Santa Cruz MeetingAugust 12th 2008
Layout options & Schedule Issues
David Lissauer
8/12/2008 1David Lissuaer, Santa Cruz
Meeting.
ID WBS Task Name
1 Linac4 project start
2 2 Linac systems
3 2.1 Source and LEBT construction, test
4 Drawings, material procurement
5 2.2 RFQ construction, test
6 2.4 Accelerating structures construction
7 Klystron prototypying
8 2.6.2 Klystrons construction
9 2.6.1 LLRF construction
10 2.7 Beam Instrumentation construction
11 2.8 Transfer line construction
12 2.9 Magnets construction
13 2.10 Power converters construction
14 5 Building and infrastructure
15 5.1 Building design and construction
16 5.2,3,4 Infrastructure installation
17 3 PS Booster systems
18 3.1 PSB injection elements construction
19 3.2 PSB beam dynamics analysis
20 4 Installation and commissioning
21 4.1 Test stand operation (3 + 10 MeV)
22 4.2 Cavities testing, conditioning
23 Cabling, waveguides installation
24 Accelerator installation
25 Klystrons, modulators installation
26 Hardware tests
27 Front-end commissioning
28 4.5 Linac accelerator commissioning
29 Transfer line commissioning
30 PSB modifications
31 4.6 PSB commissioning with Linac4
32 Start physics run with Linac4
01/01
01/05
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12007 2008 2009 2010 2011 2012 2013 2014
Milestones
End CE works: December 2010
Installation: 2011
Linac commissioning: 2012
Modifications PSB: shut-down 2012/13 (6 months)
Beam from PSB: 1rst of May 2013
LHCC – 1 July, 2008
8/12/2008 2David Lissauer, Santa Cruz
Meeting.
Construction of LP-SPL and PS2 will not interfere with the regular operation of Linac4 + PSB for physics.
Similarly, beam commissioning of LP-SPL and PS2 will take place without interference with physics.
Milestones Project proposal: June 2011 Project start: January 2012 LP-SPL commissioning: mid-2015 PS2 commissioning: mid-2016 SPS commissioning: May 2017 Beam for physics: July 20173
LHCC – 1 July, 2008
8/12/2008 3David Lissuaer, Santa Cruz
Meeting.
Normal Ramp No phase II
YearPeak Lumi
(x 1034)
Annual Integrated
(fb-1)
Total Integrated
(fb-1)Peak Lumi
(x 1034)
Annual Integrated
(fb-1)
Total Integrated
(fb-1)
2009 0.1 6 6 0.1 6 6
2010 0.2 12 18 0.2 12 18
2011 0.5 30 48 0.5 30 48
2012 1 60 108 1 60 108
2013 1.5 90 198 1.5 90 198
2014 2 120 318 2 120 318
2015 2.5 150 468 2.5 150 468
2016 3 180 648 3 180 648
2017 3 0 648 3 0 648
2018 5 300 948 3 180 828
2019 8 420 1428 3 180 1008
2020 10 540 2028 3 180 1188
2021 10 600 2628 3 180 1368
2022 10 600 3228 3 180 1548
2023 10 600 3828 3 180 1728
2024 10 600 4428 3 180 1908
2025 10 600 5028 3 180 2088
Collimation
Linac4 + IR upgrade phase 1
New injectors
+ IR upgrade phase 2
Radiation damage limit ???
8/12/2008 4David Lissuaer, Santa Cruz
Meeting.
Note: Predicted integrated Luminosity Lower than assumed.
Collimation phase 2
Linac4 + IR upgrade phase 1
New injectors
+ IR upgrade phase 2
Early operatio
n
8/12/2008 5David Lissuaer, Santa Cruz
Meeting.
Collimation phase 2
Linac4 + IR
upgrade phase 1
New injectors
+ IR upgrade phase 2
Early operatio
n
8/12/2008 6David Lissuaer, Santa Cruz
Meeting.
8/12/2008 7David Lissuaer, Santa Cruz
Meeting.
Layout (4+3+2) Fixed Length Barrel
4 Pixel Layers: 1(2) b-layers “easily replaceable” inside a support tube. 3(2) Layers incorporated in the Fixed length Barrel.
