Road Map for Improvement of SAIFI , SAIDI & CAIDI
-
Upload
lacy-maddox -
Category
Documents
-
view
84 -
download
0
description
Transcript of Road Map for Improvement of SAIFI , SAIDI & CAIDI
Presented by:Eng. A.Aziz Al Alawi
Director,Electricity Distribution Directorate
Kingdom of Bahrain
ROAD MAP FOR IMPROVEMENT OFSAIFI , SAIDI & CAIDI
3rd Arab Union of Electricity,Electricity Distribution Conference
Salalah-Sultanate Oman27th – 29th August 2012
Contents Road Map for Improvement of SAIFI , SAIDI & CAIDI DMAIC Approach Learning From The Current Experience Electricity Distribution Directorate (EDD) Maintenance Process Operational Loading Policy of Feeders Maintenance Policy EDD Maintenance Strategies Maintenance Criteria Maintenance Program 2011-2012 HV / LV Reinforcement & Replacement Program 11kV Cable Fault Elimination Improvement Program 2012-2013 SAIFI, SAIDI, CAIDI Targets Recommendations
Road Map for Improvement of SAIFI , SAIDI & CAIDI
Maintenance Practice
Maintenanceprograms
Reinforcement & Replacement
Programs
Improvement
Improvement
Improvement of KPI (SAIFI, SAIDI, CAIDI)
Achievement of Target
11kV & LV Cable Fault Elemenation
KPIsAn Assessment tool for improvement process
Presented byEngineer Heyam Nassr
Operation & Loading Policy
Condition Monitoring Program Condition
Based Maintenance Asset
Replacement Program
Network Protection Systems
Remote Controlling and Monitoring Capabilities
Operational Readiness and Fast Response
Generator Mobilization
Prevention
Containment
Prevention
Containment
Reliability and Quality- Power Delivery
Decide What To Do Based On Our Own Experience
Policies, SOPs, Design, Specifications, Strategy
Fixed Time Maintainence
Learning From The Current Experience
Maintenance
FUNCTION
Maintenance
OBJECTIVES
Establishing a
PLAN to achieve
the maintena
nce Objective
Building an
ORGANIZATION to carry out the
plan
CONTROL
systems to check
if the plan and organization are meeting
the objectives and to correct if necessar
y
Ensuring and Controlling the reliability of HV & LV
Networks
To align EDD’s objectives with EWA‘s objectives of achieving
the agreed N/W operating conditions
and quality, within the accepted N/W
conditions and safety standards and at minimum cost.
• 3-Lines Maintenance• Wall boxes, Service
Twin Wires, 11kV Over head lines and s/s
• 3 Maintenance Depots of Muharraq, Manama and Riffa
• Outsourcing .• Implementing of Asset
Management Concept.
Controlling and monitoring of Productivity,
Effectiveness, and Organization Efficiency.
EDD Maintenance Process
11kV network• 150A(3 MVA) up to open point for copper cable feeders (50% cable
loaded)• 125A (2.5MVA) up to open point for aluminum cable feeders (50%
cable loaded)• Controlled by Distribution Control Centre (DCC)
400V network• Maximum feeder load is 150kVA
(5*60Amp, 3*100Amp, 2*160Amp or 1*250Amps)• Controlled by Low Voltage Operations
Operational Loading Policy of Feeders
Maintenance Scheduling: • Planned maintenance will be scheduled on an annual and monthly basis and be
approved, in advance by DCC & LV Operation, as appropriate.• Preventive maintenance and corrective maintenance should be planned and
scheduled jointly by Maintenance & Operations groups.• Overtime will be authorized based on the related Standard Operating Procedure
(SOP).
Materials Requirements: • Maintenance planning will include identification of requirements of materials and
manpower; EDD and outsourced.• Materials Requirements will be identified and expressed by Maintenance Group.• Planning & Materials section will then deliver materials as and when specified.
Safety and Operating Procedures: • HV and LV isolation works shall be done in accordance with the standard operating
procedures.• Mobilization of generators connection shall be done in accordance with standard
operating procedure.
Maintenance Policy
3-lines Maintenance Strategy. Continuous improvement of the network: Reinforcement and Correction
Maintenance. Fully implementation of CASCADE, via computerized Maintenance
Management System. Staff training and development (Multi skilling) Deployment of new technologies such as Responder, to enhance quality of
our services.
EDD Maintenance Strategies
First Line Maintenance Strategy
o To Carry-Out Inspection:• Objectively, by using Infrared Camera for inspection of
Transformers, LV Panels & 11kv Overhead), 11KV Network partial Discharge test. (Condition Based Maintenance)
• Subjectively, by visually inspection of HV and LV transformer connection, oil checking, silica gel checking, etc.
o To Respond to Inspection Results: • Cleaning and minor rectification of equipment defects of LV
Panel Board and Ring Main Units (RMUs)• Refurbishment and cleaning of wall boxes.
