Resources Calculations for Bldg. A

14
Activity ID Activity Describtion Unit Total QTY (A) Prod. Rate (Unit/Day) (B) Days C = (A/B) Crew QTY (D) Theritocal Duration E = (C/D) Original Duration Carpenter Mason Helper (Labor) Mirror Skilled Labor Plumber Metal Worker Technician Painter Alum. Tech Waterproofer Suspended Ceiling Skilled Labor Steel Structure Skilled Labor hardware skilled people/window Carpet Labors Wall Paper Skilled Labor FF&E Studio Apartement (3 No.) 1st Floor to 2th Floor TIME LIMIT Manpower Al Muraqqabat Mixed Use Development Resource Plan Calculations Building A - Hotel Apartments Block Works m2 162 8 20.25 10 2.025 3 10 10 Plaster Works m2 Internal Plaster Accessories 312 35 8.914286 5 1.782857 2 5 5 Internal Plaster Works 312 12 26 5 5.2 5 5 5 Installation of Doors& Windows Subframe No. 6 4.5 1.333333 1 1.333333 1 1 1 Water Proofing for Wet Area m2 25 10 2.5 1 2.5 3 1 1 1st Coat Paint m2 366 Primer Application Works 366 54 6.777778 4 1.694444 1 4 4 Stucco Application Works 366 16 22.875 4 5.71875 5 4 4 Instalaltion of Suspened Ceiling Grid (Wet) m2 17 7.2 2.361111 1 2.361111 3 1 1 Instalaltion of Suspened Ceiling Grid (Dry) m2 42 7.2 5.833333 1 5.833333 6 1 1 Screed for Wet Area m2 18 25 0.72 1 0.72 1 1 1 Screed for Dry Area m2 93 25 3.72 1 3.72 4 1 1 Floor Tiles Work (Wet) m2 18 10 1.8 1 1.8 2 1 1 Floor Tiles Work (Dry) m2 42 15 2.8 1 2.8 3 1 1 Wall Tiles Work (Wet) m2 63 8 7.875 1 7.875 8 1 1 Finishes Wall Tiles Work (Dry) m2 10 12 0.833333 1 0.833333 1 1 1 Installation of Wardrobes No. 3 0.75 4 2 2 2 2 2 Installation of Kitchen Cabinets No. 3 0.6 5 3 1.666667 2 3 3 Instalaltion of Balustrades& Handrails No. 3 15 0.2 1 0.2 1 1 1 Instalaltion of Vanity Counter No. 3 1 3 2 1.5 1 2 2 Instalation of Windows&Doors No. 6 4.8 1.25 2 0.625 1 2 2 Instalaltion of Toliets Accessories No. 3 0.5 6 3 2 2 3 3 Suspended Ceiling Tiles (Wet) m2 17 7.2 2.361111 1 2.361111 2 1 1 Suspended Ceiling Tiles (Dry) m2 42 7.2 5.833333 2 2.916667 3 2 2 Instllation of Mirrors No. 3 1 3 2 1.5 1 2 Doors Ironmogery No. 3 4.8 0.625 1 0.625 1 1 1 Final Coat Paint m2 366 32 11.4375 2 5.71875 6 2 2 Installation of Carpets m2 50 20 2.5 1 2.5 3 2 Installation of Sinages No. 3 5 0.6 1 0.6 1 1 Installation of Furniture No. 3 0.5 6 1 6 6 8 Studio Apartement (3 No.) 3th Floor to 7th Floor Block Works m2 162 8 20.25 10 2.025 3 10 10 Plaster Works m2 Internal Plaster Accessories 312 35 8.914286 5 1.782857 2 5 5 Internal Plaster Works 312 12 26 5 5.2 5 5 5 Installation of Doors& Windows Subframe No. 6 4.5 1.333333 1 1.333333 1 1 1 Water Proofing for Wet Area m2 25 10 2.5 1 2.5 3 1 1 1st Coat Paint m2 366 Primer Application Works 366 54 6.777778 4 1.694444 1 4 Stucco Application Works 366 16 22.875 4 5.71875 5 4 Instalaltion of Suspened Ceiling Grid (Wet) m2 17 7.2 2.361111 1 2.361111 3 1 1 Instalaltion of Suspened Ceiling Grid (Dry) m2 42 7.2 5.833333 1 5.833333 6 1 1 Screed for Wet Area m2 18 25 0.72 1 0.72 1 1 1 Screed for Dry Area m2 93 25 3.72 1 3.72 4 1 1 Floor Tiles Work (Wet) m2 18 10 1.8 1 1.8 2 1 1 Floor Tiles Work (Dry) m2 42 15 2.8 1 2.8 3 1 1 Wall Tiles Work (Wet) m2 63 8 7.875 1 7.875 8 1 1 Finishes Wall Tiles Work (Dry) m2 10 12 0.833333 1 0.833333 1 1 1 Installation of Wardrobes No. 3 0.75 4 1 4 2 1 1 Installation of Kitchen Cabinets No. 3 0.6 5 2 2.5 3 2 2 Instalaltion of Balustrades& Handrails No. 3 15 0.2 1 0.2 1 1 1 Instalaltion of Vanity Counter No. 3 1 3 2 1.5 2 2 2 File:Resources Plan Page 1 of 14 Printed On :07/07/2012 at 11:21

Transcript of Resources Calculations for Bldg. A

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

Studio Apartement (3 No.)1st Floor to 2th Floor

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Block Works m2 162 8 20.25 10 2.025 3 10 10Plaster Works m2

Internal Plaster Accessories  312 35 8.914286 5 1.782857 2 5 5Internal Plaster Works  312 12 26 5 5.2 5 5 5

Installation of Doors& Windows Sub‐frame No. 6 4.5 1.333333 1 1.333333 1 1 1Water Proofing for Wet Area m2 25 10 2.5 1 2.5 3 1 11st Coat Paint m2 366

 Primer Application Works  366 54 6.777778 4 1.694444 1 4 4Stucco Application Works  366 16 22.875 4 5.71875 5 4 4

