Scada Siemens

download Scada Siemens

of 308

Transcript of Scada Siemens

  • Siemens AG 2008

    Distribution NetworkAutomation & Control

    SeminarJan 29/30, 2008Tehran/Iran

    Dr. Roland Eichler

  • Page 3 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar

    Substation Substation Substation

    Outstation

    Outstation

    OutstationOutstation

    OutstationOutstation

    OutstationOutstation

    Outstation

    Control Center

    Strategies for distribution automationControl in substations and outstationsCommunicationProcess optimization in the Control

    Center and customer related activities

  • Page 4 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar Contents (I)

    Section 6: Distribution automation standards

    Section 5: Selection criteria for hardware, software and communications

    Section 4: Which parameters should be measured or controlled ?

    Section 3: Selection of substations to work under automation automation layout

    Section 2: Impacts on planning of distribution automation

    Section 1: Goal, task and aspects of distribution automation

    Tuesday, Jan 29, 2008

  • Page 5 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar Contents (II)

    Section 7: SCADA functionalities

    Section 8: DMS functionalities

    Section 9: Case study presentation

    Section 11: Maintenance and support procedures

    Section 10: Distribution system automation personnel skills

    Wednesday, Jan 30, 2008

  • Page 6 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar Contents (I)

    Section 6: Distribution automation standards

    Section 5: Selection criteria for hardware, software and communications

    Section 4: Which parameters should be measured or controlled ?

    Section 3: Selection of substations to work under automation automation layout

    Section 2: Impacts on planning of distribution automation

    Section 1: Goal, task and aspects of distribution automation

    Tuesday, Jan 29, 2008

  • Page 7 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Mission of the Electricity Supply System

    The primary aim of an electricity supply system is to meet the customers demands for energy (in sufficient quantity and quality, at the required time and at an acceptable price)

    Similarity to other goods consumption processes, the Electricity Business comprises 4 basics components

    Demand Production (Generation) (Sub-)Transmission Distribution

  • Page 8 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Requirements to the Distribution System

    Suppliers View

    high efficiency with low losses few assets easy service less maintenance fast fault detection

    Customers View

    high availability no faults high power quality low price quick recovery

  • Page 9 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Customer Requirements and Supply Standards

    Availability no interrupts i.e. continuity of supply

    Power QualityVoltage FrequencyHarmonics Transients

    Definitions of supply reliability are quite different therefore statistic values can not be compared exactlymost countries count outages longer than 3 minutes, some define a 1

    minute limit (Great Britain, Portugal)Continuity indicators are calculated in a different way

    Weighted by the number of customer Weighted by the power affected (Spain, Portugal) Some consider Acts of God, some dont

  • Page 10 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Power Quality Standards

    Voltage in EuropeAccording IEC 61000

    Voltage in the USA : the American National Standard Institute (ANSI) defines "Voltage Range " as: 120/240V 5% at the user's service entrance, and 120/240V 8,33% at the point of utilisation.

    Frequency The vast majority of equipment appliances are not much sensitive to variation of

    frequency. Furthermore, in interconnected networks (e.g. UCPTE,..) the frequency (50 Hz or 60 Hz) is generally very stable and secondly source of problems.

    QualityAccording IEC 61000

  • Page 11 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Power Interrupt Statistic in Europe

    Length of power interrupts in minutes per year (1999) in some countries

    Source: Council of European Energy Regulators CEER 2001

    1525

    57 63

    152

    180191

    157

    364

    0

    50

    100

    150

    200

    250

    300

    350

    400

    GER NLD FRA GBR SWE NOR ITA SPA POR

    Country

    T

    i

    m

    e

    [

    m

    i

    n

    ]

    Customer-weighted indicators Power-weighted indicators

  • Page 12 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Domestic $ 0.15 / kW + $ 0.30 / kWh

    Agriculture

    $ 0.75 / kW +

    $ 2.50 / kWh

    Large Indust

    ry $ 2.70 / kW

    + $ 3.00 / kW

    h

    Small In

    dustry

    $ 1.35

    / kW + $

    5.25 / k

    Wh

    Trade

    & Se

    rvices

    $ 1.9

    5 / kW

    + $ 9

    .60 / k

    Wh

    Customers Costfor an Unexpected

    Outage[ $ per Interrupted kW ]

    Outages Duration

    [ Minutes ]

    Swedish nationwide surveyfor unexpected outages, 1993

    Social Cost for Unplanned Outage

    4020

    1

    2

    3

    4

    5

    6

    7

  • Page 13 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Transmission 33 - 420 kV

    27%

    Distribution 1-22 kV 73%

    Distribution 1-22 kVTransmission 33 - 420 kV

    Energy not Supplied due to Fault Outages

    Source: Cigr Conference, Paris, 2002

  • Page 14 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Why to Improve the Distribution System

    The transmission and the sub-transmission system have already high reliability

    Therefore:Distribution Automation has the best ratio Improvement to Invest

    Strategies to optimize the distribution system n-1 strategies are very expensive structure of the system can not be changed easily

    But even with rather cheap measures one can reduce the outage times dramatically

  • Page 15 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Maintenance

    Erection

    Commissioning

    Assembly

    Design

    Equipment

    5%

    10%

    25%

    10%

    40%

    10%

    10kV Overhead Line

    Diminishing ReturnsC1 = C2Rel1 >> Rel2

    C1

    Rel1

    C2Rel2

    0

    0.2

    1.0

    0.4

    0.6

    0.8

    Investment [C]

    R

    e

    l

    i

    a

    b

    i

    l

    i

    t

    y

    [

    R

    e

    l

    ]

    Reliability vs Investment Cost

    Breakdown of Capital Expenditure

  • Page 16 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Supply Quality

    C

    o

    s

    t

    s

    Supply Quality vs. Cost: A Macro Economic Consideration

    Cost for Interrupts(Less Sold, Penalties)

    Cost for Invest and Maintenance

    Macro Economic CostsLimits

    (Law, Standards)

  • Page 17 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    What is Distribution Automation

    There is no fixed definition of the term.

    Definition from EPRI 2004: The objective of (Advanced) Distribution Automation Function is to enhance the reliability of power system service, power quality, and power system efficiency,

    by automating the following three processes of distribution operation control: data preparation in near-real-time; optimal decision-making; and the control of distribution operations in coordination with transmission and

    generation systems (Note: Distributed Energy Resources !) operations

    Others (e.g. CIRED AD HOC Working Group 2 ) add topics such as establish closer and more responsive relationship with customers.

  • Page 18 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Improved automated workflow of the Operation and Planning Department ( North York Hydro )

    Improved supply quality and minimising of not sold kWh (CIRED 1987)

    Improved efficiency and quality of service, more rational use of energy (ENEL)

    Utilities view on Distribution Automation

  • Page 19 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Customer Interface,

    Management& Control

    Loads and Meters ReadingsControl

    Customer Trouble Information

    Billing &Settlement

    Distribution AutomationMain Function Sets

    Network Operation

    Operational Planning,

    Optimization

    Data Management

    Operation Statistics and

    Reporting

    Fault Management

    Power Import Scheduling and

    Optimization

    Network OperationMonitoring

    Network OperationSimulation

    Technical Data Management

    Network ControlSwitching Actions

    Scheduling

    Dynamic Data Management

    Source: CIRED Ad Hoc Working Group 2

    GeographicalDisplays

    ManagementInformation

    System

    Maintenance Management

    Operation Feedback Analysis

    Maintenance Works Scheduling

    and Control

  • Page 20 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Benefits in Network Operation (I)

    Improving the quality of serviceData acquisition, monitoring and remote control also at remote sites

    allows responding to alert and emergency conditions quickly and confidently and with the correct action, e.g.

    low voltage unbalanced flows low power factor overload

    Less and shorter outages lead to increased revenue

    Better network supervision means less equipment failureEquipment lifetime is lengthenedCost for maintenance material and manpower is reduced

  • Page 21 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Increased safety and securityOperation of any electrically controllable device can be securely inhibited

    at the SCADA master stationRemote outstations can be monitored for intrusion

    Reduction of staff in remote outstations

    Power Quality Calculations (Power Auditing) the open market imposes penalties for quality of service not compliant

    with minimum characteristics.