3-Lines Maintenance Strategy
Second Line Maintenance Strategy
o Replacement of defective items/components based on:• Inspection of the First Line Maintenance• Time Schedule Maintenance.
Third Line Maintenance Strategy
o Life cycle Asset Assessment:• Transformers (35-40 years),• RMUs Oil (25 years) and RMU SF6 (15 years),• LV Board (30 years),• HV Cables (40 years), LV cables (35 years), • 11kV poles switches (35 years), • Air Break Switches(35 years)
Electrical Equipment Frequency
Distribution Substation Equipments Four Years
Intake Substation Equipments Two Years
11kV Overhead Lines Two Years
Wall Boxes Three Years
Substation Civil Structures
• Based on the annual inspection of S/S Maintenance Section, urgent repairs will be carried out by Civil Unit.
• For those substations which are ten years or older, a five yearly inspection is carried out by civil unit.
• Block work enclosure for package units and replacement of wooden doors is on going.
Maintenance Criteria
3. Replacement of 20 km of service twin wires.4. Maintenance of 1,000 Substations.
The target will be increased to 4,000 Substations (S/S) for 2012,2013 . 5. Inspection of all overloaded Substations with emphasis on equipment with
history of repeated faults.6. Replacement of 200 units of transformer RMUs and LV Panels in the
Substations.7. Inspection and maintenance of 11 kV circuits terminations in Primary S/S, and
in coordination with Transmission Directorate program.
Nov 2011
Dec Jan2012
Feb Mar Apr May Jun Jun Aug Sep Oct Nov Dec 2012
1. Inspection and Overall of All 11kV O/H Lines
2. Maintenance of 15,000 Wall Boxes
Maintenance Program 2011-2012
8. 11kV Partial Discharge measurements for feeders whose load is more than 300Amp.
9. Upgrade Transformers of which loads exceed 80% of it capacity.
10. Verifying functionality of 11kV protection system in RMUs.
11. Replace any RMUs of which fault current capacity is lower than 350MVA.
12. Install Moulded Case Circuit Breakers (MCCB) at Customer side.
13. Using Mini Feeder Pillars for the 400 Volts N/W.
14. Activate/ install new Earth Fault Indicators (EFIs).
15. Procurement of advanced HV Cable Fault locating equipment.
Maintenance Program 2011-2012
HV / LV Reinforcement & Replacement Program
o HV reinforcement 43
o HV cable replacement 5
o LV reinforcement 496
o LV replacement 71
o Uprating transformer from 1000kVA to 1500KVA 81
11kV Cable Fault Elimination
Partnership with Electricity Distribution Directorate Pre-qualification of Contractors Work Specifications / Job Catalogue Training on proper practices - Contractors Cable Joint procedures / Tools Procedure for Contractor reporting of materials defects Qualification of Supervisors/inspectors Supervisors Procedure and List of Actions by the Supervisors Maintain proper record of Joints/Cables? Tagging system Procedure for Supervisor reporting of materials defects /bad
workmanship Training on proper practices – EDD Supervisors
Automation of RMU Operations Automation of Earth Fault Indicators MCCB (Moulded Case Circuit Breakers) to control unauthorized load To replace the LV Underground joints with Mini Feeder Pillars Activation of CASCADE system (Computerised Maintenance System) Utilization of Vehicle Tracking System
Improvement Program 2012-2013
SAIFI, SAIDI, CAIDI Targets
The number of interruptions 2011 and 2012
The interruptions in 2012 increased due to unauthorised loads.
SAIFI, SAIDI, CAIDI Target
Significant improvement is registered in SAIFI & SAIDI in 2012 over 2011.
2011
(April-May-Jun-Jul)2012
(April-May-Jun-Jul)%
ImprovedTarget
SAIFI0.7
interruptions/customer0.2
interruptions/customer71.43%
0.5interruptions/customer
SAIDI107
minutes/customer77
minutes/customer28.04%
25minutes/customer
CAIDI143
minutes/interruptions379
minutes/interruptions-165.03%
50minutes/interruptions
Recommendations
Learning from the current experience and decide what to do based on our experience
People Drive Performance – enabling more people across the enterprise to increase competitive advantage
Adaption of 3 skilled capabilities (Monitoring, Analyse, Plan)
• Superiority in Monitoring – The monitoring capabilities will allow to execute on strategy and to increase the competitive advantage by improving on benchmarks on day-to-day operations.
• Superiority in Analyse – The analytic capabilities can be leveraged to enhance monitoring and planning capabilities.
• Superiority in the Plan – The capability in plan can attain the power to compete and to increase monitor plan & budget forecasts more broadly across the board.