SASTT contact details · SASTT contact details: Web: President: ... Technologies has been awarded...
Transcript of SASTT contact details · SASTT contact details: Web: President: ... Technologies has been awarded...
SASTT contact details:
Web: www.sastt.org.za
President: Michael king
Tel: (021) 417 2900Fax: (021) 417 2999
E-mail: [email protected]
Honorary director: Joop van Wamelen
Tel: (012) 567 4026 Fax: 086 668 4026
E-mail: [email protected]
FOR FURTHER INFORMATION CONTACT:Tel: (011) 206 2000Fax: 086 517 8122
Email: [email protected]
JACKED PIPELINES a division of WK CONSTRUCTION (PTY)LTD
PIPE JACKING AUGER BORING
"Pioneers and leaders in South African Trenchless Technologies"
YOU ARE NEVER AN
ILLUSION IN OUR WORLD
IMIESA April 2013 49
SASTT
THE AWARD WAS presented in rec-
ognition of a contract that the com-
pany undertook for the Mandela Bay
Development Agency involving the
rehabilitation of two parallel sewers located in
the heart of Port Elizabeth’s CBD.
Trenchless Technologies’ managing
member Sam Efrat says that the ISTT
Annual Project Award is the highest
accolade available worldwide in the
trenchless technology industry and
is chosen from nominations received
from companies that are members
of the 30 ISTT-affiliated trenchless
societies across the globe.
The contract was undertaken by
Trenchless Technologies in con-
junction with Afri-Coast Consulting
Engineers, Sekisui Rib Loc Australia
(part of SPR Asia), subcontractor
Tuboseal as well as consultant Pipes
and Engineering Advice and Services.
Efrat explains that this was the sec-
ond phase of a two-phase project –
phase one was completed in 2009
Local entity receives highest accoladeSubsurface pipeline construction and rehabilitation company Trenchless Technologies has been awarded the International Society for Trenchless Technology (ISTT) 2012 Annual Project Award.
ANNUAL PROJECT AWARD
and involved the reha-
bilitation of 570 m of
450DN sewer using
SPR EX technology,
as well as 560 m of
840DN sewer using
SPR PE spiral wound
technology. The pipe-
line rehabilitation
took place concurrent
with an urban envi-
ronmental upgrad-
ing project involving
decorative paving and
resurfacing works on
the surface above the
existing pipes.
Further downstream, the 450DN and 840DN
sewers increased in capacity to 525 mm and
1 000 mm in diameter. Phase two involved
the rehabilitation of these two sewers. Efrat
explains that what made this project unique
was its location – the 525DN
sewer was located beneath one
of Port Elizabeth’s busiest and
most heavily congested streets,
Govan Mbeki Avenue. Additionally,
the 1050DN sewer was located
underneath a newly constructed
Bus Rapid Transport (BRT) lane.
Considering that the BRT and road
lanes are utilised every day, only
non-destructive trenchless tech-
niques could be employed for the
rehabilitation of these pipelines.
Efrat explains that condition
assessments were carried out on
both sewers using CCTV inspec-
tion and cutting of windows from
the sewers for physical inspection.
LEFT Phase 1: 450 cast iron pipe before cleaning
ABOVE Trenchless Technologies’ managing member Sam Efrat
BELOW Phase 1 (before): 840 concrete sewer with deep sill worn away at pipe base
50 IMIESA April 2013
SASTT
Our range of services include:
• Pipe Bursting
• Horizontal Directional Drilling
• Pipe Rehabilitation
• Slip Lining
• Pipe R ming
• CCTV Inspection
• Dewatering
• Industrial Pipe Cleaning
• HDPE Welding
• Deep Excavation and Shoring
• Underground Service Detection
• Close-fi t lining: COMPACT PIPE
For more information you can contact us: +27 (0)21 761 3474 F +27 (0)21 797 1151 E [email protected] www.tt-innovations.co.za
Trenchless Technology Specialists
It was ascertained that the 525DN sewer was
severely corroded around its entire circumfer-
ence due to acidic effluent with pH values
measuring as low as 3.3. The sewer’s mortar
had corroded out of the construction joints and
was no longer watertight.
Additionally, the 1050DN sewer was severely
corroded above the water line and the reinforce-
ment was exposed and corroded away at plac-
es. Particularly severe deterioration occurred
at the sides and invert of the sewer due to a
combination of corrosion and erosion along the
sections of the sewer where the fluid velocity
was high. Efrat explains that this corrosion is
typical of what occurs in a sewer downstream of
a rising main where there is an accumulation of
gas due to long retention times. He points out
that it was estimated that sections of the sewer
would collapse within 10 years.
Speaking on the technology used by
Trenchless Technologies on the project,
Efrat explains: “Altogether the project used
five different trenchless techniques: spi-
ral wound expanded to a close fit, spiral
wound in-place, ambient cured-in-place pipe
(CIPP), UV CIPP and pipe bursting. The
contract was awarded based on utilising
spiral wound technology, namely SPR EX
for the 525 sewer and SPR RO for the
1050 sewer. However, during the project
unforeseen site conditions, such as a 15 m
90-degree radius bend on the 525 pipe and
a 43 m length of 800 mm diameter pipe
was discovered where the 1 000 sewer
reduces in size, which required the intro-
duction of additional ambient cure and UV
CIPP methods. Additionally, pipe bursting of a
225DN clay lateral pipe became necessary as
a cracked and leaking lateral 225DN clay pipe
was preventing plugging and over-pumping at a
critical manhole.”
