SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an...

6
Bangladesh LNG Update: FSRU Import Projects kslaw.com SEPTEMBER 2017 How to structure LNG FSRU projects and navigate key legal and regulatory issues in Bangladesh

Transcript of SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an...

Page 1: SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an MOU for GE to potentially provide USD$50 m of equity to Summit, to be used for the

Bangladesh LNG Update: FSRU Import Projects

kslaw.com

SEPTEMBER 2017

How to structure LNG FSRU projects and navigate key legal and regulatory issues in Bangladesh

Page 2: SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an MOU for GE to potentially provide USD$50 m of equity to Summit, to be used for the

1. http://www.worldbank.org/en/results/2016/10/07/bangladesh-ensuring-a-reliable-and-quality-energy-supply 2. http://www.lngworldshipping.com/news/view,asias-2030-lngdemand-prospects-the-highs-and-the-lows_44614.htm 3. https://www.reuters.com/article/us-bangladesh-power-lng/bangladesh-lng-drive-likely-to-hit-its-diesel-fuel-oil-demand-idUSKBN19R0R5

Of Bangladesh’s installed electricity capacity, 63% is from

gas-fired plants.3 Bangladesh is currently able to supply

approximately 2,700 mmcf/d of gas from various domestic

gas fields and according to Bangladesh Oil, Gas and Mineral

Corporation (“Petrobangla”), there is a shortfall of around

700 to 800 mmcf/d. With Bangladesh’s gas reserves

depleting and the discovery of new gas fields in Bangladesh

decreasing (the last gas field was discovered in 2014), the

GOB initiated a project to import LNG from Qatar in 2010.

Now, seven years later, Bangladesh’s first LNG import

terminal is under construction and set to come online in 2018.

Bangladesh is becoming an increasingly hot topic in the

Asian LNG sector, with six agreements and memoranda of

understanding (MoU) having been signed for LNG import

terminals and additional expressions of interest (EoI)

issued for further terminals. We have set out below our

understanding of the current LNG import projects planned

in Bangladesh.

King & Spalding is advising Summit Corporation Limited on

the second LNG import project in Bangladesh, as well as a

potential supplier to another LNG (FSRU) import project.

Read “King & Spalding Advises Summit Corporation on New

Bangladesh LNG Import Terminal” kslaw.com/news-and-

insights/king-spalding-advises-summit-corporation-on-new-

bangladesh-lng-import-terminal.

We understand how to structure LNG projects of this nature

and how to navigate some of the legal and regulatory issues in

Bangladesh. In this report, we set out five key issues to consider.

The Need for Power

A decade ago, less than 50% of the Bangladeshi population

had access to electricity; today that figure stands at 78%. This

underlines the impressive progress made by the Government

of Bangladesh (the “GOB”) in achieving its goal of providing

power1 to all its citizens, which it aims to do by almost doubling

power capacity to 24,000 MW by 2021.1 The Oxford Institute

of Energy Studies (OIES), which has studied the high and

low growth scenarios for LNG imports to Asia, predicts that

Bangladesh could be importing up to 18.8 MTPA by 2030.2

1 KING & SPALDING

Page 3: SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an MOU for GE to potentially provide USD$50 m of equity to Summit, to be used for the

1. PROJECT DOCUMENTATION

The Moheskhali Floating LNG (FSRU) Project (“MLNG”) and the

Summit LNG FSRU LNG Import Terminal (“SLNG”), were awarded to

Excelerate Energy and Summit Corporation, respectively, on a build,

own, operate, transfer (“BOOT”) basis for a 15 year term. Summit has

entered into a long-term charter party agreement with Excelerate

Energy for the provision of an FSRU vessel to the SLNG project.

The key project documents for the projects are: (i) the

Implementation Agreement (the “IA”), to be entered into between

the GOB and the project company (“Project Co”); and (ii) the

Terminal Use Agreement (the “TUA”), to be entered into between

Petrobangla and Project Co. The IA maps out the GOB’s and

Project Co’s rights and obligations towards each other and

includes the GOB’s authorisation for the LNG terminal and a

government guarantee with respect to Petrobangla’s obligations.

