Schedule from Arturo 1/5

5
Schedule from Arturo 1/5 Load test done as soon as possible (September) Does it mean that load test cannot be performed in August ? Present status about transversal ribs shows that the product is within schedule and expected at CERN on first August week. DCal standard supermodules : still 1/5 supermodule to built. It may be ready early october . DCal extension : modules available. No stripmodules. No supermodules. The 2 x 1/3 supermodules may be ready early November. For both std supermodules and extension supermodules, the critical path may be the carriages that are still not ordered (funding reason), quotation available (5.6 K). Shuttle (required by compatibility with PHOS) : conceptual design done, fabrication drawings not done. DCal insertion tooling (rotator + base) : fabrication drawings on the way. 2 rough quotations available. PHOS modules : what are all required tasks in order to have a PHOS module available for insertion test ? I guess that some tasks are required before/after removal from L3.

description

Load test done as soon as possible (September ) Does it mean that load test cannot be performed in August ? Present status about transversal ribs shows that the product is within schedule and expected at CERN on first August week. - PowerPoint PPT Presentation

Transcript of Schedule from Arturo 1/5

Page 1: Schedule  from  Arturo 1/5

Schedule from Arturo 1/5

Load test done as soon as possible (September)Does it mean that load test cannot be performed in August ?Present status about transversal ribs shows that the product is within schedule and expected at CERN on first August week.

DCal standard supermodules : still 1/5 supermodule to built. It may be ready early october .DCal extension : modules available. No stripmodules. No supermodules. The 2 x 1/3 supermodules may be ready early November.For both std supermodules and extension supermodules, the critical path may be the carriages that are still not ordered (funding reason), quotation available (5.6 K).

Shuttle (required by compatibility with PHOS) : conceptual design done, fabrication drawings not done.

DCal insertion tooling (rotator + base) : fabrication drawings on the way. 2 rough quotations available.

PHOS modules : what are all required tasks in order to have a PHOS module available for insertion test ? I guess that some tasks are required before/after removal from L3.

Page 2: Schedule  from  Arturo 1/5

1/3 Supermodule pushing system 2/5

Page 3: Schedule  from  Arturo 1/5

1/3 Supermodule pushing system 3/5

Page 4: Schedule  from  Arturo 1/5

1/3 Supermodule pushing system 4/5

Page 5: Schedule  from  Arturo 1/5

1/3 Supermodule pushing system 5/5