Results of Münster- Meeting 4 flanges on roof instead of 12 (two 2 DN250, 2 DN100) Stiffeners can...

3
Results of Münster- Meeting 4 flanges on roof instead of 12 (two 2 DN250, 2 DN100) Stiffeners can be placed on the roof Also variabel in amount and/or placement Rails have to be built on the roof for safe access to the flanges Top disk is flanged to roof Diameter of top disk will be changed to 2.75m; to keep height the slope of roof will be increased Cryo-pipe is lead through wall of water-tank by a flange

Transcript of Results of Münster- Meeting 4 flanges on roof instead of 12 (two 2 DN250, 2 DN100) Stiffeners can...

Page 1: Results of Münster- Meeting 4 flanges on roof instead of 12 (two 2 DN250, 2 DN100) Stiffeners can be placed on the roof Also variabel in amount and/or.

Results of Münster-Meeting

4 flanges on roof instead of 12 (two 2 DN250, 2 DN100)

Stiffeners can be placed on the roof

Also variabel in amount and/or placement

Rails have to be built on the roof for safe access to the flanges

Top disk is flanged to roof

Diameter of top disk will be changed to 2.75m; to keep height the slope of roof will be increased

Cryo-pipe is lead through wall of water-tank by a flange

Page 2: Results of Münster- Meeting 4 flanges on roof instead of 12 (two 2 DN250, 2 DN100) Stiffeners can be placed on the roof Also variabel in amount and/or.

Status Water-tank before Münster-meeting

Page 3: Results of Münster- Meeting 4 flanges on roof instead of 12 (two 2 DN250, 2 DN100) Stiffeners can be placed on the roof Also variabel in amount and/or.

More activities

• TPC– Cryo for TPC– Outer vessel– Accessories

• Gassystem– Check Layout– Check already bought valves– List of to be ordered parts (MFC,

etc.)– Place in lab? Accessories.