Rigging and Lifting Handbook Sample
description
Transcript of Rigging and Lifting Handbook Sample
Whereas, if the load is divided into simple / symmetrical shapes, approximate measurements taken and basic calculations used i.e. load weight = volume x density (reference weight calculation in the following section), a greater degree of accuracy can be achieved.
However, even with this method, if the load weight is estimated, a suitable factor, for example 25%, should be added to compensate for the inaccuracy in the estimation.
16.2 Weight Calculation
To calculate load weight use the following formula:
Load Weight (LW) = Volume (VVOL) x Density (DDEN)
Note | The use of formulae in this handbook does not produce competence. Formulae should be used to enhance and refresh existing knowledge. Only authorised personnel with the appropriate engineering qualifications should produce, review or approve engineering calculations. To enhance efficiency, go to www.rigex.com for online calculation tools.
When using formulae:
• When two letters are together, e.g. ‘ab’ this means ‘a’ times ‘b’
• a/b means ‘a’ is divided by ‘b’• a2 means ‘a’ times ‘a’• a3 means ‘a’ times ‘a’ times by ‘a’• π = 3.142• Always write out the formula first• Ensure that all units are the same• Write calculations out line by line and keep work tidy
1 lb. 0.45 kg
2.2 lb. 1 kg
2000 lb.1
Short ton907 kg
2204 lb. 1000 kg 1 tonne
2240 lb.1
Long ton1016 kg
225 lb. 1 kN
38 People. Process. Performance.
16.3 Conversion Table
16.4 Density Table
Imperial Metric
1 inch 25.4 mm 2.54 cm 0.0254 m
1 foot 305 mm 30.5 cm 0.305 m
1 yard 914.4 mm 91.44 cm 0.9144 m
Material lb./ft³ kg/m³
Aluminium 165 2640
Brass 545 8730
Concrete 150 2400
Copper 557 8930
Lead 708 11340
Printing Paper 50 800
Stainless Steel 500 8000
Steel 490 7850
Water 62 1000
Water (sea) 64 1025
Wood (pine average) 36 580
Note | The values in the previous table are given as guidance only (1 kg/m³ = 0.0624 lb./ft³ = 0.000036127 lb./in³).
1 lb. 0.45 kg
2.2 lb. 1 kg
2000 lb.1
Short ton907 kg
2204 lb. 1000 kg 1 tonne
2240 lb.1
Long ton1016 kg
225 lb. 1 kN
www.rigex.com | [email protected] 39
Rigging and Lifting Operations Handbook
16.5 Volume Formulae
Cube
L³
Cuboid or Plate
L x W x H
Cylinder
πR² x H
L
W
L
L
L
H
H
R
40 People. Process. Performance.
Pipe
(πR² - πr²) x H
Cone
(πR²H) ÷ 3
Sphere
(4πR³) ÷ 3
R
H
H
Rr
R
www.rigex.com | [email protected] 41
Rigging and Lifting Operations Handbook
17.0 Centre of Gravity
Where the CoG is located, is just as important as knowing the weight of the load.
The CoG is located where the total weight of an object is assumed to be concentrated.
For symmetrical loads the CoG will be located in the geometric centre.
For asymmetrical (not symmetrical) loads, that can be divided into symmetrical shapes, two of the simplest methods that can be used to find the CoG are to draw the load to scale and use inverse proportionality or use moments around an axis / datum line.
On the following pages:
• Example 1 uses a scale drawing and inverse proportionality • Example 2 uses moments around an axis / datum line
42 People. Process. Performance.
Example 1 - Scale Drawing and Inverse Proportionality
1. Draw the load (front elevation) to scale.
2. Determine the total weight of the load: 30 ton
3. Divide the load into symmetrical shapes and label: A and B
4. Determine the weight of each shape: A = 10 ton, B = 20 ton
5. Locate the CoG for each shape.
6. Draw a connecting line between each CoG.
7. Shape ‘A’ represents one third (1/3) of the total weight, shape ‘B’ two thirds (2/3).
8. Use these proportions inversely as distances on the connecting line to identify the location of the actual / combined CoG.