    Energy and Power Balancessome utilities have high amount of energy losses. The first step for

    correcting this problem is to determine where losses larger than normal are located, this includes both technical and non-technical losses

    Benefits in Network Operation (II)

  • Page 22 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Improve Quality of ServiceSPM: Operator always has a clear picture about the current status and

    further planned steps of each switching sequence faster switching at lower riskFloc / FISR: Shorten interruption time by automatically identifying

    candidate switching actions forisolation of faultsrestoration of supplyswitching back to normal

    DSPF: Detection of Limit Violations that would occur after planned switching actions avoiding overloads and accidental customer supply interruptions

    Improve Efficiency of Network OperationVVC/OFR: Keep the system at the minimum of technical losses thus

    reducing costFichtner Consulting estimates reduction of losses gained from optimized network operation using applications such as OFR and VVC to 0.4% 0.5% of the electrical energy delivered.

    Fichtner Consulting estimates reduction of losses gained from optimized network operation using applications such as OFR and VVC to 0.4% 0.5% of the electrical energy delivered.

    Benefits in Network Operation (III)

  • Page 23 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Customer Interface,

    Management& Control

    Loads and Meters ReadingsControl

    Customer Trouble Information

    Billing &Settlement

    Distribution AutomationMain Function Sets

    Network Operation

    Operational Planning,

    Optimization

    Data Management

    Operation Statistics and

    Reporting

    Fault Management

    Power Import Scheduling and

    Optimization

    Network OperationMonitoring

    Network OperationSimulation

    Technical Data Management

    Network ControlSwitching Actions

    Scheduling

    Dynamic Data Management

    Source: CIRED Ad Hoc Working Group 2

    GeographicalDisplays

    ManagementInformation

    System

    Maintenance Management

    Operation Feedback Analysis

    Maintenance Works Scheduling

    and Control

  • Page 24 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Benefits from Automatic Meter Reading (AMR) Systems

    Loss identification Loss reduction Revenue enhancement Operational Efficiency and Asset UtilizationMonitor energy balance & peak demand reductionFaster response time to customersEarn from innovative services to consumers e.g.

    Load profile via web accessSecurity services e.g. door control

    By using the AMR infrastructure

    Power Quality system on top

  • Page 25 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Customer Interface,

    Management& Control

    Loads and Meters ReadingsControl

    Customer Trouble Information

    Billing &Settlement

    Distribution AutomationMain Function Sets

    Network Operation

    Operational Planning,

    Optimization

    Data Management

    Operation Statistics and

    Reporting

    Fault Management

    Power Import Scheduling and

    Optimization

    Network OperationMonitoring

    Network OperationSimulation

    Technical Data Management

    Network ControlSwitching Actions

    Scheduling

    Dynamic Data Management

    Source: CIRED Ad Hoc Working Group 2

    GeographicalDisplays

    ManagementInformation

    System

    Maintenance Management

    Operation Feedback Analysis

    Maintenance Works Scheduling

    and Control

  • Page 26 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Benefits from Real Time Energy Management System (RTEMS)

    Integration of meter-to-bill processes and systems Improve cash flow, and system reliability

    Consolidation of customer data and meter data repositories Improve trust and reduce cost

    Allowing web-based display and usage of energy demandand consumption information at the consumers site

    Reduce cost, improve customer retention / satisfaction and quality

    Enabling real time monitoring of power quality informationand automated response to energy distribution events

    Sell power quality services and increase margin

  • Page 27 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Customer Interface,

    Management& Control

    Loads and Meters ReadingsControl

    Customer Trouble Information

    Billing &Settlement

    Distribution AutomationMain Function Sets

    Network Operation

    Operational Planning,

    Optimization

    Data Management

    Operation Statistics and

    Reporting

    Fault Management

    Power Import Scheduling and

    Optimization

    Network OperationMonitoring

    Network OperationSimulation

    Technical Data Management

    Network ControlSwitching Actions

    Scheduling

    Dynamic Data Management

    Source: CIRED Ad Hoc Working Group 2

    GeographicalDisplays

    ManagementInformation

    System

    Maintenance Management

    Operation Feedback Analysis

    Maintenance Works Scheduling

    and Control

  • Page 28 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Obtain more information from the network for a safer, more reliable and more efficient operationextremely useful for cost efficient network planning because information

    on real equipment loading avoids over-sizing e.g. for installed transformer capacityplanning of just-in-time maintenance based on actual equipment stressgeneration of logs and reports for after-the-fact system analysis and

    management information; everybody can create the reports he/she needs (no software or database knowledge required, only brief handling training)Precise, on-time, and comprehensive information increases management

    awareness of actual situation and increases efficiency of department co-operation

    Calculation of Quality of Service Indices for individual distribution points clear proof of power supply quality

    A distribution utility has reported a 100,000 US$/per year saving because new distribution substations could be better planned - at the right time at the right place.

    Benefits from Management Information System

  • Page 29 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Minimization of non-in-time delivered energy reduce by 20% the current values (conservative figure)

    Network losses minimization reduce by 5% the current values (conservative figure)

    Improved Operation efficiency10% of the Operations budget

    Improved Imageequivalent or better market penetration with reduced marketing costs

    Improved working conditions and environmentstable personnel, less recruitment costs (and related training)

    Distribution AutomationSome more potential achievements

  • Page 30 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar Contents (I)

    Section 6: Distribution automation standards

    Section 5: Selection criteria for hardware, software and communications

    Section 4: Which parameters should be measured or controlled ?

    Section 3: Selection of substations to work under automation automation layout

    Section 2: Impacts on planning of distribution automation

    Section 1: Goal, task and aspects of distribution automation

    Tuesday, Jan 29, 2008

  • Page 31 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Impacts on planning of distribution automation (I)

    The general benefits from distribution automation have been clarified in Section 1. This has answered the WHY of distribution automation.

    The utilitys priority of goals defines WHAT shall be done i.e. what is more important to achieve:

    increasing supply reliabilityincreasing power qualitydecreasing costdecreasing loss of revenueetc

    This priority list will guide the selection of the most suitable program for distribution automation i.e. what will be done first.

  • Page 32 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Impacts on planning of distribution automation (II)

    After the utility has answered the strategic WHAT question the next question is HOW the distribution automation solution shall be implemented i.e. what are technical / environmental / legal / constraints. This concerns issues such as:

    overhead vs. underground networksavailability of communication technologyavailable (inter-)national standardsalready existing automation / communication infrastructureaccessibility of substationscurrent and future importance of substationsetc

  • Page 33 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Impacts on planning of distribution automation (III)

    Normally there will be several proposals for achieving the WHAT goals considering the HOW constraints.

