Septic Tank
-
Upload
mrrakesh786 -
Category
Documents
-
view
23 -
download
5
Transcript of Septic Tank
THE INSTITUTION OF CIVILENGINEERS (INDIA)
PROJECT REPORT
ON
ANALYSIS AND ESTIMATE FOR CONSTRUCTION OF
WASH ROOM, SEPTIC TANK & SOAK PIT
SUBMITTED BY
KULDEEP CHANDER RAINAMEMBERSHIP NO. 50940
UNDER THE GUIDANCE OF
ER. SALVANT RAJ DR. SANJEEV KUMAR GUPTALECTURER, CIVIL ENGG. H.O.D CIVIL ENGG.
DEPARTMENT OF CIVIL ENGINEERING,G.C.E.T,JAMMU
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
CERTIFICATE
This is to certify that this Project Report Entitled
ANALYSIS AND ESTIMATE FOR CONSTRUCTION
OF WASH ROOM, SEPTIC TANK & SOAK PIT
is original and has been successfully completed by the student
KULDEEP CHANDER RAINA
(MEMBERSHIP NO. 50940)
For the completion of his A.M.I.C.E course in
CIVIL ENGINEERING
FROM
THE INSTITUTION OF CIVIL ENGINEERS (INDIA),
UNDER THE GUIDANCE OF
ER. SALVANT RAJ DR. SANJEEV KUMAR GUPTA LECTURER, CIVIL ENGG. H.O.D CIVIL ENGG.
DEPARTMENT OF CIVIL ENGINEERING ,G.C.E.T, JAMMU
2
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
ACKNOWLEDGEMENT
Keeping up with the
tradition of torch bearer of the nation, I
would like to highly acknowledge and pay
respect to one and all who helped me in
completion of this project at different
stages.
I owe my sincere gratitude
and humbleness to Respected Head of
the Department, Dr. Sanjeev K Gupta
and Er. Salvant Raj, Lecturer in Civil
Engg. Deptt. for being a guiding light,
and whose persuit and confidence in me
were instant booster during this
Endeavour. They also helped me in
understanding basic aspects of the
project.
3
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
My family members and
friends also hold a speial mention her
believing in me and supporting me.
Kuldeep Chander Raina)
M. No.50940
SYNOPSIS
For my project work, it was given to me to carry out
Analysis of various items of work associated with the
construction of Wash room, Septic tank and Soak pit
for a small educational institute (of say 100 strength).
The drawings for the project were given to me by my
Guide Sir.
To start with, I thoroughly studied
the drawing and the help, wherever, found necessary
was taken. Then, the quantities of various items of
4
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
work as per the drawings, such as Earthwork in
Excavation, Concrete work, Brickwork in foundation
and super structure, Plaster work, White washing,
painting etc., were calculated using the Long wall –
Short wall method. For ease to understand, the
quantities for Wash cum WC, Septic tank and Soak pit
have been worked out separately under different
heads and listed in the report the same way.
For me to be conversant to the
prevalent rates, I have been given to work out the
analysis of rates of various items of work associated
as stated above. The analysis of items of work have
been prepared using the market prevalent rates to
get the per unit rate of the item.
Finally the abstract cost of the
project work has been calculated multiplying the
quantities worked out with the rates as per the
analysis. Also, the abstract of consumption of
materials have been worked out.
5
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
(Kuldeep Chander Raina)
M. No.50940
6
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
INDEX
TOPIC PAGE NO.
1) INTRODUCTION 9-18
2) ESTIMATION 19-29
3) DETAILS OF ITEMS 30-60 INVOLVED IN WORK
4) DRAWINGS 61-64
5) ESTIMATION OF QUANTITIES 65-82 OF WASHROOM CUM WC
6) ESTIMATION OF QUANTITIES 83-89 OF SEPTIC TANK
7) ESTIMATION OF QUANTITIES 90-92 OF SOAK PIT
8) ABSTRACT OF CONSUMPTION 93-96 OF MATERIALS
9) CONSUMPTION STATEMENT OF 97-98 MATERIALS
10) ANALYSIS OF RATES OF DIFFERENT 99-124 ITEMS
11) ABSTRACT OF RATES & QUANTITIES 125-130
12) REFERENCES 131-132
7
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
LIST OF TABLES
TABLE NO. PAGE NO.
