Revised Draft JTP for Hydraulic & Pneumatic Actuators

National Technical Systems / Elwin Jang / 916-392-6163

April, 2001

Page 2: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Overview of Joint Test Protocol

• The Entire JTP is composed of 3 Parts– Part I – Material Testing

– Part II – Component or Rig Testing

– Part III – Flight Testing

• This draft JTP is composed of Parts I & II – Part III will be prepared at a later date

Page 3: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Test Types

• Standard Test – Joint Test-Service & OEM agreed test

• Extended Test – Joint Test-Service or OEM component-specific test

Page 4: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Part I – Coatings & Substrates

• Primary Coating - WC/Co-Cr – Secondary Coatings – WC/Co, Tribaloy T-400,

Cr3C2/NiCr

• Primary Substrates: 4340 ESR steel, PH15-5 SS– Secondary Substrates: HP9-4-30 steel, PH17-4

SS, & Ti-10-2-3 titanium

Page 5: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Material Testing

• Fatigue, Axial (1980 specimens vs. 720 specimens for LG)

• Corrosion (rod specimens)– Neutral Salt Fog (190 specimens vs. 135 specimens for LG)– Sulfur Dioxide– Anodic Polarization (extended test)– Galvanic (extended test)

• Immersion – Liquid and grease• Fretting & Oscillating Wear (no need for follow-on test)

Page 6: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Material Testing (continued)

• Gardner Impact (extended test)• Functional Hydraulic Rod/Seal (draft PWS)• Chemical Stripping• 4-Point Bending (extended test)• Quality Control Tests

– Microhardness– Structural Analysis– Oxide Content; Porosity; Unmelted Particles, Interface

Page 7: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Material Testing (continued)

• Quality Control Tests (continued)– Bond Strength– Bend– Almen Strip

Page 8: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Component or Rig Testing

• Neutral Salt Fog• Sand & Dust• Humidity • Vibration• Impulse• Fluid Immersion• Functional Hydraulic

– Endurance– Leakage– Temperature Shock

Page 9: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Appendix A

• Douglas Aircraft Spec. PS-17134, Qualification Test Procedure for Sterer P/N 70795-24

• “C-17 Door Locking Actuator Assembly”• This utility actuator spec. has valuable tech info and

administrative procedure that can be tailored to other utility actuators and flight control actuators

Page 10: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Draft PWS for Functional Hydraulic Rod/Seal Testing

Greene Tweed PWS

Coating WC/Co-Cr, WC/Co, WC/Co-Cr, WC/Co,

T-400, EHC T-400, EHC, Cr3C2/NiCr

Finish 2-5 Ra 2-5 Ra & SuperfinishSubstrate 4340 steel or equivalent 4340 steel or equivalentDuty Profile Flight control Flight control & utility

Seals Greene Tweed Several major seal suppliers

Sideload None 72 lbs.

Page 11: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Draft PWS for Functional Hydraulic Rod/Seal Testing (cont.)

Greene Tweed PWS

Seal/Rod

Combination 21 120 (may reduce to 60)

Test Temp 120F 120F (may change to: room-

180F-200F)

Leakage at Thermal None -40F to 225F (for Extremes nitrile seal)

-40F to 275F (for Teflon seal)

Page 12: Revised Draft JTP for Hydraulic & Pneumatic Actuators National Technical Systems / Elwin Jang / 916-392-6163 April, 2001.

Future Work

• Will revise the draft JTP & the PWS, after receiving your comments

• PWS specifies testing seals from two major seal suppliers – To avoid appearance of conflict of interest, consider soliciting

independent labs or third party seal suppliers for testing– They may not have available hydraulic test equipment &

associated temp control systems. Thus might ask for higher price