Roadway Design Process Using The GDCP for Developing Bridge Project Timelines 2 nd Annual Pre-Construction Conference April 3, 2014

Transcript of Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits...

Page 1: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Roadway Design ProcessUsing The GDCP for Developing Bridge Project Timelines

2nd Annual Pre-Construction ConferenceApril 3, 2014

Page 2: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Guide For Developing Construction Plans (GDCP)• 267 Steps

• Attachments• Traffic Data Request• FHWA Oversight Agreement• Required Hydraulic Report

Format• Bridge Hydraulic Submittal

Requirements• Design Exception Requirements• Plan Review Check List• Value Engineering

Requirements• Railroad Notes www.dot.state.al.us/dsweb/EngineeringSupport/pdf/GDCP.pdf

Page 3: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Scheduling Book

• Major Steps In Scheduling Book• 80 – 30% Review

• 92 – Geotech Submittal

• 130 – Bridge Submittal

• 166 – Plan-In-Hand Inspection

• 215 – PS&E Inspection

• 236 – FBC Submittal

• 252 – Construction Submittal

• 262 – OE Submittal

Page 4: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• PE Authorization

• Bridge Funding Limits Eligibility

Page 5: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Bridge Funding Limits Eligibility

• What do you need?• Aerial Photography

• Surface Information – Lidar or DEMS

• Scope of Project

• Begin Bridge Corridor Study• Develop Design Criteria

• Design Speed

• Roadway Template

• GN-2 Notes

• Initial Hydraulic Investigation

Page 6: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Bridge Funding Limits Eligibility

• Bridge Corridor Study • Develop Design Criteria

• Initial Bridge Hydraulic Investigation• Send Request to Bridge Hydraulic Engineer

• GFO 3-60

Page 7: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Initial Hydraulic Investigation

• Bridge Hydraulic Engineer• Site Inspection

• Hydraulic Analysis

• Flood Plain Evaluations

• Geomorphic Factors of the Stream

• Hydraulic Summary Report• Type of Girder & # of Spans

• Begin/End Stations

• Minimum Deck Elevation

• Size of Bridge Culvert

• Bridge Identification Number (BIN)

Page 8: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Bridge Funding Limits Eligibility

• Bridge Corridor Study • Develop Design Criteria

• Initiate Bridge Hydraulic Investigation

• Develop Horizontal/Vertical Alignments

Page 9: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Develop Horizontal / Vertical Alignment

• Alternate Design (2 Months)• In-Place, Left, and or Right

• Evaluate Alternate Costs• Construction Estimate

• Right-of-Way

• Utilities

• Detours• GFO 3-43 Requires Chief Engineer Approval

www.dot.state.al.us/dsweb/EngineeringSupport/pdf/AldotGFO1.pdf

Page 10: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Bridge Funding Limits Eligibility

• Bridge Corridor Study • Develop Design Criteria

• Initiate Bridge Hydraulic Investigation

• Develop Horizontal/Vertical Alignments

• Select Alternate

• Develop Location Memorandum and Get

Funding Approval (Attachment #2)

(2 Months)

• Send ETS Begin Environmental Process

• Develop Cost Estimate (Update CPMS)

Page 11: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• PE Authorization

• BR Funding & Location Memo Approval

( 4 Months)

• Complete Survey ( 2 Months)

• #1 Begin Plan Development (Set up CADD files)

• #16 Title Sheet

• #17 Request CN ( ) #

• #18 Request Traffic Data

• #21 Develop Typicals

• #22 Initial M&T Submittal (Cut Sheets onBR Funding Approval)

• #39 Initial RR Submittal

• #80 30% Review

Page 12: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#80 – 30% Review (2 Months)

• Tie Horizontal & Vertical Alignment To Survey

• Develop ROW Using GN-2 Notes (30’-40’ Buffer)

• Develop Typical Sections (Backbone) GN-2 Notes

• Look at Major Drainage Structures (48” Pipes & Larger)

• Develop Geometric Controls

• Paving Layout Sheets

• Utility Sheets

• Cross-section Sheets & Earthwork Summary

• Title & Index Sheets

• Set ROW: www.dot.state.al.us/rwweb/doc/proceduralmanuals/ROW%20guidelines%20with%20letter_031912.pdf

• Create Plan/Profile Sheets

• Create Preliminary Construction Estimate: (Update CPMS)http://cpmsweb2.dot.state.al.us/ConsultMgmt/Docs/CE-%20Blank10%20(3-21-11).xls

Page 13: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• PE Authorization

• BR Funding & Location Memo Approval ( 4 Months)

• Complete Survey ( 2 Months)

• #1 Begin Plan Development (Set up CADD files)