Instalaltion of Suspened Ceiling Grid (Wet) m2 17 7.2 2.361111 1 2.361111 3 1 1Instalaltion of Suspened Ceiling Grid (Dry) m2 42 7.2 5.833333 1 5.833333 6 1 1Screed for Wet Area m2 18 25 0.72 1 0.72 1 1 1Screed for Dry Area m2 93 25 3.72 1 3.72 4 1 1Floor Tiles Work (Wet) m2 18 10 1.8 1 1.8 2 1 1Floor Tiles Work (Dry) m2 42 15 2.8 1 2.8 3 1 1Wall Tiles Work (Wet) m2 63 8 7.875 1 7.875 8 1 1

Finishes

Wall Tiles Work (Dry) m2 10 12 0.833333 1 0.833333 1 1 1Installation of Wardrobes No. 3 0.75 4 2 2 2 2 2Installation of Kitchen Cabinets No. 3 0.6 5 3 1.666667 2 3 3Instalaltion of Balustrades& Handrails No. 3 15 0.2 1 0.2 1 1 1Instalaltion of Vanity Counter No. 3 1 3 2 1.5 1 2 2Instalation of Windows&Doors No. 6 4.8 1.25 2 0.625 1 2 2Instalaltion of Toliets Accessories No. 3 0.5 6 3 2 2 3 3Suspended Ceiling Tiles (Wet) m2 17 7.2 2.361111 1 2.361111 2 1 1Suspended Ceiling Tiles (Dry) m2 42 7.2 5.833333 2 2.916667 3 2 2Instllation of Mirrors No. 3 1 3 2 1.5 1 2Doors Ironmogery No. 3 4.8 0.625 1 0.625 1 1 1Final Coat Paint m2 366 32 11.4375 2 5.71875 6 2 2Installation of Carpets m2 50 20 2.5 1 2.5 3 2Installation of Sinages No. 3 5 0.6 1 0.6 1 1Installation of Furniture No. 3 0.5 6 1 6 6 8

Studio Apartement (3 No.)3th Floor to 7th Floor

Block Works m2 162 8 20.25 10 2.025 3 10 10Plaster Works m2

Internal Plaster Accessories  312 35 8.914286 5 1.782857 2 5 5Internal Plaster Works  312 12 26 5 5.2 5 5 5

Installation of Doors& Windows Sub‐frame No. 6 4.5 1.333333 1 1.333333 1 1 1Water Proofing for Wet Area m2 25 10 2.5 1 2.5 3 1 11st Coat Paint m2 366

 Primer Application Works  366 54 6.777778 4 1.694444 1 4Stucco Application Works  366 16 22.875 4 5.71875 5 4

Instalaltion of Suspened Ceiling Grid (Wet) m2 17 7.2 2.361111 1 2.361111 3 1 1Instalaltion of Suspened Ceiling Grid (Dry) m2 42 7.2 5.833333 1 5.833333 6 1 1Screed for Wet Area m2 18 25 0.72 1 0.72 1 1 1Screed for Dry Area m2 93 25 3.72 1 3.72 4 1 1Floor Tiles Work (Wet) m2 18 10 1.8 1 1.8 2 1 1Floor Tiles Work (Dry) m2 42 15 2.8 1 2.8 3 1 1Wall Tiles Work (Wet) m2 63 8 7.875 1 7.875 8 1 1

Finishes

Wall Tiles Work (Dry) m2 10 12 0.833333 1 0.833333 1 1 1Installation of Wardrobes No. 3 0.75 4 1 4 2 1 1Installation of Kitchen Cabinets No. 3 0.6 5 2 2.5 3 2 2Instalaltion of Balustrades& Handrails No. 3 15 0.2 1 0.2 1 1 1Instalaltion of Vanity Counter No. 3 1 3 2 1.5 2 2 2

File:‐ Resources Plan Page 1 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Instalation of Windows&Doors No. 6 4.8 1.25 1 1.25 2 1 1Instalaltion of Toliets Accessories No. 3 0.5 6 3 2 2 3 3Suspended Ceiling Tiles (Wet) m2 17 7.2 2.361111 1 2.361111 2 1 1Suspended Ceiling Tiles (Wet) m2 17 7.2 2.361111 1 2.361111 2 1 1Suspended Ceiling Tiles (Dry) 42 7.2 5.833333 2 2.916667 2 2 2Instllation of Mirrors No. 3 1 3 2 1.5 2 2Doors Ironmogery No. 9 4.8 1.875 1 1.875 2 1 1Final Coat Paint m2 366 32 11.4375 2 5.71875 6 2 2Installation of Carpets m2 50 20 2.5 2 1.25 4 2Instllation of Sinages No. 3 5 0.6 1 0.6 1 1Instllation of Furniture No. 3 0.5 6 1 6 6 8

Block Works m2 504 8 63 10 6.3 6 10 10Plaster Works m2

Internal Plaster Accessories  900 35 25.71429 10 2.571429 2 10 10Internal Plaster Works  900 12 75 10 7.5 7 10 10

Installation of Doors& Windows Sub‐frame No. 16 4.5 3.555556 1 3.555556 5 1 1Water Proofing for Wet Area m2 83 10 8.3 2 4.15 4 2 2

Finishes1st Floor 1 BD Apartement (4 No.)

1st Coat Paint m2 Primer Application Works  1032 54 19.11111 9 2.123457 2 9 9Stucco Application Works  1032 16 64.5 9 7.166667 7 9 9

