SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

29
SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS Revision 0 February 2021

Transcript of SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Page 1: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Revision 0

February 2021

Page 2: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-i

SECTION I – CLOSURE PLAN

TABLE OF CONTENTS

1.0 INTRODUCTION...................................................................................................... 1 2.0 GENERAL CLOSURE ISSUES ................................................................................. 1

2.1 Closure Performance Standard ................................................................................ 1 2.2 Amendment to Closure Plan.................................................................................... 2 2.3 Partial Closure........................................................................................................ 2 2.4 Location and Retention of Closure Plan ................................................................... 2 2.5 Notification of Final Closure................................................................................... 2 2.6 Schedule for Closure .............................................................................................. 2

2.6.1 Time Allowed for Closure ............................................................................... 2 2.6.2 Extension for Closure Time ............................................................................. 2

2.7 Closure Procedures Summary ................................................................................. 2 2.7.1 Inventory Removal and Disposal ..................................................................... 3 2.7.2 Disposal or Decontamination of Tanks and Ancillary Equipment and Truck

Unloading Bays .............................................................................................. 3 3.0 CLOSURE PROCEDURE DETAILS ......................................................................... 3

3.1 Description of Regulated Units ............................................................................... 3 3.2 Anticipated Closure Date ........................................................................................ 3 3.3 Notification of Final Closure................................................................................... 4 3.4 Closure Schedule .................................................................................................... 4 3.5 Maximum Inventory of Hazardous Liquid Waste-Derived Fuel ................................ 5 3.6 Closure Procedures ................................................................................................. 5

3.6.1 Tank Closure .................................................................................................. 5 3.6.2 Ancillary Equipment Closure........................................................................... 6 3.6.3 Tank Truck Unloading Area Closure................................................................ 7 3.6.4 Subsurface Investigation ................................................................................. 7

4.0 CLOSURE CRITERIA............................................................................................... 8 4.1 Tanks Closure Criteria ............................................................................................ 8 4.2 Ancillary Equipment Closure Criteria...................................................................... 8 4.3 Tank Truck Unloading Area Closure Criteria........................................................... 9 4.4 Subsurface Closure Criteria .................................................................................... 9

5.0 CLOSURE COST ESTIMATE ................................................................................. 10 6.0 FINANCIAL ASSURANCE MECHANISM FOR CLOSURE AND LIABILITY ...... 11

LIST OF ATTACHMENTS:

ATTACHMENT I-1 CLOSURE SAMPLING AND ANALYSIS PLAN ATTACHMENT I-2 CLOSURE COST ESTIMATE ATTACHMENT I-3 FINANCIAL ASSURANCE DOCUMENTS

Page 3: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-1

CLOSURE PLAN AND FINANCIAL REQUIREMENTS

1.0 INTRODUCTION The information in this section is submitted in accordance with 40 CFR 270.14(b)(13) as incorporated by OAC 252:205-3-2(k). This section includes:

• Closure plan description;

• Closure cost estimate;

• Financial assurance mechanism for closure; and,

• Liability coverage mechanism for sudden accidental occurrences.

A copy of the Closure Plan will be maintained at the facility as part of the Operating Record until Completion of Closure Certification has been submitted and accepted by the Oklahoma Department of Environmental Quality (ODEQ).

A Post-Closure Plan is not required since the waste management activities at the facility do not include the land disposal of hazardous waste; nor will there be wastes, waste residuals, or waste constituents remaining at the facility that would require post-closure maintenance. This Plan includes soil sampling at the facility at the time of final closure. If the soil sampling indicates contamination above the clean-closure criteria, the contaminated soils will be removed and shipped off-site or processed in the on-site kilns owned by CPCC. If any soil contamination above the soil clean-up standards established by ODEQ at the time of closure is left in place, either a risk assessment showing that human health or the environment will not be harmed, or a Post-Closure Plan will be submitted to ODEQ for approval.

2.0 GENERAL CLOSURE ISSUES

2.1 Closure Performance Standard

This Closure Plan was designed in accordance with 40 CFR 264.111 and OAC 252:205- 3-2(f) to ensure that, after closure, the waste management facility will:

1. Minimize the need for further maintenance and control;

2. Minimize or eliminate threats to human health and the environment; and, 3. Minimize or eliminate the escape of hazardous waste, hazardous waste constituents, or

contaminated run-off to the soil, ground water, surface water, or atmosphere.

This Closure Plan is prepared to meet these closure performance standards. Hazardous wastes, including waste generated from decontamination activities, will be either treated thermally in CPCC-owned pyroprocessing units or will be shipped off-site for disposal at an authorized facility. The container storage area and tanks systems and equipment associated with the management of Fuel Quality Waste (FQW) will be decontaminated to meet closure standards.

Page 4: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-2

2.2 Amendment to Closure Plan

In accordance with 40 CFR 264.112(c), Systech will submit a written notification or request for a permit modification to ODEQ to obtain authorization to amend the Closure Plan if: 1) changes in the operating plans or facility design affect the Plan; 2) the year of expected closure changes, if applicable; or 3) modifications to the Plan become necessary because of unexpected events during partial or final closure activities.

2.3 Partial Closure

If partial closure is implemented at the facility, the same closure procedures outlined for final closure will be implemented during partial closure.

2.4 Location and Retention of Closure Plan

A copy of this Closure Plan and subsequent amendments will be maintained in the Operating Record at the facility until Completion of Closure Certifications have been submitted to and accepted by ODEQ.

2.5 Notification of Final Closure

Systech will notify ODEQ in writing at least 45 days before final closure activities are expected to begin. If the facility permit is terminated or the facility is ordered closed by judicial decree or a final order under RCRA §3008, closure notification is not required.

2.6 Schedule for Closure

2.6.1 Time Allowed for Closure

Systech anticipates completing closure activities within 180 days of receipt of the final volume of waste materials.

The projected schedule of closure activities for full closure of the Systech Tulsa FQW operations is presented in Table I-1. This schedule complies with the time limitations of 40 CFR 264.113(b) and OAC 252:205-3-2(f) by anticipating full closure within 180 days of receipt of the final volume of FQW.

2.6.2 Extension for Closure Time

Systech does not anticipate that closure activities will take more than 180 days to complete. If unforeseen circumstances result in a delay of the closure schedule, CPCC will request a schedule extension from ODEQ in accordance with 40 CFR 264.113(b)(2) and OAC 252:205-3-2(f).

2.7 Closure Procedures Summary

Section I.3 describes the closure procedures Systech will implement to close the FQW tanks and ancillary equipment (including Systech-owned waste feed system components) and the FQW container storage area.

Page 5: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-3

2.7.1 Inventory Removal and Disposal

Existing inventory in tanks and the truck unloading bay will be processed in the CPCC cement kilns, if possible. Otherwise, it will be transported to an off-site permitted facility for use as a substitute fuel or for treatment.

2.7.2 Disposal or Decontamination of Tanks and Ancillary Equipment and Truck Unloading Bays

After removal of the FQW inventory from the tanks and the truck unloading bays, they will be decontaminated using detergents or solvents capable of removing hazardous-derived fuel constituents. Ancillary equipment associated with the tanks (including the Systech-owned portion of the FQW feed line to the kiln and the return line from the kiln) will be decontaminated by using high-pressure water cleaner, degreasing agents, or other appropriate cleaning technology. Final rinsate samples will be taken to determine if the decontamination process achieved the clean closure criteria. Rinse water generated from the decontamination process will either be processed in the CPCC kilns or shipped off-site to a permitted facility for treatment and/or disposal.

If any metal equipment cannot achieve clean closure criteria, the decontamination procedure will be repeated, or the equipment will be shipped off-site as scrap metal if it is visually clean.