1. Estimation of quantities 66 of wash room cum wc
2. Estimation of quantities of septic tank 84
3. Estimates of qty. Of soak pit 91
4. Abstract of consumption of materials 94
5. Consumption statement of materials 98
6. Abstract of rates & quantities 126
LIST OF DRAWINGS
8
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
DRAWING PAGE NO.
1) Septic tank 61
2) Soak pit 62
3) Wash room 63
9
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
INTRODUCTION
10
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
A Septic Tank may be defined as a primary
sedimentation tank with a longer detention period (12
-36 months) against period of 2 hours in a ordinary
sedimentation tank and with extra provisions for
digestion of settled sludge.
Since the digestion of settled sludge
is carried out by anaerobic decomposition process,
the septic tank unit is generally classified under the
units which work on the principle of anaerobic
decomposition. Moreover, due to anaerobic
decomposition of the settled sludge, foul gases will
evolved in the tank, and as such, a septic tank will be
completely covered tank, provided with a high vent
shaft for a escape of gases
A septic tank is thus, a horizontal
continuous flow type of a sedimentation tank, directly
admitting raw sewage, and removing about 60 to 70
% of the dissolved matter from it. The effluent from
such a tank will be sufficiently foul in nature, and will
have to be disposed of either for submerge irrigation
11
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
or in cess–pools or soak pits, or to be treated in
trickling filters before disposing it of in water courses.
The sludge settled at the bottom of
the tank, and the oils and greasy matter rising to the
top surface of sewage as scum, are allowed to remain
in the tank for a period of several months, during
which they are decomposed by the anaerobic
bacteria to form gases and liquids by the process of
sludge digestion. The resultant sludge so obtained,
will consequently be less than that obtained in the
ordinary settling tank (the quantity is reduced
because of digestion).
The digested sludge from the tank is
periodically (at intervals of 6 to 12 months, and in no
case exceeding 3 years) removed , and taken to a
nearby sump, from where it is pumped up to the
ground, and disposed of in a sanitary manner,
preferably after drying it
The septic tank are generally
provided in areas where sewers have not been laid
12
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
and for catering to the sanitary disposal of sewage
production from isolated communities, schools,
hospitals, other public institutions, etc.
IMPORTANCE OF A SEPTIC TANK
Septic tanks are required in those
areas where there is dearth of sewage system and
seepage or soak pits are required if in addition of non-
availability of sewerage system there is a dearth to
drainage system. This is to make the area hygienic
and freedom from all those diseases which are
caused due to unhygienic condition.
In the urban areas the people are
very much aware about the importance of drainage
and sewerage but still there are some places even in
urban areas which lack the system of disposal of
human waste and liquid particularly in the rural areas
this is a biggest challenge before the government
machinery such as ministry of health rural
development and work department . There are many
13
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
villages which do not have proper system of drainage
and sewerage and as a result the resisdance are
prone to various type of diseases.
TECHNICAL SPECIFICATIONS
Septic tank is usually designed so that waste water
takes at least 24 hours to pass through them. It
should be cleaned once in three years and sometimes
earlier depending upon the number of users. It should
be located at such a place which is accessible for
cleaning and slightly away from main unit.
A septic tank works on the basis of
biological actions brought by bacteria which converts
the solid matter of sewerage into liquid and gases. He
mineral matter settler as sludge and is converted into
liquids and gases by anaerobic action in the absence
of oxygen. 50% to 60% sludge is dissolved and the
remaining is removed and cleaned.
It should be a water tight chamber
provided with a vent pipe provided with owl. A free
14
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
board of about 30 cms is kept above the water for the
purpose of gases to collect and escape.
SOAKAGE PIT
Soakage Pits :- The converted pit through which the
effluent from septic tank is allowed to be soaked or
absorbed into the surroundings the soils is called a
Soak pit
15
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
The capacity of such pits depends
upon the percolation rates conducted in each
pervious strata. The effective area of soak pit is
generally the vertical wall area of the pervious strata
below the inlet. The area at the bottom and that of
the impervious strata are not considered.
