Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
-
Upload
project-controls-expo -
Category
Presentations & Public Speaking
-
view
1.391 -
download
14
Transcript of Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
![Page 1: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/1.jpg)
Copyright @ 2011. All rights reserved
Delay Claims and Analysis Based on FIDIC Forms of Contract
Project Controls Expo – 13th Oct 2015Emirates Stadium, London
![Page 2: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/2.jpg)
Copyright @ 2011. All rights reserved
About the Speaker
Ewen Maclean, Eur Ing MEng (Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
Director, Berkeley Research Group
Ewen is an experienced expert in the field of programming; delay and disruption; and associatedprolongation costs in relation to construction and engineering projects. In particular, he has worked forboth international consultants and contractors and has first-hand experience of assisting and representingclients in litigation, arbitration, mediation and adjudication, both for the claimant and respondent. He hasprepared numerous expert witness reports; drafted standard forms of contract and lectured on variouscommercial and contractual subjects within the construction industry. Ewen has also acted in commercialnegotiations and settlements, resolving potential disputes as well as providing advice on contractprocurement.
Ewen is well versed in many of the standard forms of construction contract including the NEC, JCT, ICE,FIDIC, GC Works Conditions as well as bespoke forms of contracts including PFI contracts and has worked oncontracts that span, inter alia, major building, civil engineering, oil and gas, energy, mechanical andelectrical, pharmaceutical, infrastructure including highways and rail as well as fit-out works.
![Page 3: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/3.jpg)
Copyright @ 2011. All rights reserved
Structure
1. What Do We Mean by Delay and Disruption?
2. Definitions in Delay and Disruption Analysis
3. Delay Analysis and its Methodologies
4. FIDIC Claims and Extension of Time Provisions
5. Scenario - Delay Analysis In Action
![Page 4: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/4.jpg)
Copyright @ 2011. All rights reserved
1. What Do We Mean By Delay and
Disruption?
Delay
Delay to completion which is a delay which will cause a
contract completion date not to be met.
![Page 5: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/5.jpg)
Copyright @ 2011. All rights reserved
Delay and its consequences
Contractor liable to employer for liquidated damages
Contractor incurs cost of maintaining resources and site establishment for longer
Employer may suffer from loss of revenue & negative publicity
Delay to completion
![Page 6: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/6.jpg)
Copyright @ 2011. All rights reserved
What Do We Mean By Delay and Disruption?
Disruption
Delay to progress which is a delay which will merely cause
delay to the Contractor’s progress without causing a contract
completion date not to be met.
Disruption (as distinct from delay) is disturbance, hindrance or
interruption to a Contractor’s normal working methods,
resulting in lower efficiency. If caused by the Employer, it may
give rise to a right to compensation either under the contract or
as a breach of contract.(SCL Delay and Disruption Protocol at page 9)
![Page 7: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/7.jpg)
Copyright @ 2011. All rights reserved
Delay and its Consequences
Disturbance of regular progress of the work
Non-critical delay
Additional costs associated with local disturbance to progress
Delay to progress
![Page 8: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/8.jpg)
Copyright @ 2011. All rights reserved
Types of Delay and Purpose of Extension of
Time Clause
Types of delay
Employer default / responsibility
Contractor default / responsibility
“Neutral” cause
Purpose of EOT clause:
Risk allocation
Common EOT clause: any cause for which E responsible
![Page 9: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/9.jpg)
Copyright @ 2011. All rights reserved
Employer’s cause
Delay
= EoT and money
Employer Delay
![Page 10: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/10.jpg)
Copyright @ 2011. All rights reserved
Contractor’s cause
Delay
= No EoT and no money
Contractor Delay
![Page 11: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/11.jpg)
Copyright @ 2011. All rights reserved
Concurrency
Both events must be effective causes of delay to critical path
EoT but, no prolongation money
Employer’s cause
Contractor’s cause
Delay
![Page 12: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/12.jpg)
Copyright @ 2011. All rights reserved
2. Definitions in Delay and Disruption
Analysis
Prospective v retrospective analysis of delay
The Critical Path
Float
Causation
![Page 13: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/13.jpg)
Copyright @ 2011. All rights reserved
Prospective vs. Retrospective Delay
Prospective:
Refer to the future and seek to determine the likely impact of
actual progress or a particular event(s) on project completion
During currency of project
Per SCL Protocol
Contract requirement (e.g. NEC)
Avoid disputes
![Page 14: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/14.jpg)
Copyright @ 2011. All rights reserved
Prospective vs. Retrospective Delay
Retrospective:
Refer to the historic and usually seek to determine the actual
impact of events upon progress and completion
During currency of project (after the event)
Claim preparation
Dispute resolution (expert analysis)
![Page 15: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/15.jpg)
Copyright @ 2011. All rights reserved
Critical Path
The critical path is the path or sequence of activities, which
represents the longest total time required to complete the project.
