SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 (C_TSCM42_64): C-TSCM42-64 Exam 1. The company you advise wants to carry out the material availability check automatically in the production order at various points in time. Which of the following options would you recommend? (Choose two.) A. Goods receipt for the product produced with the order B . Creation of the production order C. Confirmation of the operation that the materials being checked are assigned to D . Release of the production order E. Goods receipt for a missing part 2. What repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate Run Schedule Quantities (RSQ) from normal planned orders? (Choose three.) A . Automatic selection of the production version in material requirements planning (MRP) using Selection Methods setting. B . Manual assignment of planned production quantities in a planning table. C. Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP). D. Using a planning algorithm from capacity planning. E. Selecting a suitable repetitive manufacturing profile that contains an option for automatic line selection. 3. Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.) A . Reorder point planned materials can be included in long-term planning. 1

description

certified exam

Transcript of Sap c tscm42-64

SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 (C_TSCM42_64): C-TSCM42-64 Exam

1. The company you advise wants to carry out the material availability check automatically in theproduction order at various points in time. Which of the following options would you recommend?(Choose two.)A. Goods receipt for the product produced with the orderB . Creation of the production orderC. Confirmation of the operation that the materials being checked are assigned toD . Release of the production orderE. Goods receipt for a missing part 

2. What repetitive manufacturing options can you use to carry out line loading in the SAP ECCsystem and thus generate Run Schedule Quantities (RSQ) from normal planned orders?(Choose three.)A . Automatic selection of the production version in material requirements planning (MRP) usingSelection Methods setting.B . Manual assignment of planned production quantities in a planning table.C. Automatic selection of the production version by applying quota arrangement records inmaterial requirements planning (MRP).D. Using a planning algorithm from capacity planning.E. Selecting a suitable repetitive manufacturing profile that contains an option for automatic lineselection. 

3. Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)A . Reorder point planned materials can be included in long-term planning.B. In case of external procurement, long-term planning creates purchase requisitions.C. A planning scenario must be released to use it in long-term planning.D. Long-term planning generally is operational planning of important components. 

4. Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?A. Set Container in transportB. Set Container in processC. Set Container emptyD . Set Container full 

5. Which of the following elements do you have to prepare for costing of a production order tofunction without errors? (Choose three.)A . Assign costing variants to order type.B. Propose a standard text key in work center.C. Assign a production scheduling profile to the material master (product).

1

D . Enter formulas for costing in the work center.E . Use an operation control key with the indicator costing-relevant. 

6. In which of the following objects can you activate backflushing of components if you want to usethis functionality during order confirmation? (Choose three.)A . Work CenterB. Production Scheduling ProfileC. Material Master (Finished Product)D . RoutingE . Material Master (Component) 

7. Which of the following master data do you need to provide for process manufacturing?(Choose three.)A . ResourcesB . Master recipeC. Serial numbersD. Product cost collectorE. Production versions 

8. In your company planning strategies are used in the SAP-ECC demand management that arebased on consumption. Which of the following statements about consumption is true?(Choose two.)A. A consumption situation is dynamic and is always restructured with the planning run.B . Consumption can also take place between order reservations and planned independentrequirements, depending on the strategy.C. Consumption always takes place on the material level between the planned independentrequirements and the planned orders.D . The consumption parameters (consumption mode and consumption interval) can be set in thematerial master or in the MRP group. 

9. In production order processing, for which of the following objects can you enter a confirmation?(Choose three.)A. Work CenterB . Individual CapacityC . OrderD. Operation / SuboperationE. Trigger Point 

10. Which types of objects can be changed with Engineering Change Management?(Choose three.)A . Bill of MaterialsB. Work CenterC . Task ListD. Production VersionE . Material Master 

2

11. When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.Which planning procedure would you use to process the problem in order to create a solution thatis feasible from a requirements planning perspective?A. Multi-level single-item planning with the simulation mode optionB. Multi-level single-item planning with the display results before saving optionC. Interactive single-item planning for the delayed assemblyD. Total planning online 

12. Which of the following statements about the SAP Solution Manager listed is correct?A. Solution Manager is part of the SAP ECC System.B. Solution Manager is an add-on industry solution.C. Solution Manager is a stand-alone system that communicates with other systems in a systemlandscape.D. Solution Manager is a satellite system in a system landscape. 

