Roundcube Webmail __ FW_ Seal Oil Cooler Repair

2
Subject FW: Seal Oil Cooler Repair From <[email protected]> To <[email protected]> Cc <[email protected]> Date 20150614 07:58 fyi From: Long Zulkarnaen B Long Zainudin (GPU/PGB) [mailto:[email protected]] Sent: Wednesday, 10 June, 2015 4:06 PM To: MOHD @ MSSB; [email protected] Cc: Kamarulzaman B Zakaria (GPU/PGB); W M Faiz B W M Asmara (GPU/PGB); Azman B Md Hashim (POD/PGB); Lim Peng Sheng (GPU/PGB) Subject: Seal Oil Cooler Repair Dear All, Please find MOM for our kick off meeting as below. Action Item Action Party Remark PGB to provide calculation for tube expansion rate. PGB Dateline on Monday 15 June 2015 Marin Sejagat to verify Pressure test (Hydrotest) procedure at their workshop Marin Sejagat Dateline on Tuesday 16 June 2015 Leak test at site using actual product after installation Marin Sejagat Info To repair and Build up Tubesheet Marin Sejagat Info To perform cleaning of tubesheet Marin Sejagat Info To inpect grooves condition at tubesheet PGB / Marin Sejagat Info Cleaning at shell side using Waterjet and air blow Marin Sejagat Info To perform painting of tubesheet and shell flange Marin Sejagat Spec 17A To provide Sample O‐Ring PGB Dateline on Monday 15 June 2015 To provide drawing of Seal Oil Cooler PGB Dateline on Monday 15 June 2015 To Fabricate new baffle plate Marin Sejagat Info 2 holding point during work execution (witnessed and verified by PGB) 1. Material inpection and verification 2. Expansion of tubes and Hydrotest on tubes PGB / Marin Sejagat Info To confirm on material delivery and readiness Marin Sejagat Dateline on Monday 15 June 2015 To submit revised schedule and detail ITP / JMS to PGB Marin Sejagat Dateline on Tuesday 16 June 2015

description

seal oil cooler

Transcript of Roundcube Webmail __ FW_ Seal Oil Cooler Repair

Page 1: Roundcube Webmail __ FW_ Seal Oil Cooler Repair

6/14/2015 Roundcube Webmail :: FW: Seal Oil Cooler Repair

http://webmail.marinsejagat.com.my/cpsess5222810021/3rdparty/roundcube/?_task=mail&_action=print&_uid=67&_mbox=INBOX&_extwin=1 1/2

Subject FW: Seal Oil Cooler RepairFrom <[email protected]>To <[email protected]>Cc <[email protected]>Date 2015­06­14 07:58

fyi

From: Long Zulkarnaen B Long Zainudin (GPU/PGB) [mailto:[email protected]] Sent: Wednesday, 10 June, 2015 4:06 PMTo: MOHD @ MSSB; [email protected]: Kamarulzaman B Zakaria (GPU/PGB); W M Faiz B W M Asmara (GPU/PGB); Azman B Md Hashim(POD/PGB); Lim Peng Sheng (GPU/PGB)Subject: Seal Oil Cooler Repair Dear All, Please find MOM for our kick off meeting as below. Action Item Action Party RemarkPGB to provide calculation fortube expansion rate.

PGB Dateline on Monday 15 June 2015

Marin Sejagat to verify Pressuretest (Hydrotest) procedure attheir workshop

Marin Sejagat Dateline on Tuesday 16 June 2015

Leak test at site using actualproduct after installation

Marin Sejagat Info

To repair and Build up Tubesheet Marin Sejagat InfoTo perform cleaning of tubesheet Marin Sejagat InfoTo inpect grooves condition attubesheet

PGB / Marin Sejagat Info

Cleaning at shell side usingWaterjet and air blow

Marin Sejagat Info

To perform painting of tubesheetand shell flange

Marin Sejagat Spec 17A

To provide Sample O‐Ring PGB Dateline on Monday 15 June 2015To provide drawing of Seal OilCooler

PGB Dateline on Monday 15 June 2015

To Fabricate new baffle plate Marin Sejagat Info2 holding point during workexecution (witnessed and verifiedby PGB)1. Material inpection and

verification2. Expansion of tubes and

Hydrotest on tubes

PGB / Marin Sejagat Info

To confirm on material deliveryand readiness

Marin Sejagat Dateline on Monday 15 June 2015

To submit revised schedule anddetail ITP / JMS to PGB

Marin Sejagat Dateline on Tuesday 16 June 2015

Page 2: Roundcube Webmail __ FW_ Seal Oil Cooler Repair

6/14/2015 Roundcube Webmail :: FW: Seal Oil Cooler Repair

http://webmail.marinsejagat.com.my/cpsess5222810021/3rdparty/roundcube/?_task=mail&_action=print&_uid=67&_mbox=INBOX&_extwin=1 2/2

To check channel head and O‐Ring at site

PGB / Marin Sejagat Dateline on Monday 15 June 2015

To take out tube bundle fromPGB premise to Contractorworkshop

Marin Sejagat Dateline on Monday 15 June 2015

Thank you Regards,Long Zulkarnaen B Long ZainudinMechanical Executive (Rotating),Turbomachinery Section,Engineering Department

PETRONAS Gas BerhadKM105, Jalan Kuantan/Kuala Terengganu, 24300 Kertih, Kemaman, Terengganu Darul Iman, MALAYSIAT: +(09) 831 2497 HP: 013­6050603 F: +(09) 827 1900 DISCLAIMER : This e­mail and any files transmitted with it ("Message") is intended only for the useof the recipient(s) named above and may contain confidential information. You are hereby notifiedthat the taking of any action in reliance upon, or any review, retransmission, dissemination,distribution, printing or copying of this Message or any part thereof by anyone other than the intendedrecipient(s) is strictly prohibited. If you have received this Message in error, you should delete thisMessage immediately and advise the sender by return e­mail. Opinions, conclusions and otherinformation in this Message that do not relate to the official business of PETRONAS or its Group ofCompanies shall be understood as neither given nor endorsed by PETRONAS or any of the companieswithin the Group.