Soak pit are generally classified into
two types as mentioned below:-
1) Empty soak pit.
2) Filled soak pit.
1) Empty Soak pit: - It is an empty covered pit
lined with bricks, stone or concrete block with a
dry open joints and with 75mm (minimum) backing
or coarse aggregate. The inlet pipe is kept 900mm
below the top level of the pit. The side of the tank
above the inlet pipe are sealed, jointed and plastered
with 20 mm thick cement plaster. The sides of the pit
below the inlet pipe are of brick or stone or cement
concrete block with dry joints. The outer side is
16
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
packed with 75mm (minimum) thick dry coarse
aggregate.
2) Filled soak pit: - It is not covered at the top. It is
filled with stone aggregates or brick bats. A masonry
ring is provided at the top in order to prevent any
damage to the pit by floods of surface run off. Lining
is not provided in this case.
The inlet pipe, is generally, kept
900 mm below the top of the pit. Above the inlet pipe
and the 150 mm below the inlet pipe, the side walls
are constructed in Masonry. Side walls below this,
are filled with300mm thick coarse sand. The pipe at
the inlet point is provided with a brick chamber with
dry joints. The thickness of the brick is 10 cm.
If the pit is filled with the stone
aggregates, then the stones should be removed
periodically for drying and cleaning purposes. If it is
not done then, the sludge fills up the voids thus
17
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
blocking the passage thereby creating a flood at the
ground surface
IMPORTANCE OF SEEPAGE OR A SOAK PIT
Seepage or Soakage pits are
required for the disposal of the liquid of the liquid
parts which overflows into it from the main septic
tank. It is constructed with a special design having
dry open joints backed by packed with coarse
aggregates which works as a fitter. These are dug up
holes having a diameter of 1 to 2 m and a depth of
minimum 1 .5m but for 100 users the depth will be
increased for about 2.5m.
18
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
19
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
ESTIMATION
An estimate is a calculation of the quantities of
various items of work, and the expenses likely
to be incurred there on. The total of these probable
expenses to be incurred on the work is
known as estimated cost of the work. The estimated
20
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
cost of a work is a close approximation of
its actual cost. The agreement of the estimated cost
with the actual cost will depend on
accurate use of estimating methods and correct
visualization of the work, as it will be done.
Importance of correct estimating
is obvious. Under-estimating may result in the client
getting an unpleasant shock when tenders are
opened and drastically modifying or abandoning the
work at that stage. Over-estimating may lose the
engineer or estimator his client or his job, or
in any case his confidence.
Estimating is the most important of
the practical aspects of construction management,
and the subject deserves the closest attention of one
aspiring to a career in the profession. It is a
comparatively simple subject to understand;
however, as it brings one up against practical
work, methods and procedure, knowledge of it cannot
be acquired without close application.
21
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Purpose of Estimating:
To give a reasonably accurate idea of the cost
An estimate is necessary to give the owner a
reasonably accurate idea of the cost to help him
decide whether the work can be undertaken as
proposed or needs to be curtailed or
abandoned, depending upon the availability of funds
and prospective direct and indirect
benefits. For government works proper sanction has
to be obtained for allocating the required
amount. Works are often let out on a lump sum basis,
in which case the Estimator must be in a
position to know exactly how much expenditure he is
going to incur on them
1. Estimating Materials
From the estimate of a work it is possible to
determine what materials and in what quantities
22
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
will be required for the work so that the
arrangements to procure them can be made.
2. Estimating Labour
The number and kind of workers of different
categories who will have to be employed to
complete the work in the specified time can be
found out from the estimate
3. Estimating Plant
An estimate will help in determining amount and
kind of equipment needed to complete the work.
4. Estimating Time
The estimate of a work and the past experience
enable one to estimate quite closely the length
of time required to complete an item of work or
23
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
the work as a whole Whereas the importance of
knowing the probable cost needs no emphasis,
estimating materials, labor, plant and time is
immensely useful in planning and execution of
any work.