13. In SAP ECC, you want to map an in-house production process for general warehouse production.The fields in the area of the lot size-dependent in-house production time are to be populated whenthe material master for the final product is created. These fields can be maintained by updatingfrom the scheduling result for the associated routing. You now think that there could be significantchanges to the production times in the routing and decide against updating the material master.What problem could this lead to?A. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.B. Requirements planning runs up against an exception message in basic dates schedulingbecause the material master parameters do not match the scheduling result from the routing.C. In the course of basic dates scheduling with requirements planning, dependent requirementsrequest the components from the bill of materials at the wrong times.D. Lead time scheduling, which occurs by the time that a planned order is converted into aproduction order (at the latest), cannot take place on the basis of incorrect basic dates. 

14. Which of the following requirements for a manufacturing plant can be supported by using process manufacturing? (Choose three.)A. Master recipe-based manufacturing.B. Material requirements planning for production resources.C. Manufacturing without orders.D. Variable calculation of material quantities (product output, material usage).E. Manufacturing in charge quantities. 

15. Which objects can you use in the production order for a material component to propose thestorage location in its reservation? (Choose three.)A. RoutingB. Work centerC. Material master (component)

3

D. Material master (product)E. Production version 

16. From what point can you no longer use the Read PP master data in the production order?A. After printing the order papers.B. After the first posting of goods movements or confirmation.C. From the release of the production order.D. After assigning the confirmed quantity of a material component due to carrying out a materialavailability check. 

17. Which options can you offer someone who uses the SAP ECC system for production orders andrequires support for material supply in production? (Choose three.)A. Automatic generation of a transport orderB. Material directoryC. Pull listD. Pick listE. Logistics Information System (LIS) 

18. When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used forscheduling? (Choose three.)A. General values from work scheduling view in the material masterB. Standard value from operation in task listC. User-defined field from operation in task listD. General operation values in task listE. General item values in bill of materials 

19. A user has entered planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a product. For the coming months, requirements with requirement type LSF(derived from the main strategy 10) have been planned. The user would like to change therequirement type from LSF to VSF planning with final assembly (in accordance with planningstrategy 40) for requirements in the production plan that have already been saved.Which of the following statements are applicable in this case? (Choose two.)A. The user has to change the requirement type for planning strategy 10 to VSF planning with finalassembly in Customizing. The requirement type for all existing requirements is then changedautomatically.B. The present requirement for the product can be changed manually from LSF to VSF in theRequirement Type field in the production plan, so that the new strategy 40 determines the nextplanning operation.C. The user can enter the new planning strategy group 40 in the material master of the product,but the requirement type is not changed automatically for existing requirements.D. The planning strategy group can be changed from 10 to 40 in the existing production plan, andthe requirement type for all requirements is changed automatically. 

4

20. Which of the following statements about the planning functions available in SAP ECC are true?(Choose two.)A. Master production scheduling (MPS) refers to preferred planning of important materials.B. Material requirements planning (MRP) does not include automatic capacity leveling.C. Long-term planning (LTP) is a long-term form of forecast planning.D. In demand management (DM) material shortage situations are identified and given requirementcoverage elements. 

C_TSCM42_64

1. Which BOM (bill of materials) selection possibilities are available for opening a production order? Note: There are two correct answers to this question.

a) Manual selection b) Automatic selection controlled with Customizing settings c) Selection by BOM number in the material master of the material to be produced d) Selection using the production scheduling profile e) Selection using a production version

2. Which statements about the reorganization of planned independent requirements in SAP ECC are true? Note: There are two correct answers to this question.

a) The reorganization only affects planned independent requirements that lie on a time axis to the past from a specified key date. b) The reorganization can be parameterized using a plant - specific reorganization interval. c) The reorganization only deletes planned independent requirements that have no fixed planned orders to them. d) The reorganization is a form of demand adjustment in which non - settled planned independent requirements for the planning are set to inactive but are not deleted.