The TUA sets forth Project Co’s obligations with respect to the

construction, ownership and operation of the LNG terminal and

Petrobangla’s purchase of regasification services from Project Co.

When negotiating the project documentation, it is fundamental to

the viability of the project to ensure that all of Project Co’s rights and

obligations under the IA and TUA are, to the fullest extent possible,

aligned with its (and the FSRU provider’s and contractor’s) rights

and obligations under the FSRU time charter party agreement

(“TCP”) and the pipeline EPC contract(s). Failure to do so could

result in Project Co being in material non-compliance of the IA and

the TUA, which in some cases may lead to termination of the project

and forfeiture of the FSRU and fixed infrastructure.

2. TERMINAL TRANSFER REGIME

The IA and the TUA each set forth a detailed procedure with respect

to (i) the transfer of the terminal to the GOB / Petrobangla at the end

of the term of the project and (ii) for early termination of the project,

including extensive FSRU transfer mechanics. It will be important

to ensure that a suitable transfer regime is agreed upfront with the

FSRU provider and that a detailed vessel transfer procedure is set

forth in the TCP, particularly given the technical and operational

nature of the services required to be provided.

The sponsors will also need to consider how the value of the

FSRU and fixed infrastructure is to be calculated on transfer.

At a minimum, the value of the FSRU upon transfer to the

GOB or Petrobangla should reflect the valuation set out (on a

depreciation basis) in the IA, but there may be additional project

costs or margin which the project sponsors or FSRU supplier

would seek to recover under the TCP.

3. PASS THROUGH OF LIABILITIES

A fundamental issue for the sponsors to consider is the different

nature of the contractual liabilities faced by Project Co under the

IA and the TUA and the FSRU provider under the TCP. The scale of

penalties and damages potentially payable under the IA and TUA is

of a much higher magnitude than those payable under a TCP. Whilst

the sponsors will need to assess how to allocate liability for the

failure of multiple parties (GOB, Petrobangla, Project Co., FSRU

provider(s), EPC contractor(s)), an FSRU provider will in most

cases seek to limit its liability to events caused by its own failure,

i.e. the FSRU’s failure to perform the regasification services.

Liabilities under the project should be allocated appropriately

among the project participants, taking into consideration

which party is best situated to mitigate the risk. This may

entail requesting the FSRU provider to share certain IA/TUA

project risks. Alignment of all project risks will be particularly

important to project finance lenders who will want to ensure

that (as far as possible) Project Co is insulated from gas

supply failure or interruption risk, for example, by requiring

that Petrobangla is required to continue to pay for terminal

services under the TUA. Similarly, there may be certain

circumstances in which Project Co cannot continue to pay hire

payments under the TCP if it is not in receipt of payments from

Petrobangla / GOB under the TUA or IA, respectively.

BANGLADESH LNG UPDATE: FSRU AND OTHER LNG IMPORT PROJECTS 2

SEPTEMBER 2017

Page 4: SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an MOU for GE to potentially provide USD$50 m of equity to Summit, to be used for the

4. RESTRICTION ON OFFSHORE GUARANTEES

FSRU providers are likely to request that Project Co issues

credit support in favour of the FSRU provider (typically

in a form of a standby-letter of credit from a reputable

international bank) to cover Project Co’s hire payment

obligations under the TCP. However, Section 5 of the Foreign

Exchange Regulations Act of Bangladesh restricts any person

or residents of Bangladesh from creating any right in favour

of non-residents to receive payments outside of Bangladesh,

including in the form of a guarantee, without the prior

approval of the Central Bank of Bangladesh. For this reason,

a Bangladesh project company may find it difficult to give a

guarantee to the FSRU provider or EPC contractor if such

project company is not a Bangladesh entity: such risks will

need to be addressed in the TCP.

5. FORCE MAJEURE AND ENVIRONMENTAL CONDITIONS

Any misalignment between the force majeure provisions in

the IA and TUA, the TCP and other project documents may

create uncertainty as to whether Project Co can claim force

majeure in respect of events affecting the FSRU project. For

example, an event of force majeure under the downstream gas

supply arrangements should (in theory) trigger a force majeure

under the IA, TUA and TCP, as this will ensure that Project

Co is relieved from its obligations to continue to provide the

regasification services.

