System
![Page 15: Shore Station UPS Requirements for the NEPTUNE Power System Tim McGinnis UW/APL.](https://reader036.fdocuments.in/reader036/viewer/2022083007/56649e365503460f94b25c5e/html5/thumbnails/15.jpg)
Conclusions
• Need to learn more about Shore Station power requirements
• Need to confirm reliability/availability data
• Need to learn more about similar installations