3. Which options can you use to convert planned orders into production orders in the SAP ECC system? Note: There are three correct answers to this question.

a) Mass processing b) Automatically in the planning run (MRP) c) Background processing in a program d) Customizing for the planned order e) Order progress report

4. The company you are advising uses a plant data collection system from company XYZ and would like to distribute production orders to the terminals on this system and enter feedback using these terminals.

5

Which integration possibil ities would you recommend so that as little work as possible is required for the customer to implement this? Please choose the correct answer.

a) SAP Manufacturing Integration and Intelligence (SAP MII) b) The plant data collection interface (PP - PDC) c) Execution Steps (XSteps) d) The process control system interface PI - PCS

5. During the implementation of SAP ECC material requirements planning, the project team defines MRP controller numbers in Customizing under the entry "Define MRP Controller" that can be assigned to the planners responsible for the material. Which of the following statements are correct concerning these MRP controllers? Note: There are two correct answers to this question.

a) The MRP controller number is a central selection b) A planner responsible for a material can have multiple MRP controller numbers. c) In multilevel single - item planning, materials are selected using the MRP controller number. d) The MRP controller number is assigned using the production version.

6. In the SAP ECC system, you interpret the result of a routing schedule. When scheduling a routing in the SAP ECC system which of the following time elements are interoperation times? Note: There are two correct answers to this question.

a) Safety time b) Floats before and after production c) Processing time d) Move time

7. You enter a new BOM (Bill of Materials) in SAP ECC but forget to enter a plant reference. Which of the following statements describes what happens when you try to save it? Please choose the correct answer.

a) When saving the BOM, a group BOM is created which can, under certain conditions, be assigned to a plant later. b) When saving the BOM, a dialog box appears prompting the user to enter a plant. c) When saving the BOM, an error message appears stating that it is not possible to save a BOM without a plant reference. d) When saving the BOM, a warning message a ppears. In the corresponding dialog box, it is possible to create a plant - specific engineering BOM.

8. Which of the following organizational units does the manufacturing, planning, and execution process use? Note: There are two correct answers to this question.

a) Storage Location b) Sales Area

6

c) Purchase Organization d) Plant

9. What options does the SAP ECC system offer to retrieve the available capacity for work centers? Note: There are three correct answers to this question.

a) Attendance list b) Standard available capacity c) Shift plan d) Interval of available capacity e) Shift sequence

10. A user of the SAP ECC system wants a rolling planning time fence (firming type = 1) to be set up for a material; in other words, new planned orders are firmed within a planning time fence. When an unforeseen production failure occurs, it can happen that such firmed planned orders are not being processed because time passes. What solution would automatically delete firmed planned orders? Please choose the correct answer.

a) In the material master, an MRP type is used in which the roll - forward mechanism is activated (Customizing for requirements planning). b) The demand adjustment activated in the Customizing for demand adjustment is used. c) Firmed planned orders can only ever be deleted manually because of the header data firming.

C_TSCM42_65

1. You set a rolling planning time fence (firming type = 1) for a material in an SAP ECC system. When an unforeseen production failure occurs, firmed planned orders might fall into the past. How can these firmed planned orders be deleted automatically? Please choose the correct answer.

a) Activate demand adjustment in Customizing.b) Use an MRP type in which the roll-forward.c) Use reorganization.d) Use an MRP type in which the roll-backwards mechanism is activated.

2. You are using MRP controllers in an SAP ECC system. Which of the following statements concerning MRP controllers are correct? Note: There are 2 correct answers to this question.

a) The MRP controller is maintained in production versions.b) In multilevel single-item planning, materials are selected using the MRP controller.c) An employee responsible for the planning of materials can be assigned to multiple MRP controllers.d) The MRP controller is a central selection criterion for evaluating material requirements planning.