Instalaltion of Suspened Ceiling Grid (Wet) m2 67 7.2 9.305556 2 4.652778 5 2 2Instalaltion of Suspened Ceiling Grid (Dry) m2 68 7.2 9.444444 2 4.722222 5 2 2Screed for Wet Area m2 68 25 2.72 1 2.72 3 1 1Screed for Dry Area m2 208 25 8.32 1 8.32 8 1 1Floor Tiles Work (Wet) m2 66 10 6.6 1 6.6 7 1 1Floor Tiles Work (Dry) m2 16 15 1.066667 2 0.533333 1 2 2Wood Floor m2 110 16 6.875 2 3.4375 3 2 2Wall Tiles Work (Wet) m2 168 8 21 4 5.25 6 4 4Wall Tiles Work (Dry) m2 24 12 2 2 1 1 2 2Installation of Wardrobes No. 4 0.75 5.333333 1 5.333333 5 1 1Installation of Kitchen Cabinets No. 4 0.6 6.666667 2 3.333333 4 2 2Instalaltion of Balustrades& Handrails No. 4 15 0.266667 1 0.266667 1 1 1Instalaltion of Vanity Counter No. 8 1 8 2 4 4 2 2Instalation of Windows&Doors No. 16 4.8 3.333333 1 3.333333 3 1 1Instalaltion of Toliets Accessories No 8 0 5 16 3 5 333333 5 3 3Instalaltion of Toliets Accessories No. 8 0.5 16 3 5.333333 5 3 3Suspended Ceiling Tiles (Wet) m2 67 7.2 9.305556 2 4.652778 5 2 2Suspended Ceiling Tiles (Dry) 68 7.2 9.444444 3 3.148148 3 3 3Instllation of Mirrors No. 8 1 8 2 4 4 2Doors Ironmogery No. 32 4.8 6.666667 2 3.333333 3 2 2Final Coat Paint m2 1032 32 32.25 5 6.45 7 5 5Installation of Carpets m2 48 20 2.4 2 1.2 4 2Instllation of Sinages No. 4 5 0.8 1 0.8 1 1Instllation of Furniture No. 4 0.5 8 1 8 8 8

Block Works m2 378 8 47.25 10 4.725 6 10 10Plaster Works m2

Internal Plaster Accessories  675 35 19.28571 11 1.753247 2 11 11Internal Plaster Works  675 12 56.25 11 5.113636 5 11 11

Installation of Doors& Windows Sub‐frame No. 12 4.5 2.666667 1 2.666667 3 1 1

1 BD Apartement (3 No.)2nd to 7th Floor Finishes

Water Proofing for Wet Area m2 63 10 6.3 2 3.15 3 2 21st Coat Paint m2

 Primer Application Works  780 54 14.44444 8 1.805556 1 8 8Stucco Application Works  780 16 48.75 8 6.09375 6 8 8

Instalaltion of Suspened Ceiling Grid (Wet) m2 51 7.2 7.083333 2 3.541667 4 2 2

File:‐ Resources Plan Page 2 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Instalaltion of Suspened Ceiling Grid (Dry) m2 54 7.2 7.5 2 3.75 4 2 2Screed for Wet Area m2 51 25 2.04 1 2.04 2 1 1Screed for Dry Area m2 156 25 6.24 1 6.24 7 1 1Screed for Dry Area m2 156 25 6.24 1 6.24 7 1 1Floor Tiles Work (Wet) m2 51 10 5.1 1 5.1 5 1 1Floor Tiles Work (Dry) m2 18 15 1.2 2 0.6 1 2 2Wood Floor m2 78 16 4.875 2 2.4375 2 2 2Wall Tiles Work (Wet) m2 126 8 15.75 4 3.9375 4 4 4Wall Tiles Work (Dry) m2 18 12 1.5 2 0.75 1 2 2Installation of Wardrobes No. 3 0.75 4 1 4 4 1 1Installation of Kitchen Cabinets No. 3 0.6 5 2 2.5 3 2 2Instalaltion of Balustrades& Handrails No. 3 15 0.2 1 0.2 1 1 1Instalaltion of Vanity Counter No. 6 1 6 2 3 3 2 2Instalation of Windows&Doors No. 12 4.8 2.5 1 2.5 3 1 1Instalaltion of Toliets Accessories No. 6 0.5 12 3 4 4 3 3Suspended Ceiling Tiles (Wet) m2 51 7.2 7.083333 2 3.541667 4 2 2Suspended Ceiling Tiles (Dry) 54 7.2 7.5 2 3.75 4 2 2Instllation of Mirrors No. 6 1 6 2 3 3 2Doors Ironmogery No. 12 4.8 2.5 1 2.5 3 1 1Final Coat Paint m2 780 32 24.375 5 4.875 5 5 5Installation of Carpets m2 63 20 3.15 2 1.575 4 2Instllation of Sinages No. 3 5 0.6 1 0.6 1 1Instllation of Furniture No. 3 0.5 6 1 6 6 6

Block Works m2 975 8 121.875 10 12.1875 12 10 10Plaster Works m2

Internal Plaster Accessories  1655 35 47.28571 10 4.728571 4 10 10Internal Plaster Works  1655 12 137.9167 10 13.79167 13 10 10

Installation of Doors& Windows Sub‐frame No. 25 4.5 5.555556 1 5.555556 6 1 1Water Proofing for Wet Area m2 155 10 15.5 2 7.75 12 2 21st Coat Paint m2

 Primer Application Works  1930 54 35.74074 10 3.574074 4 10 10Stucco Application Works  1930 16 120.625 10 12.0625 12 10 10

Instalaltion of Suspened Ceiling Grid (Wet) m2 125 7.2 17.36111 3 5.787037 6 3 3Instalaltion of Suspened Ceiling Grid (Dry) m2 155 7.2 21.52778 3 7.175926 7 3 3Screed for Wet Area m2 125 25 5 2 2 5 3 2 2

1st FloorFinishes

2 BD Apartement (5 No.)

Screed for Wet Area m2 125 25 5 2 2.5 3 2 2Screed for Dry Area m2 375 25 15 3 5 5 3 3Floor Tiles Work (Wet) m2 125 10 12.5 3 4.166667 4 3 3Floor Tiles Work (Dry) m2 100 15 6.666667 2 3.333333 4 2 2Wood Floor m2 85 16 5.3125 2 2.65625 3 2 2Wall Tiles Work (Wet) m2 350 8 43.75 4 10.9375 11 4 4Wall Tiles Work (Dry) m2 35 12 2.916667 2 1.458333 2 2 2Installation of Wardrobes No. 10 0.75 13.33333 2 6.666667 7 2 2Installation of Kitchen Cabinets No. 5 0.6 8.333333 1 8.333333 8 1 1Instalaltion of Balustrades& Handrails No. 5 15 0.333333 1 0.333333 5 1 1Instalaltion of Vanity Counter No. 15 1 15 2 7.5 8 2 2Instalation of Windows&Doors No. 25 4.8 5.208333 1 5.208333 5 1 1Instalaltion of Toliets Accessories No. 15 0.5 30 3 10 10 3 3Suspended Ceiling Tiles (Wet) m2 125 7.2 17.36111 3 5.787037 5 3 3Suspended Ceiling Tiles (Dry) 155 7.2 21.52778 3 7.175926 7 3 3Instllation of Mirrors No. 15 1 15 2 7.5 8 2Doors Ironmogery No. 25 4.8 5.208333 1 5.208333 5 1 1Final Coat Paint m2 1930 32 60.3125 8 7.539063 8 8 8Installation of Carpets m2 190 20 9.5 2 4.75 5 2Instllation of Sinages No. 5 5 1 1 1 1 1Instllation of Furniture No. 5 0.5 10 1 10 10 10

