Sharing understanding of risk

through the planning process

Sizarta Sarshar [email protected]

PhD candidate at NTNU

Senior researcher at IFE

IO13 Conference – IO1 Teamwork and Capabilities

Trondheim, Norway, 24th-25th September 2013

Page 2: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities

Corrective

maintenance

Backlog

Priority

2

Design

Technical safety

Preventive

maintenance

program

Technical hierarchy

Consequence classification

Risk based preventive

maintenance Maintenance

management

Technical barrier

management

Other

operations

Execution

Safe Job

Analysis Work Permit plan

Work Order plan

Operational plan

Page 3: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities 3

Onshore

Operation

Organisation

(HUB)

Contractors/

Vendors

Headquarter

Offshore

Operations

Organisation

Contractors/

Vendors

at other

locations

Page 4: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities 4

Corrective

maintenance

Backlog

Priority

Design

Technical safety

Preventive

maintenance

program

Technical hierarchy

Consequence classification

Risk based preventive

maintenance Maintenance

management

Technical barrier

management

Other

operations

Execution

Safe Job

Analysis Work Permit plan

Work Order plan

Operational plan

Page 5: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities

Corrective

maintenance

Backlog

Priority

Design

Technical safety

Preventive

maintenance

program

Technical hierarchy

Consequence classification

Risk based preventive

maintenance Maintenance

management

Technical barrier

management

Other

operations

Execution

Safe Job

Analysis Work Permit plan

Work Order plan

Operational plan

5

Zone classification

Laydown area

Potential hazards/

weakened barriers

Planned work

to be executed

• Allow for participants having different backgrounds and thus

not the same ability for interpreting data

• Allow for knowledge sharing

• Visualize history, consensus and implications

• Provide an overview of the planned activities

[Skjerve et al, 2011]

Page 6: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities 6

Onshore

Organisation

Offshore

Organisation

IO MAP prototype

Developed in the IO-FuCE project

in phase 1 of the IO Center by IFE

[Braseth & Sarshar, 2012]

Page 7: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities

Findings from the usability study 1/2

• IO-MAP fills an important function in visualising risk

factors in connection to tasks and location, offering

an extra highlight and reminder of these on the map.

• Visualization may help onshore staff with limited

offshore familiarity to align to the existing offshore

setting.

7

Page 8: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities

Findings from the usability study 2/2

• The findings from the usability study of the first

version of the tool showed that users could more

easily share understanding and communicate

through a shared visualization.

• Such tools can help simplify the day to day operation

in the way that information is gathered in one place

and it allows users to see relations and possible

outcome of the job planning.

8

Page 9: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities 9

[email protected]

IO Collaboration

[Kaarstad & Rindahl, 2011]

Page 10: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities

On-going study:

• Explore the relation between high quality plans for

offshore maintenance and operational activities and

major accident prevention.

Assumption:

• Low quality planning processes lead to low quality

plans, which in turn increase the risk for major

accidents.

10

Page 11: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities 11

Onshore

Organisation

Offshore

Organisation

Page 12: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities 12

• Maintenance management is illustrated as a work

flow where products are produced with low HSE risks

and high production performance [NORSOK Z-008].

• A high quality plan shall make it possible to execute

the work in a safe manner, without accidents, and

make it possible to deliver a finished work

state/product that can be operated safely.

Page 13: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities 13

What are attributes of high-quality plans vis-à-vis

preventing major accidents?

How should the planning process be organized to

promote development of high-quality plans?

• The plan is robust and is comprehensible to its users

• Description of task execution includes contributions from all

disciplines and parties

• All safety issues have been resolved

• Allow time and avoid pressure

• Competence

• Involvement

• Communication

• Feedback loop

[Sarshar et al., 2013]

Page 14: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

Sizarta Sarshar

[email protected]

PhD Supervisors:

Stein Haugen and Ann Britt Skjerve

IO1 Program manager: IO1 Project leader:

Jon Kvalem Grete Rindahl

IO13 Conference – IO1 Teamwork and Capabilities

Trondheim, Norway, 24th-25th October 2013

Sharing understanding of risk

through the planning process

Page 15: Sharing understanding of risk through the planning · PDF fileSharing understanding of risk through the planning process ... [NORSOK Z-008]. ... Sharing understanding of risk through

IO1 Teamwork and Capabilities

References

• S. Sarshar et al. “Towards an understanding of information needed

when planning offshore activities”, ESREL 2013.

• A.O. Braseth and S. Sarshar “Improving Oil & Gas Installation Safety

through Visualization of Risk Factors”, SPE 2012.

• M. Kaarstad and G. Rindahl “Shared collaboration surfaces to

support adequate team decision processes in an Integrated

Operations setting”, ESREL 2011.

• S. Sarshar et al. “Quality Aspects in Planning of Maintenance and

Modification on Offshore Oil and Gas Installations”, ESREL 2011.

• A.B. Skjerve et al. “The Integrated Operations Maintenance and

Modification Planner (IO-MAP) First Usability Evaluation”, IO

CENTER report 2011.

• NORSOK Z-008 “Risk based maintenance and consequence

classification”, 3rd ed., 2011.

15