Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

5
B5 The calibration of the holiday detector is checked at least twice per 8-hour shift against a calibrated voltmeter and adjusted as necessary. (SAES-H-200 Para 7.2) SAES-H-100 Para 8.2.6 B4 The dry spark tester shall be a pulse-type DC holiday detector employing an audible signaling device. (SAES-H-200 Para 7.2) SAES-H-100 Para 8.2.6 A Inspection of Dry Top Coat B3 A wet sponge Holiday tester at 67.5 volts is employed if coating thickness does not exceed 500 microns. Note: Wetting agent such as Foto flow is added to water to aid in finding holidays. SAES-H-100 Para. 8.2.6 SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER COAT - SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05 PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR Inspection of Top Coat(s) of Liquid Coating System SAIC-H-2031 1-Dec-06 EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. LAYOUT DRAWING NUMBER PLANT NO. EQUIPMENT ID NUMBER(S) FAIL N/A RE-INSP DATE MH's SPENT TRAVEL TIME QUANTITY INSP. WORK PERMIT REQUIRED? SCHEDULED INSPECTION DATE & TIME SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER CONTRACTOR INSPECTION LEVEL ACTUAL INSPECTION DATE & TIME EC / PMCC / MCC NO. REV. NO. PURCHASE ORDER NUMBER A7 SAUDI ARAMCO INSPECTION LEVEL ITEM No. ACCEPTANCE CRITERIA REFERENCE PASS SAES-H-100 Para 8.2.7 SAUDI ARAMCO USE ONLY B Requirements of Epoxy Coating Systems for Immersion service Dry Film Thickness of the total system conforms to that specified in APCS-sheets of SAES-H-101and indicated in item A1 above. ( Refer to Attachment 3 for Dry Film Thicknesses of the specified coating system) * Note: Record the measured dry film thickness in SATR-H-2006. SAES-H-100 Para 8.1.6 APCS sheets B2 All coated tanks, vessels and off shore structures in immersion service shall be holiday checked. SAES-H-100 Para 8.2.6 B1 Paint thickness within 2 m of anode connections shall be at least 30% greater than the specified minimum DFT. (Exceptions: APCS-19 & APCS-20 series) A3 Finshed coat has no evidence of coating defects such as: Runs/sags/drips/embedded foreign matter/blister/cracks/mud cracking (for Zinc Coating) and visible holidays. A1 Saudi Aramco Paint Data Sheet for the coating system (APCS) are made available on site. NOTES: Fill in the required information for Coating System: __________ Reqd. DFT: __________ SAES-H-101 Para 4.2 Dry Film Thickness gage is calibrated in accordance with SSPC PA-2. (Refer to Attachment 1, or as per the Manufacturer's instructions.) (SSPC-PA 2, Para. 4.3.1) SAES-H-100 Para 8.1.6 a A2 Finished coating have a uniform appearance. SAES-H-100, Para 8.1.6 c A6 The minimum required number of DFT measurements (spot measurements) based on coated area are taken as per the Attachment 2. (SSPC-PA 2, Sec. 5) SAES-H-100 Para 8.1.6 A4 SAES-H-100, Para 8.1.6 a A5 DFT gage calibration is performed at the beginning and end of the work. (NOTE: If gage is found to be out of calibration at the end of the work, all measurements made since the last calibration are suspect. ) * (SSPC-PA 2, Para. 4.3.3) SAES-H-100, Para 8.1.6 a Page 1 of 5

description

Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

Transcript of Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

Page 1: Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

B5

The calibration of the holiday detector is checked at least twice per

8-hour shift against a calibrated voltmeter and adjusted as necessary.

(SAES-H-200 Para 7.2)

SAES-H-100

Para 8.2.6

B4The dry spark tester shall be a pulse-type DC holiday detector

employing an audible signaling device. (SAES-H-200 Para 7.2)

SAES-H-100

Para 8.2.6

A Inspection of Dry Top Coat

B3

A wet sponge Holiday tester at 67.5 volts is employed if coating

thickness does not exceed 500 microns.

