Road & Bridge Design Publications€¦ · Updated contact names of requestees to Engineer of Road...
Transcript of Road & Bridge Design Publications€¦ · Updated contact names of requestees to Engineer of Road...
Road & Bridge Design Publications
Monthly Update – May 2020
1
Revisions for the month of May are listed and displayed below and will be included in
projects submitted for the September letting. E-mail road related questions on these changes
to [email protected]. E-mail bridge related questions to
Standard Plan Distribution
The distribution letter explaining the changes and the inserts used to keep a hard copy of the
standard plan booklet up to date can be found at:
https://mdotjboss.state.mi.us/SpecProv/getDocumentById.htm?docGuid=463735f9-1af8-
4c78-adc3-07a16bfa03f7
The new standard plans have been placed on the website and the special detail index has been
updated for the distribution.
Special Details
R-28-J: Curb Ramp and Detectable Warning Details: Revised the term “Sidewalk Ramp” to
“Curb Ramp”.
R-60-J: Guardrail Types A, B, BD, T, TD, MGS-8, & MGS-8D: Eliminated the “**” note on
the Type MGS-8D (wood post) detail, as it does not apply.
Road Design Manual
3.08.01E: Design Exceptions/Variances: Revised the approving authority for design
exceptions from the Engineer of Design to the Engineer of Road Design or the Chief Structure
Design Engineer.
3.12D: 3R Freeway Underclearances: Revised the section to allow retaining existing vertical
under clearances without a design exception on 3R freeway projects when a pattern of high
load hits does not exist.
3.12G: Vertical Clearance Requirement Table: Added a note (designated by ***) to the table
regarding retaining the existing vertical clearances without a design exception on 3R freeway
projects when a pattern of high load hits does not exist. Revised to match FHWA policy
(2017 Michigan Division clarification) regarding retaining the existing controlling criteria on
3R freeway projects.
Road & Bridge Design Publications
Monthly Update – May 2020
2
6.04.02, 6.06.02, 6.08.02, 6.08.05: Revised the term “Sidewalk Ramp” to “Curb Ramp”.
14.11: Design Exceptions/Variances: Revised the approving authority for design exceptions
from the Engineer of Design to the Engineer of Road Design or the Chief Structure Design
Engineer.
Bridge Design Manual
7.01.04 F. (LRFD Only), 7.02.05 C. (LFD & LRFD),7.02.12(LFD & LRFD): Updated contact
name to Chief Structure Design Engineer.
7.01.06 B. (LRFD Only): Updated criteria to live load plus dynamic load allowance.
7.01.08 (LFD & LRFD): Added a note (designated by ***) to the table regarding retaining the
existing vertical clearances without a design exception on 3R freeway projects when a pattern
of high load hits does not exist. Revised to match FHWA policy (2017 Michigan Division
clarification) regarding retaining the existing controlling criteria on 3R freeway projects.
Updated contact names of requestees to Engineer of Road Design and Chief Structure Design
Engineer.
7.02.13 (LFD & LRFD): Updated contact person to Bridge Design Project Manager.
8.05 A3. (LRFD Only): Clarified note to utilize HL-93 loading.
12.02.01: Added vertical clearance information for 3R construction which is defined in
section 7.01.08.
12.08.01: Updated “The Plan Review Meeting”.
Updates to MDOT Cell Library, Bridge Auto Draw Program, etc., may be required in tandem
with some of this month's updates. Until such updates to automated tools can be made, it is
the designer's/detailer's responsibility to manually incorporate any necessary revisions to
notes and plan details to reflect these revisions.
Index to Special Details 5-27-2020
SPECIAL DETAIL
NUMBER
NUMBER OF
SHEETS TITLE CURRENT
DATE
21 2 GUARDRAIL AT INTERSECTIONS 4-9-18
24 8 GUARDRAIL ANCHORED IN BACKSLOPE TYPES 4B, 4T, & 4MGS-8 9-28-18
99 2 CHAIN LINK FENCE WITH WIRE ROPE 9-22-14
R-15-G 3 COVER K 7-26-19
R-27-F 1 BRIDGE APPROACH CURB & GUTTER (USING EXISTING CATCH BASIN) 10-14-19
*R-28-J 7 CURB RAMP AND DETECTABLE WARNING DETAILS 5-8-20
R-32-F 8 APPROACH CURB & GUTTER DOWNSPOUTS 12-16-19
R-32-SD 6 APPROACH CURB & GUTTER DOWNSPOUTS (FOR EXISTING RAILINGS) 11-14-19
R-33-G 2 CONCRETE VALLEY GUTTER AND URBAN FREEWAY CURB 8-14-19
R-53-A 22 TEMPORARY CONCRETE BARRIER LIMITED DEFLECTION 8-14-15
R-56-F 6 GUARDRAIL MEDIAN OBJECT PROTECTION 2-5-19
*R-60-J 17 GUARDRAIL TYPES A, B, BD, T, TD, MGS-8, & MGS-8D 5-14-20
R-62-H 4 GUARDRAIL APPROACH TERMINAL TYPE 2M 5-1-18
R-63-C 16 GUARDRAIL APPROACH TERMINAL TYPES 3B & 3T 2-5-19
R-66-E 4 GUARDRAIL DEPARTING TERMINAL TYPES B, T, & MGS 9-28-18
R-67-G 16 GUARDRAIL ANCHORAGE, BRIDGE, DETAILS 11-6-19
R-67-SD 7 GUARDRAIL ANCHORAGE, BRIDGE, DETAILS (FOR EXISTING RAILINGS) 11-13-19
R-72-D 6 GUARDRAIL LONG SPAN INSTALLATIONS 3-4-20
R-73-F 3 GUARDRAIL OVER BOX OR SLAB CULVERTS 8-1-19
R-126-I 5 PLACEMENT OF TEMPORARY CONCRETE & STEEL BARRIER 8-25-15
* Denotes New or Revised Special Detail to be included in projects for (beginning with) the September letting.
Note: Former Standard Plans IV-87, IV-89, IV-90, and IV-91 Series, used for building cast-in-place concrete head walls for elliptical and circular pipe culverts, are now being replaced with plans that detail each specific size. The Bureau of Bridges & Structures, Structure Design Section will provide special details for inclusion in construction plans for MDOT jobs. To assure prompt delivery, requests must be made in advance. Contact: [email protected]
Former Standard Plans IV-93 and IV-94 series have been replaced with precast concrete box & three-sided culverts as per the 2012 Standard Specifications for Construction.
Index to Bridge Detail Sheets 5-27-2020
DETAIL NUMBER
NUMBEROF
SHEETS TITLE CURRENT
DATE
B-22-E 5 BRIDGE RAILING, THRIE BEAM RETROFIT (R4 TYPE RAILING) 10-23-19
B-23-F 6 BRIDGE RAILING, THRIE BEAM RETROFIT (OPEN PARAPET RAILING) 10-23-19
B-28-A 7 BRIDGE BARRIER RAILING, TYPE 7 1-27-20
B-29-A 8 BRIDGE BARRIER RAILING, TYPE 6 1-27-20
B-50-A 3 BRIDGE RAILING, CONCRETE BLOCK RETROFIT 10-15-19
B-101-G 2 DRAIN CASTING ASSEMBLEY DETAILS 7-26-18
EJ3AC 1 to 3 EXPANSION JOINT DETAILS 10-8-19
EJ4P 1 to 3 EXPANSION JOINT DETAILS 10-8-19
PC-1M 1 PRESTRESSED CONCRETE I-BEAM DETAILS 8-23-17
PC-2H 1 70" PRESTRESSED CONCRETE I-BEAM DETAILS 8-23-17
PC-4F 1 PRESTRESSED CONCRETE 1800 BEAM DETAILS 8-23-17
* Denotes New or Revised Special Detail to be included in projects for (beginning with) the September letting.
Note: Details EJ3AC & EJ4P are interactive, i.e. designers and detailers choose details based upon railing type and angle of crossing. Place all details appropriate for the project, structure specific information, and the Expansion Joint Device quantity on the sheet. The sheet shall then be added to the plans as a normal plan sheet.
Detail PC-1M, PC-2H and PC-4F shall have structure specific information and quantities added to the sheet. The sheet shall then be added to the plans as a normal plan sheet.
A
A
A
MAXIMUM SIDE FLARE SLOPE
REDUCED TO ACCOMMODATE
FULL CURB HEIGHT MAY BE
** R
AMP
SIDEWALK
SIDE FLARE
SIDE FLARE
5' MI
N.
SIDEWALK
5' MIN.
SIDE FLARE
SIDE FLARE
** RAMP
(FLARED SIDES, TWO RAMPS SHOWN)
(SEE NOTES)
SLOPE
10% MAX.
(SEE NOTES)
SLOPE
10% MAX.
(SEE N
OTES)SLOPE10% MAX.
(SEE N
OTES)SLOPE10% MAX.
B.L.T.
W.K.P. 71
A
(SEE NOTES)
(SEE
NOTES)
R-28-J
A
A
OBSTRUCTION
PERMANENT
** R
AMP
5' MI
N.
SIDEWALK
SIDEWALK
(ROLLED SIDES)
ROLLED CURB
"NON-WALKING" AREA
(SEE
NOTES)
(SEE NOTES)
24" ACROSS FULL WIDTH
DETECTABLE WARNING SURFACE
(SEE NOTES)
24" ACROSS FULL WIDTH
DETECTABLE WARNING SURFACE
(SEE NOTES)
24" ACROSS FULL WIDTH
DETECTABLE WARNING SURFACE
* LANDING
5% - 7% (8.3% MAXIMUM). SEE NOTES.
** MAXIMUM RAMP CROSS SLOPE IS 2.0%, RUNNING SLOPE
* LANDING
SEE NOTES.
OF TRAVEL. LANDING MINIMUM DIMENSIONS 5' x 5'.
* MAXIMUM LANDING SLOPE IS 2.0% IN EACH DIRECTION
DEPARTMENT DIRECTOR MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVALCHECKED BY:
DRAWN BY:
Michigan Department of Transportation
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
APPROVED BY:
APPROVED BY:
Paul C. Ajegba
BY
PREPARED
DESIGN DIVISION
DIRECTOR, BUREAU OF FIELD SERVICES
DIRECTOR, BUREAU OF DEVELOPMENT
CURB RAMP TYPE R
CURB RAMP TYPE F
DETECTABLE WARNING DETAILS
CURB RAMP AND
5-8-2020
72R-28-J
SECTION A-A
PAVEMENT
1" EXPANSION JOINT
GRADE BREAK
(8.3% MAXIMUM) SEE NOTES
RAMP SLOPE 5% - 7%
A SIDEWALK
5' MI
N.
SIDE FLARE
(ROLLED / FLARED SIDES)
** R
AMP
(SEE N
OTES)SLOPE10% MAX.
WALKING AREA
"NON-WALKING" AREA
A
(SEE
NOTES)
ROLLED CURB
(SEE NOTES)
24" ACROSS FULL WIDTH
DETECTABLE WARNING SURFACE
2" MAX.24" ACROSS FULL WIDTH (SEE NOTES)
DETECTABLE WARNING SURFACE
RAMP RUN
* LANDING
SHALL BE AS CALLED FOR ON THE PLANS
RAMP AND LANDING SLAB THICKNESSES
B1
B2
B3
D1
D2
D3
C1
C2
C3
C4
C5
C6
F1
F2
F3
F4
F5
F6
A B
CURB TYPE
1
1
ƒ
ƒ
1
1
1
1
1
1
1
1
•
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
•
•
•
•
•
•
•
•
•
•
•
•
•
ƒ
ƒ
•
•
STANDARD PLAN R-30-SERIES
FOR CURB TYPES SEE
OPENING
CURB RAMP
* LANDING
(INCHES)
RISE
MAXIMUM
WITH THE GUTTER PAN
PAVEMENT SHALL END FLUSH
(TYPICAL ALL RAMP TYPES)
*** 5.0% MAX.
A B
SECTION THROUGH CURB RAMP OPENING
MAXIMUM RISE B
NOT TO EXCEED
MATCH RAMP SLOPE
5% - 7% (8.3% MAXIMUM). SEE NOTES.
** MAXIMUM RAMP CROSS SLOPE IS 2.0%, RUNNING SLOPE
SEE NOTES.
OF TRAVEL. LANDING MINIMUM DIMENSIONS 5' x 5'.
* MAXIMUM LANDING SLOPE IS 2.0% IN EACH DIRECTION
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
OF CURB
FLUSH WITH BACK
RAMP SHALL END
THE RAMP OPENING.
MAXIMUM COUNTER SLOPE ACROSS
CROSS SECTION TO PROVIDE 5.0%
*** TRANSITION ADJACENT GUTTER PAN
SEE STANDARD PLAN R-30-SERIES
AS IN ADJACENT CURB & GUTTER
LANE TIE AND REINFORCEMENT
5-8-2020
DETECTABLE WARNING DETAILS
CURB RAMP AND
CURB RAMP TYPE RF
(MEDIAN ISLAND)
5' MI
N.
(PARALLEL RAMP)
5' MI
N.
DO NOT USE IN AREAS WHERE PONDING MAY OCCUR
SIDEWALK
SIDEWALK
** RAMP
** R
AMP
"NON-WALKING" AREA
5' MI
N.
SIDEWALK
SIDEWALK
** RAMP
** R
AMP
"NON-WALKING" AREA
"NON-WALKING" AREA
73
MEDIAN WIDTH
(COMBINATION RAMP)
ROLLED CURB
(SEE
NOTES)
(SEE
NOTES)
(SEE NOTES)
24" ACROSS FULL WIDTH
DETECTABLE WARNING SURFACE
(SEE NOTES)
24" ACROSS FULL WIDTH
DETECTABLE WARNING SURFACE
R-28-J
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
* LANDING
* LANDING
DETECTABLE WARNING IS REQUIRED.
IS AT LEAST 6'-0". OTHERWISE NO
ACROSS FULL WIDTH IF MEDIAN WIDTH
DETECTABLE WARNING SURFACE 24"
5% - 7% (8.3% MAXIMUM). SEE NOTES.
** MAXIMUM RAMP CROSS SLOPE IS 2.0%, RUNNING SLOPE
SEE NOTES.
OF TRAVEL. LANDING MINIMUM DIMENSIONS 5' x 5'.
* MAXIMUM LANDING SLOPE IS 2.0% IN EACH DIRECTION
5-8-2020
DETECTABLE WARNING DETAILS
CURB RAMP AND
CURB RAMP TYPE P
CURB RAMP TYPE C
CURB RAMP TYPE M
74
** R
AMP** RAMP
ROLLED CURB
"NON-WALKING" AREA
(DEPRESSED CORNER)
24"
USE ONLY WHEN INDEPENDENT DIRECTIONAL RAMPS CAN NOT BE CONSTRUCTED FOR EACH CROSSING DIRECTION
SIDEWALK
** R
AMP** RAMP
SIDEWALK
( TANGENT DETECTABLE WARNING SHOWN )
"NON-WALKING" AREA
24"
( RADIAL DETECTABLE WARNING SHOWN )
FROM THE ENDS OF THE RADIUS. SEE NOTES
2" MAXIMUM DETECTABLE WARNING BORDER OFFSET MEASURED
FROM THE ENDS OF THE RADIUS. SEE NOTES
2" MAXIMUM DETECTABLE WARNING BORDER OFFSET MEASURED
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-28-J
* LANDING
* LANDING
5% - 7% (8.3% MAXIMUM). SEE NOTES.
** MAXIMUM RAMP CROSS SLOPE IS 2.0%, RUNNING SLOPE
SEE NOTES.
OF TRAVEL. LANDING MINIMUM DIMENSIONS 5' x 5'.
* MAXIMUM LANDING SLOPE IS 2.0% IN EACH DIRECTION
5-8-2020
DETECTABLE WARNING DETAILS
CURB RAMP AND
CURB RAMP TYPE D
75
SIDEWALK (TYP.)
RAILROAD CROSSING MATERIAL (TYP.)
6'
MI
N.*
15'
MA
X.*
WARNING ON RAILROAD CROSSING MATERIAL.
