Structural Engineering and Earthquake Simulation Laboratory 1 Experimental and Micromechanical Computational Study of Pile Foundations Subjected to Liquefaction-Induced Lateral Spreading - Task 1 (1g Tests) Task 1 (1g Tests) S. Thevanayagam, UB Research Progress Meeting September 11, 2006, 2-4 pm; UB-VTC PI: R. Dobry, co-PI’s: A. Elgamal, S. Thevanayagam, T. Abdoun, M. Zeghal UB-NEES Lab: A. Reinhorn, M. Pitman, J. Hanley, T. Albrechcinski Tulane: Usama El Shamy Students: UB and RPI Students

description

- PowerPoint PPT Presentation

Transcript of Review of Minutes (ST, RD) UB Progress (ST)

Page 1: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory1

Experimental and Micromechanical Computational Study of Pile Foundations Subjected to Liquefaction-Induced Lateral Spreading - Task 1 (1g Tests)Task 1 (1g Tests)

S. Thevanayagam, UB

Research Progress MeetingSeptember 11, 2006, 2-4 pm; UB-VTC

PI: R. Dobry, co-PI’s: A. Elgamal, S. Thevanayagam, T. Abdoun, M. ZeghalUB-NEES Lab: A. Reinhorn, M. Pitman, J. Hanley, T. AlbrechcinskiTulane: Usama El ShamyStudents: UB and RPI Students

Page 2: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory2

Review of Minutes (ST, RD) UB Progress (ST)

Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) Laminar Box Readiness (NE) (Ready)

Preparatory Shake tests (ST, MP) 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 6m Box – LG-0 – 10/06-10/25/06

Project Shake Tests (ST, RD) & Impacts on Project Coordination 6m Box – LG-1 – 10/30 – 11/15/06 6m Box – SG-1 – 11/15 -11/30/06 Single Pile – Test 1A – 3/15-4/15/07 Single Pile – Test 1B – 4/15-5/15/07 Group Pile – Test 2 – 6/1-7/30/07 Lateral shaking tests (3 & 4) – 8/1-11/30/07

Non-Destructive Shaking (ST) Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)

Agenda – 9/11/06Agenda – 9/11/06

Page 3: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory3

Box Assembly - ReadyBox Assembly - Ready

Page 4: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory4

Membrane - ReadyMembrane - Ready

Page 5: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory5

Review of Minutes (ST, RD) UB Progress (ST)

Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) Laminar Box Readiness (NE) (Ready)

Preparatory Shake tests (ST, MP) 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 6m Box – LG-0 – 10/06-10/25/06

Project Shake Tests (ST, RD) & Impacts on Project Coordination 6m Box – LG-1 – 10/30 – 11/15/06 6m Box – SG-1 – 11/15 -11/30/06 Single Pile – Test 1A – 3/15-4/15/07 Single Pile – Test 1B – 4/15-5/15/07 Group Pile – Test 2 – 6/1-7/30/07 Lateral shaking tests (3 & 4) – 8/1-11/30/07

Non-Destructive Shaking (ST) Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)

Agenda – 9/11/06Agenda – 9/11/06

Page 6: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory6

Revised Ground MotionRevised Ground Motion

umax= ±0.74’’

umin= ±0.01’’

f = 2 Hz

-0.006

-0.004

-0.002

0.000

0.002

0.004

0.006

0 1 2 3 4 5Time (s)

Acc

eler

atio

n (g

)

Page 7: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory7

Schedule for Preparatory Shake TestsSchedule for Preparatory Shake Tests Task Name Duration Start Finish

Preparatory Shake Tests 28 days Mon 9/18/06 Wed 10/25/06

3m Box Test 14 days Mon 9/18/06 Thu 10/5/06

Fill the box with water for leak test 2 days Mon 9/18/06 Tue 9/19/06

Reduce water level to 2ft 1 day Wed 9/20/06 Wed 9/20/06

Pump the slurry to theLB up to 3m 3 days Thu 9/21/06 Mon 9/25/06

Cone & Bucket Density Tests 3 days Thu 9/21/06 Mon 9/25/06

CPT 1 day Tue 9/26/06 Tue 9/26/06

Remove top 3m rings 1 day Wed 9/27/06 Wed 9/27/06

Install accelerometers top of the soil 1 day Wed 9/27/06 Wed 9/27/06

Safety Cables; Shaking/Actuator controls; Sensor/DAQ tuning3 days Wed 9/27/06 Fri 9/29/06