A delay in any activity on the critical path causes a delay in the
completion of the project.
There may also be more than one critical path depending upon
the logical dependencies between activities.
Additionally, the critical path is not fixed for any particular project,
but may change as activities are either delayed or able to
progress ahead of programme.
![Page 16: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/16.jpg)
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
![Page 17: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/17.jpg)
Copyright @ 2011. All rights reserved
Float
‘The time available for an activity in addition to its duration’
(BS4335)
Or
The period by which a task can be delayed without affecting
other tasks or the project end date.
![Page 18: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/18.jpg)
Copyright @ 2011. All rights reserved
Types of Float
‘Free float - the period by which a task can be delayed or
extended without affecting any other tasks, or the completion of
the project.
Total float - the period by which a task can be delayed or
extended without delaying the completion of the project.
Terminal Float: the float between the planned completion date
and the date for completion in the contract
Who owns the float?
![Page 19: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/19.jpg)
Copyright @ 2011. All rights reserved
Causation
Part of legal requirement to demonstrate that event was causal of
the delay or loss (cause and effect)
![Page 20: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/20.jpg)
Copyright @ 2011. All rights reserved
Delay Analysis
Components
Programme
Events
Progress Records/As-built
Contract requirements
Other supporting evidence
![Page 21: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/21.jpg)
Copyright @ 2011. All rights reserved
Programme
The objectives of a programme:
to determine the earliest date upon which completion can be
achieved;
to show the interrelationship of activities
to show the rationale of the sequence of site operations;
to identify the time constraints imposed by labour, plant and
materials.
![Page 22: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/22.jpg)
Copyright @ 2011. All rights reserved
Programme as basis of delay analysis
Complete and reliable
Accurate and reasonable activity durations
Logical relationships between activities
Plant and equipment delivery dates
Milestone dates
Includes all work to be carried out by sub-contractors
Includes all public holidays
Includes all employer constraints
Makes appropriate allowances for seasonal weather conditions
Compliant with conditions of contract/specification
![Page 23: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/23.jpg)
Copyright @ 2011. All rights reserved
Master/Baseline Programme
Allows comparison of what would have happened with what
actually happened
Needs to:
Meet contract requirements
Be a workable management tool
Be current
Be shared
![Page 24: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/24.jpg)
Copyright @ 2011. All rights reserved
Progress records
Allow comparison of what would have happened with what
actually happened
Need to:
Meet contract requirements
Be expressed by reference to a programme
Be quantitative
Be accurate
Be regularly kept
Be public
Be consistent
Record context
![Page 25: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/25.jpg)
Copyright @ 2011. All rights reserved
Records
Minimum requirements:
Meet contract
requirements
Start and finish
Degree of completion
Labour resources
Plant resources
Key procurement activities
Consider:
Marked up drawings
Photographs
Videos
More sophisticated
techniques
![Page 26: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/26.jpg)
Copyright @ 2011. All rights reserved
3. Delay Analysis and its Methodologies
Common Methods of Delay Analysis
As-planned vs As-built
Impacted as-planned
Collapsed as-built
Time impact analysis
![Page 27: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/27.jpg)
Copyright @ 2011. All rights reserved
Parameters
Relevant conditions of contract
Nature of causative events
Value of the dispute
Time available
Records available
Programme information available
Programmer’s skill level
![Page 28: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/28.jpg)
Copyright @ 2011. All rights reserved
A. As-planned vs As-built
Essentials
Good base programme (ideally agreed at start)
Programme as closely as possible reflects project logic
As-built information to establish as-built comparison