• Shape ‘A’ weight = 1/3, distance of CoG from ‘A’ = 2/3
• Shape ‘B’ weight = 2/3, distance of CoG from ‘B’ = 1/3
Note | If you have a load that can be divided into three symmetrical shapes, first determine the combined CoG for two and then use this information with the third shape.
10
20
20
10
10
10
A
B
10
20
20
10
10
10
10
20
20
10
10
10
10
20
20
10
10
10
www.rigex.com | [email protected] 43
Rigging and Lifting Operations Handbook
Example 2 - Moments Around an Axis / Datum Line
For asymmetrical loads, that can be divided into symmetrical shapes, the location of a load's CoG can be determined by using moments around an axis / datum line. A moment, used in this way, is the distance a weight is from an axis / datum line, times weight:
• Moment = Distance x Weight
1. Draw the load (front elevation) to scale.
2. Determine the total weight of the load: 7 ton
3. Divide the load into symmetrical shapes and label: A, B and C
4. Determine the weight of each shape: A = 4 ton, B = 1 ton and C = 2 ton
10
10
30
20
40
10
10
A B C
10
10
30
20
40
10
10
44 People. Process. Performance.
5. Locate and indicate the CoG for each for shape.
6. Draw a datum line on the ‘Y’ axis. This is used to determine the distance along the ‘X’ axis where the combined / actual CoG will be located.
7. Determine the distance that each CoG is located from the datum line: A = 5, B = 15 and C = 25
A B C
10
10
30
20
40
10
10
A
Dat
um L
ine
B C
515
25
www.rigex.com | [email protected] 45
Rigging and Lifting Operations Handbook
8. Produce the following table.
9. Enter the weight of each symmetrical shape and its distance from the ‘Y’ axis / datum line into the table. Next, multiply each to determine the moment.
10. Divide the total moment by the total weight to produce the distance from the ‘Y’ axis / datum line where the combined / actual CoG is located.
• 85 ÷ 7 = 12.1
Shape WeightDistance
from Datum
Weight x Distance (Moment)
A
B
C
Total: Total:
Shape WeightDistance
from Datum
Weight x Distance (Moment)
A 4 5 20
B 1 15 15
C 2 25 50
Total: 7 Total: 85
A
Dat
um L
ine
B C
12.1
46 People. Process. Performance.
21.0 Vertical Reaction Force
By determining the Vertical Reaction Force (VRF), before a load is lifted, personnel will ensure that the force to be applied is less then the lifting point’s capacity.
This information can then be used to determine the tension applied to lifting appliances and accessories.
21.1 Single Point Lifts
For vertical single point lifts the VRF is the same as the weight of the load, tension applied to the appliance and the accessories.
Load applied to Hoist Ring, Shackle, Link and Hoist = 200kg
Load Weight = 200kg
www.rigex.com | [email protected] 51
Rigging and Lifting Operations Handbook
21.2 Two Point Lifts
To determine the VRF on each lifting point, use the following formulae:
• VRF1 = (TW x DDIST2) ÷ TD• VRF2 = (TW x DDIST1) ÷ TD
• TW: Total Weight• DDIST1: Distance between VRF1 and the CoG• DDIST2: Distance between VRF2 and the CoG• TD: Total Distance between VRF1 and VRF 2
Example
VRF1 = (TW x DDIST2) ÷ TD VRF2 = (TW x DDIST1) ÷ TD (600 x 600) ÷ 1400 (600 x 800) ÷ 1400 360,000 ÷ 1400 480,000 ÷ 1400VRF1 = 257 kg VRF1 = 343 kg
Note | Ensure that VRF1 and VRF2 add up to the Total Weight.
TD = 1400mm
Total Weight = 600 kg VRF 2VRF 1
DDIST1 = 800mm DDIST2 = 600mm
52 People. Process. Performance.
21.3 Three and Four Point Lifts
If the lifting points are all at the same height, uniformly and symmetrically distributed around the CoG then the VRF in each will be identical e.g. in a three point lift each VRF will be one third of the total weight.
