Retrocommissioning of Existing Buildings
-
Upload
wigreenbuilding -
Category
Education
-
view
90 -
download
0
description
Transcript of Retrocommissioning of Existing Buildings
1
Retrocommissioning of Existing
Buildings
2
Presenters
Manus McDevitt, PE, LEED AP
Principal
Sustainable Engineering Group,
Madison, WI
Alex Harris,
Engineer
Sustainable Engineering Group,
Madison, WI
3
• Understand the motivation and methods for
accomplishing Retrocommissioning (R-Cx)
• Appreciate the value of Retrocommissioning
by considering several case studies
• Recognize some typical issues uncovered by
Retrocommissioning
Learning Objectives
4
What is Retro-Cx?
The process of optimizing the
performance of an existing building
5
Retrocommissioning Benefits
• Improve building performance
• Provide appropriate training
to O&M staff
• Improve occupant comfort
• Improve system reliability
6
Commercial
Industrial
Transportation
Residential
Buildings
Environmental Impact of Buildings
U.S. Energy Consumption by Sector – 2000
98.5 Quadrillion Btu
7
When is Retro-Cx Appropriate?
When there is a good chance of success!
8
Approach - Overview
1. Gather Information
2. Identify improvements
3. Monitor implementation
4. Functional testing
5. Update documentation, train operators
6. Final report
9
1. Gather Information
From Stakeholders
From DocumentationFrom Observation
10
Deliverables
• Operational Intent
– Narratives of facility functional use
– Verifiable performance criteria
– Stakeholder requirements for
• usability, operability, maintainability, functionality
• Basis of Operation
– Documents current building operation
• Installed equipment database
• Control sequences
11
10,000SF Office Building Energy Use
Mid-West US (Chicago)
Space Heating,
32%
Space Cooling,
8%
Ventilation , 5%
Water Heating ,
10%
Lighting , 26%
Other, 19%
Building Energy Usage
12
Approach - Overview
1. Gather Information
2. Identify improvements
3. Monitor implementation
4. Functional testing
5. Update documentation, train operators
6. Final report
13
2. Identify Improvements
• Can the system meet your requirements?
– If so, tune the system to meet your needs
• Examples: Calibrate sensors, adjust control sequences, repair or
replace equipment
– If not, re-design the system as required
• Costs and savings for each improvement
– Prioritize
14
Deliverable
• Facility Optimization Study
– Narrative and technical evaluation of each improvement opportunity
– Estimate of project costs
– Analysis of utility savings and other benefits
– Includes:
• Discussion of documentation improvements
• Discussion of training needs
15
Audit / Investigation Phase
• Collaborate with facilities
team to identify opportunities
• Review building drawings
and documentation
• Performance testing of
building systems
• Develop list of recommended
improvements
16
Potential Measures
• Operational
– Equipment schedules, set points,
• Maintenance
– Valve and damper control issues
• Design
– Identify space function changes, control optimization
17
Common Problems Identified
• Time clocks disabled
• Control sequences not optimized
• Energy Management Systems not understood or fully utilized
• Controls/sensors/actuators out of calibration
• Ventilation excessive
• Documentation & training inadequate
18
VAV Scheduling
15 kW
Fan Savings
19
VAV Scheduling
0
200
400
600
800
1000
1200
8/14/13 8:00:00 PM CDT 8/14/13 10:30:00 PM CDT 8/15/13 1:30:00 AM CDT 8/15/13 5:00:00 AM CDT
Tota
l VA
V B
ox
Reh
eat
(kB
tu/h
r)
AHU-14/15 VAV Box Reheat
20
Data Room Setpoints
Data room set-
points are too tight
for temperature and
humidity, leading to
excessive energy
use.