Efrat adds that the
wide range of tech-
nologies used on this
project allowed for
a complete ‘no-dig’
solution that enabled
rehabilitation to take
place entirely through
access chambers.
What’s more, the solu-
tion was design-com-
pliant and the risk was
lower as the entire
process could be
reversed in the event
of unforeseen problems. With CIPP, once the
liner cures, it is extremely difficult to remove
in the event of a failure, whereas with spiral
wound it is far easier to remove your liner if you
have a failure, thus your risk is lower.
Despite the challenges encountered, the
combined team managed to pull off the suc-
cessful rehabilitation of the two sewer pipe-
lines without any disruptions to traffic or the
public. “This project is an excellent example
of using trenchless technology options to
address unanticipated site conditions allow-
ing the project to be completed success-
fully without excavation and site disruption,”
maintains Efrat.
LEFT Phase 1: 450 cast iron pipe after cleaning
BELOW Phase 1 (after): 840 concrete pipe after relining with Rib Loc Ribline
IMIESA April 2013 51
SASTT
THE PROJECT INVOLVED the instal-
lation of four ducks of 110 mm in
diameter over a distance of 130 m
through solid rock, crossing under N1
in Centurion and under the very active Gautrain
rail lines. “Several companies had failed and
the project had been waiting for a year or
two for the right contractor,” says Robert
‘Chico’ Garcia, JCS Pipeline’s operations and
horizontal directional drilling (HDD) manager,
adding that the evidence of previous contrac-
tors’ attempts to get all the way across were
cleary visible.
Challenging conditionsThe biggest challenge on-site was the hard
rock. “South Africa has some of the hardest
rock in the world,” says Garcia. The majority
of the bore was solid rock, tested at over
300 MPa. The continuous traffic on the N1
was also challenging, according to Garcia,
as well as the fact that the drilling had to
cross under the tracks of the Gautrain line.
“All of these are very different obstacles that
not everybody can overcome, but we did,”
states Garcia.
The equipment of choice in this challeng-
ing context was a downhole hammer sup-
plied by Vermeer’s alliance partner Pioneer,
on a Vermeer D130 x 150 drill rig, which
Craig Burnie, MD at Vermeer Equipment
Suppliers, says was sourced from Vermeer’s
Beijing Factory. The rig itself was designed for
large-diameter HDD projects and, according to
Burnie, has “the features and power needed
for demanding job site conditions”.
In addition, the open-top vice increases vis-
ibility for the operator and offers the ability to
set large tooling in the vice with ease.
The hammer in this case was used to trav-
erse the approximately 130 m of solid sub-
surface rock, after the initial hole was opened
to a diameter as prescribed by the consulting
engineers. “Using the hammer was Step 1 –
the hammer is only 160 mm in diameter – but
it allowed us to get all the way across, which
then allowed us to proceed with the rest of the
project,” explains Garcia.
The entire drilling process took only 15 days
for Garcia and his team from JCS Pipelines,
with the pilot bore itself done in only a couple
of days. Several days were required for a size-
able single jump to the final 355 mm hole
opener (rock reamer). “The hammer and rig
worked very well in the South African condi-
tions,” adds Garcia.
Training essential“Not many people have the experience to use
the hammer and the related equipment. This
takes a lot of specialised skill,” warns Garcia,
adding that the hammer and rig that Vermeer
supplied were supported by training from a
Pioneer specialist from the US, with Vermeer‘s
assistance, who showed Garcia and his team
exactly what the hammer and rig were capable
of. This allowed the already highly skilled team
to push the equipment to the limits of its capa-
bilities on-site in order to deliver on time and
according to exacting specifications.
“I was very impressed with the team from
Vermeer. They always give us outstanding
service and their aftersales service is also
excellent,” concludes Garcia.
Downhole drilling successA recent drilling project crossing under the N1 in Centurion, near the active Gautrain high speed rail, proved tricky until the right contractor for the job, armed with the right equipment, managed a breakthrough.
The entire drilling process on-site took only 15 days
HORIZONTAL DIRECTIONAL DRILLING
SASTT
IMIESA April 2013 55
Trenchless versus traditional
Trenchless technology is recognised as environmentally and sociably acceptable
COMPARING COSTS
THE POTENTIAL USE and application
of trenchless technology in rehabili-
tation or renewal of water services
in Australasia is staggering, with an
This article compares costs and discusses the factors that impact a project and the environment and society that should be considered when selecting the appropriate pipeline construction methodology.By Steve Apeldoorn: Australasian Society for Trenchless Technology
estimated 96 000 km of sewer and
sewer pressure mains approaching or
exceeding their design life. This situa-
tion is akin to other western nations;
56 IMIESA April 2013
SASTT
• GRUNDOMAT soil displacement hammers for pipes up to ND 150 - extremely precise due reciprocating chisel head.