May be chosen where issues are simple and liability is clear
No CPA required
Steps
Determine baseline programme
Determine as-built programme and plot against planned
![Page 29: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/29.jpg)
Copyright @ 2011. All rights reserved
A. As-planned vs As-built
As-built
Claim
As-planned
![Page 30: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/30.jpg)
Copyright @ 2011. All rights reserved
A. As-planned vs As-built
‘As-planned’ vs ‘As-built’
Only retrospective
No cause and effect
Takes no account of concurrency
Assumes fault lies with others
Unreliable in dispute resolution
![Page 31: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/31.jpg)
Copyright @ 2011. All rights reserved
B. Impacted ‘As-planned’
Essentials
Good base programme (ideally agreed at start)
Programme reflects project logic
Likely choice where programme not updated and limited/no
as-built information available
Steps
Impact all events on planned programme
Can be done in steps of time intervals - cross checked with
key as-built milestones
![Page 32: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/32.jpg)
Copyright @ 2011. All rights reserved
B. Impacted ‘As-planned’ - illustrated
Claim
Baseline
EOT eventAs-built
![Page 33: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/33.jpg)
Copyright @ 2011. All rights reserved
B. Impacted ‘As-planned’
Impacted ‘As-planned’
Prospective/Retrospective
Limited cause and effect
Takes no account of:
Progress
Resources
Changing logic
Unreliable in dispute resolution
![Page 34: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/34.jpg)
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
Essentials
Detailed as-built records
Detailed understanding of construction logic
Access to site team
Basis for measuring and identifying the extent of delays
Steps
Reconstruct As-built programme & determine Logic
Identify delay periods & responsibility for delays
Carry out delay analysis
Explain approach and results
![Page 35: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/35.jpg)
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
Identify Employer Delays
Contract
period
As-built
Project Completion
Actual Completion
![Page 36: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/36.jpg)
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
Zero the Employer Delays
Contract
period
As-built
Actual Completion ‘but for’
Employer Delays
Actual
Completion
![Page 37: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/37.jpg)
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
Entitlement
Contract period
As-built
Contractor
culpable delays
Contractor EoT
entitlement
Actual
Completion
![Page 38: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/38.jpg)
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
Collapsed ‘As-built’
Retrospective (limited Prospective)
Factually based
If done properly:
Demonstrates cause and effect
Takes account of concurrency
Relatively quick
Reliable in dispute resolution
![Page 39: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/39.jpg)
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
Essentials
Good base programme (ideally agreed at start)
Programme reflects project logic
Reliable and consistent progress data, in sufficient detail and
at small enough intervals to make the analysis meaningful
![Page 40: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/40.jpg)
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
Steps
Verify base programme and correct for errors
Identify delay events and periods
Input progress up to start of first window period or first delay
Reschedule and check completion
Impact delay and record any logic changes to deal with
mitigation
Reschedule and check completion and record any further delay
![Page 41: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/41.jpg)
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
Master Programme
Activity 1
Activity 2
Activity 3
Project completion
![Page 42: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/42.jpg)
Copyright @ 2011. All rights reserved
D. Time Impact Analysis - illustrated
Step 2, Enter progress & record effect
Activity 1
Activity 2
Activity 3
Project completionTime Now
Delay to
Project completion
![Page 43: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/43.jpg)
Copyright @ 2011. All rights reserved
D. Time Impact Analysis - illustrated
Step 3, Analyse the delaying event
Activity 1
Activity 2
Activity 3
Project completionTime Now
Delaying Event
Delay to
Project completion
Period
of EoT