OF THE NEAREST RAIL. DO NOT PLACE DETECTABLE
6' MINIMUM AND 15' MAXIMUM FROM THE CENTERLINE
SO THAT THE EDGE NEAREST THE RAIL CROSSING IS
* THE DETECTABLE WARNING SURFACE SHALL BE LOCATED
SH
OU
LD
ER
SIDEWALK
DETECTABLE WARNING AT RAILROAD CROSSING
DETECTABLE WARNING AT FLUSH SHOULDER OR ROADWAY
24" ACROSS FULL WIDTH (SEE NOTES)
DETECTABLE WARNING SURFACE
24" ACROSS FULL WIDTH (SEE NOTES)
DETECTABLE WARNING SURFACE
(SEE NOTES)
24" ACROSS FULL WIDTH
DETECTABLE WARNING SURFACE
2" OF SHOULDER
NEAREST EDGE WITHIN
R-28-J
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
PEDESTRIAN GATE (WHERE PROVIDED)
5-8-2020
DETECTABLE WARNING DETAILS
CURB RAMP AND
LEGEND
CROSSWALK MARKING
SLOPED SURFACE
"NON-WALKING" AREA
PAVEMENT
1" EXPANSION JOINT
SECTION B-B
* GRADE BREAK
76
( )
B
B
THE BOTTOM GRADE BREAK.
ON THE RAMP SURFACE AT
WARNING SHALL BE LOCATED
CURB, THE DETECTABLE
WITHIN 5' OF THE BACK OF
BOTTOM GRADE BREAK ARE
WHERE BOTH ENDS OF THE
(8.3% MAXIMUM) SEE NOTES
RAMP SLOPE 5% - 7%
(TYP.)
OF DRAINAGE INLET
PREFERRED LOCATION
5'
* GRADE BREAK (TYP)
BREAK
* GRADE
THE DIRECTION OF TRAVEL.
CURB RAMPS SHALL BE PERPENDICULAR TO
* GRADE BREAKS AT THE TOP AND BOTTOM OF
DETECTABLE WARNING
OF CURB
END FLUSH WITH BACK
APPROACH AREA SHALL
BOTTOM GRADE BREAK
2% (5.0% MAX.) SLOPE BEYOND
*** 5.0% MAX. (5.0% MAX.)
2%
SLOPE ACROSS THE RAMP OPENING.
SECTION TO PROVIDE 5.0% MAXIMUM COUNTER
*** TRANSITION ADJACENT GUTTER PAN CROSS
SEE SECTION B-B
BEYOND BOTTOM GRADE BREAK.
5.0% MAX. RUNNING SLOPE
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-28-J
RAMP RUN
SHALL BE AS CALLED FOR ON THE PLANS
RAMP AND LANDING SLAB THICKNESSES
THE RAMP.
EXTENDING THE WIDTH OF
24" DETECTABLE WARNING,
OPENING
CURB RAMP
DETAILS.
SEE SHEET 2 FOR CURB RAMP OPENING
5-8-2020
DETECTABLE WARNING DETAILS
CURB RAMP AND
(GRADE BREAK OFFSET GREATER THAN 5')
CURB RAMP LOCATED IN RADIUS (TYPE R SHOWN)
CURB RAMP PERPENDICULAR TO RADIAL CURB (TYPE F SHOWN)
IS NOT SIGNIFICANT ON RADIUS)
BACK OF CURB. (DOME ORIENTATION
WARNING SHALL BE LOCATED AT THE
THE BACK OF CURB, THE DETECTABLE
GRADE BREAK IS MORE THAN 5' FROM
WHERE EITHER END OF THE BOTTOM
(TYP.)
OF DRAINAGE INLET
ALTERNATE LOCATION
(TYPE F AND TYPE RF SHOWN)
CURB RAMP PERPENDICULAR TO TANGENT CURB
(GRADE BREAK OFFSET LESS THAN 5')
CURB RAMP LOCATED IN RADIUS (TYPE R SHOWN)
CURB RAMP ORIENTATION
ARE NOT ALIGNED
USE WITH RADIAL CURB WHEN THE CROSSWALK AND CURB RAMP
WITH THE ADJACENT CONCRETE.
THE TOP OF THE JOINT FILLER FOR ALL RAMP TYPES SHALL BE FLUSH
MUNICIPALITY.
SIDEWALK SNOW REMOVAL EQUIPMENT NORMALLY USED BY THE
RAMP WIDTH SHALL BE INCREASED, IF NECESSARY, TO ACCOMMODATE
24"
DOME ALIGNMENT
DETECTABLE WARNING DETAILS
DOME SPACING0.2"
DOME SECTION
1.4"
TO
0.9"
OF BASE
50% TO 65% 1.6" - 2.4"
1.6" - 2.4"
0.65"
MI
N.
0.65"
MIN.
PERPENDICULAR (OR RADIAL) TO GRADE BREAK
ALIGNED IN DIRECTION OF TRAVEL AND
77
OF TRAVEL.
THE LONG DIMENSION IS PERPENDICULAR TO THE DOMINANT DIRECTION
GREATER THAN •". ELONGATED OPENINGS SHALL BE PLACED SO THAT
MANUFACTURER'S ADA COMPLIANT GRATE. OPENINGS SHALL NOT BE
STRUCTURES ARE LOCATED IN THE RAMP PATH OF TRAVEL, USE A
LOCATION OF THE DRAINAGE STRUCTURE. WHERE EXISTING DRAINAGE
THE LOCATION OF THE RAMP SHOULD TAKE PRECEDENCE OVER THE
DRAINAGE STRUCTURES SHOULD NOT BE PLACED IN LINE WITH RAMPS.
NOTES:
CROSSINGS.
SHALL ALSO BE PROVIDED AT MARKED AND/OR SIGNALIZED MID-BLOCK
WHERE THERE IS EXISTING OR PROPOSED SIDEWALK AND CURB. RAMPS
RAMPS SHALL BE PROVIDED AT ALL CORNERS OF AN INTERSECTION
ACROSS THE WALK.
SIDEWALK SHALL BE RAMPED WHERE THE DRIVEWAY CURB IS EXTENDED
BROOMING, TRANSVERSE TO THE RUNNING SLOPE.
SURFACE TEXTURE OF THE RAMP SHALL BE THAT OBTAINED BY A COARSE
TRAVEL.
RAMP BE IN ONLY ONE DIRECTION, PARALLEL TO THE DIRECTION OF
WHERE CONDITIONS PERMIT, IT IS DESIRABLE THAT THE SLOPE OF THE
CARE SHALL BE TAKEN TO ASSURE A UNIFORM GRADE ON THE RAMP.
SHIFTING OR HEAVING.
FIELD CUT UNITS CAST AND/OR ANCHORED IN THE PAVEMENT TO RESIST
DETECTABLE WARNING PLATES MUST BE INSTALLED USING FABRICATED OR
CURB THE OFFSET IS MEASURED FROM THE ENDS OF THE RADIUS.
THE EDGES OF THE DETECTABLE WARNING IS ALLOWABLE. FOR RADIAL
AREAS. A BORDER OFFSET NOT GREATER THAN 2" MEASURED ALONG
RAMP/PATH OPENING EXCLUDING CURBED OR FLARED CURB TRANSITION
DIRECTION OF RAMP/PATH TRAVEL AND THE FULL WIDTH OF THE
DETECTABLE WARNING SURFACE COVERAGE IS 24" MINIMUM IN THE
IN THE PUBLIC RIGHT OF WAY.
RECONSTRUCTION, OR ALTERATION OF STREETS, CURBS, OR SIDEWALKS
DETAILS SPECIFIED ON THIS PLAN APPLY TO ALL CONSTRUCTION,
R-28-J
FULL LENGTH OF THE RAMP.
THE CROSS SLOPE TRANSITION SHALL BE APPLIED UNIFORMLY OVER THE
SLOPE MAY BE TRANSITIONED TO MEET AN EXISTING ROADWAY GRADE.
EXCEED 2.0%. FOR ALTERATIONS TO EXISTING ROADWAYS, THE CROSS
FOR NEW ROADWAY CONSTRUCTION, THE RAMP CROSS SLOPE MAY NOT
UNIFORM TRAFFIC CONTROL DEVICES".
FOR MARKING APPLICATIONS ARE GIVEN IN THE "MICHIGAN MANUAL ON
AS TO STOP TRAFFIC SHORT OF RAMP CROSSINGS. SPECIFIC DETAILS
CROSSWALK AND STOP LINE MARKINGS, IF USED, SHALL BE SO LOCATED
4' x 4'.
REDUCED TO NOT LESS THAN 4' AND LANDINGS TO NOT LESS THAN
WHEN 5' MINIMUM WIDTHS ARE NOT PRACTICABLE, RAMP WIDTH MAY BE
TRANSITIONS.
OF RAMPS TO EXCEED 15 FEET IN LENGTH NOT INCLUDING LANDINGS OR
REFERENCE. HOWEVER, IT SHALL NOT REQUIRE ANY RAMP OR SERIES
THE MAXIMUM RUNNING SLOPE OF 8.3% IS RELATIVE TO A FLAT (0%)
PERPENDICULAR TO ITS OWN DIRECTION(S) OF TRAVEL.
INDEPENDENTLY MAINTAIN A CROSS SLOPE NOT GREATER THAN 2%
ROUTE CROSSING THROUGH OR INTERSECTING THE CURB RAMP MUST
LANDING. HOWEVER, ANY CONTINUOUS SIDEWALK OR PEDESTRIAN
CURB RAMPS WITH A RUNNING SLOPE 5% DO NOT REQUIRE A TOP
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
5-8-2020
DETECTABLE WARNING DETAILS
CURB RAMP AND
DIRECTED BY THE ENGINEER.
CURB RAMPS ARE TO BE LOCATED AS SPECIFIED ON THE PLANS OR AS
ORDER TO AVOID SHARP CURB RETURNS AT RAMP OPENINGS.
WHERE THEY ARE NOT REQUIRED, FLARED SIDES CAN BE CONSIDERED IN
LANDSCAPING, UNPAVED SURFACE OR PERMANENT FIXED OBJECTS.
SIDES ARE NOT REQUIRED WHERE THE RAMP IS BORDERED BY
CIRCULATION PATH LATERALLY CROSSES THE CURB RAMP. FLARED
ROADSIDE CURB LINE, SHALL BE PROVIDED WHERE AN UNOBSTRUCTED
FLARED SIDES WITH A SLOPE OF 10% MAXIMUM, MEASURED ALONG THE
WOOD POST STEEL POST ELEVATION SHOWING POST SPACING
GUARDRAIL, TYPE A
ELEVATION SHOWING POST SPACING
GUARDRAIL, TYPE B
( WOOD POST )
22"
GROUND LINE
(TYP.)
SPLICE BOLT
6"
7"
6'-0"
3'-7"
WOOD LINE POST
6" x 8"
22"
(TYP.)
SPLICE BOLT
7"
6'-0"
3'-7"
UNDER NUT
ROUND WASHER
POST BOLT WITH
8"
UNDER NUT
ROUND WASHER
POST BOLT WITH
GROUND LINE
AND TYPICAL POST SPACING
EFFECTIVE BEAM ELEMENT LENGTH
12'-6"
* 28"
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
GROUND LINEOPTIONAL
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
GROUND LINE
* 2
8"
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
POST SPACING
6'-3" TYPICAL6" x 8" WOOD LINE POST
LINE
GROUND
HINGE POINT
SHOULDER
WASHER UNDER NUT
POST BOLT WITH ROUND
COATED NAIL
3" LONG HOT-DIP ZINC
WOOD POST WITH A MINIMUM
TOE NAIL WOOD BLOCK TO
SHOULDER
NORMAL
2'-0"
8"8"(TYP.)
SPLICE BOLT
14"
7"
22"
3'-7"
6'-0"
** 5'-0" OR AS SPECIFIED ON PLANS
** FOR PAVED SHOULDER WIDTHS OF AT LEAST 12', USE 3'-0".
B.L.T.
W.K.P. 1 17R-60-J
STEEL LINE POST
W6 x 9 OR W6 x 8.5
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
DEPARTMENT DIRECTOR MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVALCHECKED BY:
DRAWN BY:
Michigan Department of Transportation
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
APPROVED BY:
APPROVED BY:
Paul C. Ajegba
BY
PREPARED
DESIGN DIVISION
DIRECTOR, BUREAU OF FIELD SERVICES
DIRECTOR, BUREAU OF DEVELOPMENT
5-14-2020
ELEVATION SHOWING POST SPACING
GUARDRAIL, TYPE BD
( WOOD POST )
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
POST SPACING
6'-3" TYPICAL
* 28"
GROUND LINE
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
6" x 8" WOOD LINE POST
GROUND LINE
WOOD OFFSET BLOCK
6" x 8"
WASHER UNDER NUT
POST BOLT WITH ROUND
8" 8" 8"(TYP.)
SPLICE BOLT
14"
7"
6'-0"
22"
3'-7"
NAIL
HOT-DIP ZINC COATED
A MINIMUM 3" LONG
TO WOOD POST WITH
TOE NAIL WOOD BLOCK
ELEVATION SHOWING POST SPACING
GUARDRAIL, TYPE B (OR BD)
( STEEL POST )
GROUND LINE
* 2
8"
POST SPACING
6'-3" TYPICAL
22"
(TYP.)
SPLICE BOLT
7"
6'-0"
3'-7"
14"
GROUND LINE
UNDER NUT
ROUND WASHER
POST BOLT WITH
FOR STEEL POST
WOOD OFFSET BLOCK
ROUTED 6" x 8"
BEAM ELEMENT
POST BOLT
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
172R-60-J
STEEL LINE POST
W6 x 9 OR W6 x 8.5
NUT
ROUND WASHER
FOR STEEL POST
ROUTED 6" x 8" WOOD BLOCK
STEEL LINE POST
W6 x 9 OR W6 x 8.5
(OPTIONAL)
GALVANIZING HOLE
2" TO 3"
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
5-14-2020
TOP
SIDEFRONT
WOOD OFFSET BLOCKS FOR GUARDRAIL, TYPE B AND TYPE BD
FOR USE ON WOOD POSTS
TOP
FRONT SIDE
FOR USE ON STEEL POSTS
WOOD POST STEEL POST
BEAM ELEMENT SPLICE DETAILS
1'-0•"
2"2" 4‚"4‚"
1„"
\ STEEL POST
POST BOLT SLOT
ƒ" x 2•"
\ POST BOLT SLOT
(TYP.)
SPLICE BOLT SLOT
x 1„"
1'-0•"
2"2" 4‚"4‚"
POST BOLT SLOT
ƒ" x 2•"
(TYP.)
SPLICE BOLT SLOT
x 1„"
\ WOOD POST
\ POST BOLT SLOT AND
3"
14"
7"
7"
1„"
ƒ" DIA. HOLE
+ „"-
\
14"
7"
7"
ƒ" DIA. HOLE
(SEE NOTES ON SHEET 16 OF 16)
173
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
8"
…"
6"
4‚" 3"3"8"
6"
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
ELEVATION SHOWING POST SPACING
GUARDRAIL, TYPE T
( WOOD POST )
ELEVATION SHOWING POST SPACING
GUARDRAIL, TYPE TD
( WOOD POST )
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
GROUND LINE
* 34"
POST SPACING
6'-3" TYPICAL
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
6" x 8" WOOD LINE POST
HINGE POINT
SHOULDER
LINE
GROUND
WASHER UNDER NUT
POST BOLT WITH ROUND
2'-0"
8"8"(TYP.)
SPLICE BOLT
SHOULDER
NORMAL
7‰
"28"
7'-0"
4'-0
Ž"
22"
7†
"
22"
(TYP.)
SPLICE BOLT
7'-0"
4'-0
Ž"
8" 8"
7†
"
WASHER UNDER NUT
POST BOLT WITH ROUND
6" x 8" WOOD LINE POST
28"
7‰
"
8"
OFFSET BLOCK
6" x 8" WOOD
GROUND LINE
GROUND LINE
* 3
4"
POST SPACING
6'-3" TYPICAL
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
** 5'-0" OR AS SPECIFIED ON PLANS
** FOR PAVED SHOULDER WIDTHS OF AT LEAST 12', USE 3'-0".
174
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
ELEVATION SHOWING POST SPACING
GUARDRAIL, TYPE T OR TD
( STEEL POST )
BLOCK AND POST CONNECTION DETAILS
GUARDRAIL, TYPE B
GUARDRAIL, TYPE T
GUARDRAIL, TYPE B
GUARDRAIL, TYPE T
22"
(TYP.)