3.0 CLOSURE PROCEDURE DETAILS This Closure Plan has been prepared in accordance with 40 CFR 264.111, 40 CFR 264.112, and OAC 252:205-3-2(f) for the Systech facility located in Tulsa, Oklahoma.

3.1 Description of Regulated Units

This Closure Plan describes how Systech intends to close the facility’s FQW storage tanks and associated Systech-owned ancillary equipment and components, and the truck unloading bays. For the purpose of this Closure Plan, the regulated units are defined as follows.

• Two FQW fuel storage tanks, each with a design capacity of 180,000 gallons, ancillary equipment (including the Systech-owned two feed lines to the kiln and one return line), and the secondary containment for the tanks.

• Two truck unloading bays with each truck capacity of 6,000 gallons, and the secondary containment area. Truck unloading bays will also store a maximum of twenty 55-gallon containers or equivalent (i.e., 1,100 gallons).

3.2 Anticipated Closure Date

Final closure of Systech’s hazardous waste units is not expected to occur before the year 2035.

Page 6: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-4

3.3 Notification of Final Closure

Systech will notify ODEQ in writing at least 45 days before the date on which final closure of its FQW facility is expected to begin. Closure is expected to be completed no later than 180 days after initiation of closure.

3.4 Closure Schedule

Systech will begin closure within 30 days of the date on which the known final volume of FQW is received for use at the facility. However, if there is a reasonable possibility that the facility will receive additional FQW, the closure will begin within a year after the date on which the facility received the most recent volume of FQW. At least 45 days before beginning the final closure, Systech will submit a notice in writing to ODEQ stating the date closure is expected to begin. Systech intends to complete closure of the units within 180 days of the start of closure. The schedule of closure activities is shown in Table I-1.

Within 60 days of completion of closure activities, Systech will submit certification to ODEQ that the unit has been closed according to the approved Closure Plan.

If closure cannot be accomplished within 180 days or if the Certificate of Closure cannot be prepared within the 60-day time period, Systech will submit to ODEQ a written request for an extension of the deadline. The request for an extension will be submitted at least 30 days before the expiration of the 180- or 60-day period.

Systech will submit to ODEQ a written request for a permit modification, including a copy of the amended Closure Plan, for approval no later than 60 days after unexpected events or at least 60 days before proposed changes in facility design or operation that affect the Closure Plan. If an unexpected event occurs during the closure period, Systech will request from ODEQ a permit modification no later than 30 days after the unexpected event.

TABLE I-1 PROJECTED SCHEDULE OF CLOSURE ACTIVITIES

CLOSURE ACTIVITY DAY STARTED DAY COMPLETED 1. Disposal of waste inventories Day 1 Day 90 2. Decontamination of tanks Day 60 Day 120 3. Decontamination of container management areas Day 60 Day 120 4. Decontamination of ancillary equipment Day 90 Day 120 5. Disposal of decontamination residuals and rinses Day 60 Day 120 6. Soil sampling and analysis Day 120 Day 150 7. Removal of any contaminated soil Day 120 Day 150 8. Completion of closure activities Day 150 Day 180 9. Submittal of Closure Certification to ODEQ Day 150 Day 240

Page 7: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-5

3.5 Maximum Inventory of Hazardous Liquid Waste-Derived Fuel

Maximum inventory of FQW at closure will consist of tank contents, two trucks in the unloading bay, and the contents in the piping (including the Systech-owned portion of two feed lines to the kiln and one return line).

• Tank Contents:

Two tanks @ 180,000 gallons each = 360,000 gallons

• Truck Unloading Bays:

Two trucks @ 6,000 gallons each = 12,000 gallons Twenty 55-gallon containers or equivalent = 1,100 gallons

• Contents in the Piping:

Piping length = 300 feet (assumed)

Volume in piping = 300 feet x π(3/24)2ft2 x 7.48 gallons/ft3

= 110 gallons

• Total Maximum Waste Inventory at Closure:

= (360,000 + 12,000 + 1,100 + 110) gallons

= 373,210 gallons FQW, including rinsates and decontamination residues, will be treated in the CPCC kilns or

will be transported to an off-site permitted TSD facility.

3.6 Closure Procedures

The following subsections outline the procedures for partial and final closure of the regulated hazardous waste units at the facility. A closure Sampling and Analysis Plan is presented in Attachment I-1.

3.6.1 Tank Closure

Standard tank cleaning activities associated with the two storage tanks closure shall consist of the following procedures:

• Drain all liquid materials from the tank through the lowest fitting on the tank. Transfer the liquid contents to transport containers.

• Remove any solids that may have settled out of the liquid at the bottom of the tank. (It is anticipated that approximately 25 cubic yards will be present in each of the two storage tanks). This may include the use of self- priming, high-clearance centrifugal pump(s) or rental vacuum pump unit(s). Some more compacted solids may have to be removed manually and conveyed to roll-off bins for temporary storage and final disposal at an off-site TSDF.

Page 8: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-6

• Use a high-pressure wash with detergent for cleaning the interior of each tank and associated fittings and piping. After use, transfer the potentially contaminated rinse water to transport container(s) for transportation off- site.

• Open the tank access ports. Allow the tank to dry out.

• Test for explosive vapors and oxygen content using standard instrument procedures.

• Inspect the tank interior for visual cleanliness. Repeat the above steps, if necessary.

• Analyze the final rinse water. The tank will be certified as clean closed (decontaminated) when analytical results on the final rinse water indicate that levels of constituents are below the closure criteria identified in Subsection I.4.

Alternately, units may be scrapped for metal recovery without performing rinsate analyses after visible signs of contamination have been removed from them. Pursuant to 40 CFR 261.6(a)(3)(iii), scrap metal being recycled is exempt from the definition of a solid waste, and therefore a hazardous waste. Decontamination will be performed to meet the requirements of the scrap metal facility used for recycling.

The tank cleaning procedures listed above will also be followed during final closure to decontaminate the associated tank appurtenances (piping, fittings, nozzles, valves, pumps, etc.). A partial closure of these items may occur during the normal operations of the facility and may include washing in parts washers and/or power washing and other methods to remove visible signs of contamination prior to reuse or scrapping for metal recovery.

Following cleaning/decontamination activities, one of the options identified in Section I.4.1 will be initiated.

Contaminated cleaning solutions, rinse waters, and other residues resulting from cleaning work will be collected in a transport container for burning in the CPCC kilns or transportation off-site for proper treatment/disposal.

3.6.2 Ancillary Equipment Closure

Routine operational replacement of Systech-owned ancillary equipment, such as filter canisters, grinders, pumps, piping, valves, hoses, and fittings, etc., may require removal and partial closure during the life of the facility. This section addresses the “partial closure” of these items during the normal, routine operations of the facility, prior to reuse, recycle for scrap metal recovery, or disposal as a hazardous waste. The same closure procedure for ancillary equipment will be implemented at the time of final closure of the facility.

Standard cleaning activities associated with ancillary equipment replacement include the following procedures:

• Isolate and remove all liquid from the equipment. A vacuum pump may be used, if necessary. Transfer the liquid contents to a tank/container that is in FQW service for further processing and/or proper disposal.

• Remove any solids/slurry that may have settled out, using a vacuum pump if necessary. Transfer the solids/slurry contents into a tank/container that is in FQW service for further processing and/or proper disposal.

Page 9: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-7

• Clean the parts and/or equipment using parts washers; recirculation of virgin or recycled solvents such as alcohols, ketones, aliphatic hydrocarbons, etc.; and/or high-pressure wash with detergent solution and other methods to remove visible signs of contamination.

• Inspect the equipment for visual cleanliness. Repeat the above steps if necessary. Visual cleanliness will be the adequate closure criteria for ancillary equipment prior to recycling as scrap metal.