• GRUNDORAM ramming machines for steel pipes up to ND 4000 - also applicable vertically for ramming sheet piles.
• GRUNDOBURST static pipe bursting systems for the replacement of pipes up to ND 1000
• GRUNDODRILL HDD systems for steerable bores up to ND 600 - with percussive hammer for stony soils.
• FÖCKERSPERGER PIPE AND CABLE PLOWS - for trenchlessly plowing in pipes up to OD 225 and cables in open terrain.
• PRIME DRILLING - Midi & Maxi HDD rigs for pipes up to 1400 mm.
ALL THIS AND MORE ONLY FROM TT.ALL THIS AND MORE ONLY FROM TT.
TT sales partner in South Africa: Reef Trenchless Technology SA (Pty) Ltd · 19 Shamrock Road, Primrose, P. O. Box 2168 · Primrose 1416 · South Africa Phone: +27 (0)11 828 2397 · 828 5782 · Fax +27 (0)11 828 7981 · E-Mail: [email protected] · www.reeftrenchless.com
the American Society of Civil Engineers (ASCE)
estimated that it would cost US$1.3 trillion
(R12.04 trillion) over the next five years to
maintain current underground infrastructure
systems (R Mohammed et al. Oct 2008).
Growth in the use of trenchless technologies
comes as communities become more aware
of the impact of infrastructure development
and renewals on our social and ecological
environments, and as the ageing pipelines
in our built up and congested urban areas
require replacement. Trenchless technology is
recognised as an environmentally and socially
acceptable method of construction, particu-
larly in comparison with traditional open exca-
vation alternatives, but comparing the costs
between trenchless and open cut methodolo-
gies on a dollar to dollar basis can be difficult
and inaccurate when we consider the total
cost to the community. The amount of money
paid for installation or renewal of water and
wastewater pipelines by local authorities does
not represent the total cost to society, broader
consideration of all costs – both project and
social costs – should be given when selecting
the best method for constructing or renewing
piped infrastructure.
Trenchless technology eliminates disruption of services
The question: “What is the cost of trenchless
construction or renewal projects relative to
conventional open-cut methods?” is the most
frequently raised question by potential trench-
less users, but unfortunately it is also the most
difficult to answer.
The cost of both open-cut and trenchless
methodologies is affected by many factors,
such as the location of the pipeline, its depth,
size and also the local availability of the various
trenchless technology methodologies. The cost
of a pipeline construction or renewal project
can be divided into several components. The
costs fall broadly into the costs paid by the
utility as direct and indirect construction costs,
and those paid for by society at large, termed
social costs, that are a result of the project
being undertaken.
The direct and indirect costs are those most
often associated with the “project costs” or
“construction costs”, which are usually relatively
straightforward to estimate using standard esti-
mating methods and are greatly represented
proportionally by the construction cost fees ten-
dered by contractors. The cost of any particular
rehabilitation or renewal method, open-cut or
trenchless method varies significantly dependant
on the site conditions.
The variability of costs and uncertainty of
what cost items are included or not included in
project estimates, makes comparing the cost
between open-cut and trenchless methods dif-
ficult and there is little recent published data
available. A published case study in 2008
compared the potential cost of open excava-
tion versus pipe bursting to replace the sewer
network in the City of Troy in Michigan, US, con-
cluded that the trenchless method of renewal if
implemented would be 25% less expensive than
open excavation (R. Mohammed et al. 2008).
The study had a number of caveats and areas
for further research: sewer laterals and lateral
connections had not been considered as part
of the comparison study, nor had the possible
effects of ground condition variability.
Approximately 70% of the cost of open exca-
vation construction is simply excavating and
replacing the ground dug up during the process
(R. Mohammed et al. 2008). However, it does
not always necessarily translate that trenchless
technology is one third the cost of open excava-
tion. In some cases the cost of construction
using trenchless technology exceeds that of
open excavation particularly in greenfield and
shallow conditions. Trenchless technologies do,
however, have a tendency to become better
priced than the open-cut options in higher density
urban areas where access, traffic control and the
cost of reinstatement of surfaces become more
expensive per meter
of pipe and where pipe
depths are greater
requiring expensive
shoring and sig-
nificant increases in
excavation resources.
In the paper
“ M i n i m i z i n g
Environmental Impact
through Trenchless
C o n s t r u c t i o n ”
(Ariaratnam et al.
2008), it was also
concluded in the
case study that the
expected reduction
in greenhouse gas
emissions by use of
horizontal directional
drilling (HDD) was
around 97%.
Another important
social cost factor
that should also be
considered in a com-
parison is the visual
impact on the envi-
ronment. Trenchless
technology projects
have a far smaller
Trenchless technology can be up to 25% less expensive than open excavation
SASTT
IMIESA April 2013 57
impact on the project zone, not only reducing
the disruption that may be caused but also the
stress and effect on the lifestyle of the inhabit-
ing community, particularly during large and long
duration projects.