    Besides the achievement of the strategic WHAT criteria there aregeneral criteria for selecting the most suitable distribution automation proposal:

    flexibility of the distribution automation solution in case of changing strategic goals of the utilityflexibility for adding more services/business in the futureexpandability of the distribution automation solution in case of

    growing system size e.g. due to mergers with other utilitiesreliability of the distribution automation solution itselfinvestment cost & cost for operation and maintenance of the

    distribution automation solution vs. monetary achievements

  • Page 34 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Components of a distribution automation solution (I)

    A properly selected distribution automation solution will comprise answers to the following questions:

    Which substations should be automated to what extent ?Remote metering/monitoringRemote switch control

    Which data shall be collected from which substation ?Which control centers shall be built/used (centralized/distributed) ?Which redundancy concepts shall be implemented ?Which communication media shall be built/used for which type of

    link?Which communication configuration shall be built (point-to-point,

    network, radial, ...) ?

  • Page 35 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Components of a distribution automation solution (II)

    Which software packages are required ?

    Which interfaces are required ?

    to external control centersto external applications, such as GIS, CRM, etc

    Which metering, accounting, settlement and billing process shall be applied ?

    Which standards shall be used ?

  • Page 36 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Components of a distribution automation solution (III)

    What is the capital expenditure for such a system ?Which achievements are expected with regard to the strategic WHAT

    goals ?reduction of outage frequencyreduction of outage durationcost reductionetc

    How can such a system be implemented and maintained ?How can databases be populated and maintained ?How can the implementation be split in several phases for early

    benefit achieving ?Which training is needed at what time for operational staff and

    administration ?

  • Page 37 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Anticipated Problems with Distribution Automation#1: Centralized Control System

    Apprehension: Due to the automation of distribution networks the number of data points and RTU lines to be processed increases dramatically and thus exceeds the processing capabilities of centralized systems

    large amount of data is not any more limiting the processing capabilities of modern SCADA/DMSmodern process interfaces can handle hundreds of RTU lines,

    furthermore there are possibilities forrunning several RTU servers in parallellean RTU interfacing by means of TCP/IP based

    protocolsuse of modem poolscascading of RTUs, i.e. small field RTUs talk through

    large substation RTUs

  • Page 38 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Anticipated Problems with Distribution Automation#2: Communication

    Apprehension: The automation of distribution networks fails due to insufficient communication lines.

    cascading of RTUs reduces the number of communication lines needed

    alternative communication media are available

    power line carrier over distribution linesmobile phone networks such as GSM, GPRSdial-up lines over public phone companies

  • Page 39 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Anticipated Problems with Distribution Automation#3: Cost

    Apprehension: The automation of the entire distribution network is too expensive.

    in the course of energy market liberalization the pressure for cost reduction from regulation authorities on distribution companies will constantly grow and justify ever more investment in distributionautomation

    cost for energy automation equipment and communication equipment is decreasing particularly for compact RTUs and dial-up connections via mobile telephone systems

    distribution automation does not come as big bang; it rather grows over time closely coordinated with investment / maintenance programs for substations

  • Page 40 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar Contents (I)

    Section 6: Distribution automation standards

    Section 5: Selection criteria for hardware, software and communications

    Section 4: Which parameters should be measured or controlled ?

    Section 3: Selection of substations to work under automation automation layout

    Section 2: Impacts on planning of distribution automation

    Section 1: Goal, task and aspects of distribution automation

    Tuesday, Jan 29, 2008

  • Page 41 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    The Last Meters: Low Voltage

    115 V /125 V SystemsMainly used in USA, Canada, Brasilia, Mexico, Saudi Arabia, Korea,

    Philippinestypical 60 Hz and requires transformer nearby the consumermain distribution to the end consumer is done by the MV grid

    230 V / 400 V SystemsMainly used in Europetypical 50 HzOhmic power losses enable distance up to 2 km to the next MV / LV

    transformermain distribution to the end consumer is done by the LV grid

  • Page 42 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Structure of the Power System in USA115 V

    TransmissionNational /International

    SubtransmissionRegional

    Low Voltage

    Distribution System

  • Page 43 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Structure of the Power System in Europe230 / 400 V

    TransmissionNational /International

    SubtransmissionRegional

    Low Voltage

    Distribution System

  • Page 44 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Typical sub-transmission/distribution configuration

    220KV220KV/33KV Rec. Stn

    33KV

    33KV/11KV Rec. Stn.

    Compact Distribution Station Ring Main Units

    11KV

    X X XXX

    X X X X

    Scope of this seminar

  • Page 45 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Urban underground MV networks

    110/20kV

    20/0,4kV

    20/0,4kV

    A

    B

    C D

    Sc d

    Circuit breaker

    Load-breakingswitch

    Fuse

    S Isolation point

    At a suitable point on the network the loop is opened by a sectionalising device S. This may be a circuit breaker, switch, fuse or link. The system then effectively operates as two radial feeders.

  • Page 46 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Overhead rural MV networks

    The figure shows schematically typical arrangements for a rural overhead radial feeder, with some of the manually operated disconnectors omitted for simplicity. It will be noted that each main trunk feeder has a number of lateral spurs.

  • Page 47 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Substations of type 1 establish permanent communication between the control centre and the distribution substation e.g. by means of optical fibres. Often the fibres of a secondary communication network are interconnected with a node (receiving station) of the primary fibreoptic ring. Applications such as RTU and AMR use TCP/IP. IEC 60870-5-104 is recommended for RTU communication.Of course, other communication media / protocols are possible.

    Battery 24/48V DC

    Battery charger

    RTU (IEC104)

    Meter

    Control & Monitor switch states,Short circuit indicators

    CT, VT

    motorized 11kV

    Switchgear

    Fibre panel 1 (2) *24

    8 port Ethernet HUB

    FO from R/S, S/S FO to next S/S

    Fibre optic to UTPMedia Converters

    Substation type #1 with permanent data access

    Sample configuration

  • Page 48 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Battery 24/48V DC

    Battery charger

    RTU (IEC101)

    Dial up Modem (WLL/Fixed wired)

    Energy Meter

    Control & Monitor switch states,Short circuit indicators

    CT, VT

    motorized 11kV

    Switchgear

    24/48 V DC

    Substations of type 2 use switched telephone communication facilities (fixed wired or mobile communication) to transfer data on demand. The demand for data exchange can be initiated by the control centre or the distribution substation itself. The control centre needs to control switchgears remotely, to ask for data update or just to test the connection. The substation need to call in the control centre if there is some urgent data to transfer, for example a fault indication on a 11kV incoming or outgoing line.

    Substation type #2 with temporary data access

    Sample configuration

  • Page 49 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Steps of Distribution AutomationStep 0: Centralization of distribution system operation

    centralized distribution system operation is less costly

    centralized distribution system operation reduces time to restore supply after disturbances

    existing mixed structures of local and centralized operation often have grown over time but do not have justification as of today

    mixed structures in case of disturbances, i.e. local operation only temporarily, are questionable in terms of organization reliability

  • Page 50 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Steps of Distribution AutomationStep 1a: Automation of feeder heads in HV/MV substations

    in case of a new HV/MV substation the whole scope of automation shall be built in:

    remote signaling of all switching element statuses remote control of circuit breakersdigital protection devices provide analog measurements in

    normal operation and fault operation

    in case of retrofitting HV/MV substations the following priority applies

    must: fault information from protection equipment per field

    optional: remote control of circuit breakersanalog measurements of feeder currents

    nice-to-have: more switching status information (isolator, earthing switch, ...)

  • Page 51 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Steps of Distribution AutomationStep 1b: Automation of major switching substations

    Major switching substation:three (3) outgoing feeders or morecircuit breaker and protection

    In case of a new switching substation the whole scope of automation shall be built in (see Step 1a)

    In case of retrofitting switching substations the same priorities apply as in Step 1a.