The environmental conditions of constructing and operating

a floating LNG terminal in Bangladesh should also be

considered. Bangladesh’s monsoon season runs from June

through to September and accounts for approximately 80% of

Bangladesh’s rainfall. For this reason, construction on the fixed

infrastructure of the LNG terminal will likely be suspended

for at least four months of a year and will need to be factored

into project timelines. In addition, project feasibility studies

and technical studies for the FSRU and its mooring will be

fundamental to the success of the project.

3 KING & SPALDING

SEPTEMBER 2017

Richard Nelson PartnerOil & Gas

Singapore: +65 6303 6092Mobile: +65 9759 [email protected]

Zoë Joy Bromage

AssociateOil & Gas

Singapore: +65 6303 [email protected]

Page 5: SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an MOU for GE to potentially provide USD$50 m of equity to Summit, to be used for the

NA

ME

SPO

NSO

RS

TYPE

LOC

ATIO

NPR

OJE

CT

CO

STEQ

UIT

YD

EBT

STA

RT

DAT

ETE

RM

SUM

MA

RY

1M

ohes

khal

i Fl

oatin

g LN

G P

roje

ct

(“M

LNG

”)

Exce

lera

te a

nd

the

IFC

13

8,0

00

m3

FSR

U w

ith b

ase

rega

sific

atio

n ca

paci

ty o

f 50

0 M

Msc

f/d

Offs

hore

M

ohes

hkha

li is

land

in th

e B

ay

of B

enga

l

US$

179.

5 m

illio

nEx

cele

rate

US$

43.1

mill

ion

IFC

– U

S$10

.8

mill

ion

$125

.7 m

, inc

ludi

ng

IFC

’s lo

an o

f $32

.8

m w

ith th

e ba

lanc

e fr

om C

DC

Gro

up,

DEG

, FM

O a

nd

JIC

A.

Q4

2018

15 y

ears

Firs

t LN

G im

port

term

inal

in B

angl

ades

h.

In Ju

ly 2

017

the

Spon

sors

ann

ounc

ed th

at th

ey h

ad

secu

red

debt

fina

ncin

g fo

r the

pro

ject

.

Con

stru

ctio

n of

the

term

inal

will

com

men

ce in

Q4

2017

.

2Su

mm

it LN

G

FSR

U L

NG

Im

port

Ter

min

al

(“SL

NG

”)

Sum

mit

138,

00

0 m

3 FS

RU

with

bas

e re

gasi

ficat

ion

capa

city

of 5

00

MM

scf/d

Offs

hore

M

ohes

hkha

li is

land

in th

e B

ay

of B

enga

l

US$

400

– 50

0 m

illio

nN

/AN

/A20

1915

yea

rsSe

cond

LN

G im

port

term

inal

in B

angl

ades

h.

GE

and

Sum

mit

have

ent

ered

into

an

MO

U fo

r G

E to

pot

entia

lly p

rovi

de U

SD$5

0 m

of e

quit

y to

Su

mm

it, to

be

used

for t

he d

evel

opm

ent o

f pow

er

proj

ects

in B

angl

ades

h. In

add

ition

, GE

Gas

Pow

er

Syst

ems

will

hav

e rig

hts

to s

uppl

y eq

uipm

ent

for t

he p

ower

pro

ject

s ba

sed

on g

as tu

rbin

e te

chno

logy

.

3Pe

tron

as

Con

sort

ium

Pe

tron

as,

Hon

g Ko

ng

Shan

ghai

M

anja

la P

ower

an

d G

loba

l LN

G

138,

00

0 m

3 FS

RU

with

bas

e re

gasi

ficat

ion

capa

city

of 5

00

MM

scf/d

Kutu

bdia

Isla

ndN

/AN

/AN

/AN

/A15

yea

rsB

angl

ades

h ca

bine

t app

rova

l was

repo

rted

ly g

iven

in

Aug

ust 2

017.