21
Adjust CRAC Set Points
22
Adjust CRAC Set Points
Annual kW-Hr
Savings
Annual Savings Implementation
Cost
Simple Payback
150,000 $10,391 $50 2 days
23
AHU Chilled Water Valve Control Issue
24
Cooling Tower Exhaust Dampers & Ductwork
Supports have rusted
out and fell into tower
Dampers linkages are corroded
and not functional
25
Disconnected Actuator
Disconnected
actuator is causing
cooling tower to run
at the same time as
boiler. We are heating
the water, only to
reject the heat to the
outdoors
26
Cracked Heat Exchanger
There is risk of
carbon
monoxide being
blown into the
occupied
space. Unit
was shutdown
and gas line
shut-off to unit.
27
Duct to Nowhere
Supply duct is
blowing into
plenum space.
This area was
remodeled and
drop ceiling
added, but the
duct was never
capped, as
shown on
remodel plans.
28
Poor Sensor Location
Heat pump
serving this
space is always
in cooling, even
though the
room
temperature is
65°F.
29
Approach - Overview
1. Gather Information
2. Identify improvements
3. Monitor implementation
4. Functional testing
5. Update documentation, train operators
6. Final report
30
3. Monitor Implementation
RCx provider’s role varies depending on
1. Needs of the client
2. Number and complexity of improvements
3. Type of improvements
31
Approach - Overview
1. Gather Information
2. Identify improvements
3. Monitor implementation
4. Functional testing
5. Update documentation, train operators
6. Final report
32
4. Functional Testing
• RCx provider’s role varies
• Verify the performance of building systems
• May use statistical sampling
33
Approach - Overview
1. Gather Information
2. Identify improvements
3. Monitor implementation
4. Functional testing
5. Update documentation, train operators
6. Final report
34
5. Documentation & Training
• Update documentation
– Drawings
– O & M manuals
– Operating sequences
– Equipment database
– Maintenance schedules
• Schedule training
35
Approach - Overview
1. Gather Information
2. Identify improvements
3. Monitor implementation
4. Functional testing
5. Update documentation, train operators
6. Final report
36
6. Final Report
• Based on the Facility Optimization Study
– Includes discussion of implemented projects and testing
– Reference document for future projects and operations
37
Persistence
Phase:
Verify
Persistence
of Savings
(Optional)
Implementation Phase:
Implement Selected
Measures & Verify Actual
Savings
Audit Phase:
Complete Audit &
Quantify Measures
Qualify
Customer
& Submit
Application
Focus on Energy RCx Process
38
Medical Clinic
• Established in 1996
• 22 Clinics
• 2 million+ outpatient visits
• 1 South Park Street
• 174,000 ft2
• 6 OR’s
• 2 MRI’s
• 392 kBtu/ft2-yr (source)
Medical Clinic, Madison, WI
39
Medical Clinic
Proposed Phase Workbook
Description
Electric
Energy
Savings
(kW-hr)
Electric
Demand
Savings
(kW)
Natural
Gas
Savings
(Therms)
Measure
Installatio
n
Incentive
($)
Energy
Cost
Savings
($)
Measure
Cost ($)
Simple
Payback
(Years)
M1On all air handlers, increase economizer
switchover from 51.5°F to 68°F 101,130 - - N/A $7,079 $100 0.0
M2Modify air handler schedules 123,599 - 5,727 N/A $10,617 $100 0.0
M3 Replace RTU-2 Control Board 44,800 - 5,880 N/A $6,570 $500 0.1
M4Replace 52W Incadescent Bulbs with
CFL's 6,841 1.8 -134 N/A $231 $200 0.9
M5Install lighting occupancy sensors on
Floors 5, 6, 7 and lower level 19,314 - -358 N/A $1,098 $9,100 8.3
Proposed Phase Savings
40
Medical Clinic
Project Summary
41
Medical Clinic
Persistence CheckGreat Persistence:
• Controls programming changes
• VFD Installs
• Equipment Upgrades
Poor Persistence:
• Schedule modifications
• Set point modifications
• Fixing valves / equipment
(Grease Fan BRGS Yearly!!)
