    1. If you have released Prdn order today and it had gone to shop floor. Next day it was found that there is shortage of material. What will you?

    Do availability check. You will get missing parts list. Procure those missingparts. Then confirm the production order. One more thing you can do, change customize setting so that user cannot release if parts are missing during order release.

    4. What are all the settings done for configuring integration of PP with FICO?Assigning of Cost center to work center. Assigning Activity type to work center,Standard Cost estimate, Costing Run, Order settlement, Product costing.

    5. How to exclude storage location from MRP Excluded storage location by OMIR by defining storage location SCRP & Put theMRP ind. as 1.

    1. Can MRP be carried out for one particular level of a bom ( Level code : 0001/0002 etc).

    Yes it can be done by running for specific materials (Single Material SingleLevel)

    2 How Requiements( PIR,Sles Order, Customer Requirement) are reduced after they are produced?

    Reqmts are reduced automatically after Delivery is made to the Particular Or

    der (In case of Strategy 11, the PIRs are consumed after the GR for Production Order)

    3. Can't one material be assigned to more than one operation in a routing?One material from a BOM CANNOT be assigned to different Operations.It can be done by defining the material for so many times as required in the

    BOM

    4. How to insert an inspection checkpoint at the end of an operation?If in process sample is to be defined, assign inspection type 03 in the Mate

    rial Master.Then create MICs and assign them in the Routings.

    System automatically generates the Inspection Lots

    5. Where we have to specify the teardown time in one operation?Teardown time can be defined as one of the Standard Parameters...

    6. How the process time is calculated in a WC when both labour, Machine categories exist?

    Scheduling is done based on the Capacity Category we define in the Workcenter

    7. How to create opbject dependencies in a BOM FOR A CONFIGURABLE MATERIAL?Go to Extras -> Object Dependency -> AssignFor this U need to create Characteristics and Class (of Class Type 300) earl

    ier

    8. Can any body explain me why work scheduling view is required for semi finished and finished products?

    (Because we'll mention all details in MRP views)A) We need to maintain working scheduling view in order to make that finished orsemi finished goods available for

    production as we assign production scheduler and production scheduler profile in this view, if not maintained

    conversion of planned order to production will not be possible.

  • 8/12/2019 SAP Production Planning Question Answers

    2/2

    1:: Can we create Production order without bom and routing?yes we can create a production order without BOM & routing. Change the Config inOPL8 ( order type dependent parameters)as routing optional. But it may ask for a sales order when we try to create order using CO01.

    3:: If there are some errors in goods movements, and less stock of material consumed, how can i solve that problem in SAP?According to me COGI is basically a SAP standardised system which will tell youthat what is the error in some cases itcan rectify it too. But if the entry is done manually by MB1A, MB1B, MB1C you have to bring back or cancell the movement or move thestock to desired material and then refresh COGI.