Risk Management for Construction
Dr. Robert A. Perkins, PE
Civil and Environmental Engineering
University of Alaska Fairbanks
![Page 2: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/2.jpg)
Class for DOT Construction Managers
• Get started– Who we are– Where we are– Why are we here?
• Book and Syllabus• Handout Material
– Electronic– http://www.faculty.uaf.edu/ffrap/CM%20Cours
e%20Info/CM%20Index.html
![Page 3: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/3.jpg)
Risk and Safety
![Page 4: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/4.jpg)
Class Outline
• Class 1, Basic risk concepts applied to project and construction management
• Class 2, Specific risk concepts applied to construction – qualitative risk analysis
• Class 3, Quantitative risk analysis, a little probability, tools.
• Class 4, Risk Assessment
![Page 5: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/5.jpg)
• Class 5, – Risk Management, owner’s perspective– How contractors manage risks
• Class 6, Presentations and Wrap up
![Page 6: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/6.jpg)
Today
• Risk in general
• Risk in projects
• Risk in construction
• Analysis of Risk
• Management of Risk
![Page 7: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/7.jpg)
Assessments
• Quiz following Class 4, 30%– Definitions– Problems
• Practicum, 60%– Team project– Risks from a project– Plan for handling them
![Page 8: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/8.jpg)
“Clouded his future is…The future is always in motion”
![Page 9: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/9.jpg)
Estimation of Future Events
• AKA “divining”
• Oracle at Delphi to my financial analyst
• Pigeon guts, Roman augers
• “The diviners have seen a lie, and have told false dreams; they comfort in vain (Zechariah 10. 2).
![Page 10: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/10.jpg)
Management
• An understanding of and dealing with the stochastic nature of management systems.– designating a process having an infinite progression
of jointly distributed random variables.– of, pertaining to, or arising from chance; involving
probability; random– from the Greek stochastikos meaning, proceeding by
guesswork
![Page 11: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/11.jpg)
Estimates
• Estimates are essentially guesses and often have a serious downside if they are wrong.
• The reason they are guesses is that there are future events (“states of nature”) that are uncontrollable and these events will control the outcome.
• Regarding what we can say about these future events, there is a continuum.
![Page 12: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/12.jpg)
![Page 13: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/13.jpg)
Terms• Certainty
– If we have full knowledge (we believe) of the future. We might approximate that if we have a firm quote from a bonded sub or supplier.
• Risk– Many estimating decisions are made under “risk.” In technical terms,
“risk” means we feel we can state the probability of the events. For example, we know the price of concrete in the summer is likely to be $200/CY but may vary by 15%.
• Uncertainty– We recognize alternate states of nature may happen, but we don’t have
a clue how likely they are. – Note the difference between the technical use of terms and the common
usage. While the entire future is “uncertain,” if we feel confident we know the probability of the future we say there is “risk” and limit the use of “uncertain” to situations where we do not know the probability of events.
![Page 14: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/14.jpg)
• Knowns
• Known-unknowns
• Unknown-unknowns
![Page 15: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/15.jpg)
• Road freeze up by October 1
• Foreman quitting
![Page 16: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/16.jpg)
Examples
– Projects• Nature of Projects
– Project cycle» Graphs, ease of change vs. completion» Cost of change vs. design
– Work Breakdown Structure
• DOT Projects– Type– What can go wrong?
• Participation
![Page 17: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/17.jpg)
![Page 18: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/18.jpg)
![Page 19: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/19.jpg)
• Risks must be evaluated according to the project cycle.
