SGC Report No. Pardue Mill Road Findings Summary

8
Page 1 of 1 2660 White Sulphur Road Gainesville, Georgia 30501 770.536.5220 phone [email protected] Geotechnical Engineering Special Inspections CMT Environmental Services GEOTECHNICAL FINDINGS SUMMARY To: Mr. Jason M. Smith, P.E. From: Mr. Rodney Clark and Mr. Glenn Motes P.E. Date: December 31, 2020 Re: Geotechnical Rock Coring Summary Pardue Mill Road Bridge Repair SGC Project No. 12973G, Report No. 80236 We recently completed geotechnical exploration of the two existing bridge abutments at Pardue Mill that had become damaged following the storm event in October 2020. Plate 1 is a site location plan. As part of the exploration, three soil tests borings were made at the site and included two borings offset about 10 feet from the east abutment (Boring Nos. 2 and 3) and one about 10 feet from the west abutment (Boring No. 1). Plate 2 provides a boring location plan. Initially, the borings penetrated a pavement that ranged from about 5- to 9-inches thick. Below the pavement at each boring location, the borings penetrated about 2½ to 7 feet of existing fill. The fill is generally described as firm to very dense brown and tan reddish brown fine sand to sandy silt. Below the fill partially weathered rock was encountered. The partially weathered rock was encountered only in Boring No. 1. The borings encountered auger refusal at a depth of about 15 feet at Boring No. 1 and about 2½ and 7 feet, respectively, for Boring Nos. 2 and 3. At Boring Location Nos. 1 and 3, rock cores were extracted below the boring refusal depths. The rock cores are generally described as a mixture of biotite gneiss and schist. The competency of the rock is generally good at Boring No. 1; however, at Boring No. 3 the shist at the rock surface appears to contain numerous soil seams the lower the overall competency. Copies of the individual boring logs are attached. Based upon the boring data, it would appear that competent rock for the west abutment can be expected to be around 15 feet. At the east abutment, varied conditions are indicated based upon the boring data. At Boring No. 2, auger refusal was encountered at a depth of 2½ feet below a thin veneer of fill. At Boring No. 3, made about 12 feet away, auger refusal was encountered at a depth of about 7 feet. It is possible that the shallower refusal at Boring No. 2 was the result of rock in the fill. Nevertheless, what the rock cores indicate is the upper rock surface is of lower competency and prone to numerous soil seams. Competent rock at this abutment appears to begin around 25 feet. Any underpinning and/or lateral tie-back system will need to penetrate the competent rock vertically for bearing and laterally for support. Geotechnical Engineering Special Inspections CMT Environmental Services

Transcript of SGC Report No. Pardue Mill Road Findings Summary

Page 1 of 1

2660 White Sulphur Road Gainesville, Georgia 30501 770.536.5220 phone [email protected]

G e o t e c h n i c a l E n g i n e e r i n g • S p e c i a l

I n s p e c t i o n s • C M T • E n v i r o n m e n t a l S e r v i c e s

G EOT ECHNICAL F INDI NG S S UMMARY To: Mr. Jason M. Smith, P.E. From: Mr. Rodney Clark and Mr. Glenn Motes P.E. Date: December 31, 2020 Re: Geotechnical Rock Coring Summary Pardue Mill Road Bridge Repair SGC Project No. 12973G, Report No. 80236 We recently completed geotechnical exploration of the two existing bridge abutments at Pardue Mill that had become damaged following the storm event in October 2020. Plate 1 is a site location plan. As part of the exploration, three soil tests borings were made at the site and included two borings offset about 10 feet from the east abutment (Boring Nos. 2 and 3) and one about 10 feet from the west abutment (Boring No. 1). Plate 2 provides a boring location plan. Initially, the borings penetrated a pavement that ranged from about 5- to 9-inches thick. Below the pavement at each boring location, the borings penetrated about 2½ to 7 feet of existing fill. The fill is generally described as firm to very dense brown and tan reddish brown fine sand to sandy silt. Below the fill partially weathered rock was encountered. The partially weathered rock was encountered only in Boring No. 1. The borings encountered auger refusal at a depth of about 15 feet at Boring No. 1 and about 2½ and 7 feet, respectively, for Boring Nos. 2 and 3. At Boring Location Nos. 1 and 3, rock cores were extracted below the boring refusal depths. The rock cores are generally described as a mixture of biotite gneiss and schist. The competency of the rock is generally good at Boring No. 1; however, at Boring No. 3 the shist at the rock surface appears to contain numerous soil seams the lower the overall competency. Copies of the individual boring logs are attached. Based upon the boring data, it would appear that competent rock for the west abutment can be expected to be around 15 feet. At the east abutment, varied conditions are indicated based upon the boring data. At Boring No. 2, auger refusal was encountered at a depth of 2½ feet below a thin veneer of fill. At Boring No. 3, made about 12 feet away, auger refusal was encountered at a depth of about 7 feet. It is possible that the shallower refusal at Boring No. 2 was the result of rock in the fill. Nevertheless, what the rock cores indicate is the upper rock surface is of lower competency and prone to numerous soil seams. Competent rock at this abutment appears to begin around 25 feet. Any underpinning and/or lateral tie-back system will need to penetrate the competent rock vertically for bearing and laterally for support.

