Request for Proposal for Professional Services For …...1Page SECTION I – GENERAL The City of...
Transcript of Request for Proposal for Professional Services For …...1Page SECTION I – GENERAL The City of...
For San Vicente Emergency Generator Project (SP2212)
Due Date: June 4, 2012 5:00 p.m. PST
Submit Electronically to: [email protected]
Approved for Advertising:
________________________Lee Swain, P.E.
City Engineer
Request for Proposal for Professional Services May 16, 2012
TABLE OF CONTENTS
SECTION I – GENERAL ............................................................................................. 1�
SECTION II - PROJECT BACKGROUND .................................................................. 1�
SECTION III - OBJECTIVES ....................................................................................... 1�
SECTION IV - SCOPE OF SERVICES........................................................................ 2�
SECTION VI - PROPOSAL REQUIREMENTS ........................................................... 3�
SECTION VII - DESIGN CONSULTANT SELECTION GUIDELINES......................... 4�
SECTION VIII - SOLE AUTHORITY ........................................................................... 4�
SECTION IX – DUE DATE .......................................................................................... 5�
SECTION X – RFP QUESTIONS ................................................................................ 5�
SECTION XI – EXHIBITS ....................................................................................... 5-23�
�
Page 1
SECTION I – GENERAL
The City of Santa Monica is soliciting proposals from qualified consulting firms to provide professional services for the San Vicente Emergency Generator Project. The project is located along 25th Street adjacent to San Vicente Boulevard within the City of Santa Monica, as shown in Exhibits 1 and 2.
SECTION II - PROJECT BACKGROUND
The 5 Million Gallon Reservoir under the median at San Vicente Boulevard is serviced by the San Vicente Booster Pump Station located under 25th Street. The current backup generator has outlived its useful life and a new generator is required to ensure adequate back up electricity in the event of an emergency. However the vault that contains the existing backup generator is not likely to be large enough to house the new one. Consideration in sizing the generator and installation in the street is anticipated to be necessary.
SECTION III - OBJECTIVES
The San Vicente Emergency Generator Project (Project) consists of site survey, utility coordination, developing phased design plans, specifications, cost estimates, procuring AQMD and other permits as necessary, and providing construction administration for the construction of a vault and installation of a new emergency generator at the San Vicente Booster Pump Station.
The Project’s objective is to provide sufficient and reliable emergency power to the vault, drain pump, 6 existing booster pumps, and other appurtenant fixtures as necessary to effectively supply water to the community in the event of an emergency.
The improvements must comply with all current City codes and standards, including but not limited to the Americans with Disabilities Act and Guidelines (ADA&G), AQMD guidelines, Santa Monica City Municipal Code.
It is anticipated that the design team may include a combination of expertise in the following fields: civil and/or transportation engineering, electrical engineering, mechanical engineering, and community outreach.
Page 2
SECTION IV - SCOPE OF SERVICES
1. General
A. Evaluate all existing documentation and operational requirements-.
B. Establish a single point of contact and commit that person for the duration of the project to provide information relative to the project issues as requested by the City.
C. Prepare project status reports for each milestone and identify critical issues early on to discuss and resolve them with the City.
D. Produce high quality reports, permit applications, application exhibits, artist renderings, construction drawings, and professional oral presentations as required for approvals.
2. Administrative
A. A sample Professional Services Agreement has been included (See Exhibit 6) Please submit any concerns regarding the contract language with your proposal.
B. The scope of design services is comprehensive and includes the preparation of schematic design, design development, construction documents, pre-construction/bidding service, and providing design services throughout construction duration.
C. The Consultant will be required to identify in this proposal their process for evaluating the operational requirements of the system, necessary utility coordination, project vision, and proposed project delivery method.
D. Provide project management services throughout the course of the project, including discipline coordination/document checking, coordination with owner’s representatives/stakeholders, data coordination, value engineering analysis, site analysis, materials research/specifications, constructability reviews and operations manual.
E. Ensure that bid documents comply with all owner and regulatory agency general conditions, general requirements, and construction regulations.
F. Prepare all applications, coordination and securing of permits, and approvals from all necessary advisory and permitting/regulatory agencies.
Page 3
G. Provide appropriate on-site surveillance during construction to maintain awareness of the project development and to assure conformance with the contract documents; provide review and approval of all submittals required by the construction contract; provide supplemental documents for clarification or resolution of conflicts encountered during construction.
H. Develop punch lists and recommendations to the City for substantial completion date and acceptance of all corrective and completion work by the contractor; ensure that all specified submittals are responsive to the intent.
I. Attend regularly scheduled meetings to discuss the Project.
4. Meetings and Presentations
The number and frequency of meetings and presentations shall be outlined in your proposal, but ultimately will be negotiated with the successful proposer.
5. Public Outreach
The number and frequency of public meetings, exhibits, and presentations shall be outlined in your proposal, but ultimately will be negotiated with the successful proposer.
SECTION VI - PROPOSAL REQUIREMENTS
For consideration, please electronically submit a proposal containing the following elements:
A. Scope of work for the project
B. Proposed timetable for the activities, including completion dates, review periods and submission of work to City staff. The timetable should be outlined by number of weeks to complete each task.
