Report Transient Analysis2
-
Upload
diego-f-rodriguez -
Category
Documents
-
view
217 -
download
0
Transcript of Report Transient Analysis2
-
7/30/2019 Report Transient Analysis2
1/4
Steady State & Electromagnetic Transient Study of a
Power Grid During Consecutive Branches
ConnectionDiego Rodrguez
AbstractSwitching transients are