42
Medical Clinic
Performance Since Implementation
43
Medical Clinic, Madison, WI
100
200
300
400
500
600
700
1 2 3 4 5 6 7 8 9 10 11 12
Ele
ctr
ic C
on
su
mp
tio
n (
MW
-hr)
Month of year (January = 1, December =12)
Monthly Electric Consumption
2009 2010 2011 2012 2013-Pre RCx 2013 2014
44
Medical Clinic, Madison, WI
Portfolio Manager Tracking
Before After
45
Medical Clinic
Review of Incentives Paid Out
46
Medical Clinic
Evaluate Economics
• Savings
$66,000/yr utility cost avoidance
• Expenses
$50,000 study cost
$30,000 implementation cost
• Incentive
+$63,000 incentive
• Simple Payback = 0.3 years (after incentive)
47
505 Passenger Vehicles / Year
62,000 trees grown for 10 years
121 Homes / Year
48
Solar Equivalent of Electric Savings
49
Retro-Cx Effort at Area School
• Built in 1960’s
• Several additions in 1980’s and 1990’s
• Total area of 250,000 ft2
• 30 Air Handling Units
• Mix of Constant Volume
and VAV
• 7 Boilers and 2 Chillers
Main concern is
energy consumption
50
Retro-Cx Effort at Area School
• A heating system controller was installed to allow for proper sequencing of all boiler units.
• The hot water system has been modified to allow for variable flow operation.
• Schedules have been modified to reflect space occupancy patterns for each air-handling unit zone.
• Economizer modes have been modified to improve comfort and energy efficiency
51
Retro-Cx Effort at Area School
• Existing chillers are being replaced with more efficient, variable flow and smaller capacity models.
• Computer labs and the IT room have been removed from main chilled water system and are now cooled by independent cooling units, which results in a shorter seasonal operating window for the chillers and improves comfort in winter.
New
Old
52
Airflow checking and rebalancing results in enhanced
occupant comfort and potentially lower operating costs
Retro-Cx Effort at Area School
• Staff have reported problems with “stuffiness” in several spaces
• Perimeter areas of Office and Guidance spaces too cold in winter
53
53
Savings of about $30-50,000 / year in gas
Retro-Cx Effort at Area School
Normalized Gas Use Comparison
0
5000
10000
15000
20000
25000
30000
35000
October November December January February March
Ga
s U
se
(T
he
rms)
)
2005
2006
54
54
Savings of about $10-20,000 / yr in electricity
Retro-Cx Effort at Area School
Electric Use Comparison
0
50000
100000
150000
200000
250000
October November December January February March
Ele
ctr
ic U
se
(kW
h)
)
2005
2006
55
Retro-Cx Effort at Area School
OLD NEW
Electric Use (kWh) 11,000 1,900
Electric Demand (kW) 18 3
• Existing roof-mounted chilled water pipe insulation is badly deteriorated
• It is being replaced with thicker aluminum shielded, weather-resistant insulation
Savings of about $500 / yr
Savings due to improved insulation
56
Retro-Cx Effort at Area School
Annual estimated savings:
$40,000 to $70,000
Estimated cost to realize savings:
~$35,000
Payback period: 6-10 months
Bonus: Improved comfort and operation!
57
Life After Retrocommissioning
• RCx Process
• RCx Results
• Life After RCx
• Next Steps
58
Portfolio Manager Tracking
59
Continuous Commissioning Tools
60
Continuous Commissioning Tools
• BAS Integrated Continuous Commissioning Tools
– “Building Analytics”
– “Building Management Performance Analytic Tools”
• Provide following capabilities
– Equipment and system fault detection and diagnostics
– Ongoing commissioning including optimization of building control
– Demand response
– Performance benchmarking
• Typically Cloud Based
– Monthly subscription fee
61
LEED EB RCx
• Credits for:
– Documenting building operations and benchmarking performance
– Retrocommissioning audit phase
– Implementing identified retrocommissioning measures
– Ongoing commissioning
62
What Can YOU Do?
• Benchmark your facilities
• Set goals
• Put an energy plan together
63
Complete the RCx Process!
64
Developing an Energy Plan
65