If there is no symmetry, they are described as statically indeterminate and should be calculated by structural analysis. However, in some four point lift configurations if there is symmetry along at least one axis the VRFs can be manually calculated using the following formulae:
• VRF1 = VRF2 = (TW x DDIST2) ÷ 2TD• VRF3 = VRF4 = (TW x DDIST1) ÷ 2TD
VRF 1
VRF 4VRF 3
VRF 2
www.rigex.com | [email protected] 53
Rigging and Lifting Operations Handbook
28.6 Wire Rope Slings
You will find that right-angled triangles are widely used when calculating sling tensions. It is therefore essential that you understand Pythagoras, Triangle Proportions and Trigonometry.
28.6.1 Pythagoras
If you know the lengths of two sides of a right-angled triangle, you can find the length of the third side, by using the following formula:
• a² + b² = c²
Note | ‘a’ and ‘b’ are usually the shortest sides, ‘c' is usually the longest.
Example
a² + b² = c²
• 3²+ 4² = c²• 9 + 16 = c²• c² = 25• c = 5
b = 4
a = 3
c = ?
c
a
+ =b b²
c²
a²
a²b² c²
www.rigex.com | [email protected] 99
Rigging and Lifting Operations Handbook
28.6.2 Triangle Proportions
A simpler method of working out the length of a triangle’s sides can be used if the triangle has the correct proportions or angles.
If all the angles within a triangle are 60°, the length of each side will be the same (1 : 1 : 1).
If the angles within a triangle are 90°, 45° and 45°, the length of two sides will be the same, with the longest side 1.414 (√2) times the length of either of the two sides (1 : 1 : √2).
If the angles within a triangle are 90°, 60° and 30°, the length of the longest side will be twice the length of the shortest, with the other side 1.732 (√3) times the length of the shortest side (1 : 2 : √3).
√2 (1.414)
1
1
45˚
45˚
√3
1
2
30˚
60˚
1
1 1
60˚
60˚ 60˚
100 People. Process. Performance.
28.6.3 Trigonometry
Pythagoras and triangle proportions are used to determine the length of a triangle’s sides. Trigonometric formulae / ratios (Sine, Cosine and Tangent) are used to determine angles and the length of sides in right-angled triangles.
1. First name each side of the triangle in relation to the angle (θ).
• Hypotenuse (HHy) is the longest side• Opposite (OOpp) is the side opposite the angle• Adjacent (AAdj) is the side next to the angle
2. Next determine what information you have, what information you need and which of the following formulae / ratios to use.
• Sine θ (SSin) = Opposite (OOpp) ÷ Hypotenuse (HHy)• Cosine θ (CCos) = Adjacent (AAdj) ÷ Hypotenuse (HHy)• Tangent θ (TTan) = Opposite (OOpp) ÷ Adjacent (AAdj)
A common way to remember the formulae / ratios is to sound them out phonetically; SOH CAH TOA.
θAAdj
Adjacent
Hypotenuse
Op
po
site H HyOOpp
www.rigex.com | [email protected] 101
Rigging and Lifting Operations Handbook
Example
What is the length of side X?
1. Names the sides.
2. Identify what information you have.
3. Identify what information you need?
4. Choose the formula / ratio that contains both the information you have and the information you need.
You have: the angle (Sin, Cos or Tan) Length of the OppositeYou need: Length of HypotenuseFormula: Sin θ = Opposite ÷ Hypotenuse Sin 31° = 4 ÷ X 0.515 = 4 ÷ X (transpose) X = 4 ÷ 0.515 X = 7.8
Note | Angles must be changed to a dimension ratio. Using a scientific calculator, press Sin, then 31 and then equals. Use inverse function to turn a dimension ratio back to an angle.
31˚
Adjacent
Hypotenuse
Op
po
site X
4
31˚
Adjacent
Hypotenuse
Op
po
site X
4
31˚
Adjacent
Hypotenuse
Op
po
site X
4
31˚
X4
102 People. Process. Performance.
28.6.4 Single Leg Wire Rope Slings
When wire rope is bent around, for example a pin, its capacity is reduced, and can be seriously damaged if bent around a sharp edge.
The following table shows D/d Ratios (D = diameter of sheave, pin or load, d = diameter of wire) and sling configuration efficiency, expressed as a percentage.