TYPES OF CONSTRUCTION ESTIMATES
There are several kinds of estimating techniques;
these can be grouped into two main categories
1. Approximate estimates
2. Detailed estimates
1. Approximate Estimates
An approximate estimate is an approximate or rough
estimate prepared to obtain an approximate cost in a
24
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
short time. For certain purposes the use of such
methods is justified.
2. Detailed Estimate
A detailed estimate of the cost of a project is
prepared by determining the quantities and costs
of everything that a contractor is required to provide
and do for the satisfactory completion of
the work. It is the best and most reliable form of
estimate. A detailed estimate may be
prepared in the following two ways
(a). Unit quantity method
(b). Total quantity method.
(c) Unit Quantity Method
In the unit quantity method, the
work is divided into as many operations or items as
are required. A unit of measurement is decided. The
total quantity of work under each item is taken out in
the proper unit of measurement. The total cost per
25
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
unit quantity of each item is
analyzed and worked out. Then the total cost for the
item is found by multiplying the cost per
unit quantity by the number of units.
For example, while estimating the
cost of a building work, the quantity of brickwork in
the building would be measured in cubic meters. The
total cost(which includes cost of materials. labor,
plant, overheads and profit) per cubic meter of
brickwork would be found and then this unit cost
multiplied by the number of cubic meters of brickwork
in the building would give the estimated cost of
brickwork.
This method has the advantage that
the unit costs on various jobs can be readily
compared and that the total estimate can easily be
corrected for variations in quantities.
(b)Total Quantity Method
26
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
In the total quantity method, an item of work is
divided into the following five subdivisions:
(I)Materials
(II)Labor
(III)Plant
(IV)Overheads
(V) Profit.
The total quantities of each kind or class of material
or labor are found and multiplied by their individual
unit cost. Similarly, the cost of plant, overhead
expenses and profit are determined. The costs of all
the five sub-heads are summed up to give the
estimated cost of the item of work.
Standard Method of Measurement of Building
Works:
27
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
The different methods of measuring used by various
Central and State Government
departments and by construction agencies were
found to be a serious difficulty to estimators
and a standing cause of disputes. For this reason a
unification of the various systems at the
technical level had been accepted as very desirable
and wanting. Although the standard has no legal
sanction and as such need not be adopted unless it is
referred to in the contracts.
Principles of Deciding Unit of Measurement:
A beginner may find it difficult to remember the units
of measurement of different items.
Memorizing of units of measurement would be greatly
simplified if he knows the principles kept
in view while selecting the units of measurements.
Following are the most important principles
of selection of unit of measurement:
28
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
1. The unit of measurement should be simple
and convenient to measure, record and
understand.
2. It should be one, which provides for fair payment
for the work involved.
3. In the result it should yield quantities, which are
neither too minute nor too large.
4. The price per unit should not be a very small figure
or a very large one, that is, generall costlier
items will be measured in smaller units, cheaper
ones in large units.
5. The unit of measurement may sometimes depend
upon the unit for the raw material and or labor
and/or important dimensions. For example, stone
masonry is measured in cubic meters
because raw materials are measured in cubic
meters plastering or pointing is measured in
square meters, as the labor is considerable.
29
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
30
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
DETAILS OF THE ITEMS OF THE WORK INVOLVED
AND ESTIMATED IN THE PROJECT WORK
Earthwork in the excavation for the foundation
trenches:
31
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Earth is excavated for the foundation trenches to the
exact width and depth of the foundation with the
vertical sides and the bottom leveled both
longitudinally and transversely .The quantity of the
earthwork is calculated in Cubic meter (cum) up to
two decimal place multiplying the actual required
length x breadth x depth of the excavation .The
earthwork for step shall be included.
Earthwork in filling: - This consists of two parts
(a) Foundation of trenches and
(b) Plinth filling.
Normally excavated earth from the foundation
trenches is used for filing. The exact rammed and
consolidated volume is calculated. But considering
the quality of the earth. Plinth filling may be done by
standard this case plinth filling work shall be
separated from foundation filling.
For Foundation filing :-
32
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
The volume is calculated in cu m considering the low
rate of earth filling the quantity s usually taken as1/5th
the volume of the earthwork in excavation. But for
the high rate due to carried earth or for accuracy,
quantity of earthwork = (volume of work in
excavation-volume of work in foundation).The volume
of work in foundation may be of brick soling ,
concreting and masonry work up to ground level.