![Page 44: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/44.jpg)
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
Time Impact analysis
Prospective/Retrospective
Cause and Effect
Takes account of Progress/Resource/Logic
Reliable in Dispute Resolution
Preferred method of SCL Protocol
Complicated (and therefore slow)
Difficult to communicate (Skanska v Egger [2004])
![Page 45: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/45.jpg)
Copyright @ 2011. All rights reserved
FIDIC Claims and Extensions of TimeClaims Under the Yellow Book
Clause EoT Costs Profit
1.9 (Errors in the Employer's Requirements) ✓ ✓ ✓
2.1 (Right of Access to the Site) ✓ ✓ ✓
4.7 (Setting Out) ✓ ✓ ✓
4.12 (Unforeseeable Physical Conditions) ✓ ✓
4.24 (Fossils) ✓ ✓
7.4 (Testing) ✓ ✓ ✓
8.4 (a) (Extension of Time for Completion) - Variations ✓
8.4 (c) (Extension of Time for Completion) - Exceptionally Adverse Climatic Conditions ✓
8.4 (d) (Extension of Time for Completion) - Unforeseeable shortages caused by Epidemic or Government Actions ✓
8.4 (e) (Extension of Time for Completion) - Delay, Impediment by Employer or his Agents or Contractors ✓
8.9 (Consequences of Suspension) ✓ ✓
10.2 (Taking Over of Parts of the Works) ✓ ✓
10.3 (Interference with Tests on Completion) ✓ ✓ ✓
12.2 (Delayed Tests) ✓ ✓
12.4 (Failure to Pass Tests after Completion) ✓ ✓
13.7 (Adjustment for Changes in Legislation) ✓ ✓
16.1 (Contractor's Entitlement to Suspend Work) ✓ ✓ ✓
17.4 (Consequences of the Employer's Risks) ✓ ✓ ✓
18.1 (General Requirements for Insurances) ✓ ✓
19.4 (Consequences of Force Majeure) ✓ ✓
For the Silver Book, see Sub-Clauses 2.1, 4.24, 7.4, 8.4, 8.9, 10.3, 12.2, 12.4, 13.7, 16.1, 17.4, 18.1 and 19.4.
![Page 46: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/46.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Contractor’s obligations (Yellow Book)
to commence the design and execution of the Works as soon
as reasonably practicable after the Commencement Date &
to proceed with the Works with due expedition and without
delay – Sub-clause 8.1
to complete within the Time for Completion – Sub-clauses 8.2
to submit a programme and revised programmes: Sub-clause
8.3
NB Clause 9 for other FIDIC Gold Book
![Page 47: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/47.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Entitlement to an extension of time – Sub-clause 8.4 (Yellow Book)
“The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s
Claims], to an extension of the Time for Completion if and to the extent that
completion… is or will be delayed by any of the following causes:”
Delay must be due to a cause listed in Sub-clause 8.4
A Variation, Sub-clause, adverse climatic conditions, unforeseeable
shortages; and an Employer default
Contractor must give notice pursuant to Sub-clause 20.1
“is or will be delayed” indicates that an entitlement can arise prior to the
effects of the delay having ceased
Once awarded, the EOT cannot be decreased
![Page 48: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/48.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Employer’s right to delay damages – Sub-clause 8.7 (Yellow Book)
Right under Sub-clause 8.7
At rate and to the maximum stated in the Appendix to Tender
Subject to requirements to sub-clause 2.5 – notice to the Contractor
“If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion],
the Contractor shall, subject to Sub-Clause 2.5 [Employer's Claims], pay
delay damages to the Employer for this default. These delay damages shall
be the sum stated in the Appendix to Tender, which shall be paid for every
day which shall elapse between the relevant Time for Completion and the
date stated in the Taking Over Certificate. However, the total amount due
under this Sub-Clause shall not exceed the maximum amount of delay
damages (if any) stated in the Appendix to Tender.”
![Page 49: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/49.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Claims, Disputes and Arbitration
Sub-clause 20.1 Contractor’s Claims (Yellow Book - Notices)
“If the Contractor considers himself to be entitled to any extension of the Time
for Completion and/or any additional payment, under any Clause of these
Conditions or otherwise in connection with the Contract, the Contractor shall
give notice to the Engineer, describing the event or circumstance giving rise to
the claim. The notice shall be given as soon as practicable, and not later than 28
days after the Contractor became aware, or should have become aware, of the
event or circumstance.”