• If Systech elects to reuse this equipment, collect a final rinse water sample and analyze the rinse water to check for the presence of hazardous waste constituents. The equipment will be certified as clean closed when analytical results of the final rinse water indicate that levels of constituents are below the closure criteria presented in Section I.4.

• Equipment that meets the clean closure criteria will be removed from service. Equipment that does not meet the criteria will have the cleaning steps repeated until they meet the requirements, or the item will be disposed at an off-site facility as hazardous waste, or it will be shipped off-site as scrap metal for recycling.

Cleaning solutions, rinse waters, and other liquids resulting from cleaning activities will be collected and may be fuel blended, if appropriate, or sent off-site for proper treatment or disposal. Following cleaning and decontamination, the parts and/or equipment will be available for reuse, recycle for scrap metal recovery, or disposed of as non-hazardous waste.

3.6.3 Tank Truck Unloading Area Closure

Standard cleaning activities associated with the tank truck unloading/storage facilities and secondary containment areas closure shall consist of the following procedures:

• Remove tank trucks, containers, and ancillary equipment from the unloading/storage facilities and secondary containment areas.

• Decontaminate the units by scrubbing down all surfaces and subsequently steam cleaning or pressure washing with detergent solution the surfaces, followed by a clean water rinse.

• Collect a final rinse water sample and analyze the sample. The structures will be certified as clean closed when analytical results on the final rinse water indicate that levels of constituents are below the closure criteria identified in Section I.4

Contaminated cleaning solutions, rinse waters, and other residues resulting from cleaning work will be collected in a transport container for transportation off-site for proper treatment/disposal.

3.6.4 Subsurface Investigation

No environmental impact on surrounding soils near the hazardous waste management units is expected because of the use of concrete for secondary containment, use of welded flanged steel piping, frequent inspections of operations, and prompt cleanup of any FQW spills. However, as a worst-case scenario, this Closure Plan includes soil sampling in the immediate vicinity (i.e., within 2-feet outside the containment areas for the tanks and the truck unloading bay). The closure cost estimate includes the cost of collecting and analyzing for twelve (12) soil samples from 6 different locations and the requisite QA/QC samples.

Page 10: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-8

4.0 CLOSURE CRITERIA

4.1 Tanks Closure Criteria

In order to verify that the tanks have been properly decontaminated, the tanks shall be considered clean closed when sampling verifies that each final rinsate sample exhibits constituent concentrations below practical quantitation limits (PQLs) or below two standard deviations of an average (three samples minimum) background constituent concentration of the rinse water used during the final rinse activities.

Final rinsate samples will be collected and analyzed for total metals, volatile organics, and semi-volatile organics. To achieve the clean closure criteria, each tank and associated ancillary equipment will be initially emptied of all FQW (i.e., liquids and solids). Subsequently, each tank and associated equipment will be cleaned and rinsed adequately to achieve the clean closure criteria. Rinsates generated during tank and equipment cleaning will be managed as a hazardous waste, with the exception of final rinsates that meet the clean closure criteria. Rinsate material not demonstrated to meet the clean closure criteria will be pyroprocessed in the CPCC cement kiln or transported off-site for proper disposal.

Following the final tank and equipment rinsing, the following options, dependent upon rinsate analysis, may be exercised.

• If the final rinsate meets the clean closure criteria, no end use restrictions shall be placed on decontaminated tanks or process equipment, and closure of each tank unit will be deemed final.

• If constituents are found in the final rinsate above the clean closure criteria, but the tanks will remain on-site for future use, and it can be demonstrated that the same constituents may be found in materials intended to be placed in the tank(s) in the future, the types of materials to be placed into the tank(s) in the future will be described, and conditional closure for “similar reuse” of the tank(s) will be requested in the Closure Report.

• Tanks or process equipment that cannot meet the clean closure standard will be recycled as scrap metal after establishing that they are visually clean.

Alternately, units may be scrapped for metal recovery without performing rinsate analyses after visible signs of contamination have been removed from them.

The secondary containment structures associated with the tanks will also undergo decontamination activities and will be decontaminated to the standards identified in Section I.4.3.

4.2 Ancillary Equipment Closure Criteria

In order to verify that ancillary equipment has been properly decontaminated, the ancillary equipment shall be considered clean closed when the sampling verifies that the final rinsate sample exhibits constituent concentrations below PQLs or below two standard deviations of an average (three sample minimum) background constituent concentration of the rinse water used during final rinse activities.

Final rinsate samples will be collected and analyzed for total metals, volatile organics, and semi-volatile organics. To achieve the clean closure criteria, the ancillary equipment will be initially emptied of all FQW (i.e., liquids and solids). Subsequently, the ancillary equipment will be cleaned and rinsed adequately to achieve the clean closure criteria. Rinsates generated during equipment cleaning will

Page 11: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-9

be managed as a hazardous waste, with the exception of final rinsates that meet the clean closure criteria. Rinsate material not demonstrated to meet clean closure criteria will be pyroprocessed in the cement kiln or transported off-site for proper disposal.

Following final ancillary equipment rinsing, the following options, dependent upon rinsate analysis, may be exercised.

• If the final rinsate meets the clean closure criteria, no end use restrictions shall be placed on decontaminated process equipment and closure of the ancillary equipment unit will be deemed final.

• Ancillary equipment that cannot meet the clean closure criteria will be recycled as scrap metal.

Alternately, units may be scrapped for metal recovery without performing rinsate analyses after visible signs of contamination have been removed from them.

4.3 Tank Truck Unloading Area Closure Criteria

In order to verify that the tank truck unloading/storage facility and secondary containment areas have been properly decontaminated, the units shall be considered clean-closed when sampling verifies that either each final rinsate sample exhibits constituent concentrations below PQLs or below two standard deviations of an average (three sample minimum) background constituent concentration of the rinse water used during final rinse activities.

Final rinsate samples will be collected and analyzed for total metals, volatile organics, and semi-volatile organics. To achieve the clean closure criteria, the areas will be decontaminated by scrubbing down all surfaces and subsequently steam cleaning or pressure washing the surfaces such that the clean closure criteria have been achieved.

Rinsates generated during decontamination activities will be managed as a hazardous waste, with the exception of the final rinsate that meets the clean closure criteria. Rinsate material not demonstrated to meet clean closure criteria will be transported off-site for proper disposal.

Following final rinsing, the following options, dependent upon rinsate analysis, may be exercised:

• If the final rinsate samples meet the clean closure criteria, no end use restrictions shall be placed on decontaminated unit and closure of the unit will be deemed final.

• If constituents are found in the final rinsate above the clean closure criteria, but the units will remain on-site for future use, and it can be demonstrated that the same constituents may be found in materials intended to be placed in the units in the future, the types of materials to be placed in the units in the future will be described, and a conditional closure for “similar reuse” of the units will be requested in the Closure Report.

• Units that cannot meet the clean closure criteria will be removed and disposed of as a hazardous waste.

4.4 Subsurface Closure Criteria

Soils immediately adjacent to (i.e., within 2 feet outside) the storage tank containment and the truck unloading bays will be sampled to determine if they are impacted with FQW or FQW constituents.

Page 12: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-10

The soils will be considered not impacted if the soil sample analyses exhibit constituent concentrations below PQLs, or two standard deviations of an average (three sample minimum) background constituent concentration, or Oklahoma soil concentration ranges.

Based on the review of soil analytical results, the following options may be exercised:

• If the soil analytical results meet the clean closure criteria, the closure of the facility will be deemed final.

• If soil analytical results exceed the clean closure standard, additional subsurface investigations will be performed to define the extent and magnitude of constituent contamination.

• Upon defining the extent and magnitude of constituent contamination, a risk assessment will be performed, or corrective action activities will be conducted.

