RISK MANAGEMENT PLAN
Project Title: Date Prepared:
Methodology
Roles and Responsibilities
Risk Categories
Page 1 of 5
Risk Management Funding
Contingency Protocols
RISK MANAGEMENT PLAN
Page 2 of 5
Stakeholder Risk Tolerances
Tracking and Audit
RISK MANAGEMENT PLAN
Project Title: Date Prepared:
Frequency and Timing
Page 3 of 5
Defi nitions of Probability
Very high
High
Medium
Low
Very low
Defi nitions of Impact by Objective
Scope Quality Time Cost
Very high
High
Medium
Low
Very low
RISK MANAGEMENT PLAN
Page 4 of 5
Probability and Impact Matrix
Very high
High
Medium
Low
Very low
Very high High Medium Low Very low
Page 5 of 5
RISK MANAGEMENT PLAN