SB Update on BHS June 15 2010 (2)

download SB Update on BHS June 15 2010 (2)

of 25

Transcript of SB Update on BHS June 15 2010 (2)

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    1/25

    1

    Update Blacksburg High School

    June 15, 2010

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    2/25

    2

    Background

    Since the roof collapse on Feb. 13, 2010 there has

    been continuous evaluation of BHS Building has been considered unsafe for use

    Main classroom building is being assessed by

    OWPR

    Initial report received June 7, 2010

    Report listed 711 line items 88 of the line items coded as condition 1 to be

    repaired before use of the building

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    3/25

    3

    Background

    New concern is the observed deflection in the floorand supports that does not appear to matchspecifications and drawings

    Field testing is in process to determine if existing

    construction matches drawings and specifications Field testing includes evaluation of concrete, use of

    ground penetrating radar and x-ray, and electrical

    resistivity survey Analysis should indicate if the structure as built

    will support the load of the building

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    4/25

    4

    Background

    OWPR report on the testing will not be

    available until July 1, 2010 Collapse of the gym investigated by

    FORCON

    Samples of steel trusses sent to lab for testing

    Report on concrete foundation is that it wasdamaged but can be repaired and is useable

    Report on steel trusses will not be received untilmid July

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    5/25

    5

    What Do We Know

    Recognize and appreciate the sacrifices made by families,students, staff and community since the February 13collapse of the BHS gymnasium

    Classroom building is not currently judged to be safe foruse

    OWPR report of additional findings regarding BHSclassroom building is not expected until July 1, 2010

    FORCON final report of findings regarding BHSgymnasium building will not be available until mid-July orlater

    Students designated to attend Blacksburg High Schoolneed an identified housing site no later than July 6 in orderto implement plans to occupy selected space

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    6/25

    6

    What Do We Know

    The BHS building complex totaled 240,746 squarefeet including the gym which was 13,000 square

    feet; there are no other buildings in thecommunity available to immediately andappropriately house 1200 students and staff

    Solutions may impact other grade levels inBlacksburg

    Solutions may impact other communities inMontgomery County

    No final determination has been made regardingthe amount of reimbursement for failed gymwhich MCPS will receive

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    7/25

    7

    Assumptions

    Safety is first priority in all solutions

    Designated full time space for the high school is essentialdue to the complexity of the comprehensive program,

    including academics, athletics and other extracurricularactivities

    Start the school year in a setting that we can commit to forthe 2010-2011 school year and beyond if needed

    Provide a high quality educational program for allstudents in all grade levels

    Maximize benefits for students/schools/staff while

    managing associate costs Decisions must be made about a solution for space no later

    than July 6 for the 2010-2011 school year and potentially

    longer

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    8/25

    8

    Assumptions

    Establish a separate process/plan for developing longrange plans for full reconstitution of BHS

    Expend no additional funds on repairs of existing BHS

    classroom building until after the July 1 report validatesthe appropriateness of the investment

    Maximize the available time to get all plans in place for the

    2010-2011 school year (consider a later start date; samplecalendar provided at the end of this presentation)

    Keep all stakeholders engaged and informed; publish atimeline for information and decision making

    Time is the complicating factor for implementing oursolution

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    9/25

    9

    Option 1

    Use the Blacksburg High School classroom building

    to house grades 9 12. Appropriate repairs andadditional portable space will be provided to offset

    the loss of some parts of the facility

    Note: This will be a different setting than theprevious high school as modifications in many

    areas will be required to accommodate the use of

    the building and the potential construction on the

    site

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    10/25

    10

    BHS GRADES 9-12

    SCHOOL

    GRADE

    9

    GRADE

    10

    GRADE

    11

    GRADE

    12 TOTAL

    Blacksburg High

    (capacity 1216 ) 330 284 246 257 1117

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    11/25

    11

    Option 2

    Use the Blacksburg Middle School facility to house

    grades 9 12 on a traditional schedule(Blacksburg Middle School facility will become the

    temporary high school)

    Use the Old Christiansburg Middle SchoolBuilding (OCMS) to house Blacksburg students,

    grades 6,7 and 8

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    12/25

    12

    Option 2

    SCHOOLGRADE9

    GRADE10

    GRADE11

    GRADE12 TOTAL

    Blacksburg High

    (capacity 1216) 330 284 246 257 1117

    SCHOOL

    GRADE

    6

    GRADE

    7

    GRADE

    8 TOTAL

    Old Christiansburg

    Middle

    (Blacksburg Middle)

    (capacity 775) 271 317 295 883

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    13/25

    13

    Option 3

    Use the current Blacksburg Middle School Facility

    to house grades 8 12 Establish the current Christiansburg Middle

    School (CMS) as the location for 6th and 7th

    grade students from Blacksburg on a unifiedschedule; The school will be operated as a 6 8

    school and will be run as one unified school;