Geotechnical Engineering Special Inspections CMT Environmental Services

Adapted from Habersham County GIS Maps

SITE LOCATION PLAN

PARDUE MILL BRIDGE SITE NORTH HOLLAND DRIVE JEFFERSON, GEORGIA

DATE : 12/31/2020 REPORT NO. 80236

DRAWN BY : AGM PROJECT NO. 12973G

HORIZ. SCALE : NTS PLATE NO. 1

SITE

Adapted from Habersham County GIS Maps

APPROXIMATE BORING LOCATION

BORING LOCATION PLAN PARDUE MILL BRIDGE SITE

NORTH HOLLAND DRIVE JEFFERSON, GEORGIA

DATE : 12/31/2020 REPORT NO. 80236

DRAWN BY : AGM PROJECT NO. 12973G

HORIZ. SCALE : NTS PLATE NO. 2

GMotes
Typewritten text
1
GMotes
Typewritten text
2
GMotes
Typewritten text
3

ASPHALT

(GM) GRADED AGGREGATE BASE(ML) FILL - FIRM RED-BROWN SANDY SILT WITH TRACE CLAYAND ROCK FRAGMENTS (MOIST)

(SM) FILL - FIRM BROWN SILTY FINE SAND TO SANDY SILTWITH TRACE CLAY AND ROCK FRAGMENTS

(SM) PARTIALLY WEATHERED ROCK SAMPLED AS VERYDENSE TAN-BROWN MICACEOUS SILTY FINE SAND

ROCK SAMPLED AS THICKLY BEDDED TAN, GRAY AND WHITEMICA SCHIST TO GNEISS WITH MULTIPLE THIN SOIL SEAMSAPPROXIMATELY 1-INCH THICK (REQ 95%, RQD 87%)

BORING TERMINATED AT 25 FEETBottom of borehole at 25.0 feet.

14

100

2-3-4(7)

5-3-3(6)

10-34-50/2"

50/3"

NOTES

GROUND ELEVATION

LOGGED BY JWR

DRILLING METHOD Automatic Hammer

DRILLING CONTRACTOR Drilling Solutions GROUND WATER LEVELS:

CHECKED BY AGM

DATE STARTED 12/7/20 COMPLETED 12/7/20

AT TIME OF DRILLING ---

AT END OF DRILLING ---

AFTER DRILLING ---

HOLE SIZE inches

FINES CONTENT (%) 20 40 60 80

20 40 60 80

PL LLMC

DE

PT

H(f

t)

0

5

10

15

20

25

GR

AP

HIC

LOG

MATERIAL DESCRIPTION

SA

MP

LE T

YP

EN

UM

BE

R

RE

CO

VE

RY

%(R

QD

)

BLO

WC

OU

NT

S(N

VA

LUE

)

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

SPT N VALUE 20 40 60 80

PAGE 1 OF 1BORING NUMBER 1

CLIENT JM Smith Engineering, LLC

PROJECT NUMBER 12973G, 80236

PROJECT NAME Pardue Mill Road Bridge Repair SE

PROJECT LOCATION Demorest, Georgia

GE

OT

EC

H B

H P

LOT

S -

GIN

T S

TD

US

LA

B.G

DT

- 1

2/31

/20

14:

01 -

S:\G

EO

TE

CH

SH

AR

ED

NE

TW

OR

K D

RIV

E\R

EP

OR

TS

\129

73G

PA

RD

UE

MIL

L R

OA

D B

RID

GE

RE

PA

IR S

E\1

297

3G, 8

0236

PA

RD

UE

MIL

L R

OA

D B

RID

GE

RE

PA

IR B

OR

ING

LO

GS

.GP

JSouthern Geotechnical Consultants, LLC2660 White Sulphur Road / 14476 Duval Place West Suite 803Gainesville, Georgia 30501 / Jacksonville, Florida 32218Telephone: 770.536.5220 / 904.374.2252

>>

>>

ASPHALT

(GM) GRADED AGGREGATE BASE

(SM) FILL - VERY DENSE BROWN-GRAY MICACEOUS SILTYFINE SAND WITH ROCK FRAGMENTS

AUGER REFUSAL AT 2.5 FEETBottom of borehole at 2.5 feet.

