Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® [email protected].

24
Risk Management or Do I Feel Lucky? Jack J. Ference, PMP®, PMI-RMP® [email protected]

Transcript of Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® [email protected].

Page 1: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

Risk Management or Do I Feel Lucky?

Jack J. Ference, PMP®, PMI-RMP®

[email protected]

Page 2: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

2October 26, 2009

Presentation Outline• Project Introduction and Background • Risk Management Process

– Risk Management Planning– Risk Identification– Risk Analysis

• Results from Process• Benefits and Lessons Learned• Questions

Page 3: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

3October 26, 2009

What this Project is About

Photo clips from abcNews.com

Page 4: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

4October 26, 2009

Project Challenges• “Low to Moderate” risk project• Basic type of work had been done before,

however, challenges included:– Completing project in four-year timeframe– Executing two concurrent field tests – Agreement upon system requirements/tests– Integration/testing of three standalone functions– Development of new capabilities– Collecting driving data in “down” economy – Varied project management culture within team

Page 5: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

5October 26, 2009

Project Timeline

Nov 2005 Nov 2006 Nov 2008 May 2010June 2008 Feb 2009

EngineeringDevelopment

Vehicles

Prototype Vehicles

Pilot Vehicles

Extended Pilot Test

FOTData

Collection

Phase II – 24 monthsPhase I – 30 months

Project Information

Five-year Cooperative Agreement (80%-20%)

“Best-efforts” cost reimbursable agreement

Federal Funds $25.6M – Private Funds $7.4M

Other Federal Partners – $7.9M Support Staff – $1.9M

Phase I – $28.3M Phase II – $14.5M

Page 6: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

6October 26, 2009

Risk Management Process

Plan Risk Management

Identify Risks

Perform Risk Analysis

Plan Risk Responses

Monitor and Control Risks

Page 7: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

7October 26, 2009

Risk Management Planning• Deciding your approach – how formal?• Scaling effort to meet project needs/budget• Showing value of process and obtaining buy-in • Acknowledging training needs• Writing, communicating and following the plan

– Developing probability and impact definitions– Writing actionable risk statements– Selecting tools and processes– All needed to ensure consistency

• Following up, making adjustments, repeating processes

Page 8: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

8October 26, 2009

Probability and Impact Matrix

Page 9: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

9October 26, 2009

Risk Identification• Phase II statement of work, schedule and

project budget• Phase I and past experience• Tools and Techniques

– Adobe® Acrobat fill-able Form/Workshop – Risk Breakdown Structure– Project-specific checklist– Interviewing

Page 10: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

10October 26, 2009

Risk Identification Worksheet

Page 11: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

11October 26, 2009

Risk Register – Part I

Page 12: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

12October 26, 2009

Risk Rating Form

Page 13: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

13October 26, 2009

Consensus Risk Rating

Name Prob Impact Matrix Pos RiskReviewer 1 1 2 2 LOWReviewer 2 3 3 13 MEDReviewer 3 2 3 8 LOWReviewer 4 2 4 9 MEDReviewer 5 2 3 8 LOWReviewer 6 2 2 7 LOWReviewer 7 1 2 2 LOWReviewer 8 2 2 7 LOWReviewer 9 2 3 8 LOWReviewer 10 0 NRReviewer 11 0 NRReviewer 12 0 NRReviewer 13 2 3 8 LOWReviewer 14 0 NR

Mean 1.9 2.7 7 LOW

Risk Level Consensus LOW

Risk # 069

IF prototype vehicles are not produced to specifications in time for the EPT, THEN the EPT will be delayed or compromised.

Page 14: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

14October 26, 2009

Risk Register – Part II

Page 15: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

15October 26, 2009

Risk Response Worksheet

Page 16: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

16October 26, 2009

Risk Radar®

Page 17: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

17October 26, 2009

Individual Risk Summary

Page 18: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

18October 26, 2009

Risk Radar® Reports

9 8 8

37 36 3639

339

83 85 85 89 9142

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Oct '08 Nov '08 Dec '08 Jan '09 Feb '09 Mar '09

High Medium Low

Page 19: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

19October 26, 2009

Risk Radar® Reports cont’d

Page 20: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

20October 26, 2009

Results from Process• Risks avoided

– Impact of model year change – Oct 2006• Identified risks realized

– High false alarm rate for heavy truck platform – Oct 2007– Impact of economy on conducting field test – Nov 2008-present

• Unidentified risks realized– Truck manufacturer leaves project – Aug 2007– Test track closes abruptly – Nov 2007– Phase II approval delayed – Dec 2007 (unknown-unknown)– Lead S/W engineer detained in China – Dec 2007– Vehicle build cost over-run and schedule delay – Feb 2009– Lead IT developer becomes ill while in India – Mar-Apr 2009– Software development cost over-run – Apr 2009– Supplier/Developer in Chapter 11 bankruptcy – May 2009

Page 21: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

21October 26, 2009

Benefits of Formal Process• Improved project focus and team

communications and coordination• Provided framework for discussing project

issues with emphasis on problem solving• Brought the whole team together, creating

a broader view of the project• Discussion of risk became a regular part of

program reviews

Page 22: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

22October 26, 2009

Lessons Learned• To improve chance of success, risk management

effort needs:– A “Process Owner”, team buy-in and cooperation– To be scaled to project needs, not be a burden– Consistent, open and honest process that is repeated

• Tendency to use past experience to judge risk and overlook associated new risks:– Vehicle build (cost over-run, schedule delay)– Database development delays affected other efforts– Data synchronization issues impacted test schedule

Page 23: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

23October 26, 2009

Resources1. MITRE Risk Management website:

http://www.mitre.org/work/sepo/toolkits/risk/2. Mulcahy, R. P. Risk Management - Tricks of the Trade for Project

Managers, Minneapolis, MN: RMC Publications, Inc., (2003). 3. Pritchard, Carl L. Risk Management Concepts and Guidance.

3rd Edition. Arlington, VA: ESI International, (2005).4. Survey Monkey® website: http://www.surveymonkey.com5. Risk Radar® website: http://www.AmericanSystems.com

Email: [email protected] Phone: (757) 424-3711, ext. 310; H. Duncan Wynne

6. Defense Acquisition University: https://acc.dau.mil/rm7. Guide to the Project Management Body of Knowledge (PMBOK).

Fourth Edition. Newton Square, PA: Project Management Institute, (2009)

8. Practice Standard for Project Risk Management. Newton Square, PA: Project Management Institute, (2009)

9. The Risk Doctor website: http://www.risk-doctor.com/

Page 24: Risk Management or Do I Feel Lucky? Jack J. Ference, PMP ®, PMI-RMP ® Jack.ference@dot.gov.

PMI Baltimore Luncheon Meeting Columbia, MD

24October 26, 2009

Questions?

Jack J. Ference, PMP®, PMI-RMP®

U.S. DOT/National Highway Traffic Safety AdministrationAdvanced Vehicle Safety Research

Intelligent Technologies Research Division

1200 New Jersey Avenue, SE, W46-447

Washington, DC 20590

(202) 366-0168

[email protected]