5.0 CLOSURE COST ESTIMATE An estimate of the closure cost for the facility has been developed and is included in Attachment I-2. The closure cost estimates have been based on off-site shipment of the maximum FQW inventory at the time of closure and the rinsate generated from the clean closure of the tanks and ancillary equipment and equipment decontamination activities. The estimated decontamination costs for equipment and containment structures have been listed. The decontamination costs include labor, equipment rental, sampling, and testing. The cost of obtaining a Closure Certificate from a registered Professional Engineer is also included. Administrative and contingency costs of 15% each of the total closure cost estimate have been included in the estimate. No salvage value from the recycling of scrap metal components has been incorporated in the estimate. The closure cost estimate was derived based on the following:

1. HWDF inventory will be disposed of at Ash Grove Cement, Chanute, KS facility at 2. $0.25/gallon and at a distance of 125 miles. 3. Rinse water generated from the decontamination of tank systems and container storage areas

will be shipped off-site to A Clean, South 25th West Avenue, Tulsa, OK at

4. $0.25/gallon and at a distance of 16 miles. 5. Sludges generated from the decontamination of tanks will be disposed of at Rineco in Benton,

AR at $0.85/lb and a distance of 290 miles. 6. Containers in the truck bay unloading area are assumed to contain sludges as a worst-case

scenario and will be disposed of at Rineco in Benton, Arkansas. 7. Sample analytical costs, work hour rates, rinsate generation labor rate, and sample collection

costs are derived from the latest CostPro© 6.0 software (2009 Edition).

Table I-3 presents a summary of the closure cost estimate calculated for the initial permit issued in 2009. Closure cost estimates are adjusted annually for inflation in accordance with 40 CFR 264.142(b) and OAC 252:205-3-2(f). The latest closure cost estimates and the latest adjustments for inflation are kept in the facility Operating Record, in accordance with 40 CFR 264.142(d) and OAC 252:205-3-2(f). The closure costs presented on Table I-3 includes the adjustment to the closure costs to incorporate the inflation factor through 2020. The amount shown on the table for dollars adjusted to 2020 dollars coincides with the financial assurance documentation submitted to the ODEQ and is included in Attachment I-3.

Page 13: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page I-11

6.0 FINANCIAL ASSURANCE MECHANISM FOR CLOSURE AND LIABILITY

Systech will establish financial assurance for the closure of its Tulsa facility prior to the first receipt of hazardous waste. The option selected by Systech to provide financial assurance is a Surety Bond, as provided in 40 CFR 264.143(c) and OAC 252:205-3-2(f). Financial assurance for closure and liability requirements for the Systech Tulsa facility are demonstrated by the documents included in Attachment I-3.

Page 14: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-1

ATTACHMENT I-1 CLOSURE SAMPLING AND ANALYSIS PLAN

Page 15: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-2

CLOSURE SAMPLING AND ANALYSIS PLAN

1.0 PURPOSE

The purpose of this Plan is to provide an outline of the sampling and analyses that will be

performed during closure of the facility and also define the criteria for “clean” closure.

2.0 MEDIA TO BE SAMPLED AND ANALYZED

Samples of soil and rinse water will be collected during the performance of closure activities. All analyses

will be performed in accordance with USEPA SW 846 or standard ASTM methods.

Soil and rinse water samples will be analyzed for volatile organics according to Method 8240; for semi-

volatile organics according to Method 8270; and for total metals by using the Method 3050 digestion

procedure followed by Inductively Coupled Argon Plasma (ICAP) analysis for metals according to

Method 6010 and the 7000 series methods for specific metals. These analytical suites will provide a suitable representation of the hazardous waste constituents managed at the RCRA units. Table AI-1

provides a list of the hazardous constituents contained in the analytical suites with the associated PQL,

sample holding times, and preservatives.

3.1 FIELD SAMPLING PROCEDURES

3.2 Rinsate Samples

The rinsate sampling procedure will consist of collecting samples of the final rinsate from each

tank and its secondary containment areas, tank truck unloading/storage area, and ancillary equipment.

Rinse water samples will be collected utilizing standard sample collection techniques and placed

into an appropriate sample jar. QA/QC samples will also be collected as described in Section

5.0. Appropriate personnel protective equipment (PPE) and sample collection procedures will be utilized in order to minimize exposure and potential cross- contamination of samples.

3.3 Background Samples

Background samples of rinse water and soil may be collected for the purpose of determining if

the clean closure criteria have been met. Background samples will be collected of the same

media at areas not affected by hazardous constituents. Background rinse water samples will be collected from the water source providing the water for rinsing activities. Background soil

samples will be collected from natural soil located on the plant property not affected by any

Page 16: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-3

hazardous waste management activity. A minimum of three background samples from the media

will be collected if it is determined that comparison to background is required.

Background samples will be collected utilizing standard sample collection techniques.

Appropriate PPE and sample collection procedures will be utilized in order to minimize

exposure and potential cross-contamination of samples.

3.4 Subsurface Investigation

Subsurface investigation activities will be conducted at the tank storage area and the tank truck

unloading area. Soil samples will be collected utilizing standard soil sample collection techniques within 2-feet of the wall opposite the tank farm sumps (2 samples) plus 1 sample

west of the container storage area. In addition, 2 samples will be taken by coring through the

tank farm floor and 1 sample by coring through the container storage area floor. The locations of these samples will be determined at the time of the sampling based on the potential presence of

cracks, water stops, staining, etc. The proposed soil borings are located so as to provide

qualitative information for characterizing the shallow surface where hazardous waste could have

potentially migrated. The proposed soil borings will extend to a depth of 2 feet. Two soil samples will be collected throughout the 2-foot sampling interval; one immediately beneath the

soil surface (approximately 6 inches) and the second at a depth of approximately 2 feet. The

sample collected from the 2-foot depth will be retained at the laboratory and analyzed only if the first sample result indicates concentrations above the closure performance criteria.

If the 2-foot depth sample at any of the given locations indicate concentrations above the closure

performance criteria, additional soil samples will be collected during a subsequent sampling

event at intervals to be determined in the field until the extent and magnitude of contamination has been determined.

4.1 SAMPLING METHODS, EQUIPMENT AND DECONTAMINATION PROCEDURES

Split spoon, stainless steel tube, auger, and/or other comparable sampling equipment will be used to

collect the soil samples. Final rinsate samples for tanks will be collected using a COLIWASA or a

weighted bottle, or other appropriate equipment. Final rinsate samples from the tank containment area and the tank truck unloading area will be collected using a dipper or a pump into the sample container .

Final rinsate from ancillary equipment will be drained directly into the sample container, or by using a

COLIWASA after draining the rinsate into a clean container. Proper cleaning and decontamination of all

Page 17: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-4

sampling implements that contact the samples will be ensured to prevent cross contamination and assure

valid analytical results.

Workers who clean or use the sampling implements must wear protective gloves to protect themselves

and to prevent the equipment from being contaminated. During the decontamination procedures, rinsate

material will be accumulated for disposal as hazardous waste, in accordance with all applicable regulations, except for the final rinsate meeting the clean closure criteria.

4.2 Sample Preservation and Holding Times

The samples will be collected in containers specified in Table AI-1. The samples will be

preserved by refrigeration at 4oC until extraction and analysis. The maximum allowable holding times are also outlined in Table AI-1.

5.1 QA/QC

5.2 QA/QC Plan for Field Sampling

In order to ensure reliable sampling results, 1 trip blank, 1 field blank, 1 equipment rinse, and 1

duplicate sample will be taken at least once with each analytical media batch. Strict chain-of-custody procedures would be followed in transferring the samples to the selected analytical

laboratory.

5.3 QA/QC Plan for Laboratory Analysis

In order to ensure reliable analytical results, a laboratory that has an established, written

QA/QC program that follows USEPA guidelines will be retained to perform the analyses.