2 BD Apartement (6 No.)2nd to 7th Floor File:‐ Resources Plan Page 3 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Block Works m2 1170 8 146.25 10 14.625 15 10 10Pl t W k 2

Finishes

Plaster Works m2Internal Plaster Accessories  1986 35 56.74286 11 5.158442 5 11 11

Internal Plaster Works  1986 12 165.5 11 15.04545 15 11 11Installation of Doors& Windows Sub‐frame No. 30 4.5 6.666667 1 6.666667 7 1 1Water Proofing for Wet Area m2 186 10 18.6 2 9.3 9 2 21st Coat Paint m2

 Primer Application Works  2316 54 42.88889 10 4.288889 4 10 10Stucco Application Works  2316 16 144.75 10 14.475 14 10 10

Instalaltion of Suspened Ceiling Grid (Wet) m2 150 7.2 20.83333 3 6.944444 7 3 3Instalaltion of Suspened Ceiling Grid (Dry) m2 186 7.2 25.83333 3 8.611111 8 3 3Screed for Wet Area m2 150 25 6 2 3 3 2 2Screed for Dry Area m2 450 25 18 3 6 6 3 3Floor Tiles Work (Wet) m2 150 10 15 3 5 5 3 3Floor Tiles Work (Dry) m2 120 15 8 2 4 4 2 2Wood Floor m2 102 16 6.375 1 6.375 6 1 1Wall Tiles Work (Wet) m2 420 8 52.5 4 13.125 13 4 4Wall Tiles Work (Dry) m2 42 12 3.5 2 1.75 2 2 2Installation of Wardrobes No. 12 0.75 16 2 8 8 2 2Installation of Kitchen Cabinets No. 6 0.6 10 1 10 10 1 1Instalaltion of Balustrades& Handrails No. 6 15 0.4 1 0.4 5 5 5Instalaltion of Vanity Counter No. 18 1 18 2 9 9 2 2Instalation of Windows&Doors No. 30 4.8 6.25 1 6.25 7 1 1Instalaltion of Toliets Accessories No. 18 0.5 36 3 12 12 3 3Suspended Ceiling Tiles (Wet) m2 150 7.2 20.83333 3 6.944444 10 3 3Suspended Ceiling Tiles (Dry) 186 7.2 25.83333 3 8.611111 12 3 3Instllation of Mirrors No. 18 1 18 2 9 9 2Doors Ironmogery No. 30 4.8 6.25 1 6.25 6 1 1Final Coat Paint m2 2316 32 72.375 8 9.046875 9 8 8Installation of Carpets m2 228 20 11.4 3 3.8 4 3Instllation of Sinages No. 6 5 1.2 1 1.2 2 1Instllation of Furniture No. 6 0.5 12 1 12 12 12

Public Areas

1st to 7th FloorGarbage Room

Block Works m2 50 8 6.25 2 3.125 3 2 2Plaster Works m2

Internal Plaster Accessories  50 35 1.428571 2 0.714286 1 2 2Internal Plaster Works  50 12 4.166667 2 2.083333 2 2 2

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  5 54 0.092593 1 0.092593 1 1 1Stucco Application Works  5 16 0.3125 1 0.3125 1 1 1

Screed for Dry Area m2 5 25 0.2 1 0.2 1 1 1Floor Tiles Work (Dry) m2 5 15 0.333333 1 0.333333 1 1 1Wall Tiles Work (Dry) m2 50 12 4.166667 1 4.166667 4 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 5 32 0.15625 1 0.15625 1 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Finishes

Public Areas

Block Works m2 310 8 38.75 10 3.875 3 10 10

1st to 7th FloorFinishes

Corridor & Lift Lobby

File:‐ Resources Plan Page 4 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Plaster Works m2Internal Plaster Accessories  310 35 8.857143 5 1.771429 1 5 5

Internal Plaster Works 310 12 25.83333 5 5.166667 5 5 5Internal Plaster Works  310 12 25.83333 5 5.166667 5 5 5Installation of Doors& Windows Sub‐frame No. 4 4.5 0.888889 1 0.888889 1 1 11st Coat Paint m2

 Primer Application Works  310 54 5.740741 5 1.148148 1 5 5Stucco Application Works  310 16 19.375 5 3.875 4 5 5

Instalaltion of Suspened Ceiling Grid (Dry) m2 120 7.2 16.66667 3 5.555556 6 3 3Screed for Dry Area m2 120 25 4.8 2 2.4 3 2 2Instalation of Windows&Doors No. 4 4.8 0.833333 1 0.833333 1 1 1Suspended Ceiling Tiles (Dry) 120 7.2 16.66667 3 5.555556 6 3 3Doors Ironmogery No. 4 4.8 0.833333 1 0.833333 1 1 1Final Coat Paint m2 310 32 9.6875 3 3.229167 3 3 3Installation of Carpets m2 120 20 6 2 3 4 1 2Wall Papers 310 20 15.5 3 5.166667 5 3Instllation of Sinages No. 1 5 0.2 1 0.2 1 1 1

Public Areas

1st to 7th FloorElect./Telephone/ELV

Block Works m2 102 8 12.75 4 3.1875 3 4 4Plaster Works m2

Internal Plaster Accessories  102 35 2.914286 3 0.971429 1 3 3Internal Plaster Works  102 12 8.5 3 2.833333 2 3 3