SPLICE BOLT
7'-0"
4'-0
Ž"
7†
"
28"
7‰
"
GROUND LINEFOR STEEL POST
WOOD OFFSET BLOCK
ROUTED 6" x 8" UNDER NUT
ROUND WASHER
POST BOLT WITH
BEAM ELEMENT
POST BOLT (TYP.)
NUT (TYP.)
(TYP.)
ROUND WASHER
GROUND LINE
* 34"
POST SPACING
6'-3" TYPICAL
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
TO WOOD OFFSET BLOCK
CONNECTING STEEL POST
POST BOLT
ROUTED WOOD OFFSET BLOCK
CONNECTING STEEL POST TO
POST BOLT
WOOD POST STEEL POST
ROUTED WOOD OFFSET BLOCK
CONNECTING STEEL POST TO
POST BOLT
TO WOOD OFFSET BLOCK
CONNECTING STEEL POST
POST BOLT
WOOD POST STEEL POST
175
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
STEEL LINE POST
W6 x 9 OR W6 x 8.5
FOR STEEL POST
ROUTED 6" x 8" WOOD BLOCK
(OPTIONAL)
GALVANIZING HOLE
2" TO 3"
STEEL LINE POST
W6 x 9 OR W6 x 8.5
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
TOP
SIDEFRONT
WOOD OFFSET BLOCKS FOR GUARDRAIL, TYPE T AND TYPE TD
FOR USE ON WOOD POSTS
TOP
FRONT SIDE
FOR USE ON STEEL POSTS
WOOD POST STEEL POST
THRIE BEAM ELEMENT SPLICE DETAILS
1'-0•"
2"2" 4‚"4‚"
1„"
\ STEEL POST
POST BOLT SLOT
ƒ" x 2•"
\ POST BOLT SLOT
(TYP.)
SPLICE BOLT SLOT
x 1„"
1'-0•"
2"2" 4‚"4‚"
POST BOLT SLOT
ƒ" x 2•"
(TYP.)
SPLICE BOLT SLOT
x 1„"
\ WOOD POST
\ POST BOLT SLOT AND
3"3"
8"
8"
…"
6"6"
4‚"
3"2
2"
1„"
ƒ" DIA. HOLE
+ „"-
\
ƒ" DIA. HOLE
7‰
"7
‰"
7†
"
22"
7‰
"7
‰"
7†
"
(SEE NOTES ON SHEET 16 OF 16)
176
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
( WOOD POST )
6" x 8" WOOD LINE POST
LINE
GROUND
HINGE POINT
SHOULDER
WASHER UNDER NUT
POST BOLT WITH ROUND
COATED NAIL
3" LONG HOT-DIP ZINC
WOOD POST WITH A MINIMUM
TOE NAIL WOOD BLOCK TO
SHOULDER
NORMAL
2'-8"
8"
14"
7"
25"
3'-4"
** 5'-8" OR AS SPECIFIED ON PLANS
** FOR PAVED SHOULDER WIDTHS OF AT LEAST 12', USE 3'-8".
6" x 8" WOOD LINE POST
8"
14"
7"
25"
3'-4"
6'-0"
WASHER UNDER NUT
POST BOLT WITH ROUND
NAIL
HOT-DIP ZINC COATED
A MINIMUM 3" LONG
TO WOOD POST WITH
TOE NAIL WOOD BLOCK
GROUND LINE
GUARDRAIL, TYPE MGS-8D
( WOOD POST )
8"
8"8"
GUARDRAIL, TYPE MGS-8
177
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
6'-0"
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
( STEEL POST )
25"
7"
6'-0"
3'-4"
14"
UNDER NUT
ROUND WASHER
POST BOLT WITH
NUT
ROUND WASHER
BEAM ELEMENT
POST BOLT
GROUND LINE
FOR STEEL POST
WOOD OFFSET BLOCK
ROUTED 6" x 8"
FOR STEEL POST
ROUTED 6" x 8" WOOD BLOCK
STEEL LINE POST
W6 x 9 OR W6 x 8.5
STEEL LINE POST
W6 x 9 OR W6 x 8.5
GUARDRAIL, TYPE MGS-8 (OR MGS-8D)
178
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
(OPTIONAL)
GALVANIZING HOLE
2" TO 3"
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
ROUTED WOOD OFFSET BLOCK
CONNECTING STEEL POST TO
POST BOLT
WOOD POST STEEL POST
TO WOOD OFFSET BLOCK
CONNECTING WOOD POST
POST BOLT
1„"
\ STEEL POST
BLOCK AND POST CONNECTION DETAILS
TOP
SIDEFRONT
FOR USE ON WOOD POSTS
TOP
FRONT SIDE
FOR USE ON STEEL POSTS
3"3"
…"
6"6"
4‚"
3"
14"
7"
7"
1„"
ƒ" DIA. HOLE
+ „"-
\
14"
7"
7"
ƒ" DIA. HOLE
WOOD OFFSET BLOCKS FOR GUARDRAIL, TYPE MGS-8 AND TYPE MGS-8D
8
8"
179
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
(SEE NOTES ON SHEET 16 OF 16)
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
6'-3" TYPICAL POST SPACING
12'-6" EFFECTIVE BEAM ELEMENT LENGTH
GROUND LINE
* 31"
TOP OF RAIL
* SEE NOTES FOR GUARDRAIL IN CONJUNCTION WITH CURB
28"
31"
GROUND LINE
34"
GROUND LINE
31"
30"
\ MGS POST
\ MGS POST
TYPE 1B, 2B OR 3B
APPROACH TERMINAL
OR GUARDRAIL
GUARDRAIL, TYPE BD
GUARDRAIL, TYPE B
1710
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
DETAIL A1, T1, T4, OR T6
GUARDRAIL ANCHORAGE, BRIDGE
GUARDRAIL ANCHORAGE, MEDIAN
GUARDRAIL, TYPE TD
GUARDRAIL, TYPE T
GUARDRAIL, TYPE MGS-8 OR MGS-8D
ELEVATION SHOWING POST SPACING FOR
GUARDRAIL, TYPE MGS-8 OR MGS-8D
GUARDRAIL, TYPE MGS-8 OR MGS-8D
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
BEAM ELEMENT LENGTH
9'-4•" EFFECTIVE
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
34'-4•" HEIGHT TRANSITION
W-BEAM ELEMENT
STANDARD (12'-6")
BEAM ELEMENT
MGS (9'-4•")
W-BEAM ELEMENT
STANDARD (12'-6")
BEAM ELEMENT LENGTH
9'-4•" EFFECTIVE
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
28'-1•" HEIGHT TRANSITION
LENGTH
EFFECTIVE
6'-3"
W-BEAM ELEMENT
STANDARD (12'-6")
BEAM ELEMENT
MGS (9'-4•")
POST SPACING
6'-3" TYPICAL
POST SPACING
6'-3" TYPICAL
GUARDRAIL APPROACH TERMINAL TYPE 1B, 2B, OR 3B
GUARDRAIL, TYPE B, GUARDRAIL, TYPE BD, OR
GUARDRAIL, TYPE MGS-8 OR MGS-8D TO
ELEVATION SHOWING TRANSITION DETAIL FOR CONNECTING
GUARDRAIL ANCHORAGE, BRIDGE DETAIL A1, T1, T4 OR T6
GUARDRAIL ANCHORAGE, MEDIAN,
GUARDRAIL, TYPE T, GUARDRAIL, TYPE TD,
GUARDRAIL, TYPE MGS-8 OR MGS-8D TO
ELEVATION SHOWING TRANSITION DETAIL FOR CONNECTING
\ GUARDRAIL POST
\ GUARDRAIL POST
TRANSITION
THRIE BEAM
SYMMETRICAL
5-14-2020
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
28"
31"
GROUND LINE
34"
GROUND LINE
31"
30"
\ MGS POST
\ MGS POST
1711R-60-J
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
BEAM ELEMENT LENGTH
9'-4•" EFFECTIVE
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
34'-4•" HEIGHT TRANSITION
W-BEAM ELEMENT
STANDARD (12'-6")
BEAM ELEMENT
MGS (9'-4•")
W-BEAM ELEMENT
STANDARD (12'-6")
BEAM ELEMENT LENGTH
9'-4•" EFFECTIVE
BEAM ELEMENT LENGTH
12'-6" EFFECTIVE
28'-1•" HEIGHT TRANSITION
LENGTH
EFFECTIVE
6'-3"
POST SPACING
6'-3" TYPICAL
POST SPACING
6'-3" TYPICAL
BEAM ELEMENT
MGS (9'-4•")
W-BEAM ELEMENT
STANDARD (12'-6")
TERMINAL TYPE 2M
GUARDRAIL APPROACH
TERMINAL TYPE 2M
GUARDRAIL APPROACH
GUARDRAIL APPROACH TERMINAL TYPE 2M
GUARDRAIL, TYPE B TO
ELEVATION SHOWING TRANSITION DETAIL FOR CONNECTING
GUARDRAIL APPROACH TERMINAL TYPE 2M
GUARDRAIL, TYPE T TO
ELEVATION SHOWING TRANSITION DETAIL FOR CONNECTING
GUARDRAIL, TYPE B
\ GUARDRAIL POST
GUARDRAIL, TYPE T
\ GUARDRAIL POST
TRANSITION
THRIE BEAM
SYMMETRICAL
5-14-2020
SECTION THROUGH BEAM ELEMENT
Œ"
1˜"
3‰" ˆ"
3‚"
-0 + „"
TOLERANCE
3‚
"
…" R
(TYP.)
1'-0‚
"
+
‰"
(TYP.)
•" R
SYMMETRICAL
ABOUT \
•" R
(TYP.) NE
UT
RA
L
AXI
S
1̂ "
10°
1712
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
BEAM ELEMENT SPLICE DETAILS
1'-0•"
2"2" 4‚"4‚"
(TYP.)
SPLICE BOLT SLOT
x 1„"
\ SLOTTED HOLE
SLOTTED HOLE
ƒ" x 2•"
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
4‚"4‚" 2"4‚"4‚"2"
3'-1•"
\ OF POST BOLT SLOTS
3'-1•" 3'-1•"
(TYP.)
SPLICE BOLT SLOT
ž" x 1„"
(TYP.)
POST BOLT SLOT
ƒ" x 2•"
10'-5"
FRONT ELEVATION OF BEAM ELEMENT
4‚"4‚" 2"
13'-6•"
4‚"4‚"2"
3'-1•"
\ OF POST BOLT SLOTS
3'-1•" 3'-1•" 3'-1•"
(TYP.)
SPLICE BOLT SLOT
ž" x 1„"
(TYP.)
POST BOLT SLOT
ƒ" x 2•"
FRONT ELEVATION OF MGS (9'-4•") BEAM ELEMENT
5-14-2020
SECTION THROUGH THRIE BEAM ELEMENT(FOR GUARDRAIL, TYPE T AND TD)
3‰" ˆ"
3‚"
-0 + „"
TOLERANCE
1˜"
3‚
"
Œ"
1„
"3‚
"
•" R
(TYP.)
1̂ "
10°
…" R
(TYP.)
(TYP.)
•" R
Œ"
1„
"3‚
"3‚
"
1'-8"
+
‰"
1713R-60-J
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
FRONT ELEVATION OF THRIE BEAM ELEMENT
4‚"4‚" 2"
13'-6•"
4‚"4‚"2"
> OF POST BOLT SLOTS
(TYP.)
SPLICE BOLT SLOT
ž" x 1„"
(TYP.)
POST BOLT SLOT
ƒ" x 2•"
3'-1•" 3'-1•" 3'-1•" 3'-1•"
5-14-2020
4‚"4‚" 2"4‚"4‚"2"
7'-3•"
3'-1•"
1'-8"
+
‰"
SPLICE BOLT SLOT (TYP.)
ž" x 1„"
POST BOLT SLOT (TYP.)
ƒ" x 2•"
4‚"4‚" 2"4‚"4‚"2"
7'-3•"
3'-1•"
+
‰"
1'-0‚
"
1'-8"
+
‰"
POST BOLT SLOT (TYP.)
ƒ" x 2•"
SPLICE BOLT SLOT (TYP.)
x 1„"
1714
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
4‚"4‚"2" 4‚"4‚" 2"
7'-3•"
3'-1•"
1'-8"
<
‰"
<
‰"
1'-0‚
"
<
‰"
1'-0‚
"
POST BOLT SLOT (TYP.)
ƒ" x 2•"
SPLICE BOLT SLOT (TYP.)
ž" x 1„"
ASYMMETRICAL THRIE BEAM TRANSITIONSNOTE: ASYMMETRICAL TRANSITION TYPE WILL VARY BY LOCATION DEPENDING ON GUARDRAIL LAYOUT
THRIE BEAM TRANSITION
SECTION THROUGH
THRIE BEAM TRANSITION
SECTION THROUGH
THRIE BEAM TRANSITION
SECTION THROUGH
THRIE BEAM TRANSITION
SECTION THROUGH
THRIE BEAM TRANSITION
SECTION THROUGH
THRIE BEAM TRANSITION
SECTION THROUGH
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
SYMMETRICAL THRIE BEAM TRANSITIONS
3'-1•"
3'-1•"
3'-1•"
5•
"4‚
"
4‚
"5•
"
5-14-2020
TO GUARDRAIL, TYPE BD (OR TYPE TD)
DETAIL SHOWING TRANSITION FROM GUARDRAIL, TYPE B (OR TYPE T)
SPLICE BOLT AND POST BOLT
MINIMUM POST BOLT THREAD LENGTHAT BEAM ELEMENT SPLICE POSTS AND AT INTERMEDIATE POSTS
POST BOLTS, SPLICE BOLTS AND WASHERS
)
150'
METAL TAG
ROUND WASHER NUT
STANDARD WIDTH VARIABLE WIDTH (FIELD BEND)
8"
MA
X.
OF TRAFFIC
DIRECTION
OF TRAFFIC
DIRECTION
(TWO REQUIRED FOR TYPE TD)
(ONE REQUIRED FOR TYPE BD)
POST BOLT LENGTH 2'-10"
PAY ITEM: GUARDRAIL, TYPE BD (OR TD) GUARDRAIL, TYPE B (OR T)
PAY ITEM EACH SIDE:
APPROX. 6'-3"OFFSET BLOCKS (TYPE TD) 6" x 1'-0" x 1'-10"
OFFSET BLOCKS (TYPE BD) 6" x 1'-0" x 1'-3"
OFFSET BLOCKS (TYPE TD) 6" x 9" x 1'-10"
OFFSET BLOCKS (TYPE BD) 6" x 9" x 1'-3"
(TWO REQUIRED FOR TYPE TD)
(ONE REQUIRED FOR TYPE BD)
POST BOLT LENGTH 2'-4"
BOLT LENGTH MINIMUM THREAD LENGTH
18"
26•" 3"
9•" 1ƒ"
2•"
POSTBLOCK
OFFSET
POST BOLTS
NO. LENGTH
SPLICE BOLTS WASHERS
WOOD
WOOD
STEEL
STEEL
WOOD
STEEL
WOOD
STEEL
WOOD
STEEL
(ROUND)
NO
T
NE
ED
ED
AT I
NT
ER
ME
DI
AT
E
PO
ST
S
WOOD
WOOD
WOOD
WOOD
WOOD
WOOD
WOOD
WOOD
A
B
BD
T
TD
1
1
1
1
1
2
2
2
2
4
8
8
16
12
24
1
1
1
2
2
4
1
2
*
REQ'D (NO. REQ'D)(NO. REQ'D)
TYPE
GUARDRAIL
N/A
N/A
26•"
9•"
18"
2"
9•"
9•"
9•"
9•"
* 26•"
18"
(1‚" LONG)
EXTEND MORE THAN •" BEYOND NUT.
(OR TYPE T) TO GUARDRAIL, TYPE BD (OR TYPE TD). POST BOLTS SHALL NOT
* EXCEPT AS SPECIFIED ON DETAIL SHOWING TRANSITION FROM GUARDRAIL, TYPE B
AND 8 ON TYPE B END).
