Risk ManagementA Key Project Management Knowledge Area
An Essential Part of the Project Plan
© Edward B. Farkas, CHS, CPM, MIEEE, PMP
![Page 2: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/2.jpg)
I’m Edward …
& you are?
![Page 3: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/3.jpg)
Total Project Plan Development (simplified view)
Scope Documents & Scope Management Plan
‘Blended’ Work Breakdown Structure
Risk Management Plan
Activity Network Diagram/Schedule
Resource Management Plan
Communications Plan
Project Quality Plan
Integrated Change Management Plan
Expectations Management
![Page 4: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/4.jpg)
Project Risk Management Process
• Risk identification• Risk qualification• Risk quantification• Risk response planning• Risk monitoring & control
![Page 5: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/5.jpg)
Project Risk Management Process
Risk Identification
![Page 6: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/6.jpg)
Risk Identification Sources• Documentation/Contracts• History
– Accurate stakeholder(s) identification– Mismanaged requirements gathering– Lack of documentation– Unchallenged assumptions
• Integration• Seamless• Compatible• Import/Export Functionality
• Work Breakdown Structure• Scheduled Triggers• Risk Breakdown Structure• Design• Testing/Technology• Operation/Maintenance/Support• Copy write/Patent/License
![Page 7: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/7.jpg)
What do I need for this activity/deliverable? Dependency RisksIs what I need available (When I need it)?
Human resources?Documentation?Hardware?Approvals?Funding?
Does this activity/deliverable assume anything? Assumption RisksIs the assumption(s) valid?
Does this activity/deliverable have constraints? Constraint RisksCan it be done with the constraints?
Work Breakdown Structure (WBS) Prompts
![Page 8: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/8.jpg)
FF
SS
SS
SS
FF
FF
SS
FF
Scheduling Prompts
FS Does anything have to happen before I can start this?
Is there any risk in that dependency?
SS If these start at the same time, do I have the resources?Are the resources at risk?
FF Why do they have to end at the same Time? Does that dependency have any risks?
SF What needs to be finished before the other can start?Is there any risk that it won’t
be finished?
![Page 9: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/9.jpg)
Risk Management Checklist
“PM completes Risk Checklist” Should Be Part of Methodology
![Page 10: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/10.jpg)
Risk Management of Triggers(Time based trigger example below.)
![Page 11: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/11.jpg)
Risk Identification
The process of systematically identifying all possible risk events which may impact a project
– Generate a Risk List that will later be quantified and qualified. – Cumulative effect of several risk events occurring in concert with each other may be of greater significance
than the impact of a single issue
Classify by cause, not effect or impact!Classify by cause, not effect or impact!
![Page 12: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/12.jpg)
Risk Breakdown Structure
Web Site
Security
Security Policy
Authentication SW
Firewalls
• Is the deliverable well defined?• Is this item a dependency?• Do I have the resources?• Do I have the funding?• Is there anything we’re assuming?• Etc…
![Page 13: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/13.jpg)
Scheduling Risks
• Level of Effort (LOE) subjectively estimated • LOE estimated by incorrect stakeholder
• Work Package in Work Breakdown Structure (WBS) too large for accurate estimates• LOE based on a resource with overestimated skills &/or experience
![Page 14: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/14.jpg)
Project Risk Management Process
Risk Qualification
![Page 15: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/15.jpg)
Qualitative Risk Rating
• High Likely to cause significant impact to schedule/cost/scope/quality
• Moderate Has potential to cause impact to schedule/cost/scope/quality
• Low Has little potential impact to Schedule/cost/scope/quality
COST
SCHEDULE
SCOPE
Remember ETR’s Triangle of Truth!
![Page 16: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/16.jpg)
Project Risk Management Process
Risk Quantification
![Page 17: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/17.jpg)
Risk Quantification
• Probabilities & Statistical Equations• Decision Tree Calculations• Subjective Scales• Formulas Project Managers use … • Can be expressed numerically
– mean– median– mode– range– variance – standard deviation
![Page 18: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/18.jpg)
Quantification of Dollar Value
• Product of two variables– Risk Event Probability:
• An estimate of the probability that a given risk event will occur
– Risk Event Value: • An estimate of the gain or loss that will be
incurred if the risk event does occur
{Probability of Impact x Dollar Value = Event Monetary Value: (P)I=EVM}
Reference: PMBOK, 1996. Ch. 11
![Page 19: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/19.jpg)
COST
SCHEDULE
SCOPE
Quantify in an integrated way!
![Page 20: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/20.jpg)
Quantification of Duration Ranges
• (O + 4M + P) / 6 is PERT (Program Evaluation & Review Technique)
• (P – 0) / 6 is Standard Deviation
• [(P – O) / 6] is Task Variance
• is Project Variance (sum of the task variances)
Handy formulas to help quantify risk activity/task duration:O = Optimistic, M = Most Likely, P = Pessimistic
Please remember that subjective P, M, and O inputs yield subjective outputs.Historical inputs are preferred for P, M, and O values
2
[(P – O) / 6] 2
![Page 21: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/21.jpg)
Project Risk Management Process
Risk Response
![Page 22: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/22.jpg)
Risk Response Options
Ways to address risk issues.
– Avoidance: Eliminate up front (e.g. activity sequence in test plan)
– Reduction: (mitigation) Minimize anticipated impact
– Transfer: (deflection) Redirect issue ownership (sub/direct property/indirect consequential)
– Retention: (acceptance) Accept real or potential impacts
![Page 23: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/23.jpg)
Project Risk Management Process
Risk Control
![Page 24: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/24.jpg)
Risk Management Plan
• Should document the procedures that will be used to manage risk throughout the project
Reference: PMBOK, 1996. Ch.11
![Page 25: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/25.jpg)
[If applicable] [Y-yes, N-no] [Open/Closed] Priority Scale [0= Will impact Critical Path, 1=1 day, 2= 1week, 3= > 1 week]
No. Unit Risk Item/Issue Status
Open Date Due Date
Revised Due Date
Finish Date Priority Initiator Owner
Notes
1 International N Contact list Open 6/20/2000 ####### 8/24/2001 1 J oe Customer J anet Smith Send Bill the List
2 EV4 Y Add unit Open 7/30/2001 ####### ####### 0 Customer PM
Esure that new unit requirements are incorporated into overall plan
3 N
4
Risk & Issues Log (for control)
![Page 26: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/26.jpg)
Risk Management Process & the Project Plan
•
• Document risks in project plan• Use communication sub-plan to manage expectations • May require WBS or RBS elaboration • Budget for risk events • May imply adding mitigation tasks in schedule • Document status of risk issue • Assume risk reviews are part of entire project life cycle
![Page 27: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/27.jpg)
Project Risk Management Process
• Risk identification• Risk quantification• Risk qualification• Risk response• Risk control
summary
![Page 28: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/28.jpg)
Q&AQ&A
For additional information & copies of this presentation: Email Edward B. Farkas, PMP Managing Director, Project Management
Practice:
ETR Technology Center, Inc.180 Oser Avenue
Hauppauge, NY [email protected]
631.952.1300A certified WBE firm established in 1980
![Page 29: Risk Management A Key Project Management Knowledge Area An Essential Part of the Project Plan © Edward B. Farkas, CHS, CPM, MIEEE, PMP.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649ef75503460f94c0acd9/html5/thumbnails/29.jpg)