![Page 20: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/20.jpg)
WBS
• Work Breakdown Structure
• The tasks needed to complete the project
• Tie WBS to risks
• Contracting strategies
![Page 21: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/21.jpg)
High Level WBS
• Planning
• Pre-design
• Design
• Procurement
• Construction
• M&O
![Page 22: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/22.jpg)
Mid-level Pre-design
• Survey
• Soils
• ROW
• Environmental
• Public
• Other
![Page 23: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/23.jpg)
More Detail - Soils
• Review Records
• Schedule Drilling
• Drill
• Analysis
• Report
![Page 24: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/24.jpg)
Finer Detail - Drill
• Costs– Labor– Equipment– Subcontract
• Schedule– Permits and approvals– Section A– Section B– Section C
![Page 25: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/25.jpg)
And more
• Labor– Bare– Benefits
• Vacation
– Supervision
![Page 26: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/26.jpg)
Nomenclature - sometimes
• Program
• Project
• Phase
• Task
• Sub-task
• Work Packages
• Etc.
![Page 27: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/27.jpg)
More
• Coordination Matrix
• Who is responsible, involved, needs to be copied, and, almost forgot,
• Who will do the work
• Contract v. In-house
![Page 28: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/28.jpg)
WBS to RMP
• Risk Management Plan
• Risks should be considered with respect to the WBS
• Who is responsible for apprizing risk
• Minimizing Risk
• Reporting on Risk
![Page 29: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/29.jpg)
Forecasting, Time
• Short-term– 1-3 years– Generally based on current knowledge
• Medium-term– 3-15 years– typically the issue
• Long-term– >15 years
![Page 30: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/30.jpg)
Your Organization’s Risks
• Discuss
• Who manages?
• Technical Risks
• Performance Risks– AKA Programmatic Risks
![Page 31: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/31.jpg)
Forecasting Methods
• Subjective methods– from within firm
• User Expectation methods– from outside the firm
• Statistical Methods– extrapolation
• Modeling methods
![Page 32: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/32.jpg)
User Expectation Methods
• Customers asked to forecast needs– Availability of gravel
• Pilot trials– test demand in one location– Alyeska tests of trenching in permafrost
![Page 33: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/33.jpg)
Statistical
• Time series
![Page 34: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/34.jpg)
Subjective Methods
• Jury of Executive Opinion– meeting of in-house experts
• Delphi Method– Aims to remove domineering effect of senior
company officials– Three rounds
• 1st anonymous• 2d knows results of first, but not authors• 3d discussion following 2d round
![Page 35: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/35.jpg)
Extrapolation
• From time series
• (See next)
• Various methods of extrapolation
• All based on past data
• Which is likely to change in future
![Page 36: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/36.jpg)
Known data
Extrapolated data
from Rose, 1976
![Page 37: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/37.jpg)
Some terms
• Precision
• Accuracy
• Biased
• Precise estimate
![Page 38: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/38.jpg)
Accurate, not precise
![Page 39: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/39.jpg)
Precise, not Accurate
![Page 40: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/40.jpg)
Precise, not Accurate
Bias (left)
![Page 41: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/41.jpg)
Experts
• Feedback– Jury– Delphi– Etc.
• Get parameters
![Page 42: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/42.jpg)
“Precise Estimate”
• Use the best number(s) you have.
![Page 43: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/43.jpg)
Other Precise
• Breakeven• Sensitivity• Examine the impact that variability will
have
![Page 44: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/44.jpg)
Problems
• Problems (or events) => Decisions
• Kinds of problems– Simple
• Cash or credit card
– Intermediate• Buy or lease equipment
– Complex• Open a new plant in New Jersey or Alabama
![Page 45: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/45.jpg)
The Decision Process
![Page 46: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/46.jpg)
Rational Decision Making
• Recognition of problem
• Definition of goal• Assembly of data• Select criteria• Interrelationship
– objective– alternatives– data– criteria
• Predict outcomes• Choice of best
![Page 47: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/47.jpg)
Recognition of Problem
Define the problem area, carefully and completely determine all uncontrollable conditions (random events) inherent in the situation.
![Page 48: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/48.jpg)
Define Goal or Objective
• A problem is something that prevents us from achieving our goal
• Determine the objective(s) to be achieved and how attainment of the objectives is to be measured.
• But what is the objective?
![Page 49: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/49.jpg)
Assembly of Data
• Accounting Data• Cost• Benefits• Difficulties
– Allocation of Overhead– non-market consequences (shadow prices)– Intangibles
• Define precisely all alternative actions that can be taken, and calculate the payoff (degree of attainment of objectives) in each case.