“If the Contractor fails to give notice of a claim within such period of 28 days, the
Time for Completion shall not be extended, the Contractor shall not be entitled to
additional payment, and the Employer shall be discharged from all liability in
connection with the claim…”
![Page 50: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/50.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Sub-clause 20.1 Contractor’s Claims (Yellow Book – Contemporary
Records)
“The Contractor shall keep such contemporary records as may be necessary to
substantiate any claim, either on the Site or at another location acceptable to the
Engineer. Without admitting the Employer's liability, the Engineer may, after
receiving any notice under this Sub-Clause, monitor the record-keeping and/or
instruct the Contractor to keep further contemporary records. The Contractor
shall permit the Engineer to inspect all these records, and shall (if instructed)
submit copies to the Engineer.”
![Page 51: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/51.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Sub-clause 20.1 (Yellow Book - Details and particulars )
“Within 42 days after the Contractor became aware (or should have become
aware) of the event or circumstance giving rise to the claim, or within such other
period as may be proposed by the Contractor and approved by the Engineer, the
Contractor shall send to the Engineer a fully detailed claim which includes full
supporting particulars of (the basis of the claim and of the extension of time
and/or additional payment claimed. If the event or circumstance giving rise to the
claim has a continuing effect:
![Page 52: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/52.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Sub-clause 20.1 (Yellow Book - Details and particulars )
“If the event or circumstance giving rise to the claim has a continuing effect:
(a) this fully detailed claim shall be considered as interim;
(b) the Contractor shall send further interim claims at monthly intervals,
giving the accumulated delay and/or amount claimed, and such further
particulars as the Engineer may reasonably require; and
(c) the Contractor shall send a final claim within 28 days after the end of the
effects resulting from the event or circumstance, or within such other period
as may be proposed by the Contractor and approved by the Engineer.
![Page 53: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/53.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Sub-clause 20.1 (Yellow Book- Engineer’s Response )
“Within 42 days after receiving a claim or any further particulars supporting a
previous claim, or within such other period as may be proposed by the Engineer
and approved by the Contractor, the Engineer shall respond with approval, or
with disapproval and detailed comments. He may also request any necessary
further particulars, but shall nevertheless give his response on the principles of
the claim within such time.”
![Page 54: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/54.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Sub-clause 20.1 (Yellow Book- Engineer’s Response )
“Each Payment Certificate shall include such amounts for any claim as have been reasonably
substantiated as due under the relevant provision of the Contract. Unless and until the particulars
supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to
payment for such part of the claim as he has been able to substantiate. The Engineer shall proceed in
accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) the extension (if any) of the
Time for Completion (before or after its expiry) in accordance with Sub-Clause 8.4 [Extension of Time
for Completion], and/or (ii) the additional payment (if any) to which the Contractor is entitled under the
Contract.
The requirements of this Sub-Clause are in addition to those of any other Sub-Clause which may apply
to a claim. If the Contractor fails to comply with this or another Sub-clause in relation to any claim, any
extension of time and/or additional payment shall take account of the extent (if any) to which the failure
has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the
second paragraph of this Sub-Clause.”
![Page 55: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/55.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
Sub-clause 2.5 (Employer’s Claims) (Yellow Book)
“If the Employer considers himself to be entitled to any payment under any Clause of these
Conditions or otherwise in connection with the Contract, and/or to any extension of the
Defects Notification Period, the Employer or the Engineer shall give notice and particulars
to the Contractor…
The notice shall be given as soon as practicable after the Employer became aware of the
event or circumstances giving rise to the claim... A notice relating to any extension of the
Defects Notification Period shall be given before the expiry of such period. The particulars
shall specify the Clause or other basis of the claim, and shall include substantiation of the
amount and/or extension to which the Employer considers himself to be entitled in
connection with the Contract. The Engineer shall then proceed in accordance with Sub-
Clause 3.5 [Determinations] to agree or determine (i) the amount (if any) which the
Employer is entitled to be paid by the Contractor, and/or (ii) the extension (if any) of the
Defects Notification Period in accordance with Sub-Clause 11.3 [Extension of Defects
Notification Period].”
