Seismic Performance of Electric Transmission Systems

28
SEISMIC PERFORMANCE OF ELECTRIC TRANSMISSION SYSTEMS Eric Fujisaki, P.E. Pacific Gas and Electric Company, San Francisco, CA

description

Seismic Performance of Electric Transmission Systems

Transcript of Seismic Performance of Electric Transmission Systems

Page 1: Seismic Performance of Electric Transmission Systems

SEISMIC PERFORMANCE OF ELECTRIC TRANSMISSION SYSTEMS

Eric Fujisaki, P.E. Pacific Gas and Electric Company, San Francisco, CA

Page 2: Seismic Performance of Electric Transmission Systems

Overview

  Introduction   Historic performance of electric transmission

systems   Substation buildings   Substation equipment/ components   Underground transmission cables   Recent R&D activities   Research needs

2

Page 3: Seismic Performance of Electric Transmission Systems

PG&E’s Electric Transmission System

  Mix of old and new equipment, structures, buildings, nearly 1,000 substations

  Transmission lines mostly overhead, some underground in Oakland and SF Peninsula

  Older Buildings—Indoor substations mostly in urban areas  URM or Lightly-reinforced masonry  Non-ductile reinforced concrete shear wall  Most have steel gravity frames

  Seismic capability varies

3

Page 4: Seismic Performance of Electric Transmission Systems

Seismic Hazard

  Bay Area  Several active fault

systems  High concentration of

substations  High concentration of

customers

4 Mapsource:USGS,2008

Page 5: Seismic Performance of Electric Transmission Systems

Recent Historic Performance

 One large earthquake—Loma Prieta  Several moderate earthquakes, e.g.,

Morgan Hill, Coalinga, San Simeon  Substation damage

5

Page 6: Seismic Performance of Electric Transmission Systems

Loma Prieta (6.9Mw), 1989

  19 phases of live tank breakers damaged, 500kV, several 230kV

  25 poles of disconnect switches damaged, 500kV

  Several radiator leaks on transformers, 500 and 230kV

  15 current transformers, 500kV   7 CCVTs damaged, 500kV   Numerous 230kV switches damaged   Rigid bus work damage 500, 230kV

6

Page 7: Seismic Performance of Electric Transmission Systems

Coalinga (6.4Mw), 1983

  Transformer bushing leaks, 500/230kV

  2 transformers sheared anchors, shifted, uplifted

  2 support frames of OCBs damaged

  2 PTs shifted   1 OCB with friction clips

shifted, 60kV   1 battery rack shifted 7

  12 phases of live tank circuit breakers damaged, 500kV

Morgan Hill (6.2Mw), 1984

Coalinga & Morgan Hill Earthquakes

Page 8: Seismic Performance of Electric Transmission Systems

Historic Performance— Live Tank Breakers

8

Page 9: Seismic Performance of Electric Transmission Systems

Historic Performance— Instrument Transformers

9

Page 10: Seismic Performance of Electric Transmission Systems

Historic Performance—Buses, Switches

10

Page 11: Seismic Performance of Electric Transmission Systems

Historic Performance—Radiators

11

Page 12: Seismic Performance of Electric Transmission Systems

Historic Performance— Connectors at Elevated Switches

12

Page 13: Seismic Performance of Electric Transmission Systems

13

Historic Performance— Elevated Switches

Page 14: Seismic Performance of Electric Transmission Systems

Underground Transmission Cables

14

Type Vintage Typical Installation

High pressure gas filled (HPGF)

1950s-1960s 6”-8” steel pipe casing, pressurized with N2 gas

High pressure oil (fluid) filled (HPFF)

1970s-1980s 6”-8” steel pipe casing, pressurized with oil

Solid dielectric (XLPE)

Late 1990s-Present

Cables in PVC conduits, encased in concrete duct bank

Page 15: Seismic Performance of Electric Transmission Systems

Underground Transmission Cables— Likely Failure Modes

15

Cable Type Failure Modes

HPGF HPFF

  Loss of pressure boundary   Excessive curvature (short bend radius)

XLPE   Cable crushing/ pinching   Excessive curvature (short bend radius)

Page 16: Seismic Performance of Electric Transmission Systems

Liquefaction Zones

16

  Segments of underground transmission lines pass thru high risk liquefaction zones

  Best addressed by contingency planning and system redundancy

Page 17: Seismic Performance of Electric Transmission Systems

Mitigation Efforts

  Substation building retrofit   Seismic qualification standards

implementation   Targeted equipment replacement   Equipment anchorage retrofit   Capital improvements—new equipment

procurement, system redundancy   Contingency planning

17

Page 18: Seismic Performance of Electric Transmission Systems

Building Retrofit

18

Page 19: Seismic Performance of Electric Transmission Systems

Seismic Qualification Standards Implementation

19

Page 20: Seismic Performance of Electric Transmission Systems

New and Replacement Equipment

20

Page 21: Seismic Performance of Electric Transmission Systems

Equipment Anchorage

21

Page 22: Seismic Performance of Electric Transmission Systems

Current R&D Activities

  Application guide for connected equipment   Network studies of seismic performance   Transformer bushing test protocols   Station post insulator studies

22

Page 23: Seismic Performance of Electric Transmission Systems

Application Guide for Connected Equipment

  Interaction between connected equipment recognized as a likely cause of failure in past earthquakes

  IEEE 1527, “Recommended Practice for Design of Flexible Buswork …” approved in 2006

  Complex methodology, limited acceptance   Application guide to supplement IEEE 1527 has

been drafted (Dastous and Der Kiureghian)

23

Page 24: Seismic Performance of Electric Transmission Systems

Recommended Shapes

24

Triple curvature

Catenary Inverse parabola

Double curvature

Page 25: Seismic Performance of Electric Transmission Systems

  Conventional wisdom—Sufficient cable slack leads to Seismic Terminal Force ≈ 0

  Experiments and nonlinear analyses—Non-trivial Seismic Terminal Force may occur even if slack is sufficient

  Further work needed

Terminal Force

25

Page 26: Seismic Performance of Electric Transmission Systems

Network Seismic Risk Assessment— SERA*

26

  Simulate/ assess post-earthquake damage state of a network

  Motivation:   Identify potential weaknesses in the system   Asset management, benefit/ cost analysis   Emergency resource planning   Loss estimation for insurance

* System Earthquake Risk Assessment

Page 27: Seismic Performance of Electric Transmission Systems

SERA Analysis—Modeling

  System topology (limited model, includes 46 important substations in SF Bay Area)  System geographic information  Equipment connectivity  Substation connectivity (transmission lines/ towers)

  Component fragilities  Different failure modes for each equipment  Based on historic data, tests, judgment

  Seismic hazard  Scenario earthquakes  Geotechnical hazards (e.g. liquefaction, landslide)

27

Page 28: Seismic Performance of Electric Transmission Systems

Research Needs

  Interaction effects (particularly terminal loading issues)

  Deformation capacities of buried transmission cables

  Base isolation/ supplemental damping technologies for substation equipment

  Insulator post-shaking test damage detection, porcelain and composites

28