Note | To simplify operational use 50% (1:1), 75% (5:1) and 100% (25:1) are used to determine wire rope sling capacities. Specific values / efficiencies should be used out with these generalisations for engineered lifts by using the following formulae:
• When Ratio = 6 or less use: E = 100 – (50 ÷ √Ratio)• When Ratio = 6 or more use: E = 100 – (76 ÷ R0.73)
D/d
Rat
io 1
:1 =
50%
Effi
cien
cy
D/d
Rat
io 5
:1 =
77%
Effi
cien
cy
D/d
Rat
io 2
5:1
= 9
3% E
ffici
ency
www.rigex.com | [email protected] 103
Rigging and Lifting Operations Handbook
28.6.8 Sling Tension Formulae
When lifting points and sling legs are at different heights and lengths to compensate for an offset CoG, Vertical Reaction Forces can be used with the following two formulae to determine sling tension:
• Sling Tension = (VRF x SL) ÷ SH (example 1)• Sling Tension = VRF ÷ Sin θ (example 2)
Example 1
Sling Tension 1 = (VRF1 x SL) ÷ SH (257 x 1592) ÷ 1389 409,144 ÷ 1389Sling Tension 1 = 295 kg
Sling Tension 2 = (VRF2 x SL) ÷ SH (343 x 1510) ÷ 1389 517,930 ÷ 1389Sling Tension 2 = 373 kg
VRF 2 = 343 kg
VRF 1 = 257 kg
Sling Tension 1 = 295 kg
Sling Tension 2 = 373 kg
Sling Length 2 = 1510 m
m
Sling
Heig
ht = 1389 m
mSlin
g Le
ngth
1 =
159
2 m
m
www.rigex.com | [email protected] 111
Rigging and Lifting Operations Handbook
Example 2
Sling Tension 1 = VRF 1 ÷ Sin θ 257 ÷ Sin 60° 257 ÷ 0.866Sling Tension 1 = 297 kg
Sling Tension 2 = VRF 2 ÷ Sin θ 343 ÷ Sin 66° 343 ÷ 0.913Sling Tension 2 = 376 kg
VRF 2 = 343 kg
VRF 1 = 257 kg
Sling Tension 1 = 297 kg
Sling Tension 2 = 376 kg
112 People. Process. Performance.
Example 1
Cross-haul a load from Point A to Point B using two vertical rigging arrangements.
In this example, if the rigging does not exceed 45° the greatest tension i.e. the weight of the load, will be applied to the appliances and accessories at position A when the load is initially lifted, and at position B when the cross-haul is complete.
Note | Engineering input / calculation / approval is required if a vertical rigging arrangement is to exceed 45° and where more than two vertical rigging arrangements are connected to and used to lift a load.
132 People. Process. Performance.
Exa
mp
le 1
To d
eter
min
e th
e ac
tual
tens
ion
at a
ny p
oint
dur
ing
a cr
oss-
haul
usi
ng v
ertic
al r
iggi
ng, u
se th
e fo
llow
ing
form
ulae
:
Tens
ion
1 =
Lo
ad W
eig
ht x
S
L1 x
DD
IST2
(SH
1 x
DD
IST2)
+ (S
H2
x D
DIS
T1)
Tens
ion
2 =
Lo
ad W
eig
ht x
S
L2 x
DD
IST1
(SH
1 x
DD
IST2)
+ (S
H2
x D
DIS
T1)
SH2
SH1
SL1
SL2
DD
IST2
DD
IST1
Tens
ion
1
Tens
ion
2
www.rigex.com | [email protected] 133
Rigging and Lifting Operations Handbook
Exa
mp
le 2
Tens
ion
1 =
Lo
ad W
eig
ht x
S
L1 x
DD
IST2
(SH
1 x
DD
IST2)
+ (S
H2
x D
DIS
T1)
Tens
ion
1 =
1 x
1
.4 x
0.7
5
(1
x 0
.75)
+ (0
.75
x 1)
Tens
ion
1 =
1 x
1.
05
0.7
5 +
0.7
5
Tens
ion
1 =
1 x
1.
05
1.5
Tens
ion
1 =
1 x
0.
