L.A. Lopez Hernandez
Septum 16 shielding increase
19 November 2013
![Page 2: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/2.jpg)
Requested: - Additionnal depth of earth of between 1.2m and 3.4m over Septum 16 area
Constraints: - Existing structures not strong enough to take the additional load- Area with a very complex geometry (PS, Linac 2&3, Leir, TT2, . .) - Works must have no influence or impact on the existing structures
![Page 3: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/3.jpg)
Proposed solution : -A new load-bearing structure taking the weight of the additional earth and redirecting it into the bedrock underneath.
-The structure consists of a 1.10 m thick reinforced concrete slab and the additional depth of backfill will be placed directly on the slab.
-The slab rests on drilled piles and on intermittent supports on the tunnel roof
![Page 4: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/4.jpg)
Slab deformation:
51 mm
56 mm
![Page 5: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/5.jpg)
- To protect the existing structures, the transfer slab must guarantee that even after long-term deformation the load-bearing relief structure does not under any circumstances come to rest on the existing structures.
- To this end, it was foreseen to use a biodegradable honeycomb cardboard formwork that could be be dissolved with water. This procedure guaranteed that, once water had been injected to dissolve the cardboard, a void of 10 cm remained after concreting, which was more than enough to allow for the long-term deformation of the slab
![Page 6: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/6.jpg)
Status – 19 November 2013
• Adjudication of the works on 19 June 2013 • June-July 2013 - Preparatory works • July 2013 – Earthworks • September 2013 - Piling works • 2 October 2013 – Start of concreting works – Stage 1a• 8 October 2013 – Works stoppage – The biodegradable
formwork gets wet before concreting !• 8-16 October 2013 – Removal of the formwork&reinforcement of
stages 1b and 2a • 18 October 2013 - a new method is developed and tested:
sand instead of biodegradable formwork, to be pumped out prior to backfilling
• Now – Stages 1b and 2a concreted using the new method
![Page 7: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/7.jpg)
Some pictures of the works:
Earthworks - July 2013 Piling works – September 2013
![Page 8: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/8.jpg)
Concreting works with biocofra – October 2013
![Page 9: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/9.jpg)
Demolition works – 8-16 October 2013
![Page 10: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/10.jpg)
New concreting operations with sand – November 2013
![Page 11: Septum 16 shielding increase](https://reader035.fdocuments.in/reader035/viewer/2022062410/56816150550346895dd0d89e/html5/thumbnails/11.jpg)
New schedule
End of the works:
15/03/2013 (to be
confirmed depending on the speed in pumping the
sand)