• #80 30% Review (2 Months)

• #89 Environmental Coordination

• #90 Haz-Mat Coordination

• #92 Materials & Tests Submittal ( 1 Month )

Page 14: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#92 M&T Submittal

• Plan Quantities• 7 sets plans ( 5 M&T, 2 Division/Region)• 2 CD w/CADD Files• 2 Location Memos• 2 Project Scope Memos

• Plans (30% Plans Corrected)• Title Sheet• Survey Control Layout• Geometric Control Layout• Typicals• Plan/Profile Sheets• Drainage Sections (48” & Larger)• Cross-Sections• Any Other Relevant Sheets

• CD Information• Microstation Files (Design & Survey)• Inroads Files (Alg & DTM Surfaces)• PDF Plan Assembly• Topographic Map 1:24000 w/ CL’s

Page 15: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• PE Authorization

• BR Funding & Location Memo Approval

( 4 Months)

• Complete Survey ( 2 Months)

• #1 Begin Plan Development (Set up CADD files)

• #80 30% Review (2 Months)

• #89 Environmental Coordination

• #90 Haz-Mat Coordination

• #92 Materials & Tests Submittal ( 1 Month )

• #100 Approved Materials Info (6-9 Months)

• #111 Public Involvement Meeting

Page 16: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#111 Public Involvement Meeting/Design Hearing

• Contact ETS & Division/Region Project Advertisement (30 Days Min)

• Create Meeting Maps (2 weeks)• 3 – Color Plots w/Aerials

• 1 – ½ size set of plans (30% Plans)

• Any other items necessary (3-D Models, etc.)

• Hold PIM

• Citizen Comment Period (10 Business Days)

• Division/Region Summarize Comments (45 Days)

• Respond to Comments & Get Document Approved (4 Months)

• Total 7 Months

Page 17: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #111 Public Involvement Meeting

• #130 Bridge Design Submittal

Page 18: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#130 Bridge Design Submittal

• Requirements (6 Part. Plans, CADD Files)• Corrected 30% Plans

• Ground Line (3-Line Profile) data

• Cross-Sections around bridges

• Profile of Feature to be crossed (Roadway, Waterway, Railroad, etc.)

• Grade Separations Require Intersecting Station & Intersection Angle

Page 19: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #111 PIM

• #130 Bridge Design Submittal

• #131 TS&L Submittal (6 Weeks)

• #164 Plan-In-Hand Submittal (2 Months After #100)

Page 20: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#164 Plan-In-Hand Submittal

• Completed Plans except for Quantities• 30% Plan Corrected & Incorporate

Geotech Information• Typicals w/Buildup• Design Sections• Stormwater Design• Sequence of Construction• Signing & Stripping• Traffic Control Plan• Plan-In-Hand Check List• Preliminary Cost Estimate (Update

CPMS)

• Plan Quantities• Division – 8 sets• ROW (Utilities Section) – 1 set• M&T Bureau – 1 set• Design Bureau (Traffic Design Section)

– 1 set min. Add sets if have Lighting, ITS, and /or Signals

• Bridge Bureau – 1 partial set• Design Bureau (ETS) – 1 partial set• FHWA – 1 set• Quality Control – 4 sets• Construction – 1 set

Page 21: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #111 PIM

• #130 Bridge Design Submittal

• #131 TS&L Submittal (6 Weeks)

• #164 Plan-In-Hand Submittal (2 Months After #100)

• #166 PIH Inspection & Comments (1 Month)

• #180 ETS Environmental Approval (2 Months Min Prior ROW Authorization)• PIH Comments Addressed that will affect ROW

• ETS Will Respond with Written Approval or Denial within 2 weeks

• If Additional Studies are required Designer will be notified with cause of ROW Authorization Delay

Page 22: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#180 ETS Environmental Approval/Denial

• What Are They Looking At?• #5 Original Environmental Cleared Limits• #89 Initial Environmental Submittal• #111 PIM Changes

• What Are Effects of Changes? (Delays)• Additional Studies

• Cultural Resources (Archeology/Historic Structures)• Air• Noise• Endangered Species• New Permits

Page 23: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #111 PIM

• #130 Bridge Design Submittal

• #131 TS&L Submittal (6 Weeks)

• #164 Plan-In-Hand Submittal (2 Months After #100)

• #166 PIH Inspection & Comments (1 Month)

• #180 ETS Environmental Approval (2 Months Min Prior ROW Authorization)

• #182 ROW Submittal w/ETS #180 Approval (6 Weeks Min Prior ROW Authorization)

• ROW Authorization (6 Weeks)

• ROW Acquisition (6-24 Months)

