    Salaya Power ProjectEssar Energy Site Visit

    31 March 2011

    KVB ReddyExecutive Director

    Madan Gopal GuptaHead Power Business Salaya

  • 7/30/2019 Salaya Power

    2/30

    Salaya Power

    Total capacity 3120 MW ( 3 Phases )

    Phase I 1200 MW

    Phase II 1320 MW

    Phase III 600 MW

    Site selected near:

    Existing refinery

    Sea coast On Highway

    Project site area - 330 Ha

    Sea water used as cooling water

    Essars own jetty for importing coal

    17 km of coal conveyer fortransporting coal from jetty

    Power evacuation at 400 KV to stateutility

    2

  • 7/30/2019 Salaya Power

    3/30

    Plot Plan

    3

  • 7/30/2019 Salaya Power

    4/30

    Technology

    BTG technology supplier Harbin Power, China

    2 X 600 MW power plant

    Pulverized boiler

    Sub critical technology

    Sea water cooling

    Evacuation at 400 KV

    4

  • 7/30/2019 Salaya Power

    5/30

    Features

    BTG technology from proven vendor Harbin Power, China

    BOP from reputed vendors

    E-BOP Areva

    I-BOP ABB

    CW system Kirloskar Brothers

    Desalination plant IDE

    AHS - McNalley Bharat

    DM plant Thermax Ltd

    EPC Essar Projects

    Engineering Essar Engineering /TCE

    5

  • 7/30/2019 Salaya Power

    6/30

    Engineering Highlights

    Engineering is almost completed (99.7%)

    Reputed consultant (TCE) is engaged for BTG

    BOP is engineered by Essar Engineering (EESL)

    17 KM long conveyor designed in house by EESL

    6

  • 7/30/2019 Salaya Power

    7/30

    Procurement Highlights

    Overall procurement progress is 94.5 %

    All Major long delivery packages ordered to globally reputed companies &

    material is received for major packages and balance dispatches is in

    advanced stage.

    Short delivery packages are being ordered under umbrella contract to cut

    short procurement cycle

    All major equipments for BTG received from HPE

    All major BOP packages received at site

    7

  • 7/30/2019 Salaya Power

    8/30

    Construction Highlights

    Overall construction progress is 71.4 %

    Concreting 92% completed

    Structural fabrication 99% completed

    Structural erection 87% completed

    Equipment erection- 66% completed

    8

  • 7/30/2019 Salaya Power

    9/30

    Status of Commissioning Activities

    Boiler 1 hydro test completed

    DM Plant commissioned with manual operations

    Unit-1 TG Lub. oil flushing in progress

    Plant UPS commissioned

    ESP pass A air leak test completed

    Unit-1 Generator Stator and Rotor pre commissioning checks

    completed

    9

  • 7/30/2019 Salaya Power

    10/30

    Status of Commissioning Activities

    Unit-1 Turbine final box up completed

    Switchyard is ready for charging

    Boiler -2 Drum erected and 50 % Pressure parts erection completed

    Unit-1 Motor driven Boiler Feed Pump erection completed

    Chimney flue cans for unit-1 and unit-2 erection completed

    Tower crane erected and commissioned in a world record time

    10

  • 7/30/2019 Salaya Power

    11/30

    Recognition by Fine Hope

    11

  • 7/30/2019 Salaya Power

    12/30

    Salaya Power ProjectEssar Energy Site Visit

    31 March 2011

    Expansion Phase II and III

  • 7/30/2019 Salaya Power

    13/30

    Salaya Phase II: 1320 MW

    2 X 660 MW Super critical PF Boilers

    PPA signed for 800 MW with SEB

    Boiler- ordered to M/S Harbin Power, China

    T G - ordered to M/S Toshiba

    Land, water available. EPC contracts awarded

    Aviation clearance is available

    13

  • 7/30/2019 Salaya Power

    14/30

    Salaya Phase III : 600 MW

    4 X 150 MW Sub critical CFBC Boilers

    Fuel - Pet coke/Imported Coal

    Entire capacity on Merchant Power

    Main Plant Equipments are in advanced stage of ordering

    Land, water available. EPC contracts awarded

    Aviation clearance is available

    14

  • 7/30/2019 Salaya Power

    15/30

    Progress Photographs Phase I

  • 7/30/2019 Salaya Power

    16/30

    Salaya Administration Building (SAB)

    16

  • 7/30/2019 Salaya Power

    17/30

    Project Overview

    17

    CHIMNEY

    COAL CONVEYORBOILER # 2

    TG #2

    BOILER #1

    TG #1SWITCH YARD

    17

  • 7/30/2019 Salaya Power

    18/30

    DM Plant Commissioning In Progress

    ACF VESSEL FLUSHING COMPLETED

    18

  • 7/30/2019 Salaya Power

    19/30

    UPS Commissioning Completed

    19

    UPS OUTPUT MEASUREMENT IN PROGRESS AT MAIN

    CONTROL ROOM EL (12.5 ) M

    19

  • 7/30/2019 Salaya Power

    20/30

    TG #1 Erection

    20

    GENERATOR STATOR

    LP # 1 ROTOR

    LP # 2 ROTOR

    HIP ROTOR

  • 7/30/2019 Salaya Power

    21/30

    Boiler #1- Erection

    21

    BOILER #1

    SECOND PASS BOILER #1 FIRST

    PASS

    21

  • 7/30/2019 Salaya Power

    22/30

    ESP # 1 - Overview

    22

    INSULATOR

    CHAMBER

    ERECTION INPROGRESS

    INNER ROOF ERECTION IN PROGRESS (1B)

    TRANSFORMER ERECTION IN PROGRESS

    22

  • 7/30/2019 Salaya Power

    23/30

    Cooling Tower # 1A

    23

    COOLING TOWER #1A

    COMMON INTAKE CHANNEL FOR COOLING TOWER

    23

  • 7/30/2019 Salaya Power

    24/30

    Switch Yard Overview

    24

    SWITCH YARD CONTROL ROOM

    24

  • 7/30/2019 Salaya Power

    25/30

    DM Plant Overview

    25

    DM TANK #1

    DM TANK #2

    DM PLANT MCC ROOM

    MISC. PUMP HOUSE STRUCTURE

    ERECTION IN PROGRESS

    EL 0.00 M BRICKWALL

    CONSTRUCTION IN PROGRESS

    25

  • 7/30/2019 Salaya Power

    26/30

    Ash Handling System

    26

    INTERMEDIATE FLY ASH SILO

    COMPRESSOR HOUSE

    ASH WATER SUMP CIVIL WORK IN PROGRESS

    26

  • 7/30/2019 Salaya Power

    27/30

    Unit #2 Front View

    BOILER #2TG #2

    JNT #1

    TRANFORMER YARD #2

    COAL BUNKERS

    27

  • 7/30/2019 Salaya Power

    28/30

    Boiler #2 Side View

    2828

  • 7/30/2019 Salaya Power

    29/30

    ESP # 2 Erection

    29

    INSULATOR ERECTION IN

    PROGRESS

    COLLECTING PLATE ERECTION IN

    PROGRESS

    29

  • 7/30/2019 Salaya Power

    30/30

    30