    Enrollment is estimated at 1402 in grades 8 12

    on the BMS campus and 1410 on the CMS campus

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    14/25

    14

    Option 3

    SCHOOL

    GRADE

    8

    GRADE

    9

    GRADE

    10

    GRADE

    11

    GRADE

    12 TOTAL

    BHS AT BMS

    Grades 8 12(capacity 1200) 295 330 284 246 257 1412

    SCHOOL

    GRADE

    6

    GRADE

    7

    GRADE

    8 TOTAL

    Christiansburg

    Middle(capacity 1200) 256 279 287 822

    Blacksburg Middle

    (capacity 1200) 271 317 0 588

    TOTAL 1410

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    15/25

    15

    Option 4

    Use the current Blacksburg Middle School Facility

    to house grades 8 12 or 9 - 12 Establish CMS as the site for CMS and for BMS

    on a split schedule; both schools will operate as

    separate schools in the same building withdifferent schedules similar to that used by the

    BMS/BHS students and staff since February

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    16/25

    16

    Option 4

    SCHOOL

    GRADE

    6

    GRADE

    7

    GRADE

    8 TOTAL

    Blacksburg Middle

    (capacity 1200) 271 317 295 883

    Christiansburg Middle

    (capacity 1200) 256 279 287 822

    SCHOOL

    GRADE

    9

    GRADE

    10

    GRADE

    11

    GRADE

    12

    Blacksburg High

    (capacity 1200) 330 284 246 257 1117

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    17/25

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    18/25

    18

    Option 5

    SCHOOL

    GRADE

    6

    GRADE

    7

    GRADE

    8 TOTAL

    Blacksburg Middle 271 317 295 883

    Christiansburg Middle(capacity 1200) 256 279 287 822

    TOTAL

    1705

    SCHOOL

    GRADE

    9

    GRADE

    10

    GRADE

    11

    GRADE

    12

    Blacksburg High

    (capacity 1200) 330 284 246 257 1117

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    19/25

    19

    Cost Considerations

    Repairs as required by the OWPR report

    Cost of other repairs that are recommended by the OWPRreport but which can be done after the building is occupied

    Portables (how many; where; available; move and set up)

    Additional space/facilities needed to support athletics and

    physical education (competitive athletics; academicprogram practice; equipment storage; etc.)

    Additional/alternative parking areas to replace those lost

    in the gymnasium area Secure campus from future construction area

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    20/25

    20

    Cost Considerations

    Modification of space and/or provision of equipmentneeded to support the instructional program on alternative

    or shared sites for middle and high school students/staff Increase in transportation costs and time to transport

    students

    Cost to relocate special programs and offices that currentlyoccupy OCM S

    Additional manpower cost for MCPS to accomplish someof these tasks in addition to the usual summer work

    Contract for services for tasks that MCPS personnel cantcomplete within the time necessary

    Technology needs/moves/set-up

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    21/25

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    22/25

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    23/25

    23

    Timeline

    June 15, 2010 Presentation in Board work sessionJune 16, 2010 Press release

    Jun 21 - 30, 2010Community and faculty/staff informational meetings

    regarding options for 2010 2011 school year

    July 1, 2010 Estimated date of receipt of second report from OWPR

    July 6, 2010

    Board meeting: Review 7/1/10 OWPR report

    recommendations and finding with Board; consider/adopt a

    modified calendar for 2010-2011; select housing plan for

    Blacksburg Strand

    July 7, 2010Press release; Begin implementation of housing plan for

    Blacksburg Strand

    July 15, 2010 Estimated date of receipt of second report from FORCON

    July 20, 2010 Board Meeting: Review status of FORCON findings; statusof implementation of Blacksburg Strand housing plan

    August 3, 2010Board Meeting: Status on progress of all school year

    housing plans for 2010

    August 17, 2010 Board meeting: Work session discussion of long rangeplanning process for Blacksburg High School

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    24/25

    24

    Next Steps

    At the July 6 Board Meeting provide a resolution for consideration of the MCPSSchool Board requesting that the Board of Supervisors provide funding tosupport the cost of the student housing plans

    The options shared today will be used in meetings with the community

    Are there any of the options which the Board could not support

    Bring the Board a later start calendar for consideration and approval at the July6, 2010 School Board meeting

    Superintendent and staff will pursue input from stakeholders regarding possibleoptions for housing in 2010-2011 (this is not the long term solution discussionregarding Blacksburg High)

    Pursue cost estimates relative to each housing option

    At the School Board meeting on July 6 provide a recommendation for housingBlacksburg students

  • 8/7/2019 SB Update on BHS June 15 2010 (2)

    25/25

    25

    Update Blacksburg High School

    June 15, 2010