THRIE BEAM TRANSITIONS REQUIRE 20 SPLICE BOLTS EACH (12 0N TYPE T END
1‚" (SPLICE BOLT)
SEE CHART (POST BOLT)
1Š"
†"
“"Š"
•"
+ˆ
"
-
"
1„
"
†"
RECESS ONE OR BOTH SIDES
•" DIA. x ˆ" DEEP¤"1ƒ" DIAMETER
•" DIAMETER
1‚" •"
0.012" THICK
ƒ" DIA. HOLE
+ „
"
1•
" ƒ"
ƒ"
1" 3"
4" + „"
METAL TAG
EMBOSSED ƒ" HIGH ON THE
CURVED GUARDRAIL RADIUS
FOR CURVED GUARDRAIL WITH RADIUS OF 150' OR LESS 1715R-60-J
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
MINIMUM POST BOLT THREAD LENGTHAT BEAM ELEMENT SPLICE POSTS AND AT INTERMEDIATE POSTS
POST BOLTS, SPLICE BOLTS AND WASHERS
STANDARD WIDTH VARIABLE WIDTH (FIELD BEND)
8"
MA
X.
OF TRAFFIC
DIRECTION
OF TRAFFIC
DIRECTION
APPROX. 6'-3"
BOLT LENGTH MINIMUM THREAD LENGTH
18"
26•" 3"
9•" 1ƒ"
2•"
POSTBLOCK
OFFSET
POST BOLTS
NO. LENGTH
SPLICE BOLTS WASHERS
(ROUND)
REQ'D (NO. REQ'D)(NO. REQ'D)
TYPE
GUARDRAIL(1‚" LONG)
WOOD
STEEL
WOOD
WOOD
1
216
2
* 26•"
9•"MGS-8D
WOOD
STEEL
WOOD
WOOD
1
18
1
1
9•"
18"MGS-8
1716
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
PAY ITEM: GUARDRAIL, TYPE MGS-8D
GUARDRAIL, TYPE MGS-8 TO GUARDRAIL, TYPE MGS-8D
DETAIL SHOWING TRANSITION FROM
OFFSET BLOCKS (TYPE MGS-8D) 6" x 1'-0" x 1'-2"
OFFSET BLOCKS (TYPE MGS-8D) 6" x 9" x 1'-2"
2'-4" FOR TYPE MGS-8D
POST BOLT LENGTH
2'-10" FOR TYPE MGS-8D
POST BOLT LENGTH
GUARDRAIL, TYPE MGS-8
PAY ITEM EACH SIDE:
NUT.
TO GUARDRAIL, TYPE MGS-8D POST BOLTS SHALL NOT EXTEND MORE THAN •" BEYOND
* EXCEPT AS SPECIFIED ON DETAIL SHOWING TRANSITION FROM GUARDRAIL, TYPE MGS-8
ON TYPE MGS END).
THRIE BEAM TRANSITIONS REQUIRE 20 SPLICE BOLTS EACH (12 0N TYPE T END AND 8
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
OF TRAFFIC
DIRECTION
PLACEMENT OF GUARDRAIL REFLECTORS
ONE-WAY TRAFFIC
TWO-WAY TRAFFIC
GUARDRAIL
NOTES GOVERNING THE USE OF GUARDRAIL REFLECTORS
GUARDRAIL REFLECTOR
DIRECTION OF RAIL LAP
TWO-WAY TRAFFIC
ONE-WAY TRAFFIC
3"
2"
ƒ"•
"
(TYP.)
REFLECTORIZED SIDE FACING TRAFFIC
13 GAGE GALVANIZED
(0.0934") NOMINAL
2ƒ"
5"
‚" R
1•
"96° + 4°
OF TRAFFIC
DIRECTION
OF TRAFFIC
DIRECTION
OF TRAFFIC
DIRECTION
OF TRAFFIC
DIRECTION
TRAFFIC
SURFACE FACING
REFLECTORIZED GUARDRAILSEE NOTES BELOW
OF TRAFFIC
DIRECTION
GUARDRAIL
SEE NOTES BELOW
ADJACENT GUARDRAIL POSTS
IN OPPOSITE DIRECTIONS ON
PLACE GUARDRAIL REFLECTORS
OF TRAFFIC
DIRECTION
OF TRAFFIC
DIRECTION
GUARDRAIL
HEIGHT AND COMPATIBILITY WITH POST HOLES.
THE POST BOLT HOLES SHALL BE LOCATED TO ENSURE PROPER RAIL
DEPTH OF THE BLOCK SHALL BE AS SPECIFIED ON THIS STANDARD AND
BEVELS SPECIFIED. THE LENGTH (FRONT AND BACK FACE), WIDTH AND
A 1" BEVELED TOP MAY BE USED IN LIEU OF WOOD BLOCKS WITHOUT
WOOD OFFSET BLOCKS WITH •" BEVELS AT THE TOP AND BOTTOM OR
HEIGHT.
THE POST BOLT HOLES SHALL BE LOCATED TO ENSURE PROPER RAIL
DEPTH OF THE POST SHALL BE AS SPECIFIED ON THIS STANDARD AND
WOOD POSTS WITHOUT BEVELS SPECIFIED. THE LENGTH, WIDTH AND
WOOD POSTS WITH •" BEVELS AT THE TOP MAY BE USED IN LIEU OF
BENT SECTION WILL BE REQUIRED FOR EACH CURVED ELEMENT.
150' OR LESS. A TAG IDENTIFYING THE CURVATURE OF THE SHOP
BEAM ELEMENTS SHALL BE SHOP BENT TO PLAN RADIUS FOR CURVE RADII
GUARDRAIL.
SHOULD BE MEASURED FROM THE GROUND JUST IN FRONT OF THE
THE GUARDRAIL PANEL IS LOCATED BEHIND THE CURB THE RAIL HEIGHT
CLOSEST TO THE EDGE OF THE TRAVELED LANE. WHEN THE FACE OF
GUTTER PAN, WHICH IS THE POINT ON THE GUTTER PAN THAT IS
THE RAIL HEIGHT SHOULD BE MEASURED FROM THE FRONT EDGE OF THE
WHEN THE FACE OF GUARDRAIL IS PLACED FLUSH WITH FACE OF CURB,
GUIDE TO STANDARDIZED HIGHWAY BARRIER HARDWARE."
AGC-ARTBA JOINT COMMITTEE, TASK FORCE 13 PUBLICATION TITLED "A
DETAILS SPECIFIED ON THIS STANDARD ARE ACCORDING TO THE AASHTO-
NOTES:
GUARDRAIL ANCHORAGE, BRIDGE.
GUARDRAIL DEPARTING TERMINALS AND STANDARD PLAN R-67-SERIES FOR
GUARDRAIL APPROACH TERMINALS, STANDARD PLAN R-66-SERIES FOR
SEE STANDARD PLAN R-61-SERIES, R-62-SERIES OR R-63-SERIES FOR
1717
MICHIGAN DEPARTMENT OF TRANSPORTATION
OF
SHEET
PLAN DATEF.H.W.A. APPROVAL
BUREAU OF DEVELOPMENT STANDARD PLAN FOR
R-60-J
BY THE ENGINEER.)
REASONABLY LEVEL BEYOND THE SHOULDER HINGE POINT, AS DETERMINED
EMBEDDED FOR ADDED STABILITY. (NOT NECESSARY WHEN THE SLOPE IS
PLAN, 8'-0" POSTS SHALL BE PROVIDED, WITH THE ADDITIONAL LENGTH
THE SHOULDER HINGE POINT, RATHER THAN AS SPECIFIED ON THIS
WHEN THE PLANS SPECIFY GUARDRAIL (TYPE B OR T) TO BE PLACED ON
REGARDLESS OF ROADWAY LIGHTING.
1. GUARDRAIL REFLECTORS SHALL BE USED ON ALL STANDARD GUARDRAIL RUNS,
b) 25'-0" ON CURVES WITH A RADIUS LESS THAN 1150'.
1150' OR MORE.
a) 5O'-0" ON TANGENT SECTIONS AND CURVES WITH A RADIUS OF
2. GUARDRAIL REFLECTORS ARE TO BE SPACED AT THE FOLLOWING INTERVALS:
APPROPRIATE GUARDRAIL APPROACH TERMINAL STANDARD PLAN.
3. FOR GUARDRAIL REFLECTOR PLACEMENT ON APPROACH TERMINALS, SEE THE
GUARDRAIL DEPARTING TERMINAL.
4. A GUARDRAIL REFLECTOR IS TO BE PLACED ON THE SECOND POST FROM THE
PLACED ON THE UPPER POST BOLT.
5. ON GUARDRAIL, TYPE T AND TYPE TD GUARDRAIL REFLECTORS ARE TO BE
6. GUARDRAIL REFLECTORS SHALL MATCH COLOR OF EDGE LINE.
BY THE ENGINEER.)
REASONABLY LEVEL BEYOND THE SHOULDER HINGE POINT, AS DETERMINED
EMBEDDED FOR ADDED STABILITY. (NOT NECESSARY WHEN THE SLOPE IS
9'-0" POSTS SHALL BE PROVIDED, WITH THE ADDITIONAL LENGTH
SHOULDER HINGE POINT, RATHER THAN AS SPECIFIED ON THIS PLAN,
WHEN THE PLANS SPECIFY GUARDRAIL TYPE MGS-8 TO BE PLACED ON THE
MGS-8, & MGS-8D
TYPES A, B, BD, T, TD,
GUARDRAIL,
5-14-2020
MICHIGAN DESIGN MANUALROAD DESIGN
3.08
3R, 4R AND OTHER PROJECTS
3.08.01 (revised 5-27-2020)
General
A. (3R) Resurfacing Restoration and Rehabilitation
This work is defined in 23 CFR (Code of Federal Regulations) as "work undertaken to extend the service life of an existing highway and enhance highway safety. This includes placement of additional surface material and/or other work necessary to return an existing roadway, including shoulders, bridges, the roadside and appurtenances to a condition of structural or functional adequacy. This work may include upgrading of geometric features, such as widening, flattening curves or improving sight distances." Examples of this type of work include:
1. Resurfacing, milling or profiling, concrete overlays and inlays (without removing subbase).
2. Lane and/or shoulder widening (no increase in number of through lanes).
3. Roadway base correction.
4. Minor alignment improvements.
5. Roadside safety improvements.
6. Signing, pavement marking and traffic signals.
7. Intersection and railroad crossing upgrades.
8. Pavement joint repair.
9. Crush and shape and resurfacing.
10. Rubblize and resurface.
3.08.01A (continued)
11. Intermittent grade modifications (used to correct deficiencies in the vertical alignment by changing the paving profile for short distances) that leave the existing pavement in service for more than 50% of the total project length.
12. Passing relief lanes.
See Chapter 12 of the Bridge Design Manual for examples of “bridge” 3R work.
B. (4R) New Construction/ Reconstruction
Projects that are mainly comprised of the following types of work are not considered 3R.
1. Complete removal and replacement of pavement (including subbase).
2. Major alignment improvements.
3. Adding lanes for through traffic.
4. New roadways and /or bridges.
5. Complete bridge deck or superstructure replacement.
6. Intermittent grade modifications (used to correct deficiencies in the vertical alignment by changing the paving profile for short distances) that leave the existing pavement in service for less than 50% of the total project length.
The above lists are not all inclusive, but are intended to give typical examples of 3R and 4R work.
MICHIGAN DESIGN MANUALROAD DESIGN
3.08.01 (continued)
General
E. Design Exceptions / Variances
The sections to follow include standards for geometric design elements for the various classifications of roadways and work types. For specific controlling geometric design elements, a formal design exception must be submitted and approved when the standards cannot be met. Other specific elements and conditions will require a less formal design variance when standards cannot be met.
3.08.01 (continued)
During the review process the Geometric Design Unit will review plans and identify the need for Design Exceptions (DE) or Design Variances (DV) when standards are not met for specified geometric design elements. These elements are listed below with their corresponding level of documentation and/or approval.
Non-Standard Design Element (NHS and Non-NHS) (See Section 3.11.01 for DE Criteria for 3R freeway work)
Applicability of Design Exception (DE) Design Variance (DV)
Design Speed
≥ 50 MPH < 50 MPH
Design Speed < Posted Speed DE DE
Lane Width* DE DV
Shoulder Width DE DV
Horizontal Curve Radius* DE DV
Superelevation Rate* DE DV
Superelevation Transition* DV DV
Maximum Grade* DE DV
Stopping Sight Distance (Horizontal and Vertical)*
DE DV
Cross Slope DE DV
Vertical Clearance DE DE
Design Loading Structural Capacity DE DE
Ramp Acceleration / Deceleration Length* DV DV
*Values based on design speeds less than posted.
Design Exception (DE) - Design Exception requests are submitted on Form DE26 and require approval by the Engineer of Road Design or the Chief Structure Design Engineer. With the exception of low speed (< 50 mph) vertical clearance DE’s, subsequent FHWA approval is required for DE elements specifically designated for federal approval in the Project Specific Oversight Agreement (PSOA). Design exceptions should be addressed as early in the life of a design as possible, preferably during the scoping process.
Along with the justification for not meeting MDOT and/or AASHTO standards the design exception includes a crash analysis and the estimated total cost required to attain full standards compliance. See Section 14.11 for design exception submittal procedures.
MICHIGAN DESIGN MANUALROAD DESIGN
3.11.03 (continued)
Safety Considerations
K. Clear Zones & Fixed Objects
The current clear zone criteria specified in Section 7.01.11 should be used when upgrading freeways. Obstacles within these limits should be shielded or removed. Obstacles beyond these limits, but within the recovery area, should be reviewed by the Geometrics Unit in the Design Division.
L. Culvert End Treatments
The ends of culverts located within the clear zone on projects programmed for upgrading shall be according to MDOT Drainage Manual, Section 5.3.5.
M. Bridges
See the Bridge Management Unit, Construction Field Services Division for FHWA conformance requirements.
3.12 (revised 5-27-2020)
UNDERCLEARANCES
A. 4R Freeway
Roadway 4R projects on the Freeway System must be designed to meet the current AASHTO vertical clearance requirement of 16'-0" (16'-3" is desired for future overlay of the road). Scoping of projects must include a determination of the most effective means of obtaining the vertical clearance standard. A cost/benefit analysis to determine how best to achieve the standard, either in full or with incremental progress needs to be prepared. The analysis should include the alternatives of obtaining all vertical clearances with the road project, a bridge project, or some combination of road and bridge work to meet the clearance requirements. In many cases it may not be possible to achieve the complete vertical clearance with the proposed road project. If the most efficient plan for meeting the vertical clearance requirement is incremental progress, a design exception will be required. The design exception should be submitted as soon as possible, preferably prior to the submittal of the call for projects. This assures that design is not started on projects that may not be approved. The following is the minimum information required to prepare a vertical clearance analysis. This information is also required if a design exception is submitted.
Preliminary grades for the bridge and approaches, the route under the structure, and ramps if appropriate.
Location of existing structure foundations related to the proposed grade changes.
Impact evaluation on existing drainage.
Evaluation of any other deficient geometric feature.
MICHIGAN DESIGN MANUALROAD DESIGN
3.12A (continued)
UNDERCLEARANCES
Determination of ROW needs.
Impacts on Environment.
Cost estimates for alternatives to meet vertical clearances.
Proposed time frame when the remainder of vertical clearance will be achieved (rough estimate)
Accident analysis where appropriate.
Soils (cut and fill information) and ground water information.
Impact on local businesses and residences.
User costs, constructability, maintaining traffic scheme and maintenance cost.
B. 4R Arterials
On Roadway 4R projects on Arterial systems, where no work is scheduled for the bridges, the bridges are considered existing structures and can be retained if they meet the 14'-6" vertical clearance standard, therefore no design exception is required. The existing clearance must be retained. It must not be reduced. Although not required, an evaluation should be performed to determine how best to achieve the standard, either in full or with incremental progress. Obtaining incremental progress toward the vertical clearance requirement with the road 4R project could prevent other more costly construction with the next major bridge rehabilitation or replacement project.
C. 4R Collectors and Local Routes
Maintain existing vertical clearance and a minimum of 14'-6" (14'-9" is desired on 4R projects if possible.)
3.12 (continued)
D. 3R Freeway
If the existing vertical clearance is not reduced and a crash pattern involving high load hits does not exist on a 3R freeway project, the vertical clearance may be retained without a design exception. However, if the vertical clearance is reduced to a value less than the standard (table value), a design exception will be required. The format for the design exception does not require a detailed evaluation but should include the basis for the request and review of the accident history and high load hits for the structures in the immediate vicinity of the structure.
