Subject FW: Seal Oil Cooler RepairFrom <[email protected]>To <[email protected]>Cc <[email protected]>Date 20150614 07:58
fyi
From: Long Zulkarnaen B Long Zainudin (GPU/PGB) [mailto:[email protected]] Sent: Wednesday, 10 June, 2015 4:06 PMTo: MOHD @ MSSB; [email protected]: Kamarulzaman B Zakaria (GPU/PGB); W M Faiz B W M Asmara (GPU/PGB); Azman B Md Hashim(POD/PGB); Lim Peng Sheng (GPU/PGB)Subject: Seal Oil Cooler Repair Dear All, Please find MOM for our kick off meeting as below. Action Item Action Party RemarkPGB to provide calculation fortube expansion rate.
PGB Dateline on Monday 15 June 2015
Marin Sejagat to verify Pressuretest (Hydrotest) procedure attheir workshop
Marin Sejagat Dateline on Tuesday 16 June 2015
Leak test at site using actualproduct after installation
Marin Sejagat Info
To repair and Build up Tubesheet Marin Sejagat InfoTo perform cleaning of tubesheet Marin Sejagat InfoTo inpect grooves condition attubesheet
PGB / Marin Sejagat Info
Cleaning at shell side usingWaterjet and air blow
Marin Sejagat Info
To perform painting of tubesheetand shell flange
Marin Sejagat Spec 17A
To provide Sample O‐Ring PGB Dateline on Monday 15 June 2015To provide drawing of Seal OilCooler
PGB Dateline on Monday 15 June 2015
To Fabricate new baffle plate Marin Sejagat Info2 holding point during workexecution (witnessed and verifiedby PGB)1. Material inpection and
verification2. Expansion of tubes and
Hydrotest on tubes
PGB / Marin Sejagat Info
To confirm on material deliveryand readiness
Marin Sejagat Dateline on Monday 15 June 2015
To submit revised schedule anddetail ITP / JMS to PGB
Marin Sejagat Dateline on Tuesday 16 June 2015
6/14/2015 Roundcube Webmail :: FW: Seal Oil Cooler Repair
http://webmail.marinsejagat.com.my/cpsess5222810021/3rdparty/roundcube/?_task=mail&_action=print&_uid=67&_mbox=INBOX&_extwin=1 2/2
To check channel head and O‐Ring at site
PGB / Marin Sejagat Dateline on Monday 15 June 2015
To take out tube bundle fromPGB premise to Contractorworkshop
Marin Sejagat Dateline on Monday 15 June 2015
Thank you Regards,Long Zulkarnaen B Long ZainudinMechanical Executive (Rotating),Turbomachinery Section,Engineering Department
PETRONAS Gas BerhadKM105, Jalan Kuantan/Kuala Terengganu, 24300 Kertih, Kemaman, Terengganu Darul Iman, MALAYSIAT: +(09) 831 2497 HP: 0136050603 F: +(09) 827 1900 DISCLAIMER : This email and any files transmitted with it ("Message") is intended only for the useof the recipient(s) named above and may contain confidential information. You are hereby notifiedthat the taking of any action in reliance upon, or any review, retransmission, dissemination,distribution, printing or copying of this Message or any part thereof by anyone other than the intendedrecipient(s) is strictly prohibited. If you have received this Message in error, you should delete thisMessage immediately and advise the sender by return email. Opinions, conclusions and otherinformation in this Message that do not relate to the official business of PETRONAS or its Group ofCompanies shall be understood as neither given nor endorsed by PETRONAS or any of the companieswithin the Group.