4R

elia

nce

Ban

glad

esh

LNG

and

Pow

er

Proj

ect

Rel

ianc

e Po

wer

Lim

ited

138,

00

0 m

3 FS

RU

with

bas

e re

gasi

ficat

ion

capa

city

of

500

MM

scf/d

Meg

hnag

hat

US$

1 bill

ion

N/A

N/A

N/A

15 y

ears

The

745

MW

CC

PP w

ill u

se th

e re

gasi

fied

LNG

as

fuel

. Fin

anci

ng o

f the

pro

ject

is u

nder

co

nsid

erat

ion

of A

sian

Dev

elop

men

t Ban

k an

d a

cons

ortiu

m o

f len

ders

.

5M

ohes

hkha

li La

nd B

ased

LN

G

Impo

rt T

erm

inal

Petr

onet

7

mta

, lan

d ba

sed

impo

rt te

rmin

alKu

tubd

ia Is

land

US$

950

mN

/AN

/A20

20N

/AM

OU

sig

ned

in D

ecem

ber 2

016

betw

een

Rup

anta

rita

Prak

ritik

Gas

and

Pet

rone

t to

set u

p an

LN

G re

gasi

ficat

ion

term

inal

at K

utub

dia

Isla

nd.

The

proj

ect e

nvis

ions

futu

re e

xpan

sion

and

can

be

used

to s

uppl

y LN

G th

roug

h sm

all b

arge

s and

LN

G

truc

ks to

use

rs w

hich

are

not

con

nect

ed b

y ga

s grid

.

6M

ohes

hkha

li Se

cond

Lan

d B

ased

LN

G

Impo

rt T

erm

inal

Pow

erce

ll 3.

5 m

ta, l

and

base

d im

port

te

rmin

al

Moh

eshk

ali

Isla

ndN

/AN

/AN

/A20

21N

/APo

wer

Cel

l has

invi

ted

tend

ers

for t

he E

PC

cont

ract

and

for a

60

% s

take

in th

e pr

ojec

t. Th

e re

mai

ning

40

% w

ill b

e ow

ned

by IF

C In

fra

Vent

ures

and

by

stat

e-ow

ned

Ban

glad

esh

Pow

er

Dev

elop

men

t Boa

rd. I

n M

arch

201

7, P

ower

Cel

l an

noun

ced

a sh

ortli

st o

f fou

r com

pani

es to

bui

ld

the

LNG

-impo

rt te

rmin

al.

Sum

mar

y of B

angl

ades

h LN

G Pr

ojec

ts

KIN

G &

SPA

LDIN

G

4

Page 6: SEPTEMBER 2017 Bangladesh LNG Update: FSRU Import Projects · GE and Summit have entered into an MOU for GE to potentially provide USD$50 m of equity to Summit, to be used for the

NA

ME

SPO

NSO

RS

TYPE

LOC

ATIO

NPR

OJE

CT

CO

STEQ

UIT

YD

EBT

STA

RT

DAT

ETE

RM

SUM

MA

RY

7Sm

all S

cale

LN

GN

/ATh

ree

smal

l FS

RU

s w

ith

rega

s ca

paci

ty

of 15

0 –

200

MM

scf/d

Karn

aphu

li Fe

rtili

ser

Com

pany

N/A

N/A

N/A

N/A

N/A

Und

erst

ood

that

the

GO

B in

tend

s to

aw

ard

smal

l sc

ale

LNG

pro

ject

und

er th

e Sp

eedy

Sup

ply

of

Pow

er a

nd E

nerg

y (S

peci

al P

rovi

sion

) Act

201

0.

8Tw

o FS

RU

te

rmin

als

Gun

vor a

nd

Trafi

gura

Two

200

mill

ion

cubi

c fe

et/d

ay

LNG

impo

rt

term

inal

s

Sout

heas

tern

B

angl

ades

hN

/AN

/AN

/A20

18N

/AR

ecen

t rep

orts

sta

te th

at P

etro

bang

la h

as

shor

tlist

ed th

ese

two

com

mod

ity

trad

ers

to

final

ise

the

deal

s an

d pa

ve th

e w

ay fo

r the

in

stal

latio

n of

two

float

ing

LNG

term

inal

s in

20

18.

Sum

mar

y of B

angl

ades

h LN

G Pr

ojec

ts

KIN

G &

SPA

LDIN

G

5