  • Page 52 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Steps of Distribution AutomationStep 1c: Remote signaling of selected fault current sensors

    With this step the utility has reached the level of automated centralized fault location:

    evaluation of topology informationevaluation of fault impedancesevaluation of fault current sensor informationconsideration of additional information received via phone

  • Page 53 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Steps of Distribution AutomationStep 2a: Automation of selected MV/LV substations

    Selected MV/LV substations:

    normally open section pointmidway of long feeders

    Remote control of load switchesThis normally implies the necessity to motorize the switches.

  • Page 54 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Steps of Distribution AutomationStep 2b: Automation of selected customer substations

    Selected customer substations:

    high-volume consumerhigh-sensitive consumer

    remote signaling of fault informationremote switchingremote signaling of analog measurements

    This enables new business opportunities for providing high-quality power supply services to those customers.

  • Page 55 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Selection of distribution substations for automation

    For the selection of distribution substations for automation two main questions have to be answered:

    (A) What is the most reasonable and beneficial rate of automation for distribution substations?

    (B) Which dedicated distribution substations shall be automated ?

    The goal of distribution substation automation is basically to reduce the average interruption time of energy supply in the distribution network. In case of a feeder trip the SCADA/DMS operators get fault indication from automated distribution substations. Within a short time a part of the affected consumers can be re-supplied by reconfiguring the distribution network by remote control actions from the SCADA/DMS. DMS applications will support the operator in defining the most appropriate switching sequence (Section 8).

  • Page 56 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Selection of distribution substations for automationQuestion (A): Automation Rate (I)

    A fault on a cable section causes the feeder to trip. Two distribution substations will send fault indications and fault-direction to the control centre. Based on this information the operator can re-supply ~ 50% of the affected consumers by performing switching actions 2 - 5. This can be done within a time period of 3 minutes.

    Normally open point

    1. trip

    2. open

    4. open5. close

    650 feeders4099 distribution substationsD6,5 substations / feeder

    2,2 million consumersD537 consumers / substation

    R/S feederR/S feeder

    Fault indicator

    Automated substation

    3. close

    About 50% of the affected customers re-supplied after 3 minutes.

    Automation rate assumed to be 25%.

  • Page 57 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Selection of distribution substations for automationQuestion (A): Automation Rate (II)

    Compared to non-automation, the restoration crew can work faster since the area of intervention is only a part of the feeder. Fault isolation and service restoration are done by conventional methods. The crew on site can be supported by the operators in the control centre. Average conventional restoration time is estimated to be reduced by 50 % (40 minutes 20 minutes).

    Remaining 50% of the affected customers re-supplied after 20 minutes.

    R/S feederR/S feeder

    Fault indicator

    Automated substation

    Automation rate assumed to be 25%.

  • Page 58 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Selection of distribution substations for automation Question (A): Automation Rate (III)

    As result of this scenario the service restoration time will be reduced from approximately 40 minutes to approximately 11 Minutes.

    50 % of consumers are re-supplied after 3 minutes50 % of consumers are re-supplied after 20 minutes=> average interruption time ~11 minutes

    This kind of estimation of outage time reduction can be repeated for other values of the automation rate.The diagram on the next page indicates the average interruption time as function of the number of automated substations (magenta) taken from a study case. Relevant study case data are given on the following page. The blue curve is representing the Net Present Value (cost/benefit ratio). The costs are based on the substation adaptation investments, the benefits are calculated from more energy sold due to reduced average interruption time.

  • Page 59 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Detailed Case Study on Cost-Benefit-Analysis of Distribution Automation with different Automation Rates in Section 9.

    Selection of distribution substations for automation Question (A): Automation Rate (IV)

  • Page 60 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Selection of distribution substations for automation (VI)Question (B): Selection of Substations

    The selection of dedicated substations for automation does not follow a strict and simple algorithm. It is rather guided by fuzzy criteria on two levels: Feeder level

    Such feeders will be preferred that have higher load density higher fault density than others

    Substation levelObviously the substation with normal open points will be automated first on a selected feeder.As regards other substations, the leading criterion is the load that can be affected i.e. those substations will be preferred that have

    large industrial consumers connectedspur lines with high load connected

    Finally, the time needed for manual switching plays a role i.e. those substations will be preferred that have

    long travel time to reach

  • Page 61 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar Contents (I)

    Section 6: Distribution automation standards

    Section 5: Selection criteria for hardware, software and communications

    Section 4: Which parameters should be measured or controlled ?

    Section 3: Selection of substations to work under automation automation layout

    Section 2: Impacts on planning of distribution automation

    Section 1: Goal, task and aspects of distribution automation

    Tuesday, Jan 29, 2008

  • Page 62 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Data to be collected from HV/MV Substations

    Active Power, Reactive Power, Voltages, Currents from allincoming feedersoutgoing feederscapacitor banks etc

    Switch Positions of the Isolators (Single Pole)Circuit Breakers (Double Pole)

    Indications of other auxiliary devices such as UPS, Battery system, Chargers, Communication Devices etc.Status from the protection devicesTransformer tap position

  • Page 63 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Data to be collected from Distribution S/S

    AlarmCharge low

    AlarmCharger failure

    AlarmPower supply failure

    Battery SystemAlarmFault current sensors

    AlarmPhase-to-ground short circuit

    AlarmPhase-to-phase short circuit

    Protection (each feeder)Measured ValueI / P / Q / V

    Analogs(Command)StatusLoad switches

    CommandStatusCircuit breakers

    SwitchesOutput from SCADAInput to SCADA

  • Page 64 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Step 2:

    Line/cable segmentengineering data

    Typical load curves forload transformers

    220 kV bus

    33 kV bus

    33 kV bus

    11 kV busM

    M

    M M

    Data to be collected for distribution automation

    Step 0:

    SCADA data model

    Step 0:

    SCADA data model

    ReceivingSubstation

    Bulk supplySubstation

    1. Extend by SCADA data model of distribution feeders (topology, switches) enabling Operation Applications (Section 8)

    2. Extend by engineering data of line/cable segments and load models enabling Distribution Network Applications (Section 8)

    3. Add measurements from automated distribution substations; substitute load models

    Step 1:Extended SCADA

    Data Model

    M MM M

    Step 3:Measurements

    from distributionautomation

  • Page 65 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    I> (t)

    tdtpick-up time dt selectable: 40 oder 80 ms

    enveloping of failure currentIS1

    selected pick-up current

    criterion Is1 and dt fullfilled-> indication is activated

    Integrative measurement avoids erroneous indication!Red signal curves must not

    activate the indicator

    Short-circuits and earth-faults indicators

    For effective failure detection and location short-circuits and earth-faults must be observed. Combined short-circuit and earth-fault indicators are most economical. Indicators can be installed on outgoing feeders of RMUs. The fault detection facility generates alarms in case of high current peaks. However, the facility shall prevent faulty indications due to magnetizing-inrush currents, other transient and no-fault conditions.