Installation of Doors& Windows Sub‐frame No. 3 4.5 0.666667 1 0.666667 1 1 11st Coat Paint m2

 Primer Application Works  102 54 1.888889 3 0.62963 1 3 3Stucco Application Works  102 16 6.375 3 2.125 2 3 3

Epoxy m3 16 40 0.4 1 0.4 1 1Instalation of Windows&Doors No. 3 4.8 0.625 1 0.625 1 1 1Doors Ironmogery No. 3 4.8 0.625 1 0.625 1 1 1Final Coat Paint m2 102 32 3.1875 3 1.0625 2 3 3Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Finishes

Room Services1 t t 7th Fl

Public Areas

Block Works m2 33 8 4.125 2 2.0625 2 2 2Plaster Works m2

Internal Plaster Accessories  33 35 0.942857 1 0.942857 1 1 1Internal Plaster Works  33 12 2.75 1 2.75 2 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  33 54 0.611111 1 0.611111 1 1 1Stucco Application Works  33 16 2.0625 1 2.0625 2 1 1

Screed for Dry Area m2 5 25 0.2 1 0.2 1 1 1Floor Tiles Work (Dry) m2 5 15 0.333333 1 0.333333 1 1 1Wall Tiles Work (Dry) m2 33 12 2.75 1 2.75 2 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 33 32 1.03125 1 1.03125 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Finishes1st to 7th Floor

Public AreasRetail 1Ground FloorFinishesFile:‐ Resources Plan Page 5 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Block Works m2 406 8 50.75 4 12.6875 13 4 4Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 445 8 55.625 4 13.90625 13 4 4Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Public AreasRetail 2Ground FloorFinishes

Public AreasEnterance & Lift LobbyGround FloorFinishes

Block Works m2 190 8 23.75 4 5.9375 5 4 4Plaster Works m2

Internal Plaster Accessories  190 35 5.428571 5 1.085714 1 5 5Internal Plaster Works  190 12 15.83333 5 3.166667 3 5 5

Installation of Doors& Windows Sub‐frame No. 3 4.5 0.666667 1 0.666667 1 1 11st Coat Paint m2

 Primer Application Works  190 54 3.518519 3 1.17284 2 3 3Stucco Application Works  190 16 11.875 3 3.958333 4 3 3

Instalaltion of Suspened Ceiling Grid (Dry) m2 100 7.2 13.88889 3 4.62963 5 3 3Screed for Dry Area m2 100 25 4 2 2 2 2 2Floor Tiles Work (Dry) m2 100 15 6.666667 2 3.333333 4 2 2Wall Tiles Work (Dry) m2 190 12 15.83333 3 5.277778 5 3 3Instalation of Windows&Doors No. 3 4.8 0.625 1 0.625 1 1 1Suspended Ceiling Tiles (Dry) 100 7.2 13.88889 3 4.62963 5 3 3Instllation of Mirrors No. 5 1 5 1 5 5 1 2Doors Ironmogery No. 3 4.8 0.625 1 0.625 1 1 1Final Coat Paint m2 190 32 5.9375 2 2.96875 3 2 2

Finishes

Final Coat Paint m2 190 32 5.9375 2 2.96875 3 2 2Instllation of Sinages No. 1 5 0.2 1 0.2 1 1Instllation of Furniture No. 1 0.5 2 1 2 2 1

Block Works m2 95 8 11.875 4 2.96875 3 4 4Plaster Works m2

Internal Plaster Accessories  95 35 2.714286 2 1.357143 1 2 2Internal Plaster Works  95 12 7.916667 2 3.958333 4 2 2

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2 0

 Primer Application Works  30 54 0.555556 1 0.555556 1 1 1Stucco Application Works  30 16 1.875 1 1.875 2 1 1

Screed for Dry Area m2 30 25 1.2 1 1.2 2 1 1Floor Tiles Work (Dry) m2 30 15 2 1 2 2 1 1

Public AreasGarbage RoomGround FloorFinishes

Floor Tiles Work (Dry) m2 30 15 2 1 2 2 1 1Wall Tiles Work (Dry) m2 95 12 7.916667 1 7.916667 8 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 30 32 0.9375 1 0.9375 1 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

File:‐ Resources Plan Page 6 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Public AreasOffice

Block Works m2 25 8 3.125 4 0.78125 2 4 4Plaster Works m2

Internal Plaster Accessories  25 35 0.714286 1 0.714286 1 1 1Internal Plaster Works  25 12 2.083333 1 2.083333 2 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2 0

 Primer Application Works  25 54 0.462963 1 0.462963 1 1 1Stucco Application Works  25 16 1.5625 1 1.5625 2 1 1

Instalaltion of Suspened Ceiling Grid (Dry) m2 10 7.2 1.388889 1 1.388889 2 1 1Screed for Dry Area m2 10 25 0.4 1 0.4 2 1 1Floor Tiles Work (Dry) m2 10 15 0.666667 1 0.666667 2 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Suspended Ceiling Tiles (Dry) 10 7.2 1.388889 1 1.388889 2 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 25 32 0.78125 1 0.78125 2 1 1

Ground FloorFinishes

Instllation of Sinages No. 1 5 0.2 1 0.2 1 1Instllation of Furniture No. 1 0.5 2 1 2 1 1

Block Works m2 50 8 6.25 4 1.5625 2 4 4Plaster Works m2

Internal Plaster Accessories  50 35 1.428571 1 1.428571 1 1 1Internal Plaster Works  50 12 4.166667 1 4.166667 4 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 2 1 11st Coat Paint m2

 Primer Application Works  50 54 0.925926 1 1 1 1 1Stucco Application Works  50 16 3.125 1 3 3 1 1

Epoxy m3 8 40 0.2 1 0.2 2 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 2 1 1

Public AreasLuggae StorageGround FloorFinishes

Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 2 1 1Final Coat Paint m2 50 32 1.5625 1 1.5625 3 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 2 1

Block Works m2 175 8 21.875 4 5.46875 5 4 4Plaster Works m2 0

Internal Plaster Accessories  175 35 5 3 1.666667 2 3 3Internal Plaster Works  175 12 14.58333 3 4.861111 5 3 3