E. 3R Arterials
On roadway 3R projects on Arterial systems, the bridges are considered existing structures and can be retained if they meet the 14'-0" vertical clearance standard, therefore no design exception is required. The existing vertical underclearance must be retained. Although not required, an evaluation should be performed to determine how best to achieve the standard, either in full or with incremental progress. Obtaining incremental progress toward the vertical clearance requirement with the road 3R project could prevent other more costly construction with the next major bridge rehabilitation or replacement project.
A design exception is required to maintain the vertical clearance below 14'-0". The likelihood of obtaining design exceptions for reducing vertical clearance is extremely remote.
F. Preventive Maintenance
Project scope of work includes but is not limited to road work consisting of thin HMA overlays, pavement grinding, concrete joint repair, slurry seal (shoulders only), and seal coat (shoulders only). Maintain existing vertical clearance. No design exception is required.
MICHIGAN DESIGN MANUALROAD DESIGN
3.12 (continued)
UNDERCLEARANCES
G. Vertical Clearance Requirement Table
The desired vertical bridge underclearance should be provided as indicated below. If the desired underclearance cannot be provided, then the minimum underclearance shall be met. Where it is considered not feasible to meet these minimums, a design exception shall be requested. See the vertical underclearance design exception matrix in this section and Section 12.02 of the Bridge Design Manual. Requests to further reduce the underclearance of structures with existing vertical clearance less than indicated in the chart below should be made only in exceptional cases.
VERTICAL CLEARANCE REQUIREMENT TABLE
Route Classification Under the Structure
All Construction (Desired)
New Construction (Min *)
Road 4R Construction (Min *)
Bridge 4R Construction (Min *)
3R Construction (Min *)
Freeways 16’-3” 16’-0” 16’-0” 16’-0” 16’-0” ***
NHS Arterials ( Local & Trunkline)
16’-3” 16’-0” Maintain Existing ** and 14'-6" Min
16’-0” Maintain Existing ** and 14'-0" Min
Non NHS Arterials (Local & Trunkline)
16’-3” 14’-6” Maintain Existing ** and 14'-6" Min
Maintain Existing ** and 14'-6" Min
Maintain Existing ** and 14'-0" Min
Collectors, Local Roads & Special Routes (1) 14’-9” 14’-6” Maintain Existing **
and 14'-6" MinMaintain Existing **
and 14'-6" MinMaintain Existing **
and 14'-0" Min
* Minimum vertical clearance must be maintained over complete usable shoulder width.
** Existing vertical clearances greater than or equal to the minimums shown may be retained without a design exception. Vertical
clearance reductions that fall below the minimums for new construction require a design exception.
*** Existing vertical clearances may be retained (or increased) without a design exception unless a pattern of high load hits exists.
Vertical clearance reductions below the standard (table value) require design exceptions.
Information on the NHS system can be obtained by contacting the Statewide Planning Section, Bureau of Transportation Planning or found on the MDOT Web site at: http://www.michigan.gov/mdot-nfc
(1) Special Routes are in highly urbanized areas (where little if any undeveloped land exist adjacent to the roadway) where an alternate route of 16'-0" is available or has been designated. Bridges located on Special Routes in Highly Urbanized Areas can be found on the MDOT website at: https://mdotjboss.state.mi.us/stdplan/getStandardPlanDocument.htm?docGuid=c7b8d687-0bcd-4ea6-a614-47736321799e
Ramps and roadways connecting a Special Route and a 16’-0” route require a vertical clearance minimum of 14’-6” (14’-9” desired). Ramps and roadways connecting two 16’-0” routes require a vertical clearance minimum of 16’-0” (16’-3” desired).
Pedestrian bridges are to provide 1’-0” more underclearance than that required for a vehicular bridge. For freeways (Interstate and non Interstate), including Special Route
Freeways, the desired underclearance shall be 17’-3” (17’-0” minimum).
A vertical clearance of 23’-0” is required for highway grade separations over railroads. Clearance signs are to be present for structures with underclearance 16’-0” or less (show dimensions 2” less than actual). See https://mdotjboss.state.mi.us/TSSD/tssdHome.htmfor additional information and guidelines.
For shared use paths (pedestrian and bicycle) the vertical clearance to obstructions, including overhead fencing, shall be a minimum of 8’-6” (10’-0” desired). However, vertical clearance may need to be greater to permit passage of maintenance and emergency vehicles. In undercrossings and tunnels, 10’-0” is desirable for vertical clearance. See AASHTO’s Guide for the Development of Bicycle Facilities.
MICHIGAN DESIGN MANUAL ROAD DESIGN
CHAPTER 6 SURFACING AND SHOULDERS INDEX (continued)
6.06.15 Minimum Curb and Gutter Grades
6.06.16 Curb and Gutter for Erosion Control
6.06.17 Concrete Curb Cap
6.06.18 Deleted
6.06.19 Driveway Openings
6.06.20 Curb and Gutter Adjacent to HMA Base Course
6.07 CONCRETE DIVIDER
6.08 SIDEWALK
6.08.01 Department Position on Sidewalk Construction
6.08.02 Thickness
6.08.03 Reinforcement
6.08.04 Earth Excavation for Sidewalk
6.08.05 Curb Ramps A. Warrants for Curb Ramps and Curb Ramp Upgrade B. Scoping Considerations C. Design Standards D. Meeting Existing Sidewalk Grades and Elevations E. Accessibility Constraints F. Driveways G. Curb Ramp Location H. Traffic and Pedestrian Signals
6.08.06 Building Entrances A. Building Access Alterations B. Historic Buildings and Districts
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.04
CONCRETE CONSTRUCTION
6.04.01
History of Concrete Paving in Michigan
The first mile of rural concrete pavement in the nation was located on Woodward Avenue between 6 and 7 Mile Roads. The 17'-8" wide pavement was built by the Wayne County Road Commission and completed in 1909.
The beginning of the state trunkline system can be traced to a law enacted in 1913. At the time, road building was largely HMA and water-bound macadam on the "Class A" roads close to cities; gravel and earth predominated everywhere else. Although records are sketchy, it appears that the first concrete paving project, let for contract by the state, was on Dixie Highway just north of Monroe, in 1918. The circumstances of this project are peculiar in that it appears that the original contract was let by the Monroe County Road Commission. The original contractor went bankrupt so the project was taken over by the Department, which let a new concrete paving contract.
6.04.02 (revised 5-27-2020)
Glossary of Terms
Aggregate interlock - Load transfer that occurs across a concrete fracture by virtue of the irregular nature of the fracture surfaces due to cracking around, rather than through, the aggregate particles. The faces must be held in close proximity to one another in order to develop aggregate interlock.
Base plate - The galvanized metal base of joint dowel baskets that last appeared on Standard Plan E-4-A-130E (October 1963) and on E-4-A-138. Its purpose was to prevent sand from working up into the joint (It was used prior to subbase stabilization).
6.04.02 (continued)
“Black and white job" - A non-technical term referring to a roadway having both HMA surfaced and concrete surfaced lanes.
Blow-up - The upheaval and sometimes spectacular shattering of a concrete pavement caused by hot weather expansion in combination with loss of room for expansion, infiltration of incompressibles, and loss of cross-section in the lower portion of the joint, with consequential reduction of compressive stability and compressive strength. Usually occurring at a joint, it may commence in the period when the pavement is 8 to 18 years old.
Bonded overlay - A concrete overlay of an existing pavement that is encouraged to chemically and physically bond to the underlying pavement surface. The existing surface must be thoroughly cleaned by milling, grinding, or sand or water blasting prior to resurfacing.
Bulkhead joint - The formed joint, either longitudinal or transverse, between two adjacent concrete slabs, created when one slab is cast up against another already hardened slab.
Cold joint - The division between two concrete pours, one of which has begun to set before the other is cast against it. This disparity prevents the mixture from forming a continuous uniformly consolidated mass and may lead to separation of the concrete along this same line of division at sometime in the future.
Composite pavement - A portland cement concrete pavement with an HMA overlay
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.04.02 (continued)
Glossary of Terms
Concrete base course - A concrete pavement slab intended to be overlaid with a surface course, usually an HMA surface course. Hence, more tolerance in the surface finish is acceptable, joints are not separately sealed, etc.
Concrete pavement - As normally used in the Department, a term referring to a pavement on which the portland cement concrete is the riding surface, as distinguished from concrete base course.
Continuously Reinforced Concrete Pavement (CRCP) - Concrete pavement which contains substantial steel reinforcement. Steel reinforcement (commonly #4 or #5 bars) is placed in either the longitudinal direction or in both directions. CRCP pavement does not normally contain joints except at structures.
Contraction Joint - A joint in concrete pavement that serves as a plane of weakness joint. Movement in the slab due to contraction occurs here.
Crg Joint (Contraction-Reinforced-Grouted) - A contraction joint between an existing concrete pavement and a full depth concrete pavement repair. Epoxy coated load transfer bars are drilled and grouted in the existing pavement at the joint.
Curb-cut - A rounded reduction of curb height such as is encountered at a driveway or curb ramp.
6.04.02 (continued)
D-cracking - Deterioration along transverse or longitudinal pavement joints or cracks, caused by moisture absorption in the concrete coarse aggregate near the joint, with cracking occurring during subsequent cycles of freezing and thawing. This type of cracking takes its name from the characteristic concentric semicircular (as viewed in the vertical plane) hairline cracks that appear as parallel lines on the surface. These cracks often contain calcium hydroxide residue causing a dark surface stain. The deterioration progresses to a series of parallel cracks adjacent to the joint and eventually to disintegration and spalling, under traffic, 1’ to 2’ away from the joint.
Dowel basket - See "Load Transfer Assembly”
Dowel Bar Inserter - A machine that inserts load transfer dowels directly into the plastic concrete at contraction joints, eliminating the need for dowel baskets.
Drilled-in anchor - A method for anchoring a bar into an existing concrete structure. The bars are inserted into a previously drilled hole and anchored by an epoxy grout.
Durability, specifically, freeze-thaw durability - A term applied to the coarse aggregate in concrete to indicate its ability to resist the action of freezing and thawing while in a moisture saturated condition. Until 1988, it was expressed in terms of "Durability Factor" (0 = poor to 100 = excellent). In 1988, durability values were changed to dilation (expansion, expressed in units of percent per 100 cycles of freezing and thawing), with values from 0.000% (excellent) to about 0.200% (poor, failure in 12 cycles). Dilation of 0.067% per 100 cycles is equal to a durability factor of 20, which was a minimum specification limit from 1976 to 1988. A value of 0.040% per 100 cycles relates to the former durability factor of 36, and is the current minimum for freeway pavements.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.06
CURB AND GUTTER
6.06.01
References
Department Standard Plans
R-29-Series, “Driveway Openings & Approaches, and Concrete Sidewalk”
R-30-Series, “Concrete Curb and Concrete Curb & Gutter”
R-31-Series, “Integral Curb and Integral Curb & Gutter”
R-32-Series, “Approach Curb & Gutter, Downspouts (For Bridge Barrier on Rural Highways)”
R-33-Series, "Concrete Valley Gutter and Urban Freeway Curb”
R-38-Series, "Concrete Divider”
6.06.02 (revised 5-27-2020)
Glossary of Terms
Back of curb - The vertical plane of the curb, or curb and gutter, structure, farthest from the roadway.
Barrier curb - In Department usage, a curb having a near - vertical front face of over 6” in height. (See definition of mountable curb, below, and further discussion under Section 6.06.05.)
Curb cut - A rounded reduction of curb height such as is encountered for an opening at a driveway or curb ramp.
6.06.02 (continued)
Face of curb - The vertical plane of the curb structure closest to the roadway.
Face-to-face - The distance between the two front faces of curbs on opposite sides of the street, shown on plans as "f-f".
Gutter pan - The horizontal portion of curb and gutter, i.e., that portion of the curb and gutter structure exclusive of the curb.
Integral curb - (Or integral curb and gutter) - The condition when the curb or curb and gutter is cast monolithically with the concrete pavement structure. When so constructed, there is obviously no visible joint line defining a gutterpan width and so it is impossible, by observation, to determine the nominal width, if any, of the gutter pan.
Mountable curb - In Department usage, a low curb height or having a low sloping or rounded face such as to allow a vehicle to drive over rather easily. (See definition of barrier curb, above, and further discussion under Section 6.06.05.)
Roll curb - (Or roll curb and gutter) - A mountable curb having a broadly rounded curb face that allows a vehicle driving over the curb rather easily.
Traffic control - The use of a linear structure, most often curb or curb and gutter, to visibly and physically define preferred points of ingress and egress to or from areas adjacent to the roadway.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.02 (revised 5-27-2020)
Thickness
Concrete sidewalks are normally 4” thick. When part of a driveway, it should be constructed to the same thickness as the driveway approach, as detailed on Standard Plan R-29-Series. See Section 12.08.03D.
When it is determined at the Plan Review Meeting that there is evidence of trucks encroaching on curb returns at short-radius intersections or where the potential for encroachment will exist after project completion, the designer should call for 6” thick concrete for sidewalk and curb ramps within the return. This thickness can be increased if there is potential for very heavy trucks to encroach on the return.
6.08.03
Reinforcement
Sidewalks are usually not reinforced. Occasionally, a municipality will request the Department to reinforce sidewalk within its limits. If such reinforcing of sidewalk is standard municipal policy elsewhere, the sidewalk may be reinforced at project cost.
The plans should note that 6” x 6” mesh should be used, with either No. 10 wire weighing 21 pounds per 100 sft or No. 6 wire weighing, 42 pounds per 100 sft, whichever is the municipal standard.
6.08.04
Earth Excavation for Sidewalk
Any earth excavation and backfilling required for construction of sidewalk is included in the pay item for sidewalk.
6.08.05 (revised 5-27-2020)
Curb Ramps
Curb ramps are mandated by Act 8, P.A. of 1973 (amended by Act 35 in 1998), as was the issuance of Standard Plan R-28-Series, “Curb Ramp and Detectable Warning Details". FHWA guidance indicates that ramps be constructed whenever construction involves curb or sidewalk. On May 8, 1973, the Department extended this requirement, by policy to include resurfacing projects that did not ordinarily require the replacement of existing curb or sidewalk.
Federal mandates followed this State law in conjunction with the Americans with Disabilities Act of 1990. The United States Access Board published the Americans with Disabilities Act Accessibility Guidelines (ADAAG) in 1991 and subsequently extended its application to Public Rights of Way in 1994. The Access Board later published the Public Rights of Way Accessibility Guideline (PROWAG) to address accessibility issues specific to public rights of way.
It should be emphasized that there is little permitted reason for failure to place or upgrade a curb ramp on a road construction project if a sidewalk meets a curb in an obvious crosswalk situation. An "obvious crosswalk situation" would be where a sidewalk intersects with the roadway, whether or not there are painted crosswalk lines or a traffic signal present.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05 (continued)
Curb Ramps
A. Warrants for Curb Ramps and Curb Ramp Upgrade
Based on FHWA guidance, curb ramp construction and/or curb ramp upgrade be incorporated with new construction, and roadway alterations.
New Construction refers to the initial construction of a new roadway facility on a new alignment for which new right of way is acquired. Curb ramp installation is required and new construction standards are fully enforced.
Alteration refers to changes that affect or could affect the usability of an existing roadway facility. Curb ramp installation and upgrading is required prior to or at the time of a roadway alteration. New construction standards are applicable to the maximum extent practicable.
Maintenance refers to maintenance activities that do not affect the usability of an existing road. Curb ramp accessibility upgrades are not required to be performed in conjunction with maintenance treatments.
The U.S. Department of Justice and the FHWA issued a joint Technical Assistance memo in 2013 to clarify which roadway treatments fall within the definition of an alteration and which are considered maintenance.
6.08.05A (continued)
Alterations include:
Reconstruction
Rehabilitation – including cold milling & resurfacing, slab replacement, slab jacking, widening, adding pavement structural capacity.
Open-Graded Surface Course (open graded friction course)
Micro-surfacing (includes rut filling)
Double Chip Seal
HMA Overlay (regardless of thickness)
Cape Seal - (Chip seal capped with a slurry seal, micro-surface or other treatment to fill voids in a chip seal).
In-Place Asphalt Recycling
Other condition requiring accessibility upgrading includes:
Altered crossings through driveways. See Section 6.08.05F for driveway applications.
Independent shared use path crossing are treated the same as sidewalks with regard to accessible roadway crossings.