  • Page 66 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Knotenpunktstationnodal point substation

    I>>IeRMU

    RMU I>>Ie

    RMU RMU

    RMURMURMU

    UmspannwerkPower substation

    I>>Ie

    I>>Ie

    I>>Ie

    I>>Ie

    I>>Ie

    I>>Ie

    I>>Ie

    Fault detection in low resistance terminated networks by means of short-circuit indicators

  • Page 67 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Typical Repairing of Permanent Faults

    Protection has tripped circuit breaker CBTransient fault? Automatic recovery? Localize fault

    phone calls, relay data, Remote Terminal Units (RTU), visually

    Open isolator and ground equipmentRestore supply as much as possibleDo nessesary repair workFault removed, line repairedRemove grounding and close isolator or replace fuseSwitch back to normal state

  • Page 68 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Urban vs. Rural Regions

    Urban underground cables with less external faults

    Rural a lot of overhead lines intermediate short circuits birds trees wind Auto recloser strategies

  • Page 69 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Distribution Automationin Urban AreasExample for Ring Main Automation

  • Page 70 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    OC

    OC

    FI

    Typical open ring configuration

    OC: over current protectionFI: fault indicator

  • Page 71 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Outstation (Ring Main Station, Satellite Station)

  • Page 72 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    -Q01

    -A5

    1

    3

    -T1

    -T5

    -Q01

    -A5

    1

    3

    -T1

    -T5

    -Q01

    -A5

    1

    -F1

    Ring Unit 1

    Ring Unit 2

    Feeder to LV trans-

    former

    M M M

    Double indications:Ring unit 1 isolator On/OFFEarth switch 1 On/OFFRing unit 2 isolator On/OFFEarth switch 2 On/OFFFeeder On/OFFEarth switch Feeder On/OFF

    Single indications:Short circuit indicator RK1 Short circuit indicator RK2Fuse blownGrouped Indication Auxiliary power failure Transformer temperature alarmRemote control offUPS failureStation open

    Meters (optional):Meter feeder

    Double commands:Ring unit 1 isolator On/OFFRing unit 2 isolator On/OFFFeeder On/OFF

    Analogs (optional):Ring unit 1 Current Phase L2Ring unit 1 Voltage L2-NRing unit 2 Current Phase L2Ring unit 2 Voltage L2-N

    Typical mini RTU solutions

    Ring main unitwith one feeder

  • Page 73 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (1)

    Example of network configuration. The network is divided into four sections. In the example is there a fault between SB21 and SB22.A central control unit is placed with the circuit breakers (E1,E2). The circuit breakers could be taken in and out from the central control unit.Decentral control units are placed with the line switches in each section(SB11,SB-R,SB21 and SB22) .These units get information from a voltage sensing system and control each line switch. In a ring configuration it is a must to have a voltage sensing system on both sides of the line switch.

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 74 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (2)

    With a fault in the network configuration, the protection relay will take the circuit breaker (E2) out. The central control unit will try to put the circuit breaker in, but in a faulty network configuration the protection relay will take out the circuit breaker again.

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 75 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (3)

    This procedure indicates to all units (SB21,SB22 and SB-R) that the network configuration is faulty, and the automatic sectioning starts.All decentral control units (SB21 and SB22) take out the line switches .

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 76 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (4)

    The central control unit closes the circuit breaker after 20 seconds, to test the first part of the network configuration .

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 77 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (5)

    After 40 seconds the decentral control unit (SB21) closes the line switch.

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 78 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (6)

    Because this part of the configuration (SB21 SB22) is faulty, the central unit will take out the circuit breaker. The decentral control unit (SB21) discovers that the voltage only was in for a short time, and then takes out the line switch and locks it.

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 79 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (7)

    The decentral control unit (SB22) discovers that the voltage was in only for a short time, and because of the voltage sensing system of both sides of the switch, the unit knows that the fault is between SB21 and SB22. The decentralcontrol unit (SB22) will then lock the line switch.

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 80 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Automation in a MV Ring (8)

    The decentral control unit (SB-R) have detect the start of the automatic sectioning.The decentral control unit (SB-R) has not detected any voltage on the side SB-R SB22. After a time (60 seconds) the unit knows that the fault is between SB21 and SB 22, and the line switch (SB-R) is closed.Now at this time the part between SB21 and SB22 (the faulty) is disconnected from the healthy part of the network configuration.

    200 40 60 [sec]

    E1

    E2

    SB11

    SB21 SB22

    SB-R

  • Page 81 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Distribution Automationin Rural AreasSectionalizer

  • Page 82 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizing in Overhead Lines

    Sectionalizer enable a system for automatic sectioning in a network configuration. Automatic sectioning is based on switching on and out line switches and circuit breaker in a controlled sequence to find errors in the network. When the errors are found, the system will take out the faulty part of the configuration.

  • Page 83 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizing in Overhead Lines

    Example of network configuration. The network is divided into six sections (S1 S6)

    Circuit breaker Load-breakingswitchPower

    TransformerVoltage sensing

    system

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 84 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (1)

    With at fault in the network configuration, the protection relay will take out the circuit breaker.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 85 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (2)

    The central control unit (E1) will try to put the circuit breaker in but in a faulty network configuration.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 86 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (3)

    The protection relay will take out the circuit breaker again.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 87 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (4)

    This procedure indicates to all units (E1 and L1 .. L5) that the network configuration is faulty, and the automatic sectioning starts.The automatic sectioning starts at relative time 0 seconds.All decentral control units (L1 .. L5) take out the line switches .

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 88 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (5)

    The central control unit closes the circuit breaker after 20 seconds, to test the first part of the network configuration (S1).

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 89 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (6)

    After 40 seconds the decentral control unit (L1) closes the line switch.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 90 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (7)

    Because this part of the configuration (S2) is faulty, the central unit (E1) will take out the circuit breaker.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 91 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (8)

    The decentral control unit (L1) discovers that the voltage only was in for a short time, and then takes out the line switch and locks it. At this time the section S2 (the faulty) is disconnected from the healthy part of the network configuration.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 92 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (9)

    After 60 seconds the central unit (E1) closes the circuit breaker.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 93 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (10)

    The decentral control unit (L2) closes the line switch in due to the voltage sensing system.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 94 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (11)

    After 80 seconds the decentral unit (L3) close the line switch in due to the voltage sensing system.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 95 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (12)

    After 100 seconds the decentral unit (L4) close the line switch in due to the voltage sensing system.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 96 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (13)

    Because this part of the configuration (S4) is faulty, the central unit (E1) will take out the circuit breaker.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 97 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (14)

    The decentral control unit (L4) discovers that the voltage only was in for a short time, and then takes out the line switch and locks it. At this time the section S4 (the faulty) is disconnected from the healthy part of the network configuration.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 98 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (15)

    After 120 seconds the central unit closes the circuit breaker and the automatic sectioning is finished. The decentral control unit (L5) could be designed to close the line switch after 120 seconds.

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 99 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer (16)

    The central control unit sets outputs (lamps) for each section (S1 S6) which is faulty.It is also possible to send this information to a network control system via IEC 6870-5-101 protocol, or/and send SMS messages.

    Seenextpage

    20 400 60 80 100 120 140 [sec]

    E1

    L1

    L2 L4 L5

    S2: 250 kW

    S3: 375 kW

    S5: 250 kW

    S6: 150 kW

    S1: 500 kW

    L3

    S4: 250 kW

    e. g.110/20kV

  • Page 100 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sectionalizer: Switch and Control

    Line Switch with voltage transformer

    Electronic with storage battery,local control andcommunication

  • Page 101 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Seminar Contents (I)

    Section 6: Distribution automation standards

    Section 5: Selection criteria for hardware, software and communications

    Section 4: Which parameters should be measured or controlled ?

    Section 3: Selection of substations to work under automation automation layout

    Section 2: Impacts on planning of distribution automation

    Section 1: Goal, task and aspects of distribution automation

    Tuesday, Jan 29, 2008

  • Page 102 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    BusinessServices

    IT Integration

    ASP

    Administration

    Operation

    E-Commerce

    Maintenance

    Field data acquisition,local control & automation

    Communication

    Network control &supervision (single-or multi-utility)

    Added value network management & optimization(applications and systems)

    Integrated utility business operation

    xxxx x xxx xxx xx

    MetersSubstation automation

    ProtectionLocal automation

    RTUs

    PowerExchange

    $$TraderPartner, market, etc.