8 6-5-50/1"

NOTES

GROUND ELEVATION

LOGGED BY JWR

DRILLING METHOD Automatic Hammer

DRILLING CONTRACTOR Drilling Solutions GROUND WATER LEVELS:

CHECKED BY AGM

DATE STARTED 12/10/20 COMPLETED 12/10/20

AT TIME OF DRILLING ---

AT END OF DRILLING ---

AFTER DRILLING ---

HOLE SIZE inches

FINES CONTENT (%) 20 40 60 80

20 40 60 80

PL LLMC

DE

PT

H(f

t)

0

1

2

GR

AP

HIC

LOG

MATERIAL DESCRIPTION

SA

MP

LE T

YP

EN

UM

BE

R

RE

CO

VE

RY

%(R

QD

)

BLO

WC

OU

NT

S(N

VA

LUE

)

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

SPT N VALUE 20 40 60 80

PAGE 1 OF 1BORING NUMBER 2

CLIENT JM Smith Engineering, LLC

PROJECT NUMBER 12973G, 80236

PROJECT NAME Pardue Mill Road Bridge Repair SE

PROJECT LOCATION Demorest, Georgia

GE

OT

EC

H B

H P

LOT

S -

GIN

T S

TD

US

LA

B.G

DT

- 1

2/31

/20

14:

01 -

S:\G

EO

TE

CH

SH

AR

ED

NE

TW

OR

K D

RIV

E\R

EP

OR

TS

\129

73G

PA

RD

UE

MIL

L R

OA

D B

RID

GE

RE

PA

IR S

E\1

297

3G, 8

0236

PA

RD

UE

MIL

L R

OA

D B

RID

GE

RE

PA

IR B

OR

ING

LO

GS

.GP

JSouthern Geotechnical Consultants, LLC2660 White Sulphur Road / 14476 Duval Place West Suite 803Gainesville, Georgia 30501 / Jacksonville, Florida 32218Telephone: 770.536.5220 / 904.374.2252

>>

ASPHALT(GM) GRADED AGGREGATE BASE(SM) FILL - VERY STIFF RED-BROWN MICACEOUS SILTY FINESAND TO SANDY SILT WITH TRACE CLAY

(SM) FILL - FIRM TAN-BROWN SLIGHTLY MICACEOUS SILTYFINE SAND TO SANDY SILT WITH TRACE CLAY

ROCK SAMPLED AS THICKLY BEDDED GRAY AND WHITEGNEISS (REQ 98%, RQD 97%)

SOIL SEAM

ROCK SAMPLED AS THINLY BEDDED TAN, GRAY AND WHITEMICA SCHIST TO GNEISS WITH MULTIPLE SOIL SEAMSRANGING FROM APPROXIMATELY 2-INCHES TO 1 FOOT THICK(REQ 67%, RQD 64%)

BORING TERMINATED AT 30 FEETBottom of borehole at 30.0 feet.

12-16-14(30)

5-4-2(6)

NOTES

GROUND ELEVATION

LOGGED BY JWR

DRILLING METHOD Automatic Hammer

DRILLING CONTRACTOR Drilling Solutions GROUND WATER LEVELS:

CHECKED BY AGM

DATE STARTED 12/10/20 COMPLETED 12/10/20

AT TIME OF DRILLING ---

AT END OF DRILLING ---

AFTER DRILLING ---

HOLE SIZE inches

FINES CONTENT (%) 20 40 60 80

20 40 60 80

PL LLMC

DE

PT

H(f

t)

0

5

10

15

20

25

30

GR

AP

HIC

LOG

MATERIAL DESCRIPTION

SA

MP

LE T

YP

EN

UM

BE

R

RE

CO

VE

RY

%(R

QD

)

BLO

WC

OU

NT

S(N

VA

LUE

)

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

SPT N VALUE 20 40 60 80

PAGE 1 OF 1BORING NUMBER 3

CLIENT JM Smith Engineering, LLC

PROJECT NUMBER 12973G, 80236

PROJECT NAME Pardue Mill Road Bridge Repair SE

PROJECT LOCATION Demorest, Georgia

GE

OT

EC

H B

H P

LOT

S -

GIN

T S

TD

US

LA

B.G

DT

- 1

2/31

/20

14:

01 -

S:\G

EO

TE

CH

SH

AR

ED

NE

TW

OR

K D

RIV

E\R

EP

OR

TS

\129

73G

PA

RD

UE

MIL

L R

OA

D B

RID

GE

RE

PA

IR S

E\1

297

3G, 8

0236

PA

RD

UE

MIL

L R

OA

D B

RID

GE

RE

PA

IR B

OR

ING

LO

GS

.GP