C. Previous projects of this type (include color copies of built examples of exemplary projects). Previous project history which must include the design team members’ specific role in the project, the date of the project, photos of all referenced projects, and a client reference list with contact names and telephone numbers.
D. Short bios of professional personnel that will be working on this project. The manager or professional who will be responsible for planning, coordinating
Page 4
and conducting the majority of the work must be identified and committed to managing the project. The City must approve changes in key personnel subsequent to the award of the contract.
D. A list of sub-consultants, if any, proposed to assist the prime consultant. This list shall also include the sub-consultants’ qualifications pertinent to this project.
G. Client reference list which indicates clients on projects similar to this project. Provide name of client contact, position and contact number.
H. A project organizational chart that identifies the consulting team and Project Manager.
I. A proposal cost and a billing rate schedule.
SECTION VII - DESIGN CONSULTANT SELECTION GUIDELINES
Factors to be considered in reviewing proposals may include but are not limited to:
� General design accomplishments and quality of work previously performed. � Previous history of work with similar projects. � Experience in the design of exemplary projects, including those that involve a
community outreach and input process. � Knowledge and familiarity with the AQMD regulations and permit procedures. � Experience with design in active residential areas. � Ability to lead a multi-disciplinary project team. � Ability to phase the project to minimize the impact on the community. � Record of the consultant in accomplishing work within required time and
budget constraints. � Understanding of the approach, tasks, and methodology necessary to
complete the required services. � Geographical location of the design team. � References.
SECTION VIII - SOLE AUTHORITY
The City of Santa Monica has the sole authority to select the consultant or team, and reserves the right to reject any and all proposals. By submitting a response to this RFP, prospective consultants waive the right to protest or seek legal remedies whatsoever regarding any aspect of this RFP. In addition, the City reserves the right to issue written notice to all participants of any changes in the proposal submission schedule or submission requirements, should the City determine in sole and absolute discretion that such changes are necessary. The City also reserves the right to approve all individuals and firms, if any, to be retained by the prime consultant. The City’s policy is to screen consultants based upon their proposal and project reference checks.
Page 5
SECTION IX – DUE DATE
An electronic proposal, no longer than 20 pages in length (including any resumes/references/etc.) must be submitted by 5:00 p.m. PST, June 4, 2012 to [email protected]. The electronic proposal cannot exceed 9 megabytes.
All Submittals must be clearly marked as “Proposal for Professional Services for San Vicente Emergency Generator Project.”
SECTION X – RFP QUESTIONS
Questions regarding this Request for Proposals must be submitted no later than 5:00 p.m. PST on May 23, 2012 by e-mail. Questions should be submitted to:
Miss Jessica Arden, Project Manager City of Santa Monica 1437 4th Street, Suite 300 Santa Monica, CA 90405
e-mail: [email protected]
Monday through Thursday, 7:30 am - 5:30 pm; alternate Fridays, 8:00 am - 5:00 pm.
SECTION XI – EXHIBITS
� Exhibit 1 – San Vicente Booster Pump Station Project Location � Exhibit 2 – Project Location Street View � Exhibit 3 – Schematic Booster Station Layout � Exhibit 4 – Pump Station construction plans � Exhibit 5 – Schematic Piping Layout � Exhibit 6 – Booster Info
SECTION XII – ATTACHMENTS � Attachment “A” – Professional Services Agreement � Attachment “B” – Insurance Requirements � Attachment “C” – Living Wage Certification Form � Attachment “D” – Oaks Initiative Form � Attachment “E” – Arizona Disclosure
Page 6
Exhibit 1
�
�
����������� ������� �� �� ����
������������
Page 8
Exhibit 2
��������������������
San�Vicente�Booster�Pump�Station�Street�View�
25th�at�San�Vicente�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
�
San�Vicente�Booster�Pump�Station�Street�View�
25th�at�San�Vicente�
Page 11
Exhibit 3
San Vicente Booster Station
Matrix B2 B3 B4 B5 B6 500' Zone Step 1 off off off off off PRV 7 setpoint 60 psiStep 2 on off off off off PRV 6 setpoint 61 psiStep 3 on on off off off Deadband 5Step 4 on on on off off VFD Setpoint 60Step 5 on on on on off Auto Timer offStep 6 off on on on on Booster 2Step 7 off on on on on Time Start 0600
Time Off 1030
PT 4
500' Zone 62 psi
350' Zone
Diesel
To / From 500' Zone
PRV 7
15% open
PRV 6
0 % open
San Vicente Level 10 '
9.0'
19.0'
LI 10
Boosterstop4.0'
3 4 56
2
DieselOn Off
San Vicente Booster Control
2On Off
Call Run Fail
3On OffCall Run FailVFD Hz
4On Off
Call Run FailVFD Hz
5On Off
Call Run Fail
VFD 55 Hz
6On Off
Call Run Fail
VFD Hz
���\SanVicente.xl
Page 13
Exhibit 4
9' 8"
���\san vicente boosters.xl
Page 15
Exhibit 5
Sheet1
San Vicente Piping Layout
500' zone
10"CIP 12"CIP
8"CIP
San Vicente Reservoir 6"CIP
12"CSC 27"CSC
18"CSC 6"CIP
18" RCP
8"CSC
6"CIP - 500' zone
reducer 12" to 6"
12"CIP
overflows to street
500' zone supplies 25th St.