![Page 50: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/50.jpg)
Identify Feasible Alternatives
• Do nothing
• Brainstorming
![Page 51: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/51.jpg)
Select Criteria
• Non-profits
• Time
• Use money most efficiently– Fixed input– Fixed output– Neither fixed
![Page 52: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/52.jpg)
Model Interrelationships
• Select and apply a decision criterion (rule) which orders the alternatives and defines which one is the best or optimum alternative.
![Page 53: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/53.jpg)
Model Interrelationships
• Room Capacity = (l * w )/ k
• k is factor based on seating– k = 0.5 for expensive fixed seats– k = 0.7 for cheap movable seats
![Page 54: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/54.jpg)
Numeric Models: Scoring
• Unweighted 0-1 Factor Model
• Unweighted Factor Scoring Model
• Weighted Factor Scoring Model
• Constrained Weighted Factor Scoring Model
• Goal Programming with Multiple Objectives
Chapter 2-6
![Page 55: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/55.jpg)
Numeric PS Models:Scoring
• Unweighted 0-1 Factor Model
• Unweighted Factor Scoring Model
• Weighted Factor Scoring Model
• Constrained Weighted Factor Scoring Model (c=0 or 1)
• S = ∑(x)
• S = ∑(s)
• S = ∑(s·w)
• S = ∑(s·w) ∏(c)
![Page 56: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/56.jpg)
Predict Outcomes
• From model
• Arrange in orderly way
• Resolve consequences– market– extra-market
• State intangibles
![Page 57: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/57.jpg)
Choose Best
• Using all relevant experience and judgment, make a choice from among the alternatives.
![Page 58: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/58.jpg)
Home Fire Insurance
• House cost $150,000
• full insurance cost $1400/yr
• p of fire 0.004/year
![Page 59: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/59.jpg)
More on Models
• Idealized view of reality
• Representing the STRUCTURE of the problem, not the detail
• Deterministic or stochastic
![Page 60: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/60.jpg)
Caveats
• Project decisions are made by Project Manager --- NOT by models!
• A model APPROXIMATES, but does NOT DUPLICATE reality!
![Page 61: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/61.jpg)
Types of Models:Nonnumeric
• Sacred Cow• Operating Necessity• Competitive Necessity• Product Line
Extension• Comparative Benefit
Model
![Page 62: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/62.jpg)
Choosing the Model
• Dependent on wishes and philosophy of management
• 80% of Fortune 500 firms choose “nonnumeric” models
• Firms with outside funding often chose scoring models
• Firms without outside funding often chose profit / profitability models
![Page 63: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/63.jpg)
Risk in Construction
• All the risks belong to who?
• Unless
• Which party should bear risk?
![Page 64: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/64.jpg)
Risk management
• Minimizing risks – regardless of whose risk it is
• Equitable sharing of risks among the various project partners.
• Contrast with Risk Assessment
![Page 65: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/65.jpg)
• The parties must be prepared to discuss and decide on the following issues:
• What are the levels of risk are realistic to assume?
• Who can best assume each risk?
• What levels and kinds of risks are properly and most economically passed on to insurance carriers?
![Page 66: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/66.jpg)
Fisk’s Categories of risk
• Construction-related risks– Crane failure
• Physical risks (subsurface conditions)– Differing site conditions
• Contractual and legal risks– Law suits
![Page 67: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/67.jpg)
• Performance risks– Project does not meet expectations
• Economic risks– Loose money or cost overruns
• Political and public risks– Lots
![Page 68: Risk Management for Construction Dr. Robert A. Perkins, PE Civil and Environmental Engineering University of Alaska Fairbanks.](https://reader036.fdocuments.in/reader036/viewer/2022062516/56649e035503460f94aef28f/html5/thumbnails/68.jpg)
Exculpatory Clauses
• Seek to reduce risk with contract language
• Limitation thereof