REQUEST FOR INTEREST IN PUBLIC-ORIENTED SPACES RFI...2018/12/11  · REBECCA BENASSINI (415)...

18
PORT OF SAN FRANCISCO REQUEST FOR INTEREST IN PUBLIC-ORIENTED SPACES Elaine Forbes, Executive Director Diane Oshima, Michael Martin, and Rebecca Benassini

Transcript of REQUEST FOR INTEREST IN PUBLIC-ORIENTED SPACES RFI...2018/12/11  · REBECCA BENASSINI (415)...

  • PORT OF SAN FRANCISCO REQUEST FOR INTEREST IN PUBLIC-ORIENTED SPACES

    Elaine Forbes, Executive Director Diane Oshima, Michael Martin, and Rebecca Benassini

  • EMBARCADERO HISTORIC DISTRICT

    • 3 miles, from Pier 45 to Pier 48

    • Accommodates public-oriented

    spaces

    • Costly repairs & seismic

    improvements

    • Opportunity to create economic,

    cultural and public resources

    Request for Interest Locations: • Pier 35 (maintaining secondary

    cruise ship berth operations)

    • Pier 33 (pier shed only)

    • Pier 31 (pier shed only)

    • Pier 29½

    • Pier 29

    • Pier 23

    • Pier 19½

    • Pier 19

    • Agricultural Building

    • Pier 26

    • Pier 28

    • Pier 38

    • Pier 40 (maintaining water

    recreation uses)

    • Pier 48 2

  • OPEN MORE PIERS TO THE PUBLIC

    Goal: To Improve Embarcadero Historic

    District Consistent with Public Trust

    Objectives

    • Issue RFI 2018 to public-oriented operators:

    • Operators who can finance full pier

    • Operators seeking smaller tenancies

    • Port will use RFI’s market-based information

    related to newly defined set of uses to craft

    subsequent RFP(s)

    Financially

    Feasible Pier

    Rehabilitation

    • Historic rehabilitation

    costs

    • Seismic repair costs

    • Market demand for

    uses

    • Revenue potential

    Public Trust

    Objectives

    • Historic

    preservation

    • Seismic/life safety

    • Maritime operations

    • Public access

    • Harbor Fund

    • Public-oriented

    uses

    3

  • WATERFRONT LAND USE PLAN UPDATE &

    PUBLIC TRUST OBJECTIVES

    4

  • EMBARCADERO HISTORIC DISTRICT

    5

  • WATERFRONT LAND USE PLAN UPDATE

    Waterfront Plan Working Group recommendations,

    endorsed by Port Commission, include:

    Embarcadero Historic District rehabilitation, to open more

    piers for a wider variety of public-oriented activities

    Public trust objectives and financial strategies to support

    economically feasible pier leases and projects

    6

  • PUBLIC TRUST OBJECTIVES

    • Visitor, public-oriented and maritime uses

    inside the pier

    • Historic preservation

    • Pier repairs & seismic upgrade

    • Public access & maritime berthing outside the

    pier

    • Revenue uses and lease terms to support

    financial feasibility & amortize pier investment

    • Harbor Fund revenues to Port to finance other

    waterfront capital improvements

    7

  • PARTNERSHIPS ARE KEY TO ACTIVATE AND

    ENHANCE PUBLIC WATERFRONT USE

    8

    • Waterfront Plan Update is resetting the

    framework and criteria for a successful

    publicly-owned waterfront

    • Partnerships are needed to achieve

    Embarcadero Historic District public

    trust objectives

  • WHY PARTNERSHIPS?

    9

    • Limited Port Capital

    Resources

    • High Pier Capital

    Needs

    10-yr Capital Need…

    .vs. 10-yr Capital

    Resources

  • WHY PARTNERSHIPS?

    An efficient delivery method to meet costly

    safety upgrades needed for a public-

    oriented project.

    10

  • WHY PARTNERSHIPS?

    Port track record for opening sites to the

    public through successful public-private

    partnerships

    11

  • RFI RESPONSES AND FEEDBACK

    12

  • 52 RESPONSES RECEIVED BY OCT 31

    Respondent by Tenant Type

    13

    Master , 20, 38%

    Smaller, 18, 35%

    Master or Smaller, 9,

    17%

    Partner, 5, 10%

  • RESPONSES BY CATEGORY

    14

  • FEEDBACK SURVEY

    Survey available

    tonight.

    Responses are online: http://bit.ly/piers-rfi-responses

    Survey is online: http://bit.ly/piers-rfi-feedback

    15

    http://bit.ly/piers-rfi-responseshttp://bit.ly/piers-rfi-responseshttp://bit.ly/piers-rfi-responseshttp://bit.ly/piers-rfi-responseshttp://bit.ly/piers-rfi-responseshttp://bit.ly/piers-rfi-responseshttp://bit.ly/piers-rfi-responseshttp://bit.ly/piers-rfi-feedbackhttp://bit.ly/piers-rfi-feedbackhttp://bit.ly/piers-rfi-feedbackhttp://bit.ly/piers-rfi-feedbackhttp://bit.ly/piers-rfi-feedbackhttp://bit.ly/piers-rfi-feedback

  • RFI PROCESS UPDATE

    16

    This RFI seeks the next great concept for the

    Waterfront.

    • RFI Responses Open House

    Tonight

    • Port Commission RFI Responses

    Informational Report Dec 11, 2018

    • Port Commission RFP Strategy

    Informational Report Feb 2019

    • Action item at Port Commission,

    RFP(s) authorization Mar/April 2019

  • TONIGHT’S AGENDA

    • 9 stations

    – Response titles, excerpts from response, &

    entire response

    – May provide written comments

    – Surveys available at each station

    17

  • THANK YOU!

    CONTACT:

    [email protected]

    REBECCA BENASSINI (415) 274-0548

    18