350' zone to/from SV
hydrant
diesel
San Vicente Booster PumpsDrain pump
sto
rm d
rain
Location of overlow to street is:
Geo
rgin
a
Manhole
storm drain
Reservoir overflow and drain from diesel to storm drain.
12"
���\SanVicente.xl
Page 1
Page 17
Exhibit 6
Location: San Vicente Booster 1
Motor Pump ron\wells.xls\SVBooster\1
Manufacturer: GE Manufacturer Layne & Bowler
HP 15 Purchased from / date
Phase 3 Depth to bowls
Frame 6 Number of stages
Volts 460 Model Number 15SV6F3
Amps 20.5 GPM 300
Type K Total design head feet 150
Design Sub
Code Seal
RPM 3450
C Rating
Upper Bearing
Lower Bearing
Oil Capacity
NRR
Nema/Noa eff.
Max.
Serial Number NSJ116405
Model 5K6XS12A
L&B 15SV6R3
Comments:
page 135
���\san vicente boosters.xl
San Vicente Booster 2
operator: John
Motor PumpManufacturer: GE Manufacturer Layne & Bowler
HP 40 Purchased from / date
Phase 3 Depth to bowls
Frame 12 Number of stages
Volts 440 Model Number 30SV10EH5
Amps 43 GPM 500
Type K Total design head feet 155
Design Sub
Code Seal
RPM 1750
C Rating
Upper Bearing
Lower Bearing
Oil Capacity
NRR
Nema/Noa eff.
Max.
Serial Number OSJ116408
Model 5K12X537A
Comments:
page 136
���\san vicente boosters.xl
San Vicente Booster 3
operator: John
Motor PumpManufacturer: GE Manufacturer Layne & Bowler
HP 40 Purchased from / date
Phase 3 Depth to bowls
Frame 12 Number of stages
Volts 440 Model Number 50SV12EH3
Amps 69 GPM 1100
Type K Total design head feet 155
Design Sub Serial 25809
Code Seal
RPM 1750
C Rating
Upper Bearing
Lower Bearing
Oil Capacity
NRR
Nema/Noa eff.
Max.
Serial Number OSJ116407
Model 5K12X536A
Comments:
page 137
���\san vicente boosters.xl
Location: San Vicente Booster 4
Motor PumpManufacturer: US Electric Manufacturer Johnston
HP 150 Purchased from / date General Pump
Phase 3 Depth to bowls 123"
Frame 1445PH Number of stages 2
Volts 440 Model Number 14DC
Amps 180 GPM 2500
Type Hollowshaft Total design head feet 150
Design B
Code F Seal
RPM 1800
C Rating
Upper Bearing 29322KC
Lower Bearing 6213J
Oil Capacity 3.5 qts
NRR
Nema/Noa eff.
Max.
Serial Number 1411767
Model Casing dia. 23"
Comments: June 1998 - Pump indicating low amps when pumping. Closed discharge - start pump - no
pressure increase. General pulled pump. Didn't find any problems. Replaced pump - tested OK - pressure with discharge
closed was 100 psi - amps 137 -
page 138
���\san vicente boosters.xl
San Vicente Booster 5
Motor PumpManufacturer: US Electrical Manufacturer Johnston
HP 150 Purchased from / date
Phase 3 Depth to bowls 206"
Frame 1445P CD = 37" Number of stages 2
Volts 440 Model Number 14DC
Amps 180 GPM 2500
Type Hollowshaft Total design head feet 150
Design B Column 12"
Code F Seal 8909 Garlock Packing
RPM 1770
C Rating
Upper Bearing 29322 MC
Lower Bearing 6213J
Oil Capacity 3.5 qts
NRR
Nema/Noa eff.
Max.
Serial Number HC1024962
Model High Thrust Casing dia. 22"
Comments: General installed on Sept. 20, 2004
Scotch Kote 134 Fusion bonded epoxy - OD Bowls - ID & OD suction bell and discharge case
ID & OD column pipe and discharge head - OD stuffing box
page 139
General Pump installed 9/20/04
���\san vicente boosters.xl
Location: San Vicente Booster 6
Motor PumpManufacturer: GE Manufacturer Layne & Bowler
HP 150 Purchased from / date
Phase 3 Depth to bowls
Frame 6323P Number of stages
Volts 440 Model Number 14RH
Amps 178 GPM 2700
Type Total design head feet 155
Design
Code F Seal
RPM 1770
C Rating
Upper Bearing CAT-629A226G2
Lower Bearing CAT-28892334P21
Oil Capacity
NRR
Nema/Noa eff.
Max.
Serial Number SRJ512002
Model 5K6323XC55A
Comments:
page 140
���\san vicente boosters.xl