    Multi-site

    SCADAetc.DB

    Networkplanning

    Networkinformation

    Meter datamanagement

    ...Advanced applications

    (EMS, DMS, EBM, Trading)

    Informationgateway

    ...Asset

    ManagementEnergy Sales

    & Care

    Enterprise Integration Bus

    Data Warehouse

    MISF&A

    Gateway

    Power Systems Control and Energy Management Multi-Level Environment

    Private & public networks

  • Page 103 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Optical Fiber

    Radio

    Copper Cable

    Power Line

    Public Network

    GSM/CDMA Network

    Communication Media

  • Page 104 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    BackboneNetwork

    RTU

    RTU

    RTU

    RTU

    RTU

    MV - Line

    RTU

    MV - Line

    Backbone Network / Access network

  • Page 105 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Control Center

    TCI

    No. 1 No. Z

    RTU

    MV - Line

    RTU

    RTUMUX

    Optical Fibre

    Backbone Network / Distribution Data Acquisition

  • Page 106 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Aspects of Network Design

    Costs Reliability

    PerformanceRegulations

    Network Design

  • Page 107 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Communication Selection CriteriaLeased Public Line

    The telephone company provides direct point-to-point connectivity between the RTU location and the control centre. On both end of the communication, a suitable modem appropriate to bandwidth (9600 bauds, 86 Kbps) is required.

    The cost of the communication of this nature comprises the fixed cost to be paid as one-time charges (for Registration fees, Installation fees of the equipment) and the operational charges (for periodical subscription as well as usage).

    Though this type of communication facility seems to be economical, on a long term it may not turn up to be cost-effective, since one has to pay the periodical operation charges.

    The other disadvantage is due to frequent failures of the lines, dependence of third party state-owned service provider.

    This type of communication has limitations for future expansion as the number of RTUs / mRTUs increases.

  • Page 108 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Communication Selection CriteriaDial-up Public Line

    Few telephones / modems are provided having dial-up facility at the control centre end, whereas at the RTU / mRTU ends the modems are to be provided with answering facility.

    For a real-time operation, this kind of communication is not preferred due to the time consuming dial-up and answering process. However, for Automated Meter Reading or for checking the status of reclosers after disturbances dial-up communication can be effectively utilized.

    The cost of the communication of this nature comprise of the fixed cost to be paid as one time Registration fees, Installation fees of the equipment) and the periodical subscription as well as usage charges.

    Disadvantages, however, are the same as indicated above for the Leased line communication.

  • Page 109 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Communication Selection CriteriaGSM Mobile Communication

    With the advent of mobile telephony, usage of GSM communication is becoming quite popular and widely used for data communication. Using GSM modems at the RTU end and the Control Centre end the data exchange can be introduced using urban mobile (GSM) networks.

    While considering the GSM network as a feasible solution one has to be sure that mobile connectivity is available at all the RTU locations.

    GPRS is also an acceptable solution.

    Disadvantages are similar as indicated above for leased line communication. Even more, GSM networks tend to be overloaded during peak hours and might make RTU communication unavailable for quite a while.

  • Page 110 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Communication Selection CriteriaDigital Networks via Fiber Optic

    It is required to lay extensive FO cables connecting primary stations, sub-divisions and the control centre. Such systems, though The Best technical option to establish a TCP/IP network, requires considerably high cost. In addition to establishing of an extensive FO network, the associated

    terminating equipment and multiplexers are required at all the location from where the data is to be collected or to be dropped in.Though the solution does not look to be cost effective at first sight due to high

    initial costs, it may turn out to be cost effective, if the utility makes use of the extra fibers of the FO cable for other communication facility requirements such as voice, Fax, other IT applications. With the establishment of an own FO network, the utility has the responsibility

    for operation and maintenance of the network, but at the same time it has full control of system expansion in case of increasing number of (field-) RTUs.Fast wireless Ethernet modems are gradually becoming popular. The

    Ethernet modems are available in the rated range of 5 miles to 25 miles. Making use of such Ethernet modems together with FO based communication network as backbone, makes an ideal communication between distribution substations, receiving substations and the control centre.

  • Page 111 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Communication Selection CriteriaRadio Communication

    The communication system using radio requires considerably high costs associated with procurement of radio systems, installation of towers and masts for antennas etc.

    However, once installed and put into operation, the communication system has low, annual costs for operations and maintenance. Thus it helps the utility to establish its own communication network.

    It is necessary to obtain the frequency allotment / approval from the wireless agency or the prescribed authority as nominated by the state / govt. In general, yearly subscription fees for utilizing the frequency are required to be paid.

    Before implementing the solution, a detailed Sight of Line study is required to be carried out for the feasibility of the solution in a particular town / city. Obstruction make occur due to high rise buildings (also by not yet existing ones !).

  • Page 112 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Costs

    Hardware

    Commissioning / Installation

    Base fees

    Connection fees

    Excavation work

  • Page 113 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    0%

    200%

    400%

    600%

    800%

    1000%

    1200%

    1400%

    1600%

    1800%

    Radio (

    no tow

    er)

    Radio B

    TC GSM

    New pilo

    t cable

    Leased

    line (lo

    cal)

    Leased

    line (fa

    r)

    Dial m

    ode line

    DCS C

    DC

    DCS C

    DI

    Transmission method

    Telecontrol service (RTU) and remote load profile reading Connection feeBase fee

    Assembly/commisioning

    Hardware cable

    Hardware equipment

    9 km MV linewith 4 kiosks

    Over 5 years 12 polling per day

    Invest for assembly and operation

    PLC PLC overover Medium Medium VoltageVoltage

    *) This calculation depends on the regional conditions, the example based on the European / African market.

    Cost Comparison

  • Page 114 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Data Transmission with Distribution Line Carrier(DLC)

  • Page 115 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    The coupling transformer encloses the earthing strap of the MV cable

    Conductor 1 Conductor 2 Conductor 3

    Sealing end

    Earthing strapCDI(ferrite ring)

    Earthing bar

    BU

    Data Transmission with Distribution Line Carrier (DLC) - Inductive coupling device

  • Page 116 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    CDC

    Cable outlet

    Conductor 1 Conductor 2 Conductor 3

    Bracket or separate supporting bar for CDC

    Earthing bar

    Connecting element

    Data Transmission with Distribution Line Carrier (DLC) - Capacitive coupling device

  • Page 117 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    CommunicationMulti carrier principleTransmission in the frequency range of

    CENELECUniform hardware for Master & SlaveTransmission rates up to 28.8kbit/s

    (depending on the line)Bypass of MV switchgearSimple & complex: MV line, tree or ring

    networks

    Interfaces Telecontrol per IEC 60870-5-101 or DNP 3.0Meters per IEC 61107Medium-voltage line and telecontrol line

    Data Transmission with Distribution Line Carrier (DLC) Basic Unit

  • Page 118 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Pole mounted switch 1

    BU

    Control center

    Distribution point

    MV Line

    V.24 IEC 60870-5-101

    MV Line

    MV substation automation - field trail DLC runs with microRTU and control center by using

    IEC communication standard

    Test with out-door CDC coupling units Transmission rate 9.6kBd

    Pole mounted repeater

    BUMaster-

    BU

    V.24 IEC 60870-5-101BU

    V.24 IEC 60870-5-101

    Pole mounted switch 2

    Data Transmission with Distribution Line Carrier (DLC) Sample project: MEA Bangkok/Thailand

  • Page 119 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Mounting a BU cabinet on an overhead line pole

    Pole mounted cabinetincluding DCS3000 BU

    Fully-installed cabinet, with DCS 3000 BU and SICAM microRTU

    Data Transmission with Distribution Line Carrier (DLC) Sample project: MEA Bangkok/Thailand

  • Page 120 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    BusinessServices

    IT Integration

    ASP

    Administration

    Operation

    E-Commerce

    Maintenance

    Field data acquisition,local control & automation

    Communication

    Network control &supervision (single-or multi-utility)

    Added value network management & optimization(applications and systems)

    Integrated utility business operation

    xxxx x xxx xxx xx

    MetersSubstation automation

    ProtectionLocal automation

    RTUs

    PowerExchange

    $$TraderPartner, market, etc.