7

3. Which SAP NetWeaver component realizes cross-system application processes? Please choose the correct answer.

a)SAP Business Warehouse (SAP BW)b)SAP Enterprise Portal (SAP EP)c)SAP Master Data Management (SAP MDM)d)SAP Exchange Infrastructure (SAP XI) / SAP Process Integration (SAP PI)

4. How can you convert planned orders into production orders in an SAP ECC system? Note: There are 3 correct answers to this question.

a)Automatically, in the planning run (MRP)b)Set the conversion indicator in Customizing for the planned order.c)Use mass processing.d)Use the order progress report.e)Use background processing.

5. Where can you maintain available capacities in an SAP ECC system? Note: There are 2 correct answers to this question.

a)Routingb)Production supply areac)Pooled capacityd)Work center

6. You want to use production/resource tools in your manufacturing process. Which production type do you use? Please choose the correct answer.

a)Repetitive manufacturingb)Production orderc)Process orderd)KANBAN

7. When scheduling a routing in the SAP ECC system, which of the following time elements is a interoperation time? Please choose the correct answer.

a)Seftz timeb)Float before productionc)Processing timed)Setup time

8. Which statements about the reorganization of planned independent requirements in SAP ECC are true? Note: There are 2 correct answers to this question.

a) The reorganization only deletes planned independent requirements that have no fixed planned orders assigned to them.

8

b) The reorganization only affects planned independent requirements that lie on a time axis on the left side of a specified key date.c)The reorganization can be defined using a plant-specific reorganization interval.d)The reorganization is a form of demand adjustment in which non-consumed planned independent requirements are set to inactive for the planning, but not deleted.

9. Which of the following organizational units can be used for planning and manufacturing in an SAP ECC system? Note: There are 3 correct answers to this question.

a)Distribution chanalb) MRP areac) Sales aread)e)Storage location

10. Which BOM selection possibilities are available for opening a production order? Note: There are 2 correct answers to this question.

a)Selection by BOM number in the material master of the material to be producedb)Selection using a production versionc)Manual selectiond)Automatic selection controlled by Customizing settingse)Selection using the production scheduling profile

QUESTION 2 What does SAP ERP mean?  A. SAP ERP is a planning system in which extended planning processes can be mapped. B. SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on. C. SAP ERP is a technological platform, on the basis of which customer-specific extensions can be imported. D. SAP ERP is an application that an enterprise can use to manage its business processes efficiently. 

QUESTION 3 Which functions can be triggered before releasing a production order? (Choose three) A. Confirmation B. Selection of a routing C. Scheduling D. Stock determination E. Selection of a BOM

QUESTION 4 What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three) A. Availability check B. Digital signature C. Resource selection

9

D. Electronic batch record E. Approved master recipes 

QUESTION 5 Which of the following statements about consumption are correct? (Choose two) A. Consumption takes place on the material level between the planned independent requirements and the planned orders. B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group. C. Consumption is restructured with the planning run. D. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.

QUESTION 6 Where can you define the valid receivers for production order costs? A. In the valuation variant B. In the production scheduling profile C. In the settlement profile D. In the costing variant

C-TSCM42-64 Free Demo Download: http://www.pass4test.com/C-TSCM42-64.htmlNO.1 A customer has been using planning strategies 30 (production by lots) and 10 (anonymousmaketo-stock production) in SAP ECC. The customer wishes to move in part to planning strategy 40 (planning with final assembly). The issue of consumption has an effect here for the first time.Which properties apply for consumption with planning strategy 40? (Choose two.)A. Consumption can lead to an increase of the originally planned overall production quantity.B. Consumption can result in the subsequent specification and adjustment of planning elements in terms of quantity and date, by means of customer orders that arrive.C. Consumption can reduce the originally planned production quantity.D. Consumption creates a static and binding assignment, between the planned independentrequirements recorded in advance and the customer requirements that arrive, for the entireprocurement process.

SAP   C-TSCM42-64   C-TSCM42-64 pdfNO.2 Which of the following requirements for a manufacturing plant can be supported by usingprocess manufacturing? (Choose three.)A. Master recipe-based manufacturing.B. Material requirements planning for production resources.C. Manufacturing without orders.D. Variable calculation of material quantities (product output, material usage).E. Manufacturing in charge quantities.