Page 18: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-5

TABLE AI-1 SOLID ANALYTICAL PARAMETERS

1Methods are from Test Methods for Evaluating Solid Waste, Physical/Chemical Methods SW-846, USEPA. Other EPA approved methods will be used as necessary. 2PQLs - Practical Quantification Limits. These PQLs represent typical laboratory reporting limits for solids.

Test Parameters Method

1 Instrument Analytes (CAS No.) PQLs

2

Sample Holding Times

Sample Container

Preservative Total Metals SW6010

(metals) ICP Antimony (Sb) (7440-36-0)

Arsenic (As) (7440-38-2) Barium (Ba) (7440-39-3) Beryllium (Be) (7440-41-7) Cadmium (Cd) (7440-43-9) Chromium (Cr) (7440-47-3) Lead (Pb) (7439-92-1) Nickel (Ni) (7440-02-0) Silver (Ag) (7440-22-4) Selenium (Se) (7782-49-2) Thallium (Tl) (7440-28-0)

1.20 (ppm) 1.00 0.40 0.10 0.10 0.10 1.00 0.20 0.20 2.00 0.10

180 days 32 oz. glass jar, cool to 4°C

SW7470 (mercury)

Cold Vapor Mercury (Hg) (7439-97-6) 0.20 (ppm) 28 days (See above)

Organic Constituents

SW8270 (semi-

volatiles)

GC/MS Phenol (108-95-2) Bis(2-Chloroethyl) Ether(111-44-4) 2-Chlorophenol (95-57-8) 1,3-Dichlorobenzene (541-73-1) 1,4-Dichlorobenzene (106-46-7) Benzyl Alcohol (100-51-6) 1,2-Dichlorobenzene (95-50-1) 2-Methylphenol (1319-77-3) Bis(2-Chloroisopropyl)Ether (108-60-1) 4-Methylphenol (108-39-4) N-Nitroso-Di-n-Propylamine Hexachloroethane (67-72-1) Nitrobenzene (98-95-3) Isophorone (78-59-1) 2,4-Dimethylphenol (105-67-9) 2-Nitrophenol (88-75-5) Benzoic Acid (65-85-0) Bis(2-Chloroethoxy)Methane 2,4-Dichlorophenol (120-83-2) 1,2,4-Trichlorobenzene (120-82-1) Naphthalene (91-20-3) 4-Chloroaniline (108-42-9) Hexachlorobutadiene (87-68-3) 4-Chloro-3-Methylphenol 2-Methylnaphthalene (91-57-6) Hexachlorocyclopentadiene (77-47-4) 2,4,6-Trichlorophenol (88-06-2) 2,4,5-Trichlorophenol (95-95-4) 2-Chloronaphthalene (91-58-7) 2-Nitroaniline (88-74-4) Dimethylphthalate (131-11-3) 2,6-Dinitrotoluene (606-20-2) Acenaphthylene (208-96-8) 3-Nitroaniline (100-01-6) Acenaphthene (83-32-9) 2,4-Dinitrophenol (51-28-5) 4-Nitrophenol (100-02-7) 2,4-Dinitrotoluene (121-14-2) Dibenzofuran (132-64-9) Diethylphthalate (84-66-2) 4-Chlorophenyl-Phenylether Fluorene (86-73-7) 4-Nitroaniline (99-09-2) 4,6-Dinitro-2-Methylphenol N-Nitrosodiphenylamine (86-30-6)

330 (ppb) 330 330 330 330 330 330 330 330 330 330 330 330 330 330 330 1600 330 330 330 330 330 330 330 330 330 330 1600 330 1600 330 330 330 1600 330 1600 1600 330 330 330 330 330 1600 1600 330

14 days 32 oz. glass jar, cool to 4°C

Page 19: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-6

TABLE AI-1 (CONTINUED) SOLID ANALYTICAL PARAMETERS

Test Parameters Method

1 Instrument Analytes (CAS No.) PQLs

2

Sample Holding Times

Sample Container

Preservative Organic

Constitu en ts (Cont'd)

SW8270 (semi-

volatiles ) (cont’d)

GC/MS 4-Bromophenyl-Phenylether (101-55-3) Hexachlorobenzene (118-74-1) Pentachlorophenol (87-86-5) Phenanthrene (85-01-8) Anthracene (120-12-7) Di-N-Butylphthalate (84-74-2) Fluoranthene (206-44-0) Pyrene (129-00-0) Butylbenzylphthalate Bis(2-Ethylhexyl)phthalate (117-81-7) 3,3'-Dichlorobenzidine (91-94-1) Benzo(A)Anthracene (56-55-3) Chrysene (218-01-9) Di-N-Octylphthalate (117-84-0) Benzo(b)Fluoranthene (205-99-2) Benzo(k)Fluoranthene (207-08-9) Benzo(a)Pyrene (50-32-8) Dibenzo(A,H)Anthracene (53-70-3) Indeno(1,2,3-CD)Pyrene (193-39-5) Benzo(G, H, I)Perylene (191-24-2)

330 330 1600 330 330 330 330 330 330 330 660 330 330 330 330 330 330 330 330 330

14 days 4 oz. glass jar, cool to 4°C

SW8240 (volatiles)

GC/MS Chloromethane (74-87-3) Bromomethane (74-83-9) Vinyl Chloride (75-01-4) Chloroethane (75-00-3) Methylene Chloride (75-09-2) Acetone (67-64-1) Carbon Disulfide (75-15-0) 1,1-Dichloroethene (75-35-4) 1,1-Dichloroethane (75-34-3) Total-1,2-Dichloroethene (540-59-0) Chloroform (67-66-3) 1,2-Dichloroethane (107-106-2) 2-Butanone (78-93-3) 1,1,1-Trichloroethane (71-55-6) Carbon Tetrachloride (56-23-5) Vinyl Acetate (108-05-4) Bromodichloromethane (75-27-4) 1,1,2,2-Tetrachloroethane (79-34-5) 1,2-Dichloropropane (78-87-5) Trans-1,3-Dichloropropene (10061-02-6) Trichloroethene (79-01-6) Dibromochloromethane 1,1,2-Trichloroethane (79-00-5) Benzene (71-43-2) Cis-1,3-Dichloropropene (10061-01-5) Bromoform (75-25-2) 2-Hexanone (591-78-6) 4-Methyl-2-Pentanone (108-10-1) Tetrachloroethene Toluene (108-88-3) Chlorobenzene (108-90-7) Ethylbenzene (100-41-4) Styrene (100-42-5) Total Xylenes (1330-20-7)

10 (ppb) 10 10 10 5 10 5 5 5 5 5 5 10 5 5 10 5 5 5 5 5 5 5 5 5 5 10 10 5 5 5 5 5 5

14 days 4 oz. glass jar, cool to 4°C

1Methods are from Test Methods for Evaluating Solid Waste, Physical/Chemical Methods SW-846, USEPA or other approved methods

2PQLs - Practical Quantitation Limits. These PQLs represent typical laboratory reporting limits for solids.