Note: Wetting agent such as Foto flow is added to water to

aid in finding holidays.

SAES-H-100

Para. 8.2.6

SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER

COAT -

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05

PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Inspection of Top Coat(s) of Liquid Coating System SAIC-H-2031 1-Dec-06

EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.

LAYOUT DRAWING NUMBER

PLANT NO.EQUIPMENT ID NUMBER(S)

FAIL N/A RE-INSP DATE

MH's SPENT TRAVEL TIMEQUANTITY INSP.

WORK PERMIT REQUIRED?

SCHEDULED INSPECTION DATE & TIME

SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER

CONTRACTOR INSPECTION LEVEL

ACTUAL INSPECTION DATE & TIME

EC / PMCC / MCC NO.REV. NO. PURCHASE ORDER NUMBER

A7

SAUDI ARAMCO INSPECTION LEVEL

ITEM

No.ACCEPTANCE CRITERIA REFERENCE PASS

SAES-H-100

Para 8.2.7

SAUDI ARAMCO USE ONLY

B Requirements of Epoxy Coating Systems for Immersion service

Dry Film Thickness of the total system conforms to that specified in

APCS-sheets of SAES-H-101and indicated in item A1 above.

( Refer to Attachment 3 for Dry Film Thicknesses of the specified

coating system)

* Note: Record the measured dry film thickness in SATR-H-2006.

SAES-H-100

Para 8.1.6

APCS sheets

B2All coated tanks, vessels and off shore structures in immersion service

shall be holiday checked.

SAES-H-100

Para 8.2.6

B1

Paint thickness within 2 m of anode connections shall be at least 30%

greater than the specified minimum DFT.

(Exceptions: APCS-19 & APCS-20 series)

A3

Finshed coat has no evidence of coating defects such as:

Runs/sags/drips/embedded foreign matter/blister/cracks/mud cracking

(for Zinc Coating) and visible holidays.

A1

Saudi Aramco Paint Data Sheet for the coating system (APCS) are

made available on site.

NOTES: Fill in the required information for

Coating System: __________

Reqd. DFT: __________

SAES-H-101

Para 4.2

Dry Film Thickness gage is calibrated in accordance with SSPC PA-2.

(Refer to Attachment 1, or as per the Manufacturer's instructions.)

(SSPC-PA 2, Para. 4.3.1)

SAES-H-100

Para 8.1.6 a

A2 Finished coating have a uniform appearance.SAES-H-100,

Para 8.1.6 c

A6

The minimum required number of DFT measurements (spot

measurements) based on coated area are taken as per the Attachment

2. (SSPC-PA 2, Sec. 5)

SAES-H-100

Para 8.1.6

A4

SAES-H-100,

Para 8.1.6 a

A5

DFT gage calibration is performed at the beginning and end of the work.

(NOTE: If gage is found to be out of calibration at the end of the work,

all measurements made since the last calibration are suspect. ) *

(SSPC-PA 2, Para. 4.3.3)

SAES-H-100,

Para 8.1.6 a

Page 1 of 5

Page 2: Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

Y = YES N = NO F = FAILED

Proponent and OthersT&I Witnessed QC Record Reviewed Work Verified

QC Supervisor

Name, Sign and Date:

Quality Record Approved:Name, Organization,

Initials and Date:

Work / Rework May Proceed

Name, Initials and Date:

T&I Witnessed QC Record Reviewed Work Verified

B6

A dry spark tester is used for holiday detection if the coating thickness

exceeds 500 microns. Holiday test voltage shall be 2400 volts +50 volts.

Note: Holiday test voltage shall be 125 volts DC per 25 micrometers of

maximum coating thickness. However, to eliminate the need for

continual adjustment, a maximum voltage of 2400 volts + 50 volts may

be used for the coating thickness range 350 to 750 micrometers. (09-

SAMSS-089)

SAES-H-100

Para. 8.2.6

B7

Functional operation of the holiday detector is checked.

Note: It is checked by making and testing an artificial holiday in the

coating (not more than 1.6 mm diameter). If the detector is working

properly, it will signal the presence of the artificial holiday.