NO.3 The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10,20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?A. Substitute sequenceB. Alternative sequence

10

C. Parallel sequenceD. Standard sequence

NO.4 The company that you advise does not want to manage certain value-intensive materials inthe warehouse stock. Instead, the user wishes to control material provision in such a way that these materials are procured directly for the production and/or process order. How can you fulfill this request? (Choose two.)A. Using the special procurement key subcontracting in the material master for the componentB. Using the special procurement key direct procurement/external procurement in the materialmaster for the componentC. Using the item type non-stock item in the bill of material for the material in questionD. Using the procurement type external procurement in the material master for the componentE. Controlling the material in question as a co-product

NO.5 Which one of the following scheduling types cannot be assigned as default to an order type(production order)?A. MidpointB. ForwardC. Only capacity requirementsD. Backward

NO.6 An enterprise based in the USA produces an end product that is used with the unit ofmeasure"pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit kilogram (KG).Which of the following solutions does SAP ECC offer?A. In the basic data customizing, you create a unit of measure group that converts pounds tokilograms. You then assign this to the material master on basic data view 1.B. You create a new material with a reference to the original material and assign the metric unit of measure to the new material master.C. In the material master, you create a conversion factor for converting pounds to kilograms onbasic data view 1.D. There is no need to take any action. There is a general conversion in the central customizing of units of measurements, so that automatic conversion of pounds to kilograms takes place.

NO.7 Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?A. Activate the availability check and assign a checking rule to the work center for the operation to be checked.B. Activate the availability check and assign the check control to the plant.C. Activate the availability check and assign an overall profile in check control for the businessfunction order release.D. Activate the availability check and assign an availability checking group to the material master for the product to be produced.

NO.8 In the SAP ECC system, a material is produced with the help of production orders. Thoughoriginally used for rate-based planning only, the planning table is to be used to plan this material.On the initial screen of the planning table, you select this material and then receive a messageinforming you that you cannot use the planning table for this material.Which one of the following reasons for this message applies?

11

A. The series production indicator has not been set.B. There is no valid production version for this material.C. There are no planned orders or production orders present.D. There are no requirements present.NO.9 The user you advise requests that you make it possible for the user to produce materials forstock,for customer orders, projects, orders and cost centers with production orders.Where can you make settings to ensure these options?A. Serial number profile.B. Settlement profile.C. Valuation variant.D. Production scheduling profile.

NO.10 Which production order function can no longer be carried out after the order is released? Read PP master data. Switching sequences. Posting a goods issue from stock to the production order. Posting a goods receipt from production to stock.

NO.11 In SAP ECC, you calculate the standard available capacity for a work center capacity with thefollowing data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization:80%, overload. 110%, number of individual capacities: 1.How large is the standard available capacity?

7 hours 8 hours 5.6 hours 6.16 hours

NO.12 A user you advise wishes to transfer variable process instructions for automated processingdirectly to certain work centers and machines in the production department (for example, feedspeed, pressing pressure, dry temperature). The user also wishes to receive variable as-ismessages (such as actual quantities, actual times) from these work centers and machines and toprocess these messages for feedback concerning production orders. Which of the followingoptions would you recommend to implement these requirements?

Execution Steps (XSteps) and process messages SAP Business Intelligence (BI) Plant data collection (PP-PDC) interface SAP Application Link Enabling (ALE)

NO.13 Which data forms the basis for calculating the capacity requirement for an operation? Standard values (routing) In-house production time (material master) 9 C. Transport time (routing) Formulas (work center) Operation control key (routing)

NO.14 A finished material is to be planned in a controlled manner in the SAP ECC system in the context of requirements planning. The planned orders are scheduled using what is known as basic date scheduling (not lead-time scheduling). Which of the following statements is true for the resulting dependent requirements? A. When a customer order is created for the finished product, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.

12

B. In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly. C. In multi-level backward scheduling, dependent requirements are triggered at the start date for the higher-level assembly planned order. D. If individual material components are explicitly assigned to operations during BOM and routing maintenance, the requirement dates of the dependent requirements for these components are scheduled at each of the operation start dates.