Installation of pedestrian signals. See Section 6.08.05G.
Existing curb ramps without detectable warnings but otherwise compliant must be retrofitted with detectable warnings in conjunction with alterations to an existing roadway.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05A (continued)
Curb Ramps
Maintenance includes:
Crack Filling and Sealing Surface Sealing (liquid sealant) Chip Seals Slurry Seals Fog Seals Scrub Sealing Joint Crack Seals Joint Repairs Dowel Retrofit Spot High Friction Treatments Diamond Grinding Pavement Patching
Other routine operations where curb ramp upgrades are not required include:
Signing, pavement marking projects.
Guardrail/Safety upgrade projects.
Landscape/Streetscape projects (except where an existing sidewalk or curb ramp is altered)
Independent Utility Work/Maintenance (except where an existing sidewalk or curb ramp is altered or when work is extensive such that an entire crosswalk is reconstructed)
Two or more maintenance treatments may be combined and still be considered a maintenance treatment. However, if more than one of those treatments contains aggregate and/or filler, the combination will be considered an alteration.
For example a cape seal is an integrated system comprised of two maintenance treatments, a chip seal and a slurry seal. The slurry seal includes aggregate and filler to fill the voids of the aggregate in the chip seal. They combine as an alteration.”
6.08.05 (continued)
B. Scoping Considerations
If the projects limits include only a portion of an intersection, all ramps within the intersection shall be evaluated for compliance and the project limits extended to include all ramps.
Smaller scale projects such as CPM may still require a right of way phase to accommodate consent to tie into existing sidewalk outside the right of way. See Section 5.05.02 for more information on right of way requirements.
Alteration projects will likely require accurate contour and elevation information prior to designing compliant curb ramps.
C. Design Standards
Standard Plan R-28-Series details the requirements for ramp width, cross slope, running slope, landings, curb transition, and detectable warning surfaces. Designers should investigate site conditions in order to determine and design the appropriate treatment for each curb ramp location. Where fully compliant curb ramps are impracticable, compliance is required to the maximum extent practicable. See Section 6.08.05E“Accessibility Constraints”. This will require preliminary field work in order to design for maximum practicable compliance.
The curb ramp types detailed on Standard Plan R-28-Series represent some of the more conventional applications. Existing conditions may require variations not shown on the standard. The designer may need to combine the features of two or more ramp types to provide a compliant design.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05C (continued)
Curb Ramps
There are several basic elements that should be incorporated into the design. These are:
1. Minimum width (5 ft.). The minimum width of 5 ft. allows side by side wheelchair passing and is consistent with most sidewalk widths. Sidewalks less than 5 ft. wide require a 5 ft. x 5 ft. wide passing space every 200 ft. or less. In order to accommodate unavoidable existing width restrictions the PROWAG allows a reduction to not less than 4 ft.
2. Maximum running slope (8.3%). The maximum running slope is absolute and therefore a target maximum of 5% to 7% is used to allow for construction inconsistencies. However, the running slope shall not require the ramp length to exceed 15 ft. (See Section 6.08.05D“Meeting Existing Sidewalk Grades and Elevations”).
3. Maximum cross slope (2%). The maximum cross slope is absolute for ramps at intersections except as stated below. Designers should use a target cross slope less than the maximum to account for inconsistencies in concrete finishing.
When resurfacing or reconstructing existing roadways, the ramp cross slope may be blended to meet existing steeper roadway grades. Significant redesign of an existing cross road to accommodate a ramp cross slope commonly exceeds the scope of a roadway alteration. The curb ramp cross slope should be transitioned through the full length of the ramp to minimize abrupt changes. If opportunities within the roadway construction scope of work are available to achieve even partial compliance, they should be pursued.
6.08.05C (continued)
For new roadways, the cross slope of the cross walk must not exceed 2% at stop controlled (stop sign) crossings and 5% at signalized and uncontrolled crossings. The cross slope at mid-block crossings may follow the roadway grade.
4. Landing - 5’ x 5’ minimum, 2% max slope in the direction(s) of pedestrian travel. A landing is required at the top of perpendicular ramps. However, if the ramp running slope is less than 5%, it is considered a “blended transition” and does not require a landing. In order to accommodate unavoidable existing width restrictions the PROWAG allows a reduction to no less than 4’ x 4’.
5. Maximum Bottom Counter Slope - (5% and flush with no vertical lip to the ramp). The maximum counter slope is provided to minimize wheelchair front caster snagging at the bottom of the ramp.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05C (continued)
Curb Ramps
6. Detectable Warning - Detectable warnings are truncated domes that serve as surface tactile cues to alert persons with sight disabilities of an upcoming change from pedestrian to vehicular way. The dimensions and location are detailed on Standard Plan R-28-Series.
They are not intended as a way finding device. Square dome alignment within the boundaries of the detectable warning is detailed on the standard plan. However, orientation of the detectable warning surface is relative to placement location. Although preferable, it is not always relative to the direction of travel. Radial alignment is acceptable to match a radial curb alignment.
Detectable warnings are required at the intersection of sidewalks at streets regardless of whether the sidewalk is ramped or flush to the street or shoulder.
In addition to roadway intersections, detectable warnings are also required at mid-block crossings, sidewalk/railroad crossings, and the intersection of sidewalks with controlled commercial driveways (see Section 6.08.05F).
6.08.05C (continued)
7. Grade Break Orientation – The grade break at the curb ramp terminals (top or bottom) should be flush and perpendicular to the direction of travel on the ramp. The objective is to provide a square approach to and from the ramp. The bottom grade break is generally located at the back of curb line for perpendicular ramps. However, it can be located up to 5 ft. from one end of a radial curb line in order to maintain a perpendicular orientation (see Standard Plan R-28-Series).
8. Flared Curb Ramps - When a sidewalk or pedestrian circulation path laterally crosses the curb ramp, the sides of the curb ramp must be flared with a 10% maximum slope as shown in Standard Plan R-28-Series for Flared Curb Ramps.
9. Rolled Curb - When the side of the ramp borders a non-walking surface such as grass or landscaping or a permanent obstruction, a rolled curb is permitted on the side of the ramp. Rolled curb is not defined as vertical faced or by a specified radius but rather curb not limited by the 10% maximum defined for flared curb. It can be as flat or steep as needed.
10. Measurement and Payment - When determining Curb and Gutter, and Curb Ramp Measurements and Payments the following illustration represents the various elements of a curb ramp. It illustrates the breakdown of pay items and their limits of payment.
Any earth excavation and/or backfilling required to construct curb ramp will be included in the pay item for curb ramp, unless the contract documents specifically include separate pay items for this work.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05C (continued)
Curb Ramps
Curb Ramp Measurement and Payment Illustration
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05 (continued)
Curb Ramps
D. Meeting Existing Sidewalk Grades and Elevations
Sidewalk grades generally tend to follow the grade of the bordering street. When the existing sidewalk grade is steep, it becomes more difficult to comply with the maximum curb ramp running slope of 8.3% without “chasing grade” to meet the existing sidewalk. In some cases it results in an infinite run. Excessive ramp runs might also result when the existing sidewalk is at a significantly higher elevation than the adjacent road.
When this occurs, the maximum running slope may be exceeded in order to limit the ramp length(s) to not more than 15 ft. measured from the ramp grade break. The need to exceed the maximum slope must be documented (See Section 6.08.05E). The 15 ft. limit on ramp length does not include the landing or transition slabs to tie into the existing sidewalk. Three examples are illustrated:
Unlike other maximum dimensions, the 15 ft. limit is not absolute. If compliance with the maximum running slope (8.3%) can be achieved by extending the ramp by one or two flags of sidewalk beyond the 15 ft. limit, it should be considered within practicable limits.
A landing is required at the top of perpendicular ramps. However, if the ramp running slope is less than 5%, it is considered a “blended transition” and does not require a landing.
6.08.05D (continued)
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05 (continued)
Curb Ramps
E. Accessibility Constraints
When it is impracticable to meet all standard compliance elements, the standards must be met to the maximum extent practicable. Impracticability does not apply for new roadway construction.
A strict definition of “practicable” is not provided since the potential circumstances for each installation is limitless. Some circumstances of impracticability are clear such as impacts on structural integrity of surrounding features, or an inability to adapt to existing immovable or unalterable conditions. Other circumstances such as real estate limitations and historic preservation can also represent impracticabilities.
The curb ramp elements are not listed in any order of preference or importance. Order of importance may vary for each application. When it is impracticable to provide compliant elements, they should be provided to the maximum extent practicable.
While cost is not itself an acceptable argument for noncompliance, scope can be a prevailing factor. If certain significant efforts required to meet the standard are not otherwise called for in a project, it may be a impracticability. Examples would be utility relocation or the acquisition of right of way for a roadway alteration project. If utility relocation or right of way acquisition is not required in the project for any other reasons, then it is preferred but not required that the same efforts be made solely for ADA compliance. See Section 5.05.02 for more information on fee, easement and consent requirements for sidewalks.
6.08.05E (continued)
When full compliance is impracticable and compromises are necessary, consideration should be given to safe refuge for the pedestrian. Flush transitions and flatter bottom entrances or a marked refuge area in the pavement allows persons in wheelchairs to leave the vehicular way prior to negotiating possible steeper ramp grades or cross slopes that result from impracticability.
When determining the correct balance to provide maximum extent practicable, it is best to follow good engineering judgment. Compromises may be needed for more than one standard element. If full compliance is impracticable, strive for maximum overall improved accessibility. Do not over compensate to favor one element. Over emphasis on a single element may cause a reduction in overall accessibility in comparison to the original condition.
Accessibility constraints should always be documented in the project files using MDOT Form 0370. This is retained as justification to address possible future claims. The documentation should include location, non-compliant element(s), reason for impracticability and maximum extent practicable.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05 (continued)
Curb Ramps
F. Driveways
When project work alters a driveway that crosses a sidewalk or alters the sidewalk abutting a driveway, the crossing through that driveway must be ADA compliant. Sidewalks are normally continuous through residential driveways and don’t require either curb ramps or detectable warnings. However, commercial driveways with curbed returns may present a barrier that requires a curb ramp.
Detectable warnings at commercial driveways are only used when the crossing is signalized or stop controlled with a regulatory stop sign. When this level of traffic control is needed, the driveway presents more of a street-like encounter for persons with sight disabilities and therefore warrants detectable warnings. Otherwise only the curb ramp is required. Overuse of detectable warnings cause misinformation for persons with sight disabilities.
The path crossing through the driveway must meet the standards for sidewalks including width, slope and cross slope. If continuous sidewalk construction or reconstruction is not in the scope of work, a short transition may be required to meet the existing sidewalk cross section at either end of the driveway crossing.
6.08.05 (continued)
G. Curb Ramp Location
Federal Code 28 CFR, Part 36 states;
“4.7.1 Location. Curb Ramps complying with 4.7 shall be provided wherever an accessible route crosses a curb.”
As stated earlier in this section, there are few permitted reasons not to provide curb ramps where a sidewalk crosses a curb. The absence of signals or marked crossings is not sufficient justification to exclude a curb ramp.
However, there are some circumstances, both obvious and obscure, that may affect the determination of curb ramp need and location.
Absence of Sidewalk In most cases the absence of sidewalk, (existing or planned) coincides with exemption from the requirement to provide curb ramps. The ADA does not require the installation of ramps or curb ramps in the absence of a pedestrian walkway with a prepared surface for pedestrian use. The ADA also does not require the provision of sidewalk where none currently exists. However, certain circumstances may require some minimum treatment for a quadrant without sidewalk.
The installation or presence of a pedestrian signal (whether pedestrian activated or not) suggests implicit intent of pedestrian travel. Accessibility from the road to a pedestrian activated signal would be required despite the absence of sidewalk. This may include curb ramps and an accessible path to a level surface at the push button. Where signals are not pedestrian activated and sidewalks are not present, the vertical portion of any curb should be gapped to provide a minimum 5 ft. wide clear opening to the implied path. See Section 6.08.05H for information on Traffic and Pedestrian Signals.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05G (continued)
Curb Ramps
Evidence of Pedestrian Travel Where sidewalk is not provided or planned at either side of a street crossing but there is evidence of pedestrian travel (worn path), a curb ramp is not required. However, the vertical portion of any curb should be gapped to provide a minimum 5 ft. wide clear opening to the path.
Prohibited Crossings Where a sidewalk meets a road and pedestrian crossing is prohibited, a curb ramp is not required at either side of the road. The end of the sidewalk should be delineated by both visible and tactile cues. A sign should be provided prohibiting crossing for all pedestrians. The tactile cue must be either detectable by cane or foot. A barrier approximately six inches in height can be detected by cane. Since a barrier is not always practical or context sensitive, a planted or gravel strip between the end of the sidewalk and the curb can serve as a tactile indication of the end of the pedestrian path. The strip should have a minimum dimension of two feet in the direction of travel.
Detrimental Crossings As previously stated, the absence of cross walk markings or signals does not imply an exemption for the provision of curb ramps. However, even where crossing is not expressly prohibited but is clearly not intended, circumstances may make it prudent to exclude ramps leading to undesirable crossing points. As with prohibited crossings, it may be desirable to end the sidewalk by separating it from the curb with a planted or gravel strip to provide underfoot detection of the path’s end.
6.08.05G (continued)
Examples of undesirable crossing situations are at mid-block locations or three legged intersections where crossings may lead to or near driveways. Turning traffic from driveways may not expect pedestrians where a crossing is not clearly marked. The same may also be true where cross roads are slightly jogged across the mainline roadway. An unmarked crossing that is offset too far from an intersection may cause a hidden vehicle/pedestrian conflict.
Logical crossing opportunities should be selected at reasonable intervals that provide safer direct corner-to-corner crossing. It may be acceptable at times to direct pedestrians to a safer alternate quadrant or nearby intersection.
When evaluating crossing intent, high consideration should be given to providing ramped crossings to public service destinations such as public transit stops, schools, hospitals, libraries, post offices, etc.
MICHIGAN DESIGN MANUAL ROAD DESIGN
6.08.05 (continued)
Curb Ramps
H. Traffic and Pedestrian Signals
While signal maintenance does not warrant a curb ramp upgrade, new signal installation might. Circumstances requiring curb ramp installation or upgrade in conjunction with signal installation include:
Alteration to existing sidewalk/curb ramp.
Absence of a curb ramp where a sidewalk is curbed at the street intersection.
Absence of a curb ramp where a crossing is served by a pedestrian signal (with or without sidewalk).
See Section 6.08.05G for signal accessibility in the absence of sidewalk.
Existing ramps may remain in place without upgrade if they are not otherwise altered by the signal work.
For roadway alteration projects without signal work, consideration should be made to improve accessibility to push button signals. If the curb ramp is to be upgraded, designers are encouraged to extend paving to provide access to pedestrian activated signals where access is not currently provided.
Curb ramp construction should not reduce the existing level of accessibility of the existing pedestrian signal.
ADA requirements for pedestrian push button signals are addressed separately in Traffic and Safety standards and guidelines. ADA requirements for signal upgrading apply in conjunction with alterations to external components of the signal. Sidewalk or curb ramp construction alone does not activate a requirement to upgrade the signal.
MICHIGAN DESIGN MANUAL ROAD DESIGN
14.10 (continued)
SCOPE VERIFICATION MEETING
NOTE: At this stage, the Project Manager should check to see if the project is required to be on the STIP (Statewide Transportation Improvement Plan). This may be done by accessing: JobNet
Job/CR Search (enter job number) Approved Job
S/TIP
The S/TIP Indicator shows if the project is required to be on the STIP or TIP. The Phase tab in JobNet shows the S/TIP Cycle each phase is proposed for and the status. Project Managers needing clarification concerning the status of the STIP should contact the Region Planner or Statewide Planning Section of the Statewide Transportation Planning Division in the Bureau of Transportation Planning.
14.11 (revised 5-27-2020)
DESIGN EXCEPTIONS / VARIANCES
After the scope verification meeting is held and the project scope has been agreed upon, the Project Manager should identify any Design Exceptions or Variances (DE or DV) to MDOT standards that will be utilized in the design of the project (See Section 3.08.01E). Exceptions and Variances to MDOT design standards should be identified, and, ideally, completed during the scoping process. However, if this has not been done, a Design Exception Request (Form DE26) or Design Variance (Form DV26) should be completed. The Project Manager should consult with the Geometrics Unit of the Design Division when identifying and developing justification for design exceptions or variances. Previously completed Design Exceptions / Variances should also be reviewed for accuracy and revised at this time.