Plinth filling: -
The volume is calculated in cu m. The internal length
and breadth, of a verandah between plinth walls i.e.,
excluding plinth off set from the
Measurements of rooms or verandah are taken and
multiplied by depth of filling the depth of feeling is
taken from ground level up to the bottom of floor
structure
Cement or lime concrete in foundation:-
33
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
The volume is computed in cu m
i.e., length x breadth x depth of concrete. Dimension
for length and breadth for concrete remains the same
as that of earthwork when section of all walls of the
building are same (For different sections this length
only varies as explained in the above chapter) For
R.C.C.foundation see R.C.C. works
Masonry work (may be brickwork or stone
masonry in the foundation and plinth :-
The volume of different offsets or layers and plinth
wall are calculated one by one in cu m by multiplying
their individual length breadth and height or
thickness. As there is no opening in the wall up to
plinth no deduction is required.
Damp proof course (D.P.C.) :-
34
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
This is usually a layer of the cement concrete mixture
in the pripition1:2:4mixed with water profiling
compound laid in between the plinth and
superstructure walls to prevent excessive damp
effectively a layer concrete (1:1/2:3)4cm in thickness
painted with two coats of hot bitumen are used D.P.C.
may also of other layers, like 2 cm thick cement
mortar (1:3) with water proofing compound or hot
Bitumenetc. The quantity is estimated in square
meter (sq m) multiplying the length and breadth. The
thickness is described in description column. The total
length is that to superstructure walls is considered
first. The breadth is thickness of superstructure walls.
After calculated total area deduction made for door
opening, verandah opening or such other where there
is no superstructure walls above the plinth level to
intercept the capillary action of the water. Similarly
there is no need to provide D.P.C. for entire top width
of plinth and superstructure walls (i.e. width of
superstructure walls) should be considered in the
calculation to find the quantity of D.P.C.
35
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Masonry work in superstructure walls :-
For walls up to one brick (i.e., upto 20 cm) thick the
volume is calculated in cu m, Length breadth or
Thickness height.
The wall is considered first solid, has no opening and
no lintel in the wall. The length is calculated by
method of calculation (illustrated next). After
calculated the the volume of brickwork (considering
the soling first) standard deduction for volumes for
opening, volume occupied by lintel or any such others
are made as per standard rules of deduction
prescribed by IS: 1200 (described in article 4-4) to
arrive estimated quantity of brickwork. For
multistoried building s brickwork for different stories
shall be kept separated.
10 cm thick brickwork : -
10 cm thick or when the length of brick are laid
parallel to the wall. (May also be 7.5 cm thick for
traditional brick on edge) the quantity of brickwork is
36
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
computed in sq m. i.e., length x height the thickness
is described in description column. Any brickwork
more than 10cm or half brick. (In case of pillar
provided in 10 cm walls) be accounted separately
R.C.C or R.B. (reinforced brick work):-Reinforced
concert may be for column, lintels, beams, roof slab
etc.The quantity is worked over in cu m, i.e., length x
breadth x depth including reinforcement. The volume
occupied by reinforcement is not deducted from the
volume of the concert.
The quantity of reinforcement in found
separately by providing aspirate item in the estimate
if not otherwise mentioned. Each type of work is
classified separately the method of measurement in
conjunction with column and beams has been stated
in the R.C.C. chapter.
According to I.S. recommendation from work i.e.,
shuttering shall be classified and measured
37
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
separately. If reinforcement or shuttering are
included and considered at the consolidated one
item, this should be fully described and measured in
cu.m. R.B. work in lintel in roof slab is measured in
cum as in the case of R.C.C. chajja is include with
R.C.C. work.
Centering and shuttering from work : - The cost
of form work is about 30% of cement concrete. Unless
otherwise specified form work is measured separately
(see chapter method of measurement for form work),
in sq m. multiplying length and breadth.
Measurement is taken as the actual surface in
contract with concrete or any other materials
requiring form work. Generally to surface area of the
buildup concrete member is measured.