NO.15 An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon. What procedure would you recommend to the project team for setting the planning horizon on the system side?

A. The planning horizon is set in the MRP groups in Customizing and variant entries are assignedvia the plant parameter settings.

B. The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.

C. The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.

D. The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.

NO.16 A supply chain planning run is to be carried out in the SAP ECC system as an example. What would be the most effective sequence in which to run through the planning modules?

A. 1. Long-term planning2.Sales and Operations Planning 3. Demand management 4.Requirements planning5. Capacity planning

B. 1.Sales and Operations Planning2. Demand management 3. Long-term planning 4. Requirements planning5. Capacity planning

C. 1. Capacity planning2. Sales and OperationsPlanning 3. Demand management 4. Long-term planning5. Requirements planning

D. 1. Demand management2. Sales and Operations Planning3. Capacity planning4. Long-term planning5. Requirements planning

NO.17 Which of the following efforts can be minimized using the KANBAN procedure?A. Organizational effort to stage material B. Organizational effort for capacity planningC. Effort for master data maintenanceD. Effort for Sales and Operations Planning (SOP)

NO.18 Which information is contained in production versions for selecting routings and bills of material?

A. The plant for which the routing and BOM have to be createdB. All the control parameters for selecting routings and bills of materialC. The routing and BOM alternatives to be used for production D. The explosion date on which the validity of the routing and bill of material is checked

13

NO.19 A material was planned in the context of SAP ECC material requirements planning and the MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares the two. Which of the following statements are true for the two lists at this stage? (Choose two.)

A. The MRP list has the status "processed".B. The MRP list displays the production order.C. The stock/requirements list was updated at the precise time it was accessed. D. The stock/requirements list displays the production order.

NO.20 An enterprise wants to absorb the uncertainty caused by fluctuating demand for a finished product by means of a buffer variable in SAP ECC. They suggest a dynamic safety stock. What specifications are used to calculate the dynamic safety stock?

A. The average daily demand and the desired days supply B. The average daily demand and the safety timeC. The static safety stock per day and the safety timeD. The static safety stock and a material forecast

1.  What is the difference between a operation-related and order-related confirmation?

a)   Order confirmation is a confirmation of the entire order at order header level and an Operation confirmation allows you to confirm an order step by step.b)  Order confirmation is a confirmation of the entire order before sending to production and operation confirmation is a step by step confirmation of production orderc)   Order confirmation is partial confirmation of the order and operation confirmation is automatic final confirmation of the orderd)   Order confirmation requires a goods receipt, operation confirmation does not require a goods receipt

There are various procedures for confirmation in SAP ECC. Each procedure implements different requirements that a company may have. Depending on the application, one or more procedures may be used. The procedures must be used to selected to suit the methods of organization within your company and the allowed workload.For the most part, the two main types are operation-related and order-related confirmations. Order confirmation is a confirmation of the entire order at order header level. An operation confirmation allows you to confirm an order step by step. For this type of confirmation, there are various procedures available. You can carry out a confirmation for an order only if no confirmations have already been entered for operations.Each confirmation is entered with a status (partial confirmation, final confirmation, automatic final confirmation).Once an order has been confirmed, follow-on functions are performed. The confirmed quantity, the status RUCK and actual costs are written to the production order.When an operation is confirmed, an automatic goods issue is posted on the basis of the quantity that has been assigned the material components (backflush). These material components must be prepared for backflush posting and also be provided for use at the work center.When you confirm the last operation that must be confirmed (or for the operation where this posting is defined in the control key), an automatic goods receipt is posted.Capacity reduction is carried out either in proportion to the quantity or activity.  If a scrap or

14

rework quantity is confirmed, a quantity notification can be generated automatically.