(SAES-H-200 Para 7.2)

SAES-H-100

Para 8.2.6

B8The electrode used for locating holidays is in direct contact with the

coating (with no visible gaps).

SAES-H-100

Para 8.2.6

B9

The travel rate of the detector's electrode shall not exceed 300 mm/sec

nor shall it be allowed to remain stationary while the power is on.

(SAES-H-200, Para. 7.1)

SAES-H-100

Para 8.2.6

B10

Holiday detector is grounded directly to the equipment being tested.

Note: The ground connection shall be made by removing a small area of

coating & attaching the ground directly to the bare surface in such a

manner that electrical arcing does not occur. If the equipment itself is

grounded, it is permissible to ground holiday detector directly to the

earth. (SAES-H-200, Para. 7.3)

SAES-H-100

Para 8.2.6

PID Representative

QC Record Reviewed Work Verified

PMT Representative T&I Witnessed

Contractor / Third-Party Saudi AramcoConstruction Representative*

ATTACHMENTS:

1. SSPC PA-2, Calibration Procedure for Dry Film Thickness Gages

3. SSPC-PA 2, Req'd Number of Measurements for Thickness Spec Conformance

3. SAES-H-101V, Approved Saudi AramcoData Sheets – Paints and Coatings, (30 April, 2002)

REMARKS:

REFERENCE DOCUMENTS:

B12

Quality Control Records: Inspection and test results are recorded on

Saudi Aramco test reports for QC Documentation:

a. SATR-H-2006 " In-process Inspection Sheet"

b. SATR-H-2008 " Holiday testing "

SAES-H-100

Para 9.2.3 &

Project TIP

*Person Responsible for Completion of Quality Work / Test

2. SAES-H-101, Approved Protective Coating Systems - Primer Coat DFT Values

B11 Holidays and discontinuities detected are marked for repair.SAES-H-100

Para 8.2.6

CONTRACTOR / SUBCONTRACTOR

Inspection of Top Coat(s) of Liquid Coating System SAIC-H-2031 1-Dec-06 COAT -

PROJECT TITLE WBS / BI / JO NUMBER

SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05

REFERENCE

Name, Initials and Date:

4. Steel Structures Painting Council, SSPC-PA 2, June 1996

PASS FAIL N/A RE-INSP DATE

1. SAES-H-100, Coating Materials & ApplicationRequirements for Industrial Facilities (31 July, 2004)

Name, Initials and Date:

Performed Inspection

Name, Initials and Date:

Work is Complete and Ready for Inspection:

QC Inspector

ITEM

No.ACCEPTANCE CRITERIA

2. SAES-H-101, Approved Protective Coating Systems (31 August, 2003)

Page 2 of 5

Page 3: Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

Also, Follow specific Gauge Manufacturer Instructions

relative to Gauge Calibrations

Attachment 1 - SSPC PA-2, Calibration Procedure for Dry Film Thickness Gages

Inspection of Top Coat(s) of Liquid Coating System SAIC-H-2031 1-Dec-06

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05

COAT -

SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER

Page 4: Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

COAT -

SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER

Attachment 2 - SAES-H-101, Approved Protective Coating Systems - Primer Coat DFT Values

Inspection of Top Coat(s) of Liquid Coating System SAIC-H-2031 1-Dec-06

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05

Page 5: Saic-h-2031 Rev 2 (How to Take Dfts Per Sspc-pa2)

1-Dec-06

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 2 (Standards Cutoff - December 2005) REV 2 31-Dec-05

COAT -

SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER

DFT reqmt of APCS-26/26T is increased to 300 microns

(two coat) minimum* due to numerous premature

failures due to low DFT (below 200 microns). *Contact

CSD if there is any question. Engineering

Alert has been issued on the matter.

SINGLE COAT APPLICATIONS = UNACCEPTABLE.

Attachment 3 - SSPC-PA 2, Req'd Number of Measurements for Thickness Spec Conformance

Inspection of Top Coat(s) of Liquid Coating System SAIC-H-2031