CAS No. - Chemical Abstract Service Number GC/MS - Gas Chromatography/Mass Spectrometer GC - Gas Chromatography ICP - Inductivity Coupled Plasma

Page 20: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-7

TABLE AI-1 (CONTINUED) LIQUID ANALYTICAL PARAMETERS

Test Parameters Method1 Instrument Analytes (CAS No.) PQLs2

Sample Holding Times

Sample Container

Preservative Total Metals SW6010

(metals) ICP Antimony (Sb) (7440-36-0)

Arsenic (As) (7440-38-2) Barium (Ba) (7440-39-3) Beryllium (Be) (7440-41-7) Cadmium (Cd) (7440-43-9) Chromium (Cr) (7440-47-3) Lead (Pb) (7439-92-1) Nickel (Ni) (7440-02-0) Silver (Ag) (7440-22-4) Selenium (Se) (7782-49-2) Thallium (Tl) (7440-28-0)

0.06 (mg/l) 0.05 0.02 0.005 0.005 0.005 0.05 0.01 0.01 0.10 0.10

180 days liter polyethy len e,

HN03, 4oC

SW7470 (mercury)

Cold Vapor Mercury (Hg) (7439-97-6) 0.20 (mg/l 28 days (See above)

Organic Constituents

SW8270 (semi-

volatiles)

GC/MS Phenol (108-95-2) Bis(2-Chloroethyl)Ether(111-44-4) 2-Chlorophenol (95-57-8) 1,3-Dichlorobenzene (541-73-1) 1,4-Dichlorobenzene (106-46-7) Benzyl Alcohol (100-51-6) 1,2-Dichlorobenzene (95-50-1) 2-Methylphenol (1319-77-3) Bis(2-Chloroisopropyl)Ether (108-60-1) 4-Methylphenol (108-39-4) N-Nitroso-Di-n-Propylamine Hexachloroethane (67-72-1) Nitrobenzene (98-95-3) Isophorone (78-59-1) 2,4-Dimethylphenol (105-67-9) 2-Nitrophenol (88-75-5) Benzoic Acid (65-85-0) Bis(2-Chloroethoxy)Methane 2,4-Dichlorophenol (120-83-2) 1,2,4-Trichlorobenzene (120-82-1) Naphthalene (91-20-3) 4-Chloroaniline (108-42-9) Hexachlorobutadiene (87-68-3) 4-Chloro-3-Methylphenol 2-Methylnaphthalene (91-57-6) Hexachlorocyclopentadiene (77-47-4) 2,4,6-Trichlorophenol (88-06-2) 2,4,5-Trichlorophenol (95-95-4) 2-Chloronaphthalene (91-58-7) 2-Nitroaniline (88-74-4) Dimethylphthalate (131-11-3) 2,6-Dinitrotoluene (606-20-2) Acenaphthylene (208-96-8) 3-Nitroaniline (100-01-6) Acenaphthene (83-32-9) 2,4-Dinitrophenol (51-28-5) 4-Nitrophenol (100-02-7) 2,4-Dinitrotoluene (121-14-2) Dibenzofuran (132-64-9) Diethylphthalate (84-66-2) 4-Chlorophenyl-Phenylether Fluorene (86-73-7) 4-Nitroaniline (99-09-2) 4,6-Dinitro-2-Methylphenol N-Nitrosodiphenylamine (86-30-6)

10 (ppb) 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 50 10 10 10 10 10 10 10 10 10 10 50 10 50 10 10 10 50 10 50 50 10 10 10 10 10 50 50 10

14 days 1 liter amber,

4oC

Page 21: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-1-8

TABLE AI-1 (CONTINUED) LIQUID ANALYTICAL PARAMETERS

Test Parameters Method1 Instrument Analytes (CAS No.) PQLs2

Sample Holding Times

Sample Container

Preservative Organic

Constitu en ts (Cont'd)

SW8270 (semi-

volatiles ) (cont’d)

GC/MS 4-Bromophenyl-Phenylether (101-55-3) Hexachlorobenzene (118-74-1) Pentachlorophenol (87-86-5) Phenanthrene (85-01-8) Anthracene (120-12-7) Di-N-Butylphthalate (84-74-2) Fluoranthene (206-44-0) Pyrene (129-00-0) Butylbenzylphthalate Bis(2-Ethylhexyl)phthalate (117-81-7) 3,3'-Dichlorobenzidine (91-94-1) Benzo(A)Anthracene (56-55-3) Chrysene (218-01-9) Di-N-Octylphthalate (117-84-0) Benzo(b)Fluoranthene (205-99-2) Benzo(k)Fluoranthene (207-08-9) Benzo(a)Pyrene (50-32-8) Dibenzo(A,H)Anthracene (53-70-3) Indeno(1,2,3-CD)Pyrene (193-39-5) Benzo(G, H, I)Perylene (191-24-2)

10 10 50 10 10 10 10 10 10 10 50 10 10 10 10 10 10 10 10 10

14 days 1 liter amber, 4°C

SW8260 (volatiles)

GC/MS Chloromethane (74-87-3) Bromomethane (74-83-9) Vinyl Chloride (75-01-4) Chloroethane (75-00-3) Methylene Chloride (75-09-2) Acetone (67-64-1) Carbon Disulfide (75-15-0) 1,1-Dichloroethene (75-35-4) 1,1-Dichloroethane (75-34-3) Total-1,2-Dichloroethene (540-59-0) Chloroform (67-66-3) 1,2-Dichloroethane (107-106-2) 2-Butanone (78-93-3) 1,1,1-Trichloroethane (71-55-6) Carbon Tetrachloride (56-23-5) Vinyl Acetate (108-05-4) Bromodichloromethane (75-27-4) 1,1,2,2-Tetrachloroethane (79-34-5) 1,2-Dichloropropane (78-87-5) Trans-1,3-Dichloropropene (10061-02-6) Trichloroethene (79-01-6) Dibromochloromethane 1,1,2-Trichloroethane (79-00-5) Benzene (71-43-2) Cis-1,3-Dichloropropene (10061-01-5) Bromoform (75-25-2) 2-Hexanone (591-78-6) 4-Methyl-2-Pentanone (108-10-1) Tetrachloroethene Toluene (108-88-3) Chlorobenzene (108-90-7) Ethylbenzene (100-41-4) Styrene (100-42-5) Total Xylenes (1330-20-7)

10 (ppb) 10 10 10 5 10 5 5 5 5 5 5 10 5 5 10 5 5 5 5 5 5 5 5 5 5 10 10 5 5 5 5 5 5

14 days 2-40 ml vials,

HCL, 4oC

1Methods are from Test Methods for Evaluating Solid Waste, Physical/Chemical Methods SW-846, USEPA or other approved methods

2PQLs - Practical Quantitation Limits. These PQLs represent typical laboratory reporting limits for liquids.

CAS No. - Chemical Abstract Service Number GC/MS - Gas Chromatography/Mass Spectrometer GC - Gas Chromatography ICP - Inductivity Coupled Plasma

Page 22: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-2-1

ATTACHMENT I-2 CLOSURE COST ESTIMATE

Page 23: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-2-2

ATTACHMENT I-2 CLOSURE COST ESTIMATE

Activity Description and Assumptions Current Facility Estimated Cost

1. Off-Site Management of Liquid HWDF Inventory from Tanks A. Removal of waste from tanks and ancillary piping (360,110

USG; 0.0003 work hr/gal; labor & equipment cost $140.41) $ 15,169

B. Transport on-site liquid HWDF inventory to an off-site fuel blending facility (360,110 USG; 5,500 USG/truck; $4.00 loaded mile; 125 miles)

$ 33,000

C. Process liquid HWDF inventory at off-site combustion facility (360,110 USG; $0.25/USG)

$ 90,000

Subtotal: Activity No. 1 $ 138,169 2. Off-Site Management of Liquid HWDF Inventory from Container

Storage Area

A. Removal of drummed waste (20 drums; $2.85/drum) $ 57 B. Transport containers to off-site facility (1 truck of containers +

2 tankers; $4.00 loaded mile; 290 miles) $ 3,480

C. Treatment/disposal cost (20 drums; 55 gal/drum; 10 lbs/gal; $0.85/lb)

$ 9,350

D. Treatment/Disposal Cost (2 tankers; 6,000 gal/tanker; $0.25/USG)

$ 3,000

Subtotal: Activity No. 2 $ 15,887 3 Decontamination of Tanks

A. Prepare tanks for decontamination: open manways, perform initial visual inspection (2 tanks; 4 hr/tank; 2 persons; $52.48/hr/person)