2.   What are the options for the material staging from a warehouse management system? (more than one option is correct)

a)   Create parts are ordered manually b)   Release order parts are ordered manually c)   Pick parts are provided for the production order in exactly the same quantity as the requirements quantityd)   Release order parts are ordered automatically

For the material staging from a warehouse management system, there are three options for the production order. These options are described here:Pick parts are provided for the production order in exactly the same quantity as the requirements quantityCreate parts are ordered manually when a crate is almost empty. Typical examples are small parts in containers such as screws, nails…..Release order parts are ordered manually: The required quantity is calculated using the targe quantities of the components in the selected released orders. Typical examples are laminates, paints

3.  Consider a product scenario where there is high product stability, high repetition rates, and low product complexity. What type of manufacturing do you suggest?

a)  Mass manufacturingb)  Bulk manufacturingc)   Repetitive manufacturing d)  Order based manufacturing

To allow the material to be used in repetitive manufacturing, you set the Repetitive Mfg indicator in the material master (in the MRP view). This means that you can use the various production versions of this material for repetitive manufacturing (that is, you can set the indicator Repetitive Mfg allowed for version in the production version.)

15

The BOM defines the planned material consumption for the components. When you backflush components in repetitive manufacturing, you can define the issue storage location from which components are to be backflushed in the status/long text of the BOM item (Production storage location field).Production lines are usually created as  simple work centers in the ECC system. In the work center, you define the availability of the production line. The production line created at the work center is entered in the Production line field in the production version. This same work center is specified in the single operation of the routing. Production lines that have more than on work center can be represented in a line hierarchy.In repetitive manufacturing, the routing define the production rate (quantity per time unit) used to produce materials on production lines. The production quantities and their capacity requirements are scheduled and calculated respectively according to the production rate.The routing therefore forms the basis of lead time of scheduling. In repetitive manufacturing often have only one operation.  The total production rate of the line is specified in this operation. It define how many materials per unit can be produced on this production line. In the singe operation, you enter the production line as the work center.

4.  A distinctive feature of you company is a relatively constant consumption of materials. For this reason, you want to process the material flow to the work centers in production of your company in an event-drive manner. Is there any possibility in SAP?

a)  No this is not possibleb)   SAP-SCM KANBAN c)   SAP-SCM REPLENISHMENTd)   SAP-SCM PRODUCT STABILITYThe KANBAN procedure can be used together with all other production types.

In KANBAN, the material flow is organized using containers that are kept directly at the appropriate work centers in production. Each contains the quantity of material that work center personnel need

16

for a certain period of time. As soon as a container is emptied by the demand source, replenishment is initiated in KANBAN. The supply source of the required material can be another place in production, an external vendor or a warehouse.The demand source can use material from other containers until the actual container returns to full. The aim is to control the replenishment process in production itself and to reduce the manual posting efforts for personnel as much as possible. This self-management process and the fact that replenishment elements are created close to time they are actually consumed means that stocks are reduced and lead times are shortened (replenishment is only triggered when a material is actually required and not before).With KANBAN material is staged where it is used and is always available in small material buffers. This means that material staging does not need to be planned; instead, material that is consumed is replenished immediately using KANBAN.By using KANBAN with the SAP ECC system, you can automate the transfer of replenishment data. For example, scanning the barcode on a KANBAN card is sufficient to transfer the data required for procurement and to post the goods receipt when the material is received.

5.  What is the industry standard that uses COM/DCOM technology to define manufacturer-independent interfaces for the industrial usage area?a)  SAP COM/COM modelb)   SAP OPC c)  SAP OCOMd)  SAP OLE

SAP OPC Data Access (SAP ODA) enables the reading and writing of data points and event using the OPC server of the ECC system. These functions are also available with the production order environment.OPC stands for “OLE for Process Control and Openness, Productivity and Connectivity, and is an industry standard that uses COM/DCOM technology to define manufacturer-independent interfaces for the industrial usage area. The OPC standard was designed especially for the process control level.OPC servers enable you to access different data sources (for example, process control systems, memory programmable controls, temperature sensors) and thus provide process data which can be requested by OPC clients.SAP ECC with the component SAP ODA is an OPC server and client that can communicate with OPC servers. This considerably simplifies the data exchange between applications.  OPC servers and OPC clients are currently PC-based systems based on which Microsoft operating system runs.