Steel work (reinforcement) :-Tor steel is now in
mass use this is measured by weight in quintal
including bending and binding in position .No
38
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
separate payment is made for binding wire. For
estimating purpose, the weight of reinforcement may
be calculated from the percentage volume in the
R.C.C. such as 0.8% or1%
Reinforcement for different members. Say 1%
reinforcement in roof slab. Than volume of
reinforcement in cum =volume of the member in cum
x1/100.Weight of steel (may be M.S. or tor steel) per
cum =78.5 quintals. So multiplying the volume of
reinforcement by 78.5. The quantity is in quintal.
Percentage method is shortcut process of
estimating the quantity of the reinforcement. But in
practice quantity of reinforced is worked out from the
bar bending schedule and paid after measuring the
bars before concreting. For reinforcement separate
bars before concreting. For reinforcement separate
bar bending and drawing prepared for different
39
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
members showing the position of the bar, position of
crank, bend etc. and works are done according
In the estimate for reinforcement
the diameter of bar is stated, its length is measured
including standard crank , overlapping and end
hooks . From the calculated length the weight for the
rod is worked out in quintal. The unit of rate of
payment is quintal (maybe in kg).
Actually the price of reinforcement
bar (M.S. or TOR varies according to their diameters.
But the P.W.D. schedule has provided a general rate
for reinforcement, and not diameter wise. To maintain
the quantity, the steel bars are provided by
department.
40
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
WOOD WORK FOR DOORS AND WINDOWS : -
Door and window frame: The quantity is worked
out in cu m. The total length of frame is found first
and thus is multiplied by both sides of the cross
section of the frame. Doors are now provided now
without bottom still. So the total length of the frame
is=two vertical + on top. Size of door or window
means the size of the opening. So length of one
vertical means the means the height of the opening.
That is, insertion in between the verticals
and horizontal are accounted. Generally vertical floor
so also measured for the verticals. If there be horn
projections at both sides for the top member the
length of the horn is added. Window frame may be
provided with bottom still and with an intermediate
member in between the top and bottom members.
41
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Then the total length=2
verticals+3horizontals.If horns are provided for the
top and bottom members this extra length is added.
Mild steel (M.S.) clamps for fixing frames are
estimated separately.
(b)Door and window leaves or shutters :-Shutters
are measured in sq m. multiplying the height by the
breadth, stating the thickness in the description. The
depth of rebates in frame usual1.25cm to2cmare
added in the measurement. For double shutters the
overlapping at the centre between the leaves is not
accounted. For free moment of the shutter a small
gap of 5mmproovded at the bottom of the shutters.
Considering high rate of the
shutters measurement should be taken excluding the
clearance. The design and class of wood are stated in
description column. In P.W.D. schedule of rates this
item of work includes fitting. Hinges for fixing the
shutters with the frame and all other fitting such as
42
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
tower bolt, sliding bolt (orAldrop), Door handles etc.,
are fully described for their quality sizes and made in
description column and paid by member after
counting them.
But in estimates, the item of door
and window shutters may include the cost of hinges
and all other fittings with fixing when mentioned as
per drawing. Working drawing is very important for
this costly item of woodwork and invariably this is
prepared by the department and so in the drawing.
The position of fitting may be
shown. Otherwise, fitting are paid individually
provided separate items nos. No other shortcut
process is allowed by P.W.D.
Mild steel (M.S.) Clamp or hold fast:-This item is
enumerated i.e., counted by numbering the estimate.
For window frame 6 nos. of clamps @ 3 nos.for each
vertical member of door frames are provided in the
estimate. For window frames4 nos. of clamps@
43
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
2nos.for each vertical are considered. The size and
type of clamps stated in the description.
The item may be paid kg after
measuring the weight of one such member(usually
11/2kg).This items includes fitting and fixing with
cement concrete(1:2:4cost of cement concrete may
be included or paid separately.
Flooring Flooring for ground floor :-
Ground means floor of plinth. The floor consists of two
parts,
(i) Bottom are bed of floor usually provided with 7.5
cm thick lime concrete (1.5:2:7)or cement
concrete(1:3:6)over a brick flat soling is done to
prevent the contamination of green concrete with
earth below it
44
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
(2) The top part above the base which may be
finished with 3mm to 6mm thick toping with coloring
pigment highly polished pigments , highly polished
and grinding. The top part may be 9mm to 12 mm
terrazzo or 20mm thick (finished)terrazzo or20 mm
thick (finished) terrazzo worked precast tiles set in
lime or cement mortar bed.