The Project Manager should request that Design Exception/Variance folders be created in ProjectWise under the project number by e-mailing [email protected] with a link to the project or by providing the TSC and the Job Number. Consultant access to ProjectWise should also be requested at this time, if necessary. Two DE folders (MDOT and PoDI) and one DV folder will be created for each project, based on possible oversight type of Design Exception or Variance. The folders will be located under “Supporting Documents” and “Design Exception” or “Design Variance”. For each design exception/variance submitted, the Project Manager should place a single Adobe (.pdf) file (no attachments) containing the Design Exception or Design Variance Form, a site specific crash analysis, and other supporting documents into the folder which matches the project oversight Design Exception type or Design Variance. The Design Exception or Design Variance Form should be flattened or printed to Adobe (no longer fillable). However, the Project Manager should also save a copy of the fillable form for future
MICHIGAN DESIGN MANUAL ROAD DESIGN
14.11 (continued)
DESIGN EXCEPTIONS / VARIANCES
revisions. Changing the "state" of the document to "next" will shift control of the DE document to the Design Exception Coordinator for comments or the DV document to the Region Associate Engineer Development. The Project Manager should address the e-mail that appears after changing state, to the appropriate recipient (DE Coordinator for DE or Region Associate Engineer, Development for DV while maintaining the E-ProjectWise address) to indicate that a Design Exception or Variance has been submitted A similar return e-mail indicates that control has shifted back to the Project Manager with comments provided. Revised documents should be inserted into the Adobe file with comment sheets deleted. Electronic signatures are added to the Design Exception or Variance, Crash Analysis, and Crash Analysis Approval Memo (if necessary) only after all changes are made and the documents are ready to be reviewed by the Engineer of Road Design or the Chief Structure Design Engineer (for DE’s) or Region Associate Engineer, Development (for DV’s).
For projects with “MDOT Oversight”, the completed Design Exception Request (Form DE26) must be approved and signed by the Engineer of Road Design or the Chief Structure Design Engineer. For Projects of Division Interest (PoDI), the completed Design Exception Request (Form DE26) must be approved and signed by the Engineer of Road Design or the Chief Structure Design Engineer and subsequently approved by the FHWA Area Engineer. The Design Exception Request (Form DE26) and instructions (Form DE26Instructions) for completing the form are available on the MDOT website.
Design Variances (Form DV26) are signed by the Region Associate Engineer, Development who then changes the state of the DV to complete the DV process.
For additional information see Sections 3.09.02C, 3.10.03, 3.11.02D and 3.11.03B.
14.12 (revised 12-17-2018)
REQUEST FOR SURVEY / MAPPING (PPD Task Descriptions 3310, 3320, 3330, 3340, 3350 & 4510)
Once the scope is verified, the need for a ground survey and/or aerial photography and/or laser scanning for mapping should be determined. Requests for this work can be made by the Region System Manager, Project Manager/Cost and Scheduling Engineer, or the Design Unit Leader. Ideally, the need for, and the requirements of, survey and mapping on a project should be discussed and agreed upon at the Scope Verification Meeting.
If Right-of-Way (ROW) may be acquired for the project, an early control survey should be ordered immediately to enable Real Estate personnel to begin landowner contact and reduce the timeline through the critical path. This early control survey would consist of horizontal survey control being set throughout the project area, government corners being tied in to the coordinate system, and enough property corners being tied to develop approximate non-legal ROW and property lines throughout the project area.
The Survey/Mapping Action Request (Form 0226) should be used to initiate the work. If survey and/or mapping work was ordered and completed during the Call-for-Projects process or under an EPE phase, and additional information is required, a pick-up survey can be ordered using the above forms.
All survey requests should be directed to the Supervising Land Surveyor or Region Surveyor. The Region will decide whether to do the project themselves or request assistance from Lansing survey staff, either in the field or in hiring consultant surveyors. This should be done as soon as possible to allow for the survey and mapping to be completed in a timely manner that does not impact the project’s critical path.
MICHIGAN DESIGN MANUAL BRIDGE DESIGN - CHAPTER 7: LRFD
7.01.04
Design Loading (8-20-2009)
The design loading is as specified in A 3.6.1.2 of AASHTO LRFD with the exception that the design tandem as specified in a.3.6.1.2.3 shall be replaced with a single 60 kip load.
A. Interstate and Trunklines (8-20-2009)
Vehicular live loading on the roadways of bridges designated HL-93 Mod, shall consist of 1.2 times the combination of the:
Design truck or single 60 kip load Design lane load
Where 90% of two design trucks are combined with 90% of the effect of a lane load for both negative moment and pier reactions per A.3.6.1.3 a 1.2 multiplier shall be applied to the resulting moment or load. Each design lane under consideration shall be occupied by either the design truck or single 60 kip load, coincident with the lane load, where applicable. The loads shall be assumed to occupy 10.0 ft. transversely within a design lane.
The design truck and design lane load are specified in AASHTO LRFD A 3.6.1.2.2 and A 3.6.1.2.4.
B. Local Roads and Streets (8-20-2009)
Structures carrying local roads or streets are to be designed according to county or city standards. The minimum design load acceptable for streets or primary county roads is HL-93 Mod loading as specified in this entire section. (8-6-92)
The load modifying factor, η (eta), related to ductility, redundancy, and operational importance, shall be considered for less important roads (AASHTO LRFD A 1.3.2.1).
7.01.04 (continued)
C. Pedestrian and Bicycle (Nonmotorized) Bridges
Pedestrian and bicycle (nonmotorized) bridges shall be designed according to the current AASHTO LRFD Bridge Design Specifications A 3.6.1.6. and current edition of the Guide Specifications for Design of Pedestrian Bridges. The assumed live load is 90 LBS/SFT. Consideration shall also be given to maintenance vehicles with regard to design loadings and horizontal clearances. For Clear Bridge Width, w, greater than 10'-0", use an H10 truck. For w between 7'-0" and 10'-0", use an H5 truck. Where vehicular access is prevented by permanent physical methods (bollards, gates, etc.) or for w less than 7'-0" the bridge does not need to be designed for a maintenance vehicle.] (8-20-2009) (11-28-2011) (5-25-2015)
D. Railroad Bridges
Railroad bridges are designed according to the current AREMA Specifications, with the Cooper loading established by the railroad company.
E. Section combined with 7.01.04 C. (5-25-2015)
F. Deck Replacement, Bridge Widening or Lengthening
When an existing deck is to be replaced or the structure is to be widened or lengthened, the proposed reconstruction should be designed according to LRFD where practicable. In cases where LRFD cannot be used, the design method shall be approved by the MDOT Chief Structure Design Engineer. (8-20-2009) (11-28-2011) (3-26-2018) (5-27-2020)
G. Ice Force on Piers
All piers that are subjected to the dynamic or static force of ice shall be designed according to the current AASHTO LRFD Bridge Design Specifications. (8-20-2009)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN - CHAPTER 7: LRFD
7.01.04 (continued)
Design Loading
H. Future Wearing Surface
All new bridges and bridge replacements shall be designed for a future wearing surface load of 25 LBS/SFT. (5-6-99)
I. Stay In Place Forms
For new bridges or superstructure replacements a design load of 15 LBS/SFT should be added for the use of stay in place metal forms. (5-6-99)
J. Barrier Loads
For purposes of beam design, the barrier dead load can be distributed equally to all beams. (AASHTO Std. Specs 17th edition 3.23.2.3.1.1 & AASHTO LRFD 4.6.2.2) However, when calculating superstructure loads on the substructure, particularly for cantilevered pier caps, 75% of the barrier dead load should be applied with the fascia beam load. The remaining 25% of the barrier load should be applied with the first interior girder load. (8-20-2009)
7.01.05
Fatigue Resistance
The nominal fatigue resistance shall be determined using a structure design life of 75 years and the truck ADTT averaged over the design life. A note providing this information should be placed on the General Plan of Structure sheet (see Section 8.05). Design shall be according to AASHTO LRFD Bridge Design Specifications 3.6.1.4 & 6.6.1. (8-20-2009)
7.01.06
Deflection
A. Deflection Limits (8-20-2009)
Deflection limits shall be as specified in the current AASHTO LRFD Bridge Design Specifications A 2.5.2.6.2.
The live load shall be taken from A 3.6.1.3.2.
B. Cantilever Deflection Computation
In computing the live load plus dynamic load allowance deflection of cantilevers of composite anchor span, the gross section of the anchor span is to be used. The length of the composite section for this analysis is to be assumed to extend from the bearing line to the point of dead load contraflexure. (5-27-2020)
7.01.07
Temperature Range
A. The temperature range used to determine thermal forces and movements shall be in conformance with AASHTO "cold climate" temperature range.
B. The type of structure used in determining the temperature range, per AASHTO, shall be defined by the material of the main supporting members of the superstructure or substructure being considered.
MICHIGAN DESIGN MANUAL BRIDGE DESIGN
7.01.04(continued)
Design Loading
J. Barrier Loads
For purposes of beam design, the barrier dead load can be distributed equally to all beams. (AASHTO Std. Specs 17th edition 3.23.2.3.1.1 & AASHTO LRFD 4.6.2.2) However, when calculating superstructure loads on the substructure, particularly for cantilevered pier caps, 75% of the barrier dead load should be applied with the fascia beam load. The remaining 25% of the barrier load should be applied with the first interior beam load. (11-28-2011)
7.01.05
Fatigue Stresses
The allowable stress range should be determined using a structure design life of 75 years and the truck ADT expected at bridge opening. A note providing this information should be placed on the General Plan of Structure sheet (see Section 8.05). (8-6-92)
7.01.06
Deflection
A. Deflection Limits (5-6-99)
LOADING SIMPLE AND CONTINUOUS SPANS
CANTILEVER
HS25 L/800 L/300
HS2044 L/1000 L/375
Pedestrian only L/800 L/300
Timber Bridges L/375 ------
B. Cantilever Deflection Computation
In computing the live load plus impact deflection of cantilevers of composite anchor span, the gross section of the anchor span is to be used. The length of the composite section for this analysis is to be assumed to extend from the bearing line to the point of dead load contraflexure.
7.01.07
Temperature Range
A. The temperature range used to determine thermal forces and movements shall be in conformance with AASHTO "cold climate" temperature range.
B. The type of structure used in determining the temperature range, per AASHTO, shall be defined by the material of the main supporting members of the superstructure or substructure being considered.
7.01.08
Vertical Clearance
A. Requirements
The desired vertical bridge underclearances should be provided as indicated in the following table. If the desired underclearances cannot be provided, then the minimum underclearances shall be met. Where it is considered not feasible to meet these minimums, a design exception shall be requested from the Engineer of Road Design and subsequently to the FHWA (approvals designated in the Project Specific Oversight Agreement (PSOA)) and from MDOT Bureau of Bridges and Structures, Chief Structure Design Engineer on "MDOT Oversight" projects (see Section 12.03 also). See the vertical clearance design exception matrix in Appendix 12.02.01. Requests to further reduce the underclearance of structures with existing vertical clearance less than indicated in the following table should be made only in exceptional cases. (12-5-2005) (1-14-2013) (6-22-2015) (5-27-2020)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN
7.01.08 (continued)
Vertical Clearance
A. Requirements
VERTICAL CLEARANCE REQUIREMENT TABLE (11-28-2011) (6-22-2015)
Route Classification Under the Structure
All Construction
(Desired)
New Construction
(Min *)
Road 4R Construction
(Min *)
Bridge 4R Construction
(Min *)
3R Construction
(Min *)
Freeways 16'-3" 16'-0" 16'-0" 16'-0" 16'-0" ***
NHS Arterials (Local & Trunkline) 16'-3" 16'-0"
Maintain Existing** and 14'-6" Min 16'-0"
Maintain Existing** and 14'-0" Min
Non NHS Arterials (Local & Trunkline) 16'-3" 14'-6"
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-0" Min
Collectors, Local Roads & Special Routes(1) 14'-9" 14'-6"
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-0" Min
3R = Rehabilitation, Restoration, Resurfacing 4R = Reconstruction
* Minimum Vertical Clearance must be maintained over complete usable shoulder width.
** Existing vertical clearances greater than or equal to the minimums shown may be retained without a design exception. Vertical clearance reductions that fall below the minimums for new construction require a design exception. (6-22-2015)
*** Existing vertical clearances may be retained (or increased) without a design exception unless a pattern of high load hits exist. Vertical clearance reductions below the standard (table value) require design exceptions. (5-27-2020)
(1) Special Routes are in Highly Urbanized Areas (where little if any undeveloped land exists adjacent to the roadway) where an alternate route of 16'-0" is available or has been designated. Bridges located over Special Routes in Highly Urbanized Areas can be found on the MDOT website at: http://mdotcf.state.mi.us/public/design/files/englishbridgemanual/Exempt_Structures.pdf. (5-28-2013)
Ramps and roadways connecting a Special Route and a 16’-0” route require a vertical clearance minimum of 14’-6” (14'-9" desired). Ramps and roadways connecting two 16’-0” routes require a vertical clearance minimum of 16’-0” (16'-3" desired). (8-20-2009)
Information on the NHS systems can be obtained by contacting the Statewide Planning Section, Bureau of Transportation Planning or found on the MDOT website at: http://www.michigan.gov/mdot-nfc(11-28-2011)
Pedestrian bridges are to provide 1'-0" more underclearance than that required for a vehicular bridge. For Freeways (Interstate and non Interstate), including Special Route Freeways, the desired underclearance shall be 17’-3” (minimum 17'-0"). (11-28-2011)
A vertical underclearance of 23'-0" is required for highway grade separations over railroads when constructing a new bridge or removing the existing superstructure. For preventative maintenance, rehabilitation and deck replacement projects the existing railroad vertical underclearance does not need to be increased unless requested by the Railroad. (11-28-2011)
Clearance signs are to be present for structures with underclearance of 16’-0” or less (show dimensions 2” less than actual). See MDOT Traffic and Safety Sign Design, Placement, and Application Guidelines for additional information and guidelines. (8-20-2009) (11-28-2011) (11-21-2013)(3-25-2019)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN - CHAPTER 7: LRFD
7.01.08
Vertical Clearance
A. Requirements
The desired vertical bridge underclearances should be provided as indicated in the following table. If the desired underclearances cannot be provided, then the minimum underclearances shall be met. Where it is considered not feasible to meet these minimums, a design exception shall be requested from the Engineer of Road Design and subsequently to the FHWA (approvals designated in the Project Specific Oversight Agreement (PSOA)) and from MDOT Bureau of Bridges and Structures, Chief Structure Design Engineer on "MDOT Oversight" projects (see Section 12.03 also). See the vertical clearance design exception matrix in Appendix 12.02.01. Requests to further reduce the underclearance of structures with existing vertical clearance less than indicated in the following table should be made only in exceptional cases. (12-5-2005) (1-14-2013) (6-22-2015) (5-27-2020)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN - CHAPTER 7: LRFD
7.01.08 (continued)
Vertical Clearance
A. Requirements
VERTICAL CLEARANCE REQUIREMENT TABLE (8-20-2009) (6-22-2015)
Route Classification Under the Structure
All Construction
(Desired)
New Construction
(Min *)
Road 4R Construction
(Min *)
Bridge 4R Construction
(Min *)
3R Construction
(Min *)
Freeways 16'-3" 16'-0" 16'-0" 16'-0" 16'-0" ***
NHS Arterials (Local & Trunkline) 16'-3" 16'-0"
Maintain Existing** and 14'-6" Min 16'-0"
Maintain Existing** and 14'-0" Min
Non NHS Arterials (Local & Trunkline) 16'-3" 14'-6"
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-0" Min
Collectors, Local Roads & Special Routes(1) 14'-9" 14'-6"
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-6" Min
Maintain Existing** and 14'-0" Min
3R = Rehabilitation, Restoration, Resurfacing 4R = Reconstruction
* Minimum Vertical Clearance must be maintained over complete usable shoulder width.