    Multi-site

    SCADAetc.DB

    Networkplanning

    Networkinformation

    Meter datamanagement

    ...Advanced applications

    (EMS, DMS, EBM, Trading)

    Informationgateway

    ...Asset

    ManagementEnergy Sales

    & Care

    Enterprise Integration Bus

    Data Warehouse

    MISF&A

    Gateway

    Power Systems Control and Energy Management Multi-Level Environment

    Private & public networks

  • Page 121 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Basic SCADA/EMS/DMS System Architecture

    DWOperational

    Database

    Transmission

    NA

    Distribution

    DMS

    DSM

    Generation

    PA

    SARO

    DW EA

    ELCOM

    ICCP DTS

    DWORACLE

    Interfaces

    FrontEnd

    BASE SCADA

    HIS SDM

    Base

    Interfaces

  • Page 122 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sample SCADA/EMS/DMS Modularity

    SCADASCADA

    UIUI

    FAFA

    DSMDSM

    PAPA

    BaseBase

    IS&RIS&R

    MultiBCK

    MultiBCK

    OAOA

    TSTS

    CFECFE

    GEIGEI

    ElcomElcom

    DataData

    DNADNA

    GISGIS

    LTOPLTOP

    GSAGSA

    TNATNA

    EMMEMM

    SDTSDT

    IndCIndC

    ICCPICCP

    MultiBck Multisite/Backup SystemBase Base SystemCFE Communication Front EndData Data EngineeringDNA Distribution Network ApplicationsDSM Demand Side ManagementELCOM Electricity Utilities CommunicationEMM Energy Market ManagementFA Forecasting ApplicationsGEI General External InterfaceGIS Interface to GISGSA Generation Scheduling Applications ICCP Inter Control Center Protocol IndC Industrial Communication IS&R Information Storage & RetrievalLTOP Long-Term Operation PlanningOA Operational ApplicationsPA Power ApplicationsSCADA Supervisory Control & Data AcquisitionSDT Software Development ToolsTNA Transmission Network ApplicationsTS Training System and SimulationUI User Interface & Operator Support

    Transmission

    Distribution

    Generation

    SCADA

  • Page 123 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Advantages of SCADA-integrated DMS Applications (I)

    There are solutions available rather where a separate DMS software is linked to the SCADA system. Integrated DMS applications, however, means software components that have been designed and implemented to form an integrated solution together with the SCADA base system.

    This provides benefits to the user: Applications obtain current loading/switching states from SCADA Applications are triggered by SCADA (periodically, on event) Switching procedures determined by applications are automatically,

    fast and securely executed via the SCADA system Closed-loop applications possible (e.g. VVC)

  • Page 124 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Advantages of SCADA-integrated DMS Applications (II)

    There are solutions available rather where a separate DMS software is linked to the SCADA system. Integrated DMS applications, however, means software components that have been designed and implemented to form an integrated solution together with the SCADA base system.

    This provides benefits to the user: same user interface - less training effort, staff is productive earlier same system base - no extra cost for dealing with another system base same data model - less effort for data maintenance common database - operator sees consistent values in SCADA and

    applications, operators have trust in the applications, operators actually use the applications and realize their benefits common system environment - applications are easy to use, operators

    actually use the applications and realize their benefits

  • Page 125 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System ConfigurationNon-Redundant All-In-One System

    UI : User InterfaceRTS : Real Time Server (SCADA)CFE : Communication Front-EndPSOS : Power System Object Server (Data Model)AAS : Advanced Application ServerWeb TS : Web Terminal Server

  • Page 126 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System ConfigurationNon-Redundant All-In-One System w/- external UI Clients

    UI : User InterfaceRTS : Real Time Server (SCADA)CFE : Communication Front-EndPSOS : Power System Object Server (Data Model)AAS : Advanced Application ServerWeb TS : Web Terminal Server

  • Page 127 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System ConfigurationNon-Redundant Dual-Server System

    UI : User InterfaceRTS : Real Time Server (SCADA)CFE : Communication Front-EndPSOS : Power System Object Server (Data Model)AAS : Advanced Application ServerWeb TS : Web Terminal Server

  • Page 128 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System ConfigurationRedundant Multi-Server System

    UI : User InterfaceRTS : Real Time Server (SCADA)CFE : Communication Front-EndPSOS : Power System Object Server (Data Model)AAS : Advanced Application ServerWeb TS : Web Terminal Server

  • Page 129 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Legend:MMI Man-Machine-InterfaceIM/AC Information ManagementISR Information Storage & RetrievalFE Front End DMS Distribution Management SystemRTU Remote Terminal UnitGPS Global Positioning System

    SCADA-DMS LAN

    IM / ISRServerIM / ISR

    Server

    Support

    Router /Modem

    ICCPServerICCP

    Server

    SCADA-DMSServerSCADA-DMS

    Server

    Support

    2 x Laser printer b/w

    Laser printer color

    Support

    GPS Time system

    WebServer

    Firewall

    m-Term

    Operation

    Rear projection Walls

    84

    Operation

    m-Term

    84

    Corporate Network

    to PDSFront-end

    ServerFront-endServer

    RTURTURTURTUSerialinterfacesSerial

    interfacesPrimary

    Substations

    Ultimately:IEC 60 870-5-104

    Initially:IEC 60870-5-101

    to Bckp

    Integration Solution for GIS Interface

    SAPGIS AMR

  • Page 130 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Legend:MMI Man-Machine-InterfaceIM/AC Information ManagementISR Information Storage & RetrievalFE Front End DMS Distribution Management SystemRTU Remote Terminal UnitGPS Global Positioning System

    SCADA-DMS LAN

    IM / ISRServerIM / ISR

    Server

    Support

    Router /Modem

    ICCPServerICCP

    Server

    SCADA-DMSServerSCADA-DMS

    Server

    Support

    2 x Laser printer b/w

    Laser printer color

    Support

    GPS Time system

    WebServer

    Firewall

    m-Term

    Operation

    Rear projection Walls

    84

    Operation

    m-Term

    84

    Corporate Network

    to PDSFront-end

    ServerFront-endServer

    RTURTURTURTUSerialinterfacesSerial

    interfacesPrimary

    Substations

    Ultimately:IEC 60 870-5-104

    Initially:IEC 60870-5-101

    to Bckp

    Integration Solution for SAP Interface

    SAPGIS AMR

  • Page 131 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Legend:MMI Man-Machine-InterfaceIM/AC Information ManagementISR Information Storage & RetrievalFE Front End DMS Distribution Management SystemRTU Remote Terminal UnitGPS Global Positioning System

    SCADA-DMS LAN

    redundant

    IM / ISRServerIM / ISR

    Server

    Support

    Router /Modem

    ICCPServerICCP

    Server

    SCADA-DMSServerSCADA-DMS

    Server

    Support

    2 x Laser printer b/w

    Laser printer color

    Support

    GPS Time system

    WebServer

    Firewall

    m-Term

    Operation

    Rear projection Walls

    84

    Operation

    m-Term

    84

    Corporate Network

    to PDSFront-end

    ServerFront-endServer

    RTURTURTURTUSerialinterfacesSerial

    interfacesPrimary

    Substations

    Ultimately:IEC 60 870-5-104

    Initially:IEC 60870-5-101

    to Bckp

    Integration Solution for AMR Interface

    SAPGIS AMR

    Meter

  • Page 132 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Possible control center structural configurations

    MCC

    CC 1 CC 2

    Independent CCs with different software configuration

    CC 1

    CC 2 CC 3

    Independent CCs with different software configuration and data exchange over ICCP with CC1

    CC 1

    CC 2 CC 3

    Dependent CCs in Multi-Site configuration, with centralized database maintenance and data

    exchange

    ??