Mechanical Support: Off the tube? Off the Barrel
3 Pixel Discs on the outside.
Internal Discs?
8/12/2008 8David Lissuaer, Santa Cruz
Meeting.
Layout Overview
Barrel Length: 240 Cm (Full length) 12 sensors/side.
Discs: 5 Discs / Side. Need optimization.
8/12/2008 9David Lissuaer, Santa Cruz
Meeting.
Layout Overview (4+3+2) Fixed Length.
8/12/2008 10David Lissuaer, Santa Cruz
Meeting.
Disc Layout is still uncertain. We need to converge on a “baseline” by the time of the Nikhef meeting.
Solution with better coverage but more complicated from an Engineering point of view and more massive. - Need optimization.
Eng. Layout Studies
8/12/2008 11David Lissauer, Santa Cruz
Meeting.
Eng. Studies of the Layout.
Global Support Tube:Pixel? – Very Short strips?
Baseline Assembly Sequence
8/12/2008 12David Lissuaer, Santa Cruz
Meeting.
“Full” Assembly on the surface in “Global Tracker Tube” Barrel SS/LSPixel outer Layers (2 or 3)Pixel Discs + Pixel TubeEC LS/SS + Pixel Tube
Full test on the surface prior to installation
Insertion from the side ~ 6.5 Meter Long~1 meter Diameter
Borated Poly insertion & Services preparation on the CryostatGlobal Tube insertion from the sideServices connections
13
ATLAS UPGRADEASSEMBLY SEQUENCE OF INNER DETECTOR
C.BAULT May 15th 2008
Outer cylinder
Barrel-LS
Pixel
Barrel-SS
Pixel Services
INSERTION END-CAP NOSE + PIXEL DISCS 5-6 INTO OUTER CYLINDER
End_Cap nose
Pixel discs 5-6
Services
14
ATLAS UPGRADEASSEMBLY SEQUENCE OF INNER DETECTOR
C.BAULT May 15th 2008
Outer cylinder
Barrel-LS
Pixel
Barrel-SS
END-CAP NOSE + PIXEL DISCS 5-6 INSTALLATION OF SERVICES
End_Cap nose
Pixel discs 5-6Services
15
ATLAS UPGRADEASSEMBLY SEQUENCE OF INNER DETECTOR
C.BAULT May 15th 2008
Outer cylinder
Barrel-LS
Pixel
Barrel-SS
End_Cap nose
Pixel discs
End_Cap main bloc
with services
INSERTION MAIN BLOC OF END-CAP INTO OUTER CYLINDER
16
Atlas IT envelope layout drawing
160 Pixel Electrical Connectors
ATLAS Timeline.
LHCC will ask experiments for:
LoI Letter of Intent – Mid 2009
TP Technical Proposal - spring 2010
TDR Technical Design report / Subsystem (do not have to be at the same time)
ID – Late 2010 (early 2011)
Calorimeters - Middle of 2011
Muons - Middle / Late 2011 (Depend on upgrade scope)
178/12/2008
David Lissuaer, Santa Cruz Meeting.
8/12/2008 18David Lissuaer, Santa Cruz
Meeting.
Schedule Overview (Preliminary)
Ready for beam December ‘17
Tracker Installation February ‘17
Tracker Ready for installation (Testing) July ‘16
Barrel Installation in the Support Tube January ‘16
EC Installation in the Support Tube April ‘16
Stave installation start June ‘14
Support Structure ready for installation January ‘14Start services installation
EC Stave Production starts June ’13
Barrel Stave Assembly starts January ’13 Readout Electronics and Stave components ready for assembly at
this time.
Conclusions
8/12/2008 19David Lissuaer, Santa Cruz
Meeting.
Little feedback from Simulation to date!!We might not have significant feedback from physics analysis before final decisions will need to be made.
To stay on Schedule need to agree on a baseline (at least for the barrel) by the NIKEHF meeting.
Assembly on the surface has significant advantages. Might be the only solution that will allow installation of the detector in 18 month shut down.
Has serious schedule implications!!!Detector needs to be ready ~12-18 month earlier.