Ames Community School District Mitchell Elementary – Schematic Design Presentation July 16, 2013
SCHEMATIC DESIGN PROPOSAL FOR NEW ELEMENTARY SCHOOL · 1. New Elementary School for the Henry...
Transcript of SCHEMATIC DESIGN PROPOSAL FOR NEW ELEMENTARY SCHOOL · 1. New Elementary School for the Henry...
20 OctoberSchool Board School Board action item presentation1
NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL
SCHEMATIC DESIGN PROPOSAL FOR
20 OctoberSchool Board 2
Project Parameters for
1. New Elementary School for the Henry Community 2. Support Strategic Plan Goal #4 – Provide Optimal
Learning Environments3. Address capacity by providing at least 725 seats4. Open by start of school 20195. Multi‐story building in northwest corner of site6. Structured parking 7. Project cost $59 million
NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL
Exhibit A
20 OctoberSchool Board 3
Project Chronology | Timeline October 2012 FY 2013‐2022 CIP identifies Kenmore site as the location of a new elementary school
June 2014 FY 2015‐2024 CIP identifies Jefferson site as preferred location for a new elementary school
September 2014 County Board appointed TJWG begins
January 2015 TJWG issues Final Report and County Board decides “not now” to a new elementary at the Jefferson site
June 2015 School Board appointed SAWG begins
November 2015 SAWG issues Final Report including a preference to build a new elementary school for Henry at Jefferson
December 2015 School and County Board approves Jefferson as the site for a new elementary school
March 2016 School Board approves first three preferences of the SAWG
April to September 2016 BLPC & PFRC input during Concept and Schematic Design phases
November 2016 Use Permit submission
March 2017 Use Permit approval
July 2017 Estimated start of construction
September 2019 School Opening
Exhibit B
20 OctoberSchool Board Calculated capacity: 752 | Gross SF per student: 147 gsf4
Space Program SummaryPre K & Kindergarten:First & Second Grades:
Third, Fourth & Fifth Grades:Special Education + Specialty Programs:
Guidance + Administration + Teacher Support:Art + Music:
Library:Food Services:
Physical Education:
Net Square Footage:Support, Structure & Circulation:
Gross Square Footage:
9,200 nsf 8 classrooms = 156.6 10,325 nsf 10 classrooms = 233.313,525 nsf 15 classrooms= 349.99,080 nsf 2 classrooms = 126,155 nsf6,305 nsf4,340 nsf5,390 nsf9,110 nsf
73,430 nsf37,449 sf
110,879 gsf Total capacity: 751.9
Capacity Generating Classrooms
Exhibit C
20 OctoberSchool Board Site plans5
Overall existing site plan Overall proposed site plan
Exhibit D
20 OctoberSchool Board Parking levels6
112 spots112 spots
112 + 112 + 11 surface = 235 (not counting +/- 24 street spots on school side of SOG)
Upper level Lower level
Exhibit E
20 OctoberSchool Board First floor plan7
Exhibit F
20 OctoberSchool Board Second & third floor plans8
Second floor Third floor
Exhibit G
20 OctoberSchool Board Fourth floor plan & roof plan9
Fourth floor Roof
Exhibit H
20 OctoberSchool Board Schematic cost information10
Available Funding Estimated Cost1
Notes:1. Furniture and equipment that cannot be bond funded.
Major Construction BondsOther1
Subtotal
County/School Board Joint Fund• APS Funding• County Funding
Subtotal Joint Fund
Grand Total Funding Available
$40.30$0.80
$41.10
$8.95$8.95
$17.90
$59.00
($ Millions) ($ Millions)
Notes:1. Based on two independent professional cost estimates.2. Possible scope additions pending outcomes of future cost estimates.
Construction Costs Owner (Soft) Costs
Total Project Costs
Proposed Alternatives2
• Photovoltaic (PV) Panel System• TJMS Stair and Façade Modifications• TJMS Canopy and Window Enhancements• Park at Corner of S. Old Glebe Rd. and S. 2nd St
$46.35$12.65$59.00
$2.48$0.10$0.15$0.18
Exhibit J
20 OctoberSchool Board Perspective view of west elevation11
20 OctoberSchool Board Perspective view of entry12
20 OctoberSchool Board Perspective view of northwest elevation13
20 OctoberSchool Board Perspective view of southeast to theater14
20 OctoberSchool Board Perspective view of gym southwest15
20 OctoberSchool Board Perspective view of south elevation16
20 OctoberSchool Board Perspective view of gym southeast17
20 OctoberSchool Board Perspective view of south elevation18
20 OctoberSchool Board Perspective view of gym east19
20 OctoberSchool Board Perspective view of interior gym east20
20 OctoberSchool Board Perspective view of east elevation21
20 OctoberSchool Board Perspective view of northwest elevation22
20 OctoberSchool Board Perspective view of northwest elevation23
20 OctoberSchool Board Perspective view of pedestrian plaza24
20 OctoberSchool Board School Board action item presentation25
NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL
SCHEMATIC DESIGN PROPOSAL FOR