• #214 Plans, Specifications & Estimates (PS&E) Submittal (3-4 Months)

Page 24: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#214 PS&E Submittal

• Submittal Requirements• Completed Roadway Plans• Disposition of PIH Comments • All Quantities Calculated• PS&E Check List• Bridge Layouts• Approved Design Exception Letter• Updated Cost Estimate (Update

CPMS)

• Plan Quantities• Division – 8 sets• ROW (Utilities Section) – 1 set• M&T Bureau – 1 set• Design Bureau (Traffic Design

Section) – 1 set min. Add sets if have Lighting, ITS, and /or Signals

• Bridge Bureau – 1 partial set• Design Bureau (ETS) – 1 partial set• FHWA – 1 set• Quality Control – 4 sets• Construction – 1 set

Page 25: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #111 PIM

• #130 Bridge Design Submittal

• #131 TS&L Submittal by Bridge Designer (6 Weeks)

• #164 Plan-In-Hand Submittal (2 Months After #100)

• #166 PIH Inspection & Comments (1 Month)

• #180 ETS Environmental Approval Submittal(2 Months Min Prior ROW Authorization)

• #182 ROW Submittal w/ETS #180 Approval (6 Wks Min Prior ROW Authorization)

• ROW Authorization (Total XXXXX)

• ROW Acquisition (6-24 Months)

• #214 Plans, Specifications & Estimates (PS&E) Submittal (3-4 Months)

• #215 PS&E Inspection & Comments (1 Month)

Page 26: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #215 PS&E Inspection & Comments (1 Month)

• #235 Final Back Check Submittal (1 Month) – (4 Months Prior to Letting min.)

Page 27: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#235 Final Back Check Submittal

• Submittal Requirements• Corrected PS&E Plans

• Disposition of PS&E Comments

• Bridge Layout & Elevation Drawings (Bridge Unique Items)

• Signal Plans (If Applicable)

• Lighting Plans (If Applicable)

• Updated Cost Estimate (Update CPMS)

• Plan Quantities• Quality Control Bureau – 4 sets

• Bridge Bureau – 1 set

• FHWA (if required) – 1 set

• Maintenance Bureau – 1 set

• Design Bureau – Traffic Design – 1 set min. Additional sets required for Signal, Lighting and/or ITS

Page 28: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #215 PS&E Inspection & Comments (1 Month)

• #235 Final Back Check Review Submittal (1 Month) – (4 Months Prior to Letting min.)

• #236 Final Back Check Review (2 Weeks)

• #252 Construction Submittal (2 Weeks) (3 Months Prior to Letting min.)

Page 29: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

#252 Construction Submittal

• Submittal Requirements• Corrected FBC Plans

• Disposition of FBC Comments

• Signed Bridge Plans

• Railroad Agreement

• Utilities

• Updated Cost Estimate (Update CPMS)

• Plan Quantities• Construction Bureau – 2 sets &

DBE Plans

• FHWA – 2 sets

• Design Bureau (Traffic Design Section) – 1 set (ITS Only)

• Maintenance Bureau – 1 set

• Division – 1 set

Page 30: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Developing Timeline For Bridge Replacement Projects

• #215 PS&E Inspection & Comments (1 Month)

• #235 Final Back Check Review Submittal (1 Month) – (4 Months Prior to Letting min.)

• #236 Final Back Check Review (2 Weeks)

• #252 Construction Submittal (2 Weeks) (3 Months Prior to Letting min.)

• #253 Construction Review (2 Weeks)

• #262 Final Plans To Office Engineer (2 Weeks) (2 Months Prior to Letting)

• Bid Project

Page 31: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Summary Timeline • PE Authorization

• #80 – 30% Review – 8 Months

• #92 – Geotechnical Submittal – 1 Month

• #130 – Bridge Submittal – 7 Months

• #166 – PIH Inspection – 1 Month

• #215 – PS&E Inspection – 4 Months

• #236 – FBC Submittal – 1 Month

• #252 – Construction Submittal – 1 Month

• #262 – Office Engineer Submittal – 1 Month

• Project Letting – 2 Months

Total Conception to Letting – 26 Months (Allows 6 Months ROW Acquisition)

Page 32: Roadway Design Process...•GN-2 Notes •Initial Hydraulic Investigation. Bridge Funding Limits Eligibility •Bridge Corridor Study •Develop Design Criteria ... •Profile of Feature

Stan Biddick, PE

Roadway Design Engineer

1409 Coliseum Blvd.

Montgomery, AL 36110

334-242-6833

[email protected]

Location Engineer – 334-242-6476

Environmental Compliance Coordinator – 334-242-6143

Consultant Mgt Engineer – 334-242-6842