6.   As a production manager how do you enable process operations parallel to and independent of other operations?a)   Parallel sequences b)  Successor relationshipsc)  Control sequencesd)   Linked sequences

The parallel sequence enables you to process operations parallel to and independent of other operations. You can copy both parallel and alternative sequence types from the routing to the order. Parallel sequences are linked to the standard sequence through predecessor/successor relationships.  Parallel sequences are a special form of overlapping operations. This gives rise to network-like structures.Order scheduling inserts operation floats according to the alignment key specifications.

17

In mechanical engineering for assemblies involving the production of individual components, inspection processes, and preparatory and closing operations.In the chemical industry for analysis processes that are carried out in parallel to the production process.

7.  What is the difference between regenerative planning and net change planning?a)   Planning all materials from the planning file, you can only plan materials for which planning file exists.b)  Planning all materials bases on demand, you plan all materials bases on previous productionc)  Planning all materials parallel, planning all materials from previous planning filed)  Planning all material online , planning is carried out as a background job

Regenerative planning means you plan all materials from the planning file. Net change planning means that you can only plan materials for which planning file exists. This means that they have undergone a change relevant to MRP within a restricted planning horizon. You can only generate planning proposals within the horizon.Planning is carried out online or as a background job.

           Creation & Conversion of Planned Order in ECC

8.  What is the report that collects all important information about a work center or a hierarchy of work centers of a shift?a)   Shift report

18

b)  Shift transfer reportc)   Transfer reportd)   Shirt work center report

The shift report is a document that is generated manually by the production scheduler once data capture for the preceding shift has been completed. The shift report is used for collecting all important information about a work center or a hierarchy of work centers of a shift. The shift report thereby facilitates shift transfer.

The shift report consists of the following parts:•        Header data and company logo•        Shift notes•        Confirmations (including activity confirmations and goods movements)•        Maintenance notifications•        Graphical evaluationsIn Customizing for the shift report, you define which information you want to be part of the shift report and which layout you want to used for the document.You cannot change the shift report manually.

9.  What is the indicator that controls whether a valuated or non-valuated goods receipt should be made and on what are the criteria that this indicator is dependent upon? (more than one option is correct)a)  The stock type indicatorb)   The GR valuation indicator c)     Material type of the product and account assignment d)   Demand and Supply

The Goods receipt indicator defines whether a goods receipt can be posted once production has been completed.The proposal for storage of goods receipt comes from material master (screen AV). The stock type indicator defines the stock to which receipts from production are to be posted. This can be the unrestricted use, blocked stock or stock in quality inspection. The indicator can be activated at different points: in the material master screen (screen AV), in a production order or at the time of goods receipt.The GR valuation indicator controls whether a valuated or non-valuated goods receipt should be made. This indicator depends on the material type of the product and the account assignment of the production order.The Delivery Completed indicator specifies whether an order is regarded as closed from the point of view of goods receipt. This means that no further goods receipt will be expected for this order.

19

10.   Settlement in product cost controller is based on? (more than one option is correct)a)     Period-oriented b)     Costs of the   product cost controller c)   Order settlementd)   No settlement rule

In product-related costs object controlling, all costs are debited and credited to a product cost controller. Individual production orders do not have cost segments or settlement rules. All functions in Production and Materials Management that are relevant to costs( material withdrawal, confirmation, goods receipt for the production order and goods receipt from production) are executed on the basis of the production order.

All controlling functions (process cost allocation, overhead allocation, WIP and variance calculation, settlement) are carried out at the end of the period on the basis of product costs collector. Thus, the relevant values are determined.The current costs for a period comprise values for:•   The material quantities delivered for the period according to the valuation control of the goods receipt.•   The unfinished product s (WIP) according to the status of the operations confirmed.•    Variances (such a scrap)•    Settlement is a period-oriented based on the costs of the product cost collector. In this case, there is no order settlement for the individual production order. In this case the production order does not have a settlement rule.•    It makes senses to use product-related COC for the following:•    Make-to-stock production•    Repetitive manufacturing and mass manufacturing•     Sales order controlling only in Profitability Analysis