Installation of Doors& Windows Sub‐frame No. 10 4.5 2.222222 1 2.222222 2 1 1Water Proofing for Wet Area m2 35 10 3.5 2 1.75 2 2 2Instalaltion of Suspened Ceiling Grid (Wet) m2 35 7.2 4.861111 1 4.861111 4 1 1Screed for Wet Area m2 35 25 1.4 1 1.4 2 1 1Floor Tiles Work (Wet) m2 35 10 3.5 1 3.5 4 1 1

Public AreasToiletsGround FloorFinishes

( )Wall Tiles Work (Wet) m2 175 8 21.875 4 5.46875 5 4 4Instalaltion of Vanity Counter No. 2 1 2 1 2 2 1 1Instalation of Windows&Doors No. 10 4.8 2.083333 1 2.083333 2 1 1Instalaltion of Toliets Accessories No. 2 0.5 4 2 2 2 2 2Suspended Ceiling Tiles (Wet) m2 35 7.2 4.861111 1 4.861111 5 1 1

File:‐ Resources Plan Page 7 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Instllation of Mirrors No. 2 1 2 1 2 2 1Doors Ironmogery No. 10 4.8 2.083333 1 2.083333 2 1 1Final Coat Paint m2 35 32 1.09375 1 1.09375 1 1 1Final Coat Paint m2 35 32 1.09375 1 1.09375 1 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 95 8 11.875 4 2.96875 3 4 4Plaster Works m2

Internal Plaster Accessories  95 35 2.714286 2 1.357143 1 2 2Internal Plaster Works  95 12 7.916667 2 3.958333 4 2 2

Installation of Doors& Windows Sub‐frame No. 2 4.5 0.444444 1 0.444444 1 1 11st Coat Paint m2

 Primer Application Works  95 54 1.759259 2 0.87963 1 2 2Stucco Application Works  95 16 5.9375 2 2.96875 3 2 2

Epoxy m3 16 40 0.4 1 0.4 2 1 1Instalation of Windows&Doors No. 2 4.8 0.416667 1 0.416667 1 1 1Doors Ironmogery No. 2 4.8 0.416667 1 0.416667 1 1 1

Elect./TelephoneGround FloorFinishes

Public Areas

Doors Ironmogery No. 2 4.8 0.416667 1 0.416667 1 1 1Final Coat Paint m2 95 32 2.96875 1 2.96875 3 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 150 8 18.75 3 6.25 6 3 3Plaster Works m2

Internal Plaster Accessories  150 35 4.285714 3 1.428571 1 3 3Internal Plaster Works  150 12 12.5 3 4.166667 4 3 3

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  253 54 4.685185 3 1.561728 3 3 3Stucco Application Works  253 16 15.8125 3 5.270833 6 3 3

Epoxy m3 105 40 2.625 1 2.625 3 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 2 1 1

Sub Station 11st Basement FloorFinishes

Public Areas

Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 2 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 2 1 1Final Coat Paint m2 253 32 7.90625 3 2.635417 4 3 3Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 90 8 11.25 3 3.75 4 3 3Plaster Works m2

Internal Plaster Accessories  90 35 2.571429 2 1.285714 2 2 2Internal Plaster Works  90 12 7.5 2 3.75 4 2 2

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  136 54 2.518519 2 1.259259 1 2 2Stucco Application Works  136 16 8.5 2 4.25 4 2 2

Epoxy m3 50 40 1.25 1 1.25 2 1

Public AreasLV Room1st Basement FloorFinishes

Epoxy m3 50 40 1.25 1 1.25 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 136 32 4.25 2 2.125 3 2 2Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Public AreasFile:‐ Resources Plan Page 8 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Mechanical Room1st Basement Floor

Block Works m2 45 8 5.625 3 1.875 2 3 3Plaster Works m2

Internal Plaster Accessories  45 35 1.285714 1 1.285714 1 1 1Internal Plaster Works  45 12 3.75 1 3.75 4 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  65 54 1.203704 1 1.203704 2 1 1Stucco Application Works  65 16 4.0625 1 4.0625 4 1 1

Epoxy m3 20 40 0.5 1 0.5 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 65 32 2.03125 1 2.03125 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Finishes

Public AreasHouse Keeping Room1 t B t Fl

Block Works m2 81 8 10.125 2 5.0625 5 2 2Plaster Works m2

Internal Plaster Accessories  81 35 2.314286 1 2.314286 2 1 1Internal Plaster Works  81 12 6.75 1 6.75 7 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  111 54 2.055556 1 2.055556 2 1 1Stucco Application Works  111 16 6.9375 1 6.9375 7 1 1

Epoxy m3 30 40 0.75 1 0.75 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 111 32 3.46875 1 3.46875 4 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

1st Basement FloorFinishes

Public AreasELV Room

Block Works m2 64 8 8 3 2.666667 4 3 3Plaster Works m2

Internal Plaster Accessories  64 35 1.828571 1 1.828571 2 1 1Internal Plaster Works  64 12 5.333333 1 5.333333 5 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  80 54 1.481481 1 1.481481 2 1 1Stucco Application Works  80 16 5 1 5 5 1 1

Epoxy m3 16 40 0.4 1 0.4 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 80 32 2.5 1 2.5 3 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

ELV Room1st Basement FloorFinishes

Public Areas

Block Works m2 68 8 8.5 3 2.833333 3 3 3

Geneset Room1st Basement FloorFinishes

File:‐ Resources Plan Page 9 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Plaster Works m2Internal Plaster Accessories  68 35 1.942857 1 1.942857 2 1 1

Internal Plaster Works 68 12 5.666667 1 5.666667 6 1 1Internal Plaster Works  68 12 5.666667 1 5.666667 6 1 1Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  115 54 2.12963 1 2.12963 2 1 1Stucco Application Works  115 16 7.1875 1 7.1875 7 1 1

Epoxy m3 45 40 1.125 1 1.125 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 115 32 3.59375 1 3.59375 4 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 52 8 6.5 3 2.166667 3 3 3Plaster Works m2

