Partnering for SuccessBuilding the Portland-Milwaukie Light Rail Transit Project
1
![Page 2: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/2.jpg)
Partnering for Success• How can partnering between transit
agencies and local government facilitate project construction beyond permitting and inspection?
• When cities contribute matching funds, how can they ensure a successful outcome of their project investment?
2
![Page 3: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/3.jpg)
A Regional Rail System
3
![Page 4: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/4.jpg)
Portland-Milwaukie Light Rail
7.3 miles10 stations
Opens September 12, 2015
4
![Page 5: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/5.jpg)
$745,200,000New Starts
$55M City of
Portland
Federal New Starts
State Lottery Bonds
Metro
ODOT
TriMet
City of Milwaukie
City of Portland
Clackamas County
Nature in Neighborhood Grant
OHSU In-Kind Property
ZRZ In-kind Property
PCC In-Kind Property
PSU In-Kind Property
Willamette Shore Line In-KindPropertyLocal Interest CostsProject costs ~$1.49 billion
Project Funding
5
![Page 6: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/6.jpg)
Building Infrastructure• Roadway Pavement• Curbs, Sidewalks, Curb Ramps• Traffic Signals• Street Lights• Water Mains• Sewers, Inlets• Stormwater Planters, Swales• Signs, Pavement Markings• Bike Lanes, Cycle Tracks, Racks• Street Trees• Roadside Landscapes
6
![Page 7: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/7.jpg)
1. Project Staffing IGAsLight rail project pays for City staff time
• Involved in decision-making
• Bring expertise to the team
• Support the project beyond basic permitting: ‘shepherd’ the project through completion
7
Traffic signal activation
![Page 8: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/8.jpg)
2. Transfer Permit AuthorityStreamlining permitting and inspections where it makes sense
Assign permit responsibilities based on type of facility regardless of underlying land:
• TriMet-owned private property
• Public right of way
8
Memorandum of Understanding
![Page 9: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/9.jpg)
3. Local BettermentsIncorporating opportunities
Link light rail construction to facilitate other projects in the City’s Capital Improvement Program
Portland Streetcar Close the Loop
9
![Page 10: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/10.jpg)
4. O&M Agreements
Understanding long-term operations and maintenance needs for all parties
• Document assumptions made during preliminary engineering
• City and TriMet maintenance staff share their practical knowledge from the field
10
Interagency Agreement Exhibits
![Page 11: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/11.jpg)
5. Embedded Staff
City staff are part of project team
• City staff, TriMet staff and Contractor co-locate in construction field office
• Facilitates communication, coordination and team-building
• Time-critical decision-making to keep the project moving
11
East Segment Field Office
![Page 12: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/12.jpg)
Partnering for Success
12
• How can partnering between transit agencies and local government facilitate project construction beyond permitting and inspection?
• When cities contribute matching funds, how can they ensure a successful outcome of their project investment?
![Page 13: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/13.jpg)
Partnering for Success
• Significant public infrastructure investment beyond the trackway
• Cities have a vested interest
• Partnering creates a collaborative spirit between agencies
13
![Page 14: RV 2014: Delivering Complex Projects: The Coordination Component by Jean Seneschal Biggs](https://reader033.fdocuments.in/reader033/viewer/2022052908/559457a41a28ab642f8b46cd/html5/thumbnails/14.jpg)
Thank you.
Jean Senechal Biggs, ASLAProject Manager