$ 840

B. Rinse and clean tank interiors (2 tanks; surface area approx. 3,820 ft2/tank; 0.0405 hr/ft2; $77.59/hr)

$ 24,008

C. Transportation of rinse waters for off-site treatment (2 tanks; surface area approx. 3,820 sq. ft./tank; rinse water generated - 1 USG/sq. ft.; 5,500 USG; truck; $4.00/loaded mile; 16 miles)

$ 128

D. Off-site treatment of rinse waters (2 tanks; 3,820 USG/tank; $0.25/USG)

$ 1,910

E. Transportation of sludge for off-site disposal (2 tanks; 25 cu. yd./tank; 18 cu. yd./truck: $4.00 loaded mile; 290 miles)

$ 3,480

F. Disposal of sludge (50 cu. yd.; 202 gal/cu yd; 10 lb/gal; $0.85/lb)

$ 85,850

G. Decontamination verification sampling cost(2 tanks; 1 sample/tank + 1 sample/tank equipment + 3 background water samples + 2 samples from containment; 0.5 hr/sample; labor & equipment $73.32)

$ 330

H. Decontamination verification analyses cost (9 samples; $548.04/sample)

$ 4,932

Subtotal: Activity No. 3 (2010 dollars): $ 121,478

Page 24: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 0, February 2021 Closure Plan Page Att I-2-3

Activity Description and Assumptions Current Facility

Estimated Cost 4. Decontamination of Tank Truck Unloading/Storage Facilities

A. Clean concrete surfaces (80 ft x 39 ft.; 0.0405 hr/ft2; $52.48/hr for labor and equipment)

$ 6,631

B. Transportation of rinse waters for off-site treatment (3,120 sq. ft.; rinse water generated: 1 USG/sq. ft.; 5,500 USG/truck; $4.00/loaded mile; 16 miles)

$ 64

C. Off-site treatment of rinse waters (3,120 USG; $0.25/USG) $ 780 D. Decontamination verification sampling cost(2 areas; 1

sample/area + 3 background water samples; 0.5 hr/sample; labor & equipment cost $73.32)

$ 183

E. Sample analyses cost (5 samples; $548.04/sample) $ 2,740 Subtotal: Activity No. 4 $ 10,398

5. Subsurface Investigation A. Tank storage

1. Sample collection cost (4 sample locations x 2 ft depth/sample; 0.3050 hr/ft; $81.97/hr)

$ 200

2. Soil verification (8 soil samples; $548/sample analysis) $ 4,384 B. Tank Truck Unloading/Storage Facility

1. Sample collection cost (2 sample locations x 2 ft depth/sample; 0.3050 hr/ft; $81.97/hr)

$ 100

2. Soil verification (4 soil samples; $548/sample analysis) $ 2,192 C. QA/QC Samples

1. Sample collection cost (4 samples in 1 hour; $81.97/hr) $ 82

Subtotal: Activity No. 5 $ 6,958 6. Closure Supervision and Certification

A. Supervision by Professional Engineer or his/her designee of key steps during the closure activities of the different units (approx. 60 hours; $110/hr)

$ 6,600

B. Preparation of Certification Report by Professional Engineer $ 6,000 Subtotal: Activity No. 6 $ 12,600

Subtotal: Activities No. 1 through No. 6 $ 305,490 7. Administration (15%) $ 45,824 8. Contingency (15%) $ 45,824

GRAND TOTAL (ACTIVITIES 1 THROUGH 8 in 2010 dollars) $ 397,138 Adjustment to 2020 dollars

$ 460,629.30

Page 25: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

Systech Environmental Corporation Tulsa, OK U.S. EPA ID No. OKR000025452

Revision 3, December 2020 Closure Plan Page Att I-3-1

ATTACHMENT I-3 FINANCIAL ASSURANCE DOCUMENTS

Page 26: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

••• Systech svsncH, Environmental

' Corporation

Oklahoma Department of Environmental Quality Land Protection Division Attn: Ms. Brigette Haley; Facility Engineer 707 North Robinson Oklahoma City, OK 73102

via Email and Certified Mail

Re: Updated Closure Cost Estimate for 2020 Systech Environmental Corporation: OKR000025452

Dear Ms. Haley:

Byproducts rn to Resources

September 4, 2020 Doc # 56-2020-09-2

As required by 40 CFR 264. l 42(b) as incorporated into the Oklahoma environmental regulations, Systech Environmental Corporation (Systech) is providing the adjusted closure cost estimate for the Systech Facility located at 2701 N. 145111 E Ave. Tulsa, OK. This is the updated closure cost update for the facility. The 2019 estimate for closure was $452,662.44 which was effective October 22, 2019. That cost is being adjusted by multiplying that estimate by the inflation factor 1.76% or 1.0176. This factor was provided to Systech by the Oklahoma Department Environmental Quality (ODEQ) and confinned as sufficient for 2020. The revised closure cost estimate for 2020 is now $460,629.30.

The inflation factor is derived from the Implicit Price Deflator (I.PD) for the Gross Domestic Product. The 1.0176 increase is an annualized number avai lable from the Federal Reserve. Please advise if the adjusted amount is acceptable to ODEQ and Systech will arrange the updated financial mechanism.

If you have any questions or need additional information, please contact me at (843) 826-1746.

Sincerely yours, SYSTECH ENVIRONMENTAL CORPORATION

9av1cfy~ Mr. Randy Sparks Regulatory Manager

cc. Joseph Sommer, Systech - via email Brigette Haley, ODEQ Carol Bartlett, ODEQ, via email

270 1 N. 1451' 1:.ASl /\VENlJ[ WLS/\, OKLAllOMA 74116 - Tl:L 918 43 7 3902 1:.XT. 295 FAX 918- 388 1488

·www.go2systech.com

Page 27: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

- Systech ~ Environmental

- Corporation

Ms. Carol Bartlett, Environmental Programs Specialist Oklahoma Department of Environmental Quality Land Protection Division 707 North Robinson, P.O. Box 1677 Oklahoma City, OK 73101-1677

Byproducts Into Resources

September 29, 2020 Doc# 56-2020-09-3

Re. Financial Assurance Documentation for Estimated Closure Cost Systech Environmental Corporation EPA ID: OKR000025452

Dear Ms. Bartlett:

Attached is the executed rider to surety bond #019032958 that provides the financial assurance for the closure for the above referenced facility in Rogers County, OK.

If you need additional information, please contact me at 93 7-609-8560 or Randy Sparks at 843-826-1746.

Sincerely,

J:E=tz:~• Terri Kanouse Systech - COO

Attachment ( 1 )

cc. Joe Sommer, Site Coordinator Marvin (Randy) Sparks Brigette Haley, ODEQ via email

2701 N. l 451h EAST AVENUE - TUI.SA, OKLAHOMA 74116 - TEL 918- 437- 3902 EXT. 295 - FAX 918-388- 1488

www.go2systech.com

Page 28: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

~Lihertx ~ Mutucil. SURE1Y RIDER

To be attached to and form a part of

Bond No.019032958 Cross Ref: n/a

Type of

Bond: Financial Assuarance Bond (Closure) - Tulsa, OK

dated effective November 1, 2011

(MONTil-OA Y-YEAR)

executed by SYSTECH ENVIRONMENTAL CORPORATION (PRINCIJ>AL)

and by Liberty Mutual Insurance Company , as Surety,

in favor of OKLAHOMA DEPARTMENT OF ENVIRONMENTAL QUALITY (ODLIGEE)

in consideration of the mutual agreements herein contained the Principal and the Surety hereby consent to changing

Bond Amount

FROM: Four Hundred Fifty Two Thousand Six Hundred Sixty Two & 44/100 -($452,662.44)

TO: Four Hundred Sixty Thousand Six Hundred Twenty Nine & 30/100 -($460,629.30)

Nothing herein contained shall vary. alter or extend any provision or condition of this bond except as herein expressly stated.