The quantity for base 7.5 cm thick
concrete is calculated in sq m stating the thickness by
multiplying the inside dimensions of plinth to plinth
walls.
Thus, the quantity of the top of
flooring is calculated also in sq m stating the
thickness by multiplying the inside dimensions of the
room.
So the area top of flooring shall be
more the area of base concrete. The variation for a
number of rooms in a building is considerable. Now, in
case the area of top is considerable to be the same as
the base area and materials such as precast tiles for
45
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
the top is procured, shortage of tiles shall beacon
actor shall get an excess payment.
For a number of rooms the amount
may be considerable. So the P.W.D.Schedule of rates
provide two separate items with rates, separating
work of flooring into two parts.
Brickwork :-Brickwork (with lime or cement mortar)
of one or more than one brick wall (one brick thick
walls when length of brick is parallel to thickness of
wall. Thickness of brickwork shall be measured in
multiples of half brick. Net measurement shall be
taken after deduction of all opening with lintels. For
small curves or chamfers measurements on the
square (i.e., without deduction for the small curves or
chamfers) is allowed.
Round pillars or the pillars of
polygonal form shall be calculated as if they were
square, the dia, and being taken as the side of the
46
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
square. Brickworks circulars on plan to mean the
radius exceeding 6m shall be measured separately.
But the brickwork at different levels as in foundation
and plinth superstructure ground floor, 1st floor etcs
hall is measured separately.
No extra payment shall be made for
foaming the small curves or chamfer. No. deduction
shall be made for the opening like ventilators, flues
etc. having opening up to 0.1 sqm in section.
Thus for ends of dissimilar materials
like beams, joists, rafters etc.up to 500sq cm in
section in walls no deduction shall be made.
Reinforced brickwork :-Unless otherwise stated
reinforcement and timber work shall be made
separately.
47
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
10cm or half brick walls :-Brick on edge wall shall
also be paid in sq m. Wire netting etc. If provided
shall be included in the item.
Lime or cement concrete in foundation :-works of
lime concrete shall be fully described.
Reinforced concrete (R.C.C) :- Each class of work
shall be measured separately.
Unless otherwise stated, frame
work and reinforcement are measured as a composite
item they shall be fully described indicating that
supply of reinforcement is included in the item. No
deduction shall be made for the volume occupied by
Reinforcement,
(b)Pipes, conduits etc. not exceeding 100sq cm each
in cross section area (opening)
(c)opening up to 0.1 sq m ,
48
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
(d) Ends of dissimilar material up to 500 sq cm,
(e) Chamfers, splays grooves and rebate.
Formwork:
Unless otherwise specified formwork shall be
classified and measured, separately. Measurement
shall be taken as the actual surfaces in contact with
the concrete or any other material requiring
formwork.
49
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Reinforcement : -
Shall include the standard length for hooking ends,
cranking and overlapping and cutting to length or
bending and binding. Binding wires are included.
Damp proof. Course (D.P.C.) :-
Measurement shall be taken stating the thickness.
R.C. Chajja sun shade : -
Where chajja is combined with the beam or lintel the
common portion shall be measured as chajja.
Precast C.C. or R.C.C. blocks :-
Formwork or mould shall be deemed to be included
with items .Preset unit shall be enumerated.
Solid block work (bed etc.) :-
May also be measured in sq m stating thickness.
50
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Hollow concrete block wall :-
No deduction shall be made for the hollows in the
blocks. Others are the same as described above
Expansion :-
Expansion joints in roofs, floors, walls roads, etc.,
shall be given in rm stating the width and depth of
the joint and material used for filling the joint.
Earthwork in excavation in any type of soil.
Measurement shall be taken as per authorized
dimensions from which soil has been taken out and
shall be measured without allowance for increase in
the bulk.
Excavation exceeding1.5m in which width as well as
10 sq. m.on plans but not exceeeding30cm in-depth
51
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
shall be considered as surface excavation and given
in sq.m. Stating the average depth.