Internal Plaster Accessories 52 35 1.485714 1 1.485714 2 1 1

Public AreasCBS Room1st Basement FloorFinishes

Internal Plaster Accessories  52 35 1.485714 1 1.485714 2 1 1Internal Plaster Works  52 12 4.333333 1 4.333333 4 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  65 54 1.203704 1 1.203704 2 1 1Stucco Application Works  65 16 4.0625 1 4.0625 4 1 1

Epoxy m3 15 40 0.375 1 0.375 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 65 32 2.03125 1 2.03125 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 35 8 4.375 3 1.458333 2 3 3Plaster Works m2

Public AreasBMS Room1st Basement FloorFinishes

Plaster Works m2Internal Plaster Accessories  35 35 1 1 1 2 1 1

Internal Plaster Works  35 12 2.916667 1 2.916667 3 1 1Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  35 54 0.648148 1 0.648148 2 1 1Stucco Application Works  35 16 2.1875 1 2.1875 2 1 1

Instalaltion of Suspened Ceiling Grid (Dry) m2 7 7.2 0.972222 1 0.972222 2 1 1Screed for Dry Area m2 9 25 0.36 1 0.36 2 1 1Floor Tiles Work (Dry) m2 9 15 0.6 1 0.6 2 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Suspended Ceiling Tiles (Dry) 7 7.2 0.972222 1 0.972222 2 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 3 1 1Final Coat Paint m2 35 32 1.09375 1 1.09375 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Public AreasLift Lobby1 t B t Fl

Block Works m2 35 8 4.375 2 2.1875 2 2 2Plaster Works m2

Internal Plaster Accessories  35 35 1 1 1 2 2 2

1st Basement FloorFinishes

File:‐ Resources Plan Page 10 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

Internal Plaster Works  35 12 2.916667 1 2.916667 3 2 2Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m21st Coat Paint m2

 Primer Application Works  35 54 0.648148 1 0.648148 2 2 2Stucco Application Works  35 16 2.1875 1 2.1875 2 2 2

Instalaltion of Suspened Ceiling Grid (Dry) m2 7 7.2 0.972222 1 0.972222 1Screed for Dry Area m2 9 25 0.36 1 0.36 1 1 1Floor Tiles Work (Dry) m2 9 15 0.6 1 0.6 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Suspended Ceiling Tiles (Dry) 7 7.2 0.972222 1 0.972222 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 35 32 1.09375 1 1.09375 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 32 8 4 2 2 2 2 2Plaster Works m2

Public AreasMechanical Room2nd Basement FloorFinishes

Plaster Works m2Internal Plaster Accessories  32 35 0.914286 1 0.914286 2 1 1

Internal Plaster Works  32 12 2.666667 1 2.666667 3 1 1Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  60 54 1.111111 1 1.111111 2 1 1Stucco Application Works  60 16 3.75 1 3.75 4 1 1

Epoxy m3 28 40 0.7 1 0.7 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 60 32 1.875 1 1.875 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 75 8 9.375 2 4.6875 5 2 2

Public AreasGSM Room2nd Basement FloorFinishes

Block Works m2 75 8 9.375 2 4.6875 5 2 2Plaster Works m2

Internal Plaster Accessories  75 35 2.142857 1 2.142857 2 1 1Internal Plaster Works  75 12 6.25 1 6.25 6 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  95 54 1.759259 1 1.759259 2 1 1Stucco Application Works  95 16 5.9375 1 5.9375 5 1 1

Epoxy m3 20 40 0.5 1 0.5 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 95 32 2.96875 1 2.96875 3 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Public AreasLift Lobby2nd Basement FloorFinishes

Block Works m2 60 8 7.5 2 3.75 4 2 2Plaster Works m2

Internal Plaster Accessories  60 35 1.714286 1 1.714286 2 1 1Internal Plaster Works  60 12 5 1 5 5 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 1File:‐ Resources Plan Page 11 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

1st Coat Paint m2 Primer Application Works  60 54 1.111111 1 1.111111 2 1 1Stucco Application Works 60 16 3.75 1 3.75 4 1 1Stucco Application Works  60 16 3.75 1 3.75 4 1 1

Instalaltion of Suspened Ceiling Grid (Dry) m2 36 7.2 5 1 5 5 1 1Screed for Dry Area m2 36 25 1.44 1 1.44 2 1 1Floor Tiles Work (Dry) m2 36 15 2.4 1 2.4 3 1 1Wall Tiles Work (Dry) m2 60 12 5 1 5 5 1 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Suspended Ceiling Tiles (Dry) 36 7.2 5 1 5 5 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 60 32 1.875 1 1.875 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 170 8 21.25 5 4.25 4 5 5Plaster Works m2

Internal Plaster Accessories 170 35 4.857143 3 1.619048 1 3 3

Public AreasPool RoomRoofFinishes

Internal Plaster Accessories  170 35 4.857143 3 1.619048 1 3 3Internal Plaster Works  170 12 14.16667 3 4.722222 5 3 3

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  365 54 6.759259 3 2.253086 3 3 3Stucco Application Works  365 16 22.8125 3 7.604167 8 3 3

Epoxy m3 195 40 4.875 1 4.875 5 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 365 32 11.40625 3 3.802083 4 3 3Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 145 8 18.125 5 3.625 4 5 5Plaster Works m2

Pump RoomRoof

Public Areas

Finishes

Plaster Works m2Internal Plaster Accessories  145 35 4.142857 3 1.380952 1 3 3

Internal Plaster Works  145 12 12.08333 3 4.027778 4 3 3Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  200 54 3.703704 3 1.234568 2 3 3Stucco Application Works  200 16 12.5 3 4.166667 4 3 3

Epoxy m3 56 40 1.4 1 1.4 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 200 32 6.25 3 2.083333 3 3 3Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 245 8 30.625 5 6.125 6 5 5

Electrical Room - GSM -Telephone RoomsRoofFinishes

Public Areas

Block Works m2 245 8 30.625 5 6.125 6 5 5Plaster Works m2

Internal Plaster Accessories  245 35 7 4 1.75 2 4 4Internal Plaster Works  245 12 20.41667 4 5.104167 5 4 4

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

File:‐ Resources Plan Page 12 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