![Page 56: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/56.jpg)
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
13 Oct 15: Contractor became or should have become aware of the event
Oct
24 Nov 15: Contractor provides fully detailed claim
Nov
10 Nov 15: Contractor gives Notice to the Engineer
2016
≤ 28 days
Dec
05 Jan 16: Engineer’s Response
≤ 42 days
≤ 42 days
2015
Jan
![Page 57: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/57.jpg)
Copyright @ 2011. All rights reserved
5. Scenario
Delay Analysis In Action!
![Page 58: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/58.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
As-Planned versus As-Built
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 59: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/59.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
As-Planned versus As-Built
with Events
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 60: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/60.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Contractor’s Global Claim
Employer late clearing site
Fire Change in Law
Design Issues
Strike
19 weeks 1 day
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 61: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/61.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 62: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/62.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
Employer blames
whole delay on riot
caused by Contractor
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 63: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/63.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
Employer claims fire is a
Contractor responsibility
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 64: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/64.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
3 (Change in Law) 1 week Employer 100 weeks 0 weeks
Employer notes
change in law not
critical
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 65: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/65.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
3 (Change in Law) 1 week Employer 100 weeks 0 weeks
4 (Strike) 1 day Force Majeure 100 weeks 0 weeks
Employer says 1 day
delay not significant
and can be mitigated
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 66: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/66.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
3 (Change in Law) 1 week Employer 100 weeks 0 weeks
4 (Strike) 1 day Force Majeure 100 weeks 0 weeks
5 (Subcontractor) 10 weeks Contractor 100 weeks 0 weeks
Employer only notes
subcontractor delay
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 67: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/67.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 68: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/68.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
Consultant believes concurrent
and claims EOT but no money
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 69: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/69.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
Consultant believes strike is a
Force Majeure event
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 70: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/70.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks
Consultant acknowledges
change in law not critical
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 71: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/71.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks
2 (Fire) 5 weeks Contractor 110 weeks 1 day 0 weeks
Consultant acknowledges fire
as a Contractor responsibility
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 72: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/72.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks
2 (Fire) 5 weeks Contractor 110 weeks 1 day 0 weeks
1 (Late Clear & Riot) 4 weeks Employer 114 weeks 1 day 4 weeks
Consultant claims late
clearance of site
dominant cause of delay
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 73: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/73.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 74: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/74.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 75: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/75.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 76: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/76.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
Riot is not critical after
impact of late clearance
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 77: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/77.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 78: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/78.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
Fire considered to be a
Contractor responsibility
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 79: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/79.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 80: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/80.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
Change in Law
not critical
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 81: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/81.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 82: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/82.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 week Force Majeure Mitigation Mitigation
Force Majeure shown
as 1 week effect
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 83: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/83.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
Force Majeure shown
as 1 day effect after
mitigation
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 84: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/84.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 85: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/85.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
5 (Design & Subcon) 10 weeks Contractor 104 weeks 1 day 0 weeks
Design is critical delay &
subcontractor delay not critical.
However, design can be attributed
to Employer if required
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 86: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/86.jpg)
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
5 (Design & Subcon) 10 weeks Contractor 104 weeks 1 day 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | [email protected]
![Page 87: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/87.jpg)
Copyright @ 2011. All rights reserved
Summary of Extension of Time Claims
1. Contractor’s claim: 19 weeks and 1 day
2. Employer’s Response: 00 weeks
3. Hired Consultant’s View: 14 weeks 1 day
4. Expert Opinion: 04 weeks 1 day
![Page 88: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/88.jpg)
Copyright @ 2011. All rights reserved
Why the Difference?
1. The Contractor’s claim was global and did not consider progress,
concurrency, culpable delay or criticality.
2. The Employer’s Response was one sided and did not consider
progress, concurrency, valid claims and actual criticality.
3. Hired Consultant’s view did not fully adjust for progress,
concurrency or actual criticality.
4. Expert Opinion considered progress, concurrency, liability and criticality.
![Page 89: Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract](https://reader033.fdocuments.in/reader033/viewer/2022042502/587067471a28ab48378b536d/html5/thumbnails/89.jpg)
Copyright @ 2011. All rights reserved
Delay Analysis Conclusions
Meet contract requirements
Focus upon what has to be established
Review the available records
Select the method accordingly
Record at each stage
Do it properly
Do it accurately!