This rider is effective September 21, 2020

(MONTll-DA Y-YEAR)

Signed and Sealed September 21, 2020 (MONTH-DAY- YEAR)

Li berty Mutual Insurance company

llolS.10443 Olll08

, as Principal ,

Page 29: SECTION I CLOSURE PLAN AND FINANCIAL REQUIREMENTS

fmi. Liberf:J. ~Mutual.

SURETY

This Power or Attorney limits the acts of those named herein, and they have no authorily to bind Ille Company excepl in the manner and to the extent herein stated.

Liberty Mutual Insurance Company The Ohio Casualty Insurance Company

West American Insurance Company

POWER OF ATTORNEY

Certificate No: 820ot263.022011

KNOWN All PERSONS BY THESE PRESENTS: That The Ohio C8sualty Insurance ~y Is a oorporatlon duly organized under the laws or the State of New Hampshire, lhat Liberty Mutual lllSlnllCe Company is a corporation duly aganized under the laws of the State of Massachusetts, and West American lnsuranc;e Company is e corporation duty Ofllanized under the laws of the Stale of Indiana (herein CXlftecllvely called the 'Companies"), fll.l'SUllnl to end by authority herein set forth, does hereby name. ccnstitule and appoint Amanda George; Andrea M. Penalou: Donna L. Williams: Erin M. Dennison; Gina Rodriquez; Lisa A. Ward; Lupe Tyler; Melissa L. Fortier; Michael J. Herrod; Misty Wrigllt; Terri L. Morrison; Vanessa Dominguez

all ol the city of Houston state of TX each individually if there be more than one named, Its true and lawful attomey-ln-fact ti make. exec:u1e, seal, acknowledge and deliver, for and on its behalf as surety and as its act and deed, any and all undertakings, bonds. recognizances and othef surety oblQalions, in pursuance of these presents and shal be as binding upon the Companies as if they have been duly sigried by the president and sttesled by the seaetary of the ~ies In tiler own proper penons.

IN WITNESS WHEREOF, this Power of At!Dmey has been subscribed by an authorized olfioer or official of the Co~nles and the COlpOrate seals of the Cofre>anies have been affixed there~ this ~day of September , 2020 .

Liberty Mu1ual lnsurenoe eon.>anr The Ohio Casualty Insurance Company

• .,,~--- u ii°~ Slate of PENNSYLVANIA David M. Carey, Assistant Secnllary .S:-§ 4> ~ Coooty of MONTGOMERY ss S .... ~

u ~ On this 16th day of September • 2020 belOl'e me peisonalty appeared David M. Carey, who acknowledged himself to be the AssiSlimt SeaelBly ol U>erty Mutual Insurance ~ .8 ~ n1 ~-;nieOhlo Casu~ company, all!! West American Insurance Company, 800 that he, as such, be~ authorized so to do, ei:ecute the foregoing Instrument for the purposes !E = S ~ theleln contained l7f signing on behaW of the capon11ions by tlmself as a duly authorized olficer. ~ -m ~ ~ ~ IN WITNESS WHEREOF, I have hereunto subscribed my name and afftxed my notanal seal at King of Prussia. Pennsylvania. on the day and year fist above written "' c- 0 CD ~ "" PAel'; 'W".J: .Q ._t) .-Olfw#.f( ~ COllllONWEALTII Of P£NN1n.WJ11A ~

-4i'O /!c; st;. _ _, ~ ~ EroE

ID OF TertN -· Na\11)' l'llblc g.o=o ~-Twp.. MonlgorMlyC<lunly By: 8 GI

ti~ <t...~~~ MyCommloolon e.pr..-. 2a,2ll2t teresaPaSteiia, Nc:Ury PubrlC <C o C>lll '"'""""'°'~ _ _ ,.........._"'_ 0 o IV~ v ~ .8 This Power of At!Dmey Is made and executBd pursuant to and by autllOl'ly of the following By~ws and Authorizations of The Ohio Casually lnSllllllC8 ~y. Liberty Mliual ~ ~ ~ -~. Insurance Company, and West Ameltan Insurance Compiriy whk:h resOOtions are now In lul force and elfeQ reading as follows: o ~ ._ S ARTICLE IV- OFACERS: Section 12. Power of Attorney. 0 ~ e Any ollcar a other official of the Corporation authorized for that purpose in writing by the Chaiman a the President and siqed lo such fimitation IS the Chairman or the :0 ..-~ President may inscribe. stian appolm such attomeys.jn.tact. as may be necessary to act In behalf of the Corporatbl to make, execute. seal ~e and dewar as surety ti~ ~ ~ eny end an undertakings, bonds, recogrmnces end other sul'Bly obligallons. Such at!omeys-iMlct, sij)jed ti the fimilations set forth n their respective ix-rs ot attorney, shall -g rJ

Zo § have fuU power to bind the Colpora1ion by their signature end e11ecutlon ct any such Instruments and to atlaeh lhel8lo the seal of the Corponition. When 90 executed, such .8 a>

0 Instruments shall be as binding as II signed by the President and attesl!!d to by the Secretary. Any powef or authority granted lo any representative or attomey-in-fact lllder Iha !r ~ llf'(Msioos of this article may be l8YOked at any time by the Boerd, the Chairman, the President or by the oll'teer or ollicels granting such power or llU1horfty. ~ ~ ARTICLE XIU - Execution of Contracts: Section 5. SUrety BonCI$ and Undellakilgs. Any ollioer of the COf11)an)' authorized for that purpose in writing by the dlairman or the president and subject to such limitalionS as the dlainnan or the president may prescribe, shall appoint such ~ as may be necessary to act In behal of the Company to make, execute. seal, acknowledge and defMlf as surety any and all uncle~. bonds, recognizances and other sul'Bly obigations. Such attomeys-ln-fact subject to the imtauons set forth in their respective powe!S of attorney, shal have Ul power lo bind the Company by their signallff and •ec:ution cl any such ~ts and to attach flam> the seal of the Company. When so executed such instruments shall be m birdng as W 5';ined by the president and attested by the secrelary.

Certificate of Designation - The President of the Company, acting pursuant to the Bylaws of the ~ny, authortzeS David M. Cal'll)', Assistant Secretary lo appoint such attomeys.ln­fad as may be necessaiy to act on behaW of the C'.ompany to make, execute, seal, acknowledge and deliver as surety any and an u~s. bonds, recogrizances and other surety oblG&tlons.

Authorization - By unanimous consent of the Co~y's Board of Directors, the ~Y consents that tacsi'nife ot mechanlcally reproduced signature ol any assislanl aecretary of the Company, wllereYel appea~ upon a C8ftified covt of any power of attorney Issued by the Company in connection wi1h surety bonds, shan be vafid and binding upon the Company wi1h the same foroe and effect as though mall.llllly allixed. I, Renee C. Llewellyn, the 11\dersfg'led, Ass~ta11t Secretary, The Ohio Casually Insurance Co~ny. Liberty Mutual Insurance Company, and West American Insurance Company do henlby certify that the ~Ina: pci.vP,r oi ~of which the foregoing Is a full, true and oonect covt of the Power of Attorney exeQl!ed by said CompanieS, ia In full folQe and effect and has not been r'IM>l<ed.

IN TESTIMONY WHERWF, I haYB hereunto sei my~ and affixed the seals of said Companies this~ day ol September • ~·

~cV<s-By: Reneeueweiin. AssiStant S«:i'lillry

LMS-12873 LMIC OCIC WAJC Mukl CO 6l20