7
Tens
ion
1 =
0
.7 t
onn
e
SH2 = 0.75m
SH1 = 1m
SL1 =
1.4
m
SL2 =
1.1
m
DD
IST2
= 0
.75m
DD
IST1
= 1
m
Tens
ion
1
Tens
ion
2
134 People. Process. Performance.
Tens
ion
in a
rig
ging
arr
ange
men
t can
als
o be
det
erm
ined
by
draw
ing
a sc
aled
vec
tor
diag
ram
. Thi
s is
whe
re a
rrow
s re
pres
ent t
ensi
on
(leng
th) a
nd d
irect
ion
(ang
le o
f ten
sion
).
Exa
mp
le 3
Sca
led
vect
or d
iagr
am u
sing
the
riggi
ng a
rran
gem
ent i
n ex
ampl
e 2.
1. D
raw
a v
ertic
al li
ne 1
0cm
long
, whi
ch w
ill re
pres
ent 1
to
nne
i.e. t
he w
eigh
t of t
he lo
ad2.
Fro
m th
e bo
ttom
of t
he v
ertic
al li
ne, d
raw
a li
ne a
t 45°
(th
is w
ill re
pres
ent t
he a
ngle
of t
ensi
on o
n th
e le
ft ha
nd
side
)3.
Fro
m th
e to
p of
the
vert
ical
line
, dra
w a
noth
er li
ne a
t 45
° un
til it
cro
sses
the
seco
nd li
ne (t
his
will
repr
esen
t th
e an
gle
of te
nsio
n on
the
right
han
d si
de)
4. M
easu
re th
e le
ngth
of t
he s
econ
d an
d th
ird li
nes.
Use
th
e sa
me
ratio
as
the
first
line
to d
eter
min
e te
nsio
n i.e
. 10
cm =
1 to
nne,
ther
efor
e 7
cm =
0.7
tonn
e
10cm = 1000kg
7cm
= 7
00kg
7cm
= 7
00kg
www.rigex.com | [email protected] 135
Rigging and Lifting Operations Handbook
Exa
mp
le 4
Cro
ss-h
aul a
load
from
Poi
nt A
to P
oint
B u
sing
one
ver
tical
an
d on
e ho
rizon
tal r
iggi
ng a
rran
gem
ent.
In th
is e
xam
ple,
the
tens
ion
in th
e ve
rtic
al r
iggi
ng a
t 45°
w
ill be
app
roxi
mat
ely
1.5
times
the
wei
ght o
f the
load
. The
te
nsio
n in
the
leve
l hor
izon
tal r
iggi
ng w
ill be
the
sam
e as
the
wei
ght o
f the
load
.
No
te |
Eng
inee
ring
inpu
t / c
alcu
latio
n /
appr
oval
is re
quire
d if
a ve
rtic
al r
iggi
ng a
rran
gem
ent e
xcee
ds 4
5° a
nd /
or
the
horiz
onta
l rig
ging
exc
eeds
the
horiz
onta
l pla
ne.
H
ori
zont
al
Pla
ne
136 People. Process. Performance.
To d
eter
min
e th
e ac
tual
tens
ion
at a
ny p
oint
dur
ing
this
type
of c
ross
-hau
l a s
cale
d ve
ctor
dia
gram
can
be
use
d.
Exa
mp
le 5
Sca
led
vect
or d
iagr
am u
sing
the
riggi
ng a
rran
gem
ent
in e
xam
ple
4.
No
te |
Dur
ing
cros
s-ha
ulin
g op
erat
ions
, do
not s
tand
or
ope
rate
hoi
sts
in th
e po
tent
ial s
win
g pa
th o
f a lo
ad,
shou
ld th
e lif
ting
equi
pmen
t par
t.
10cm = 1 tonne
10cm
= 1
to
nne
14cm
= 1
.4 to
nne
www.rigex.com | [email protected] 137
Rigging and Lifting Operations Handbook
Exa
mp
le 6
In th
is e
xam
ple
a sc
aled
vec
tor
diag
ram
illu
stra
tes
the
tens
ions
app
lied
to th
e ve
rtic
al a
nd h
oriz
onta
l rig
ging
arr
ange
men
ts a
fter
the
angl
es h
ave
been
in
crea
sed
by 1
0°.
10cm = 1 tonne
23.3
cm =
2.3
3 to
nne
19.4
cm =
1.9
4 to
nne
138 People. Process. Performance.