Brendan Clarke Review of Notifications for Distribution Connected Generators MAC Meeting 14 November 2012 DM 10036178

Transcript of Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement...

Page 1: Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement 7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise

Brendan Clarke

Review of Notifications for Distribution Connected GeneratorsMAC Meeting 14 November 2012

DM 10036178

Page 2: Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement 7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise

2

Current Requirement

7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise Scheduled Generator, then it must confirm with System Management the expected time of synchronisation:(a) at least one hour before the expected time of synchronisation; and(b) must update this advice immediately if the time confirmed pursuant toclause 7.9.1(a) changes.

7.9.5. Subject to clause 7.9.6A, if a Market Participant intends to desynchronise a Scheduled Generator, then it must:(a) confirm with System Management the expected time of desynchronisation at least one hour before the expected time of desynchronisation; and(b) update this advice immediately if the time confirmed pursuant to clause7.9.5(a) changes.

Note this does not apply if issued an instruction that requires commit/decommit within 1 hour , but does apply if issued an instruction that requires commit/decommit later than 1 hour .

cl. 7.9.1 C first contravention: $30 000, subsequent contraventions: $60 000

cl. 7.9.5 C first contravention: $45 000, subsequent contraventions: $90 000

DM 10036178

Page 3: Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement 7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise

3

Difference in Safety Approach between Transmission and Distribution

Transmission Connected Generators

- Safety is monitored by the System Operation Controller (SSOC).

- Control is enabled by telephone communication with the Power Station Operator.

- Synchronisation / desynchronisation is granted by SOCCC upon request

Distribution Connected Generators

- Safety is monitored by the Networks Operation Controller (NOC).

- Control is enabled by electronic communication with the Power Station Control System.

- Synchronisation is generally granted by NOC continuously. NOC removes this granting for synchronisation for maintenance or safety reasons. Desynchronisation is permitted at any time.

DM 10036178

Page 4: Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement 7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise

4

The Technical Rules specifically detail the electronic communication

requirements for distribution connected generators to allow this to happen

3.6.9 Remote Control, Monitoring and Communications(a) For generating units exporting 1 MVA or more to the distribution system theGenerator must provide for:(1) tripping of the generating unit remotely from the Network ServiceProvider’s control centre;(2) a close-enable interlock operated from the Network ServiceProvider’s control centre; and(3) remote monitoring at the control centre of (signed) MW, MVAr andvoltage.

DM 10036178

Page 5: Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement 7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise

5

Proposition

System Management may waiver the requirements for distribution connected generators that fall into this category by giving written consent to the Market Participant – this removes the risk of civil penalty

DM 10036178

Page 6: Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement 7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise

6

Proposed Wording

The proposed change is given below:

7.9.1. Subject to clauses 7.9.1A, and 7.9.2 and 7.9.2A, if a Market Participant intends to synchronise a Scheduled Generator, then it must confirm with System Management the expected time of synchronisation:

(a) at least one hour before the expected time of synchronisation; and(b) must update this advice immediately if the time confirmed pursuant toclause 7.9.1(a) changes.

7.9.2A. System Management may advise in writing that a Market Participant that owns a Scheduled Generator connected to the distribution network that it is not required to give a confirmation under clause 7.9.1. in respect of that Scheduled Generator. System Management may only do this where is it satisfied that safe operation facilities and procedures an in place.

DM 10036178

Page 7: Review of Notifications for Distribution Connected … of Notifications for...2 Current Requirement 7.9.1. Subject to clauses 7.9.1A and 7.9.2, if a Market Participant intends to synchronise

7

Proposed Wording

The proposed change is given below:

7.9.5. Subject to clause 7.9.6A and 7.9.6B, if a Market Participant intends to desynchronise aScheduled Generator, then it must:

(a) confirm with System Management the expected time of desynchronisationat least one hour before the expected time of desynchronisation; and(b) update this advice immediately if the time confirmed pursuant to clause7.9.5(a) changes.

7.9.6B. System Management may advise in writing that a Market Participant that owns a Scheduled Generator connected to the distribution network is not required to give a confirmation under clause 7.9.5. in respect of that Scheduled Generator. System Management may only do this where is it satisfied that safe operation facilities and procedures an in place.