Excavation in the hard rock
Earthwork in the different kinds of the soil and rock
formation shall be kept separate.
Excavation in trenches for the foundation and
for pipes, cables etc .
The actual measurement s of the fill shall be
calculated by taking levels of the original ground
before start of the work and after completion of the
fill at suitable intervals.
Earthwork in filling (with sand or loose earth) in
foundation trenches or plinth
52
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
The filling shall be measured and the following
deductions shall be made for settlement to arrive at
the net quantities.,
(A)10% in consolidated fills , except where the
consolidation is done by heavy machinery in which
case the deduction shall be 5%;
(B) where measured in loose stacks or in carts or
lorries, a25% deduction;(c)no deduction shall be
made in the case of consolidated fills in confined
situations like floors.
Random rubble masonry, Ashlars masonry
walling and arches
If facing stones are the same as those used in body of
walling, additional work involved in dressing stones
shall be as ‘extra over’ walling. Other
particularsshallbe same as brickwork.
53
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Stonework in the wall facing etc .
The character of facing, the average width of width
of bed and thickness of joints shall be stated. Circular
facings exceeding6m in radius on plan shall be
included in the general facing.
Stonework in sills, steps, string, cources,
cornices, columns lintels, coping etc
Type of dressing shall be described and measured in
sq m as extra - over.
Terraced roofing portion of tiles, bricks or stone
slabs
The thickness, size and quantity of the tiles, bricks or
stone slabs shall be stated. The numbers of layers,
method of laying, pointing and kind of mortar with
54
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
proportion shall be stated and include in the item.
The supporting rafter and beams shall be measured
sparely under relevant clauses.
Ridges, hips & valley
Hip hooks shall be enumerated.
Asbestos corrugated (A.C.) or galvanized
corrugated Iron (G.C.I.) sheet roofing
Corrugated sheets shall be measured flat and not by
girth. No addition shall be made for laps. Ridges hips
and valley shall be measured in r m stating the laps
for A.C. sheeting and thickness shall be described.
Water proofing on roof.
Surface painting if applied shall be measured
separately
55
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Terrazzo or Mosaic flooring .
The thickness shall be measured after polishing the
floor materials of dividing strips shall be stated and
given running m mentioning the thickness.
Doors and window shutters of different types
Net measurement shall be taken as per opening in
the framework including rebate but excluding extra
width for rebated or splayed meeting styles of doors
and windows.
Woodwork in door and window frames
Measurement shall be taken as opening and included
the length for joints, horns etc.
M.S. Structural works, R.S.J., channels, angles,
Tee or bar etc .
56
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
No deduction shall be made for rivet or bolt holes.
The weight of cleats gusset plates, packing pieces,
rivets heads etc. shall be added to respective items.
Holding down bolts shall be measured separately.
Steel doors and window
The sizes of the varies members, methods of fixing
and hanging and fastening shall be included in the
item.
All pipe lines water pipe, rain water sanitary
etc.
The measurement shall be taken along the central
line of the pipe & fitting or specials. All fitting or
specials shall be enumerated separately as extra over
the pipes. Alternatively measurement shall take along
57
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
the central line of the pipes and in between the fitting
or specials. All joints, fitting or specials shall be fully
described and enumerated separately.
Sewer lines
Same as water lines.
Manholes or Inspection chamber
Shall be measured in detail as recommended in
relevant I.S. for different items.
Rain-water, vent, waste pipes etc
The length shall be measured along the central line
of the pipes and fitting. Length as laid or fixed shall
be measured over all fittings such as bends, angles
etc. Which shall not be measured separately? The
diameters shall be nominal dia. Of the internal bore.
58
ANALYSIS & ESTIMATE FOR CONSTRUCTION OF WASHROOM, SEPTIC TANK & SOAK PIT
Sanitary fittings .
Sanitary fittings such as closet pans, wash basins,
sinks, urinals, shower roses , flushing pipes etc. shall
be fully described.
Glass panes
Each plane of glass shall be measured to the nearest
0.5 cm Irregular or circular planes shall be measured
as the smallest rectangular area from which the
panes can be cut.
59