** Existing vertical clearances greater than or equal to the minimums shown may be retained without a design exception. Vertical clearance reductions that fall below the minimums for new construction require a design exception. (6-22-2015)
*** Existing vertical clearances may be retained (or increased) without a design exception unless a pattern of high load hits exist. Vertical clearance reductions below the standard (table value) require design exceptions. (5-27-2020)
(1) Special Routes are in Highly Urbanized Areas (where little if any undeveloped land exists adjacent to the roadway) where an alternate route of 16'-0" is available or has been designated. Bridges located over Special Routes in Highly Urbanized Areas can be found on the MDOT website at: http://mdotcf.state.mi.us/public/design/files/englishbridgemanual/Exempt_Structures.pdf. (5-28-2013)
Ramps and roadways connecting a Special Route and a 16’-0” route require a vertical clearance minimum of 14’-6” (14'-9" desired). Ramps and roadways connecting two 16’-0” routes require a vertical clearance minimum of 16’-0” (16'-3" desired). (8-20-2009)
Information on the NHS systems can be obtained by contacting the Statewide Planning Section, Bureau of Transportation Planning or found on the MDOT website at: http://www.michigan.gov/mdot-nfc(11-28-2011)
Pedestrian bridges are to provide 1'-0" more underclearance than that required for a vehicular bridge. For Freeways (Interstate and non Interstate), including Special Route Freeways, the desired underclearance shall be 17’-3” (minimum 17'-0"). (8-20-2009)
A vertical underclearance of 23'-0" is required for highway grade separations over railroads when constructing a new bridge or removing the existing superstructure. For preventative maintenance, rehabilitation and deck replacement projects the existing railroad vertical underclearance does not need to be increased unless requested by the Railroad. (11-28-2011)
Clearance signs are to be present for structures with underclearance of 16’-0” or less (show dimensions 2” less than actual). See MDOT Traffic and Safety Sign Design, Placement, and Application Guidelines for additional information and guidelines. (8-20-2009) (11-28-2011) (11-21-2013) (3-25-2019)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN
7.02.05
Bearings
A. Sole Plates
Plate thicknesses are to be specified in ¼” increments. For beveled sole plates, this ¼” increment is based on the maximum thickness.
For steel beams, sole plates are to be beveled when the calculated bevel is greater than 1% for curved steel bearings and greater than 0.5% for elastomeric bearings. For requirements for prestressed concrete beams, see Subsection 7.02.18. (8-6-92)
B. Elastomeric Pads
Elastomeric pads (⅛”) are required under all steel masonry plates and are to be 1½” longer and wider than the masonry plates. (10-24-2001)
C. Elastomeric Bearings
Plain bearings shall have a shear modulus, G, of 200 (±30psi), laminated bearings shall have a shear modulus of 100 psi (±15psi). Pads shall be 4” minimum (generally 6”) by 34” with ¾” minimum thickness (increase in ¼” increments). (11-28-2011)
Fabric laminated (cotton-duck or other fiber reinforcement) bearings shall not be used unless approved by MDOT Structural Fabrication Engineer or MDOT Chief Structure Design Engineer. (3-20-2017) (3-26-2018) (5-27-2020)
Additional information (polymer type, minimum low-temperature grade, etc.) can be found at MDOT’s Elastomeric Bearing Guidance Document. (3-20-2017)
D. Anchor Bolts
Calculated lengths of bridge anchor bolts should be based on a bolt projection of 1" beyond the nut. (5-6-99)
7.02.06
Precamber - Steel Beams
Where dead load deflection, vertical curve offset, and deflection due to field welding (rare occurrence) is greater than ¼”, the beams shall have a compensating camber. Camber is to be figured to the nearest ¼” and shall be parabolic.
In certain instances, such as for continuous spans or long cantilevers, reverse camber should be called for in order to obtain uniform haunch depths.
When several beams in a bridge have corresponding camber ordinates which differ only slightly from each other, the Engineer should attempt to average these into one set for all beams.
7.02.07
Moment of Inertia - Composite Beam
The composite moment of inertia shall be used throughout positive moment regions. This moment of inertia is to be used in negative moment regions to compute beam stiffness only.
7.02.08
Multiple Span Design
A. Beam Depth
Use the same depth beams for all spans with the longest span controlling the beam depth.
B. Composite Design
Composite design shall be used on all spans. Composite design uses the entire deck/slab thickness versus deck/slab stand-alone design which eliminates the top 1 ½” wearing surface. (5-6-99) (8-17-2015)
C. Suspended Spans
The suspended span should be poured first (see Section 7.02.01).
MICHIGAN DESIGN MANUAL BRIDGE DESIGN - CHAPTER 7: LRFD
7.02.05
Bearings (continued)
C. Elastomeric Bearings
Plain bearings shall have a shear modulus, G, of 200 (±30psi), laminated bearings shall have a shear modulus of 100 psi (±15psi). Pads shall be 4” minimum (generally 6”) by 34” with ¾” minimum thickness (increase in ¼” increments). (8-20-2009)
Design steel-reinforced elastomeric bearings with AASHTO LRFD Method A. Method B shall not be used unless approved by MDOT Structural Fabrication Engineer. (11-28-2011) (3-26-2018)
Fabric laminated (cotton-duck or other fiber reinforcement) bearings shall not be used unless approved by MDOT Structural Fabrication Engineer or MDOT Chief Structure Design Engineer. (3-20-2017) (3-26-2018) (5-27-2020)
Additional information (polymer type, minimum low-temperature grade, etc.) can be found at MDOT’s Elastomeric Bearing Guidance Document. (3-20-2017)
D. Anchor Bolts
Calculated lengths of bridge anchor bolts should be based on a bolt projection of 1" beyond the nut. (5-6-99)
7.02.06
Precamber - Steel Beams
Where dead load deflection, vertical curve offset, and deflection due to field welding (rare occurrence) is greater than ¼”, the beams shall have a compensating camber. Camber is to be figured to the nearest ¼” and shall be parabolic.
In certain instances, such as for continuous spans or long cantilevers, reverse camber should be called for in order to obtain uniform haunch depths.
When several beams in a bridge have corresponding camber ordinates which differ only slightly from each other, the Engineer should attempt to average these into one set for all beams.
7.02.07
Moment of Inertia - Composite Beam
The composite moment of inertia shall be used throughout positive moment regions. This moment of inertia is to be used in negative moment regions to compute beam stiffness only.
7.02.08
Multiple Span Design
A. Beam Depth
Use the same depth beams for all spans with the longest span controlling the beam depth.
B. Composite Design
Composite design shall be used on all spans. Composite design uses the entire deck/slab thickness versus deck/slab stand-alone design which eliminates the top 1 ½” wearing surface. (5-6-99) (8-17-2015)
C. Suspended Spans The suspended span should be poured first (see Section 7.02.01).
MICHIGAN DESIGN MANUAL BRIDGE DESIGN
7.02.12
Welding
All welding details are to be according to AWS specifications, except for minimum fillet weld sizes, which should be as shown in the Standard Specifications. Any intended deviations are to be called to the attention of the MDOT Chief Structure Design Engineer. (5-6-99) (5-27-2020)
Plans should show welding details but should not show the size unless a deviation from AWS specifications is intended.
Plans should also show beam or girder flange tension and stress reversal zones where lifting lugs will not be permitted.
7.02.13
Field Splices in Plate Girders
A. General
Girder Length Field Splice0’ to 125' None provided.
Over 125' to 160'
Field splice is shown on plans as optional; it is designed and detailed, but not paid for.
Over 160' Field splice is designed, detailed, and paid for. *
Fabricators that wish to field splice other than as called for on the plans will need prior Bridge Design Project Manager approval. (5-27-2020)
* Additional steel weight from splices will be added to quantity for “Structural Steel, Plate, Furn and Fab”. (12-22-2011)
7.02.13 (continued)
B. Location
Field splices are to be located at low-stress areas at or near the point of contraflexure for continuous spans.
C. Bolts
All high strength bolts are to be hot-dip galvanized. (3-18-2013)
7.02.14
Diaphragms and Crossframes
A. Orientation
When bridges are on grades, the diaphragm or crossframe connection plates are to be set normal to the flange.
B. End Diaphragms
End diaphragms or crossframes are required at ends of beams to support the end of slab unless it is supported by other means. Curved girders shall have diaphragms or crossframes placed at the centerline of support. To provide access for painting, these diaphragms or crossframes shall be no closer than 2'-0" from the beam end at independent backwalls and shall have no less than 2'-0" of clearance at simple supports. (5-6-99)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN - CHAPTER 7: LRFD
7.02.12
Welding
All welding details are to be according to AWS specifications, except for minimum fillet weld sizes, which should be as shown in the Standard Specifications. Any intended deviations are to be called to the attention of the MDOT Chief Structure Design Engineer. (5-6-99) (5-27-20)
Plans should show welding details but should not show the size unless a deviation from AWS specifications is intended.
Plans should also show beam or girder flange tension and stress reversal zones where lifting lugs will not be permitted.
7.02.13
Field Splices in Plate Girders
A. General
Girder Length Field Splice
0’ to 125' None provided.
Over 125' to 160'
Field splice is shown on plans as optional; it is designed and detailed, but not paid for.
Over 160' Field splice is designed, detailed, and paid for. *
Fabricators that wish to field splice other than as called for on the plans will need prior Bridge Design Project Manager approval. (5-27-2020)
* Additional steel weight from splices will be added to quantity for “Structural Steel, Plate, Furn and Fab”. (12-22-2011)
7.02.13 (continued)
B. Location
Field splices are to be located at low-stress areas at or near the point of contraflexure for continuous spans.
C. Bolts
All high strength bolts are to be hot-dip galvanized. (3-18-2013)
7.02.14
Diaphragms and Crossframes
A. Orientation (8-20-2009)
Diaphragms or cross-frames shall be provided at abutments, piers and hinge joints. Intermediate diaphragms may be used between beams in curved systems or where necessary to provide torsional resistance and support the deck at points of discontinuity or at angle in girders.
The need for diaphragms or cross-frames shall be investigated for all stages of assumed construction procedures and the final condition. Diaphragms or cross-frames required for conditions other than the final condition may be specified to be temporary bracing.
B. End Diaphragms
End diaphragms or crossframes are required at ends of beams to support the end of slab unless it is supported by other means. Curved girders shall have diaphragms or crossframes placed at the centerline of support. To provide access for painting, these diaphragms or crossframes shall be no closer than 2'-0" from the beam end at independent backwalls and shall have no less than 2'-0" of clearance at simple supports. (5-6-99)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN - CHAPTER 8: LRFD
8.05
GENERAL PLAN OF STRUCTURE SHEET
A1. The design of this structure is based on 1.2 times the current AASHTO LRFD Bridge Design Specification HL-93 loading with the exception that the design tandem portion of the HL-93 load definition shall be replaced by a single 60 kip axle load before application of this 1.2 factor. The resulting load is designated HL-93 Mod. Live load plus dynamic load allowance deflection does not exceed (1/425*) (1/800) (1/1000**) of span length (and 1/375) (1/300) of cantilever arm. [*Wood construction.] [**Use for structures with pedestrian loads.] [See Subsection 7.01.06 for deflection limits.] (8-20-2009)
A2. The design of this structure is based on current AASHTO LRFD Bridge Design Specification pedestrian loading of 90 psf (and a maintenance vehicle (H5) (H10) loading, not acting concurrently). Live load deflection does not exceed 1/360 of span length and 1/220 of cantilever arm. [Use for pedestrian bridges. For Clear Bridge Width, w, greater than 10'0", use an H10 truck. For w between 7'-0" and 10'-0", use an H5 truck. For w less than 7'-0" the bridge does not need to be designed for a maintenance vehicle.]
(11-28-2011) (5-25-2015)
A3. The design of the deck slab is based upon the strip method as defined in the current AASHTO LRFD Bridge Design Specification, utilizing HL-93 Loading.
(8-20-2009) (5-27-2020)
8.05 (continued)
B1. The (reconstruction) (rehabilitation) design is based on 1.2 times the current AASHTO LRFD Bridge Design Specification HL93 loading with the exception that the design tandem portion of the HL-93 load definition shall be replaced by a single 60 kip axle load before application of this 1.2 factor. The resulting load is designated HL-93 Mod. Live load plus dynamic load allowance deflection does not exceed (1/425**) (1/800) (1/1000***) of span length (and 1/375) (1/300) of cantilever arm. The original structure was designed for (and alternate military*) loading (based on AASHTO Standard Specifications for Highway Bridges). [*Used only for structures on interstate routes.] [**Wood construction.] [***Use for structures with pedestrian loads.] [See Subsection 7.01.06 for deflection limits.] [Use note for LRFD method of design.] (8-20-2009)
B2. The (reconstruction) (rehabilitation) design is based on the 17th Edition of AASHTO Standard Specifications for Highway Bridges (HS25) (HS20-44) (and alternate military*) loading. Live load plus impact deflection does not exceed (1/425) (1/800) (1/1000) of span length (and 1/375) (1/300) of cantilever arm. The original structure was designed for (and alternate military*) loading based on AASHTO Standard Specifications for Highway Bridges. [*Use only for structures on interstate routes.] [See 17th
Edition of AASHTO for deflection limits.] [Use note for Load Factor method of design.] (8-20-2009)
MICHIGAN DESIGN MANUAL BRIDGE DESIGN
12.02
GEOMETRIC CRITERIA
(9-1-88) While it is desirable to improve all structures to current design standards, upgrading to this extent may not be considered cost effective where a project is otherwise programmed for only rehabilitation. Criteria for roadway widths and design loading structural capacity have been established in A Policy on Design Standards - Interstate System, 2005, and A Policy on Geometric Design of Highways and Streets, 2011, 6th
Edition, published by AASHTO. These criteria are based on the type of roadway carried by the structure and are summarized in Appendix 12.02. Criteria for structures carrying interstate freeways are provided in AASHTO’s 2005 edition of A Policy On Design Standards - Interstate System. The policy states: “The standards used for horizontal alignment, vertical alignment, and widths of median, traveled way, and shoulders for resurfacing, restoration and rehabilitation projects may be the AASHTO interstate standards that were in effect at the time of the original construction or inclusion into the interstate system.” Non Interstate structures shall adhere to A Policy on Geometric Design of Highways and Streets, 2011, 6th
Edition design criteria (standards). Therefore, if a bridge on a road project is not altered it is subject to design exceptions or design variances for full new/reconstruction standards. (8-20-2009) (3-21-2016) (2-21-2017)
12.02.01
Vertical Clearance (5-1-2000) (5-27-2020)
For Design Exception Requirements for Vertical Clearance see Appendix 12.02.01.
For 3R freeway projects, if the existing vertical clearance is not reduced and a crash pattern involving high load hits does not exist, the vertical clearance may be retained without a design exception. However, if the vertical clearance is reduced to a value less than the standard (table value in Section 7.01.08), a design exception will be required. The format for the design exception does not require a detailed evaluation but should include the basis for the request and review of the accident history and high load hits for the structures in the immediate vicinity of the structure.
For the remaining 3R route classifications (Section 7.01.08), existing vertical clearances greater than or equal to the minimums shown may be retained without a design exception. Vertical clearance reductions that fall below the minimums for new construction require a design exception.
MICHIGAN DESIGN MANUAL BRIDGE DESIGN
12.07.09
A588 Steel Beams (9-2-2003)
The following rehabilitation situations exist for A588 beams:
1. Little or no section loss (< 20%), painting is not required.
2. Significant section loss (> 20%), the entire structure is painted. This includes projects with beam end repairs.
3. Pin and hanger projects where beams are otherwise in good condition (< 20% section loss), beams are zone painted (with the outside of the fascia beams top coated brown in the zone area).
12.07.10
Partial Painting
Where structural steel cleaning and coating involves only partial sections of beams or diaphragms the entire perimeter of the beams or diaphragms, less any portions encased in concrete, shall be cleaned and coated. Cleaning and Coating shall be according to the Standard Specifications for Construction or Special Provisions. (3-26-2012)
12.08
MISCELLANEOUS REHABILITATION
Some miscellaneous rehabilitation is significant and is programmed for the specific purpose. More frequently, miscellaneous work is an adjunct to other work. As such, its nature and cost should be determined as early as possible so that the primary project programming can be adjusted.
Include saw cut depth dimensions when removing portions of abutments, piers and columns on the plans. (8-20-2009)
12.08.01
Field Inspections
The Plan Review Meeting with a field inspection should be conducted on all rehabilitation projects. This inspection should be made within six months of the contract letting to most accurately determine the extent of deterioration. If a project is postponed, it may be necessary to conduct a second inspection. (5-27-20)