NDS & DS Shaking 1 day Mon 10/2/06 Mon 10/2/06

Pump the slurry back to the storage areas 3 days Tue 10/3/06 Thu 10/5/06

Test LG-O 14 days Fri 10/6/06 Wed 10/25/06

Put soil instruments inside the box 2 days Fri 10/6/06 Mon 10/9/06

Fill the box with water up to 2ft 0.5 days Tue 10/10/06 Tue 10/10/06

Pump the slurry to theLB 3.5 days Tue 10/10/06 Fri 10/13/06

Cone & Bucket Density Tests 4 days Tue 10/10/06 Fri 10/13/06

CPT 1 day Mon 10/16/06 Mon 10/16/06

Safety cables, Actuator/sensor/DAQ fine tuning1 day Tue 10/17/06 Tue 10/17/06

NDS & DS Shaking 1 day Wed 10/18/06 Wed 10/18/06

CPT 1 day Thu 10/19/06 Thu 10/19/06

Pump the slurry back to the storage areas 4 days Fri 10/20/06 Wed 10/25/06

17 24 1 8 15 22Sep 17, '06 Sep 24, '06 Oct 1, '06 Oct 8, '06 Oct 15, '06 Oct 22, '06

Page 8: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory8

Preparatory Shake Test #1Preparatory Shake Test #13m Box Test : 9/21 – 10/05

Step 1: Fill the box with water for leak test & reduce level to 2 ft.

Step 2: Pump the slurry to the laminar box up to 3m; density tests; CPT tests

Step 3: Install accelerometers top of the soil

Step 4: Remove Top 3m Rings

Step 5: Safety Cables; Shaking/Actuator controls; Sensor/DAQ tuning

Step 6: NDS & DS Shaking

Step 7: Pump the slurry back to storage

Page 9: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory9

3m Box Test Instrumentation3m Box Test Instrumentation

•Ring and Base Instrumentation:•Accelerometers (Already installed)

•Soil Instrumentation:•Put a steel/wood plate on top of the soil and install X-Accelerometers & Y-Accelerometers

Page 10: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory10

3m Box Test - Instrumentation3m Box Test - InstrumentationY-Acc(Top of the soil)

X-Acc (Top of the soil)

Total Need:

3

3

Readiness:

East

South

2.0

1.0

0.0

Readily Available

Readily Available

Wood/Steel on top of the soil

Page 11: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory11

Preparatory Shake Test #2Preparatory Shake Test #2

Step 1: Install limited soil instruments inside the box

Step 2: Fill the box with water up to 2 ft.

Step 3: Pump the slurry to the laminar box up to 6m; Density tests

Step 4: CPT

Step 5: Safety cables, Actuator/sensor/DAQ fine tuning

Step 7: NDS & DS Shaking

Step 8: CPT

Step 9: Pump the slurry back to the storage areas

6m Box – LG-0 – 10/06-10/25/06

Page 12: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory12

LG-0 InstrumentationLG-0 Instrumentation

Page 13: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory13

LG-0 Instrumentation (NS & EW View)LG-0 Instrumentation (NS & EW View)

Page 14: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory14

Instrumentation TableInstrumentation Table: Test LG-0: Test LG-0

Page 15: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory15

Review of Minutes (ST, RD) UB Progress (ST)

Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) Laminar Box Readiness (NE) (Ready)

Preparatory Shake tests (ST, MP) 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 6m Box – LG-0 – 10/06-10/25/06

Project Shake Tests (ST, RD) & Impacts on Project Coordination 6m Box – LG-1 – 10/30 – 11/15/06 6m Box – SG-1 – 11/15 -11/30/06 Single Pile – Test 1A – 3/15-4/15/07 Single Pile – Test 1B – 4/15-5/15/07 Group Pile – Test 2 – 6/1-7/30/07 Lateral shaking tests (3 & 4) – 8/1-11/30/07

Non-Destructive Shaking (ST) Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)

Agenda – 9/11/06Agenda – 9/11/06

Page 16: Review of Minutes  (ST, RD)    UB Progress (ST)

Structural Engineering and Earthquake Simulation Laboratory16

To review 3m Box Test Data & Fine tune Test LG-0