SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05...

8
SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007 Appendices Appendix A – Schedule of Consultation Appendix B – SCA Public Participation Program Report (dated September 2006)

Transcript of SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05...

Page 1: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

Appendices Appendix A – Schedule of Consultation Appendix B – SCA Public Participation Program Report (dated September 2006)

Page 2: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

A-1

Appendix A – Schedule of Consultation

Date Organisation Position

26-05-05 Airservices Australia Customer Relationship Manager

26-04-05 Virgin Blue Facilities Co-ordinator

Station Manager Regional & International Airport Operations

Airport Manager (Aerocare)

26-04-25 Tourism Sunshine Coast General Manager

27-04-05 Singapore Airlines Flying College Operations Administrator

Chief Pilot

27-04-05 Sunshine Coast Cabs General Manager

Director

27-04-05 Hertz Branch Manager

27-04-05 The Sunshine Coast Regional Organisation of Councils Executive Director

27-07-05 Maroochy Shire Council Acting Manager Development Assessments

Development Assessment Senior Planner

27-04-05 Aeromil

(Parent of AeroMech, Sunshine Express)

General Manager

28-04-05 Commerce Queensland Business Development Manager

28-04-05 Noosa & Maroochydore Flying Svcs Director

28-04-05 Queensland Government Senior Ranger Sunshine Coast District

Ranger in Charge Southern Region

28-04-05 Hyatt Regency Collum Transport Manager

Page 3: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

A-2

Date Organisation Position

28-04-05 McDermott Aviation

28-04-05 Aviation Ground Handling Pty Ltd (Jetstar Agent) Airport Manager – Sunshine Coast Airport

28-04-05 Maroochy Shire Council Councillor for Division 4

Deputy CEO & GM Governance

GM Finance & Corporate Services

Manager Sunshine Coast Airport (former)

Study Manager Sunshine Coast Airport

Airbiz Study Manager

Airbiz

29-04-05 Civil Aviation Safety Authority District Airport Inspector, Brisbane

29-04- 05 DOTARS Office of Transport Security Inspector

29- 04-05

Queensland Parliament

Member for Maroochydore

Shadow Minister for Transport and Main Roads

Urban Planning and Women’s Policy

02- 06- 05 Maroochy Shire Council Mayor

15-06-05 Aeromil Executive Chairman

16-06-05 Car Rental Company Reps.

16-06-05 Maroochy Shire Council

(Presentation – work in progress)

22-06-05 Sunshine Coast Airport Manager Sunshine Coast Airport (former)

Airport Property Coordinator

22-06-05 Sunshine Coast Airport Manager Sunshine Coast Airport (former)

Retail Owners

Kiosk Manager

Page 4: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

A-3

Date Organisation Position

22-07-05 Shell Aviation Project Engineer

22-07-05 Aviation Ground Handling Manager – Sunshine Coast

12-08-05 Virgin Blue Normal Position – Ramp Operations Contoller

12-08-05 Queensland Transport

15-08-05 Phoenix Air Express Managing Director

17-08-05 Freedom Air Acting Airline Services Manager

Page 5: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

B-1

Appendix B – SCA Public Participation Program Report (dated September 2006)

Page 6: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

B-2

1. EXECUTIVE SUMMARY Sunshine Coast Airport (SCA) appointed Three Plus in May 2006 to devise and implement a high level public participation program for the Preliminary Draft Master Plan (PDMP). Between June and August, a robust methodology was employed to ensure transparent and inclusive consultation and an effective, two-way communication process. The aim of the public participation program was to:

• Ensure the community was aware of the PDMP; • Inform the community about the key components and development options of the PDMP;

• Provide a range of opportunities for community feedback and input into PDMP;

• Collect and process community feedback and deliver comments to the project team for

examination and information for the final Master Plan Report. Three Plus was requested by SCA to provide a communication and consultation process that upheld the philosophy:

To inform interested parties of the Master Plan process, seek their comments on impacts of airport operation and incorporate these comments where appropriate into the preliminary draft of the Master Plan.

From the outset, community input was sought to inform the development of the PDMP. A communication plan was prepared and a variety of communication tools were developed. The consultation period began on June 15 and concluded on August 14, 2006. This date was also the deadline for public submissions. Community feedback mechanisms included email, fax, website feedback form, information flyer form, letters and public meetings. Many people also registered their feedback using proformas as supplied by various interest and community groups. In addition, a database was developed using a web-based software program, Consultation Manager, that enabled Three Plus to track and report inquiries, issues and team responses across all project interfaces, thus minimising risk while enhancing transparency and accountability. Project information was also available on the website as was a copy of the Master Plan. Communication activities included community and industry group forums, static information displays, public meetings, direct mail letters, discussions with key stakeholders and information flyers. SCA Manager Peter Pallot visited and talked to ten separate community and industry groups, held “meet the people” sessions with a display at four separate shopping centres and addressed 150 community members at public forums at the airport.

Page 7: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

B-3

A media relations campaign was also conducted resulting in print and electronic coverage. As a result of the consultation process, the top 10 community values (see below) were identified and the issues informed the development of the PDMP.

Issues Raised: 15 Jun 2006 - 14 Aug 2006

Extension of existing runway 471

Public Safety Areas (PSAs) 424

Construction of the E/W runway 411

Noise 404

Air traffic movements 336

Consultation process and timeframe 290

Relocation of airport 254

Land use strategies/planning 160

Environmental impacts 67

Airport ownership 64

In addition, specific technical issues were identified through feedback mechanisms such as input at the community and industry group meetings, letters and emails. These issues were collated and referred to the project team for further investigation and response if required. By the close of submissions on 14 August 2006, 723 submissions had been received.

Page 8: SCA Master Plan Sept 07 DRAFT V5 - Sunshine Coast Airport › wp-content › ... · 27-04-05 Singapore Airlines Flying College Operations Administrator Chief Pilot 27-04-05 Sunshine

SUNSHINE COAST AIRPORT MASTER PLAN SEPTEMBER 2007

B-4

It should be noted that several peak bodies indicated high levels of interest in the project by their members. By close of submissions on 14 August 2006, 12 submissions had been received from peak bodies – Buderim Chamber of Commerce, Coolum Chamber of Commerce, Maroochydore Chamber of Commerce, Sunshine Coast Business Council, Tourism Sunshine Coast, Coolum Beach Progress and Ratepayers Association, Coolum Ratepayers Association, Marcoola Progress Association, Twin Waters Residents Association, Maroochy Economic Development Advisory Board (MEDAB), Aviation and Regional Transport and Development Watch Inc. In summary, the robust and extensive community engagement undertaken during the PDMP process resulted in significant outcomes including a high level of community awareness, effective means of communication between community groups and the project team, considerable media coverage that increased public awareness and strong uptake by key stakeholders of opportunities provided for active participation.