  • Page 133 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Multisite Operation of Control Centers

    Multiple Control Centers in a hierarchical and/or equal-rank configuration can cooperatively manage a power system.

    Multisite keeps statuses and values in the process images of the Control Centers up-to-date with statuses and values from other Control Centers and distributes supervisory control commands, manual updates, tagging and alarm acknowledgments.

  • Page 134 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Multisite Operation of Control CentersFeatures

    Exchange of information between Control Centers Uniform data model and central data management, i.e.

    reduced maintenance effort Controlling the network from different Control Centers Increased availability Compensation of communication failures (i.e. automatic

    transmission of missing data after return of the connection)

    Possibility of delegating operator tasks permanently or during periods where Control Centers are un-staffed or understaffed

    Provision of backup or emergency systems Simple and fast design of emergency and system

    management concepts as well as straightforward implementation (configurability)

  • Page 135 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    The Multisite concept allows connecting two or more control centers to a Multisite network. Hierarchical or equal-rank configurations and also combinations of them are possible. Each control center is autonomous and independent in the Multisite network.

    The control centers can have different hardware combinations anddifferent data. The hardware configuration of one system is not visible to the software system of other control centers, i.e. each control center is regarded as a unit by all other control centers.

    All control centers are connected to each other via LAN/WAN links. The control centers communicate with each other via TCP/IP.

    Multisite Operation of Control CentersBasic Concept

  • Page 136 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Control Center RedundancyMultisite features enable control center redundancy, if the information areas of the control centers are defined with an appropriate large overlapping. Two control centers can share theoperation control tasks for the same area.

    Multisite features enable the configuration of an emergencysystem. For this aim, identical information areas are assigned to both control centers. The hardware configuration and functions need not be identical.

    Delegation of Operation Control TaskThe operation control task can be moved between the control centers at request of the operator. This allows operating a control center unmanned during periods when management requirements are low e.g. during night time.

    Multisite Operation of Control CentersBasic Concept

  • Page 137 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Multisite Operation of Control CentersHierarchical Configuration

    MainControl Center

    MainControl Center

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    RegionalControl Center

    RegionalControl Center

    RegionalControl Center

    RegionalControl Center

    RegionalControl Center

    RegionalControl Center

  • Page 138 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Multisite Operation of Control CentersMain/Backup Configuration

    MainControl Center

    MainControl Center

    BackupControl Center

    BackupControl Center

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

    Information Network

    (RTUs, ICCP, ...)

  • Page 139 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Sample Main/Backup Configuration

    Independent (dual port) communication between RTU and Main/Bckp The Multisite backup concept allows data entry once for both locations Main and Backup are redundant and self-contained Fully automatic update of databases at both locations

    Main PC SB BckpPC SB

    Port 1 Port 2

    RTU

    Backup CC LinkFO Link > 2 MBps

    Initially: IEC 101Ultimately: IEC 104 via FO

    Primary Substations

  • Page 140 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Normal operation: Port 1 sends to/receives from Main Port 2 sends to Backup Backup is continuously updated from Main (operator entered data) Backup is ready for take-over at any instant of time without any human interaction

    Main PC SB BckpPC SB

    Port 1 Port 2

    RTU

    Backup CC LinkFO Link > 2 MBps

    Initially: IEC 101Ultimately: IEC 104 via FO

    Primary Substations

    Sample Main/Backup Configuration

  • Page 141 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Disturbed operation: Server fault at ECS standby server at ECS takes over, no other changes, completely

    transparent to operator

    Fault of communication link to ECS data to /from the affected RTU goes via the Backup CC Link and BCS, no other changes, completely transparent to operator

    All servers down at ECS (i.e. incl. spares !) operator at ECS can immediately connect his/her workstation to BCS or operation is performed from BCS

    Main PC SB BckpPC SB

    Port 1 Port 2

    RTU

    Backup CC LinkFO Link > 2 MBps

    Initially: IEC 101Ultimately: IEC 104 via FO

    Primary Substations

    PC PC

    Sample Main/Backup Configuration

  • Page 142 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System SecurityIT Trends for SCADA/EMS/DMS

  • Page 143 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System SecurityThread Analysis

  • Page 144 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System SecurityThread Analysis Potential Attackers

  • Page 145 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System SecurityThread Analysis Sample Attacks & Countermeasures

  • Page 146 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System Security Multi Level Security Concept

    Interconnection(e.g. to other utilityComputer networks,Internet, etc.)

    User access to systemfunctionality (none,

    view, modify)

    Logging(audit records)

    User access rights for

    controlling the accessto the IMM data model

    UserAuthorization

    by login

  • Page 147 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System Security Typical Secure Network Setup

    (*) Support TLS/SSL/PKI Security for ICCP Communications

    (*)

  • Page 148 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    System SecuritySample System Integrity and Confidentiality Methods

    Adding, deleting and modifying user profiles with an O/S User Administration application of the SCADA/DMS database management system

    Assigning of user roles to users Runtime verification of user authorities Assigning of Areas of Responsibility to users Restricted access by outside parties and security protection against unauthorized

    attempts to procure internal passwords

    Mechanisms for data authentication to ensure data integrity (complete and unmodified data) and data privacy

    Networking and internet security settings, turning off of unnecessary network services All user logon/ logoff activities are logged in the System Alarm Summary list Automatic user logoff with configurable timer (configurable) Password security, including encryption of transmitted and stored passwords Administrator security measures that include enabling account lockout methods,

    renaming the account, establishing separate accounts for multiple administrators, setting up an administrator password control process and configuring of administrator access with critical but limited privileges.

  • Page 149 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Distribution Automation projects are multi-part/multi-technology

    Bulk Data Management SystemsGeographical Information Systems (GIS), Automatic Meter Reading (AMR) systems, etc.

    SCADA/DMS Control CenterSevers, consoles, large screen projections, etc.

    Communication EquipmentPower Line Carrier, Radio, GSM, etc.

    Substation EquipmentMeters, Remote Terminal Units, Motorized Switchgear, etc.

    NS

    Distribution-Substation

    MV MV MV

    HV

    Cable Overhead-Line

    R

    R S

    R

    R

    R

    Tn.o.

  • Page 150 Jan 2008

    Siemens AG 2008Power Transmission and DistributionDr. Roland Eichler

    Distribution Automation projects callfor particular vendor qualifications

    9DA systems must be designed as a whole, parts must fit together (interfaces, capacity, redundancy, ...)9DA grows over time9Must stay open to technology advances during

    implementation time

    9DA constitutes a system/solution business(as opposed to a product business)

    9Need long-term vendor stability9Need profound vendor experience in large, complex, multi-

    technology projects9Need profound vendor understanding of business processes

    in the electricity distribution bus