Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and...

8
Monitoring and maintenance 15 Rozelle Interchange Urban Design and Landscape Plan

Transcript of Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and...

Page 1: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

Monitoring and maintenance

15

Rozelle Interchange

Urban Design and Landscape Plan

Page 2: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

Artist’s impression: Aerial view over Rozelle Rail Yards Parklands (landscape shown at full maturity and is indicative only).

Page 3: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

Monitoring Maintenance

15—1

15 Implementation and monitoring

15.1 Timing of access, landscape and open space initiatives

Landscape installation works will occur progressively throughout the project as project areas and work sites become available.

A portion of the urban design will not be implemented by the Rozelle Interchange Project Team and will be completed in the future by Transport for New South Wales (or their delegate). This area within the Rozelle Rail Yards Parkland (refer to Section 2.10) will be utilised as a construction compound by the proposed Western Harbour Tunnel Project (subject to approval), during late construction and operational stages of the Rozelle Interchange Project. Following the completion of construction works for the proposed Western Harbour Tunnel Project this area will be rehabilitated in accordance with the design presented within this Plan. Further timing regarding this work is provided within the Environmental Impact Statement for the Western Harbour Tunnel project.

15.2 Monitoring and maintenance procedures for the built elements

Prior to the commencement of operation of the Project an Operations and Maintenance Manual will be developed which provides details procedures for the monitoring and maintenance of built elements throughout the Project. Monitoring and maintenance requirements have been summarized in Table 15-1 and will be included in detail in the Manual.

Page 4: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

15—2 | WestConnex Rozelle Interchange • Urban Design and Landscape Plan •

Table 15-22: Rozelle Interchange - Summary table of landscape and built element maintenance required

MAINTENANCE ACTIONS TASKS TIME FRAMES / FREQUENCY

Weekly Monthly Seasonal As required As specified below

Sum Aut Win Spr

CIVIL STRUCTURES INCLUDING BRIDGES, RETAINING WALLS, PRECAST PANELS AND FIXINGS ALL AREAS

1. Detailed inspections

Cursory inspection involving visual inspection, photographic documentation and reporting on the condition of major elements, e.g. girders, headstocks, abutments, linings, sour protection, embankment

Every two years

Detailed inspection involving visual inspection, photographic documentation and reporting on the condition of major elements including measurements of defects, e.g. cracks, settlement

Every two years

Evidence based inspections and testing which may include testing of materials, surveys and measurements.

Where evidence of deterioration or an anomaly is present.

2. Graffiti Inspect walls for graffiti and remove as soon as possible.

FACILITY BUILDINGS

1. Inspections Visual inspection for signs of damage including cracking, discolouration, settlement, stability, leakage, rust, defects, and termites),

2. Cleaning Cleaning of the building and fittings, including toilets, hand dryers, surfaces, air conditioning Various

3. Inspect, clean and repair

Inspect, clean and if needed repair damage to external stone paving and flooring and interlock blocksInspect clean and if needed repair damage to sand trap louversClean, inspect and if needed repair damage to external metal panels, canopy panels, joints and supportsSweep roof gutters for dust, sand and debris; check for damage, corrosion, and signs of leakage; clean gutters, downpipes, drains, outlet points and manholes 3 monthly

4. Pest and vermin control A pest and vermin control program will be developed and implemented with advice from a Pest Control Contractor As Required

FENCES

1. InspectionsInspect all posts, fence panels and fixings for signs of damage, discolouration, tension, rust; if damage is identified, maintain and/or replace to ensure the motorway facilities and the City West Link corridor is not accessible.

3 monthly

2. Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly

Page 5: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

Monitoring Maintenance

15—3

Table 15-22: Rozelle Interchange - Summary table of landscape and built element maintenance required

MAINTENANCE ACTIONS TASKS TIME FRAMES / FREQUENCY

Weekly Monthly Seasonal As required As specified below

Sum Aut Win Spr

ALL AREAS

1. Pruning of vegetation for safety Maintaining driver sightlines

Pruning trees over carriageways, roads, paths and cycleways.

2. Management of non-frangible vegetation Remove woody “non-frangible” vegetation in setbacks Once a year

3. Noxious weed control Treat noxious weeds according to control category

4. Rubbish removal Remove all roadside litter and debris. And prior to mowing

5. Mowing verge areas (applies to turf species only)

Maintain a 2m wide mown strip to the edge of all road surfaces When growth exceeds 100mm highMow grass to a maximum height of 50mm

6. Auditing and reporting Audit and report on maintenance and additional works Monthly

MULCHED MASSED PLANTING AREAS

1. Watering

Water hydromulched areas as required to germinate seed and maintain healthy growth. Ensure that a distinct level of moisture in the soil is maintained at all times and that plants do not dry out during this period.The frequency of watering may be varied during periods of adequate rainfall.

First 8 weeks after planting - 20 litres per plant

Thereafter to 26 weeks after planting – 10 litres per plant At 14 day intervals At 14 day intervals

2. WeedingWeed planting areas (manual or herbicide) before weed seed set.

Replace landscape planting damaged or killed by herbicide

3. Mulching Reapply mulch to maintain to a depth of 10cm

4. Removal of dead / dying plant material Remove dead or dying planting material and replace.

5. Replacement plantingsReplace failed plantings with specified species and densities.

Water replacement plantings as listed in item 1 As listed in item 1

6. Tree guards and stakes

Replace damaged tree guards and stakes during establishment

Remove tree guards and stakes.

12 months after planting is established as required to maintain healthy condition

Page 6: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

15—4 | WestConnex Rozelle Interchange • Urban Design and Landscape Plan •

Table 15-22: Rozelle Interchange - Summary table of landscape and built element maintenance required

MAINTENANCE ACTIONS TASKS TIME FRAMES / FREQUENCY

Weekly Monthly Seasonal As required As specified below

Sum Aut Win Spr

7. Horticultural maintenance

Fertilise all plantings at specified rates.

Prune all plantings in specified manner:

Canopy trees

Sub-canopy trees / large shrubs

Low shrubs Annually after flowering Annually After flowering Every 4 years

Climbers

Grasses and ground covers

TREE PLANTINGS

1. Watering

Water plants to maintain adequate soil moisture availability during establishment and to prevent plants from drying out:

first 8 weeks after planting - 20 litres per plant

thereafter to 26 weeks after planting – 10 litres per plant At 14 day intervals At 14 day intervals

2. WeedingWeed mulch pads to spot plantings (manual or herbicide) before weed seed set.

Replace landscape plants damaged or killed by herbicide.

3. Mulching Reapply mulch to maintain to a depth of 10cm to an area 1.0m in diameter around each plant Every 2 years

4. Removal of dead / dying plant material Remove dead or dying planting material and replace.

5. Replacement plantingsReplace failed plantings with specified species and densities.

Water replacement plantings as listed in item 1 As listed in item 1

6. Tree guards and stakesReplace damaged tree guards and stakes during establishment.

Remove tree guards and stakes. 12 months after planting

7. Horticultural maintenance

All tree management assessment and reporting activities to be undertaken by Level 5 Arborist or Arboriculturalist. Fertilise all plantings at specified rates.

As required to maintain healthy condition

Prune all plantings in specified manner:

Canopy trees

Sub-canopy trees / large shrubs

Page 7: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

Monitoring Maintenance

15—5

Table 15-22: Rozelle Interchange - Summary table of landscape and built element maintenance required

MAINTENANCE ACTIONS TASKS TIME FRAMES / FREQUENCY

Weekly Monthly Seasonal As required As specified below

Sum Aut Win Spr

TURFED AREAS

1. Watering Water turf to maintain adequate soil moisture availability during establishment and to prevent turf from drying outWater the turf immediately after laying until the underlay is moistened to its full depth. Continue watering every second day for the first fourteen (14) days, then at regular intervals until the turf is established.

Daily

ThereafterAs required until turf has taken root and is making healthy growth

2. Mowing Mow grass to a maximum height of 50mm When growthWhen growth exceeds 75mm

3. Replace damaged turf Remove damaged areas of turf and replace with new turf

4. Weed control Control weeds in turf areas using selective herbicide

PLAY AREAS AND EQUIPMENT

1. Inspections and reporting

Visual inspections to identify developing issues for safety of play equipment including wear and tear of structures, moving parts, ropes cables etc. To be undertaken in accordance with play equipment supplier general maintenance instruction.Visual inspection and maintenance log

Annual comprehensive inspection and reporting

Annually and/or in accordance with supplier general maintenance instruction.

2. Cleaning Remove soil, leaves and debris on or around equipment

3. Inspect, clean and repairInspect, clean and if needed repair damage to playground equipment

Check for broken, loose or missing parts and repair necessary in accordance with manufacturers recommendations

Page 8: Rozelle Interchange Urban Design and Landscape Plan...Maintenance Lightly oil gate mechanisms and wipe out extra oil 3 monthly Monitoring Maintenance 15—3 Table 15-22: Rozelle Interchange

This page is intentionally left blank