 Primer Application Works  300 54 5.555556 3 1.851852 2 3 3Stucco Application Works  300 16 18.75 3 6.25 6 3 3

Epoxy m3 60 40 1.5 1 1.5 2 1Epoxy m3 60 40 1.5 1 1.5 2 1Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 300 32 9.375 3 3.125 4 3 3Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 99 8 12.375 5 2.475 3 5 5Plaster Works m2

Internal Plaster Accessories  99 35 2.828571 2 1.414286 1 2 2Internal Plaster Works  99 12 8.25 2 4.125 4 2 2

Installation of Doors& Windows Sub‐frame No. 3 4.5 0.666667 1 0.666667 1 1 11st Coat Paint m2

 Primer Application Works  99 54 1.833333 1 1.833333 2 1 1Stucco Application Works 99 16 6.1875 1 6.1875 6 1 1

Public AreasGymnasiumRoofFinishes

Stucco Application Works  99 16 6.1875 1 6.1875 6 1 1Instalaltion of Suspened Ceiling Grid (Dry) m2 70 7.2 9.722222 1 9.722222 10 1 1Screed for Dry Area m2 70 25 2.8 2 1.4 2 2 2Floor Tiles Work (Dry) m2 70 15 4.666667 1 4.666667 5 1 1Wall Tiles Work (Dry) m2 99 12 8.25 2 4.125 4 2 2Instalation of Windows&Doors No. 3 4.8 0.625 1 0.625 1 1 1Suspended Ceiling Tiles (Dry) 70 7.2 9.722222 2 4.861111 5 2 2Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 99 32 3.09375 1 3.09375 3 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 143 8 17.875 5 3.575 4 5 5Plaster Works m2

Internal Plaster Accessories 143 35 4.085714 2 2.042857 2 2 2

TolietsRoof

Public Areas

Finishes

Internal Plaster Accessories  143 35 4.085714 2 2.042857 2 2 2Internal Plaster Works  143 12 11.91667 2 5.958333 6 2 2

Installation of Doors& Windows Sub‐frame No. 3 4.5 0.666667 1 0.666667 1 1 1Water Proofing for Wet Area m2 35 10 3.5 1 3.5 4 1 1Instalaltion of Suspened Ceiling Grid (Wet) m2 35 7.2 4.861111 1 4.861111 5 1 1Screed for Wet Area m2 35 25 1.4 1 1.4 2 1 1Floor Tiles Work (Wet) m2 35 10 3.5 1 3.5 4 1 1Wall Tiles Work (Wet) m2 143 8 17.875 2 8.9375 9 1 1Instalation of Windows&Doors No. 3 4.8 0.625 1 0.625 1 1 1Suspended Ceiling Tiles (Wet) m2 34 7.2 4.722222 1 4.722222 5 1 1Instllation of Mirrors No. 2 1 2 1 2 2 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Lift LobbyRoofFinishes

Public Areas

Block Works m2 20 8 2.5 1 2.5 3 1 1Plaster Works m2

Internal Plaster Accessories  20 35 0.571429 1 0.571429 1 1 1Internal Plaster Works  20 12 1.666667 1 1.666667 2 1 1

Installation of Doors& Windows Sub‐frame No. 3 4.5 0.666667 1 0.666667 1 1 1File:‐ Resources Plan Page 13 of 14 Printed On :‐07/07/2012 at 11:21

Activity ID Activity Describtion Unit Total QTY (A)

Prod. Rate (Unit/Day)

(B)

Days C = (A/B)

Crew QTY(D)

Theritocal DurationE = (C/D)

Original Duration Carpenter Mason Helper

(Labor)Mirror Skilled

Labor Plumber Metal Worker Technician Painter Alum.

Tech WaterprooferSuspended

Ceiling Skilled Labor

Steel Structure

Skilled Labor

hardware skilled

people/window

Carpet Labors

Wall Paper Skilled Labor FF&E

TIME LIMIT Manpower

Al Muraqqabat Mixed Use DevelopmentResource Plan CalculationsBuilding A - Hotel Apartments

1st Coat Paint m2 Primer Application Works  20 54 0.37037 1 0.37037 1 1 1Stucco Application Works 20 16 1.25 1 1.25 2 1 1Stucco Application Works  20 16 1.25 1 1.25 2 1 1

Instalaltion of Suspened Ceiling Grid (Dry) m2 12 7.2 1.666667 1 1.666667 2 1 1Screed for Dry Area m2 12 25 0.48 1 0.48 2 1 1Floor Tiles Work (Dry) m2 12 15 0.8 1 0.8 2 1 1Wall Tiles Work (Dry) m2 20 12 1.666667 1 1.666667 1 1 1Instalation of Windows&Doors No. 3 4.8 0.625 1 0.625 1 1 1Suspended Ceiling Tiles (Dry) 12 7.2 1.666667 1 1.666667 2 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 20 32 0.625 1 0.625 2 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

Block Works m2 15 8 1.875 1 1.875 2 1 1Plaster Works m2

Internal Plaster Accessories 15 35 0.428571 1 0.428571 1 1 1

Finishes

Public AreasChillersRoof

Internal Plaster Accessories  15 35 0.428571 1 0.428571 1 1 1Internal Plaster Works  15 12 1.25 1 1.25 1 1 1

Installation of Doors& Windows Sub‐frame No. 1 4.5 0.222222 1 0.222222 1 1 11st Coat Paint m2

 Primer Application Works  15 54 0.277778 1 0.277778 1 1 1Stucco Application Works  15 16 0.9375 1 0.9375 1 1 1

Screed for Dry Area m2 660 25 26.4 3 8.8 9 3 3Floor Tiles Work (Dry) m2 660 15 44 4 11 11 4 4Instalation of Windows&Doors No. 1 4.8 0.208333 1 0.208333 1 1 1Doors Ironmogery No. 1 4.8 0.208333 1 0.208333 1 1 1Final Coat Paint m2 15 32 0.46875 1 0.46875 3 1 1Instllation of Sinages No. 1 5 0.2 1 0.2 1 1

File:‐ Resources Plan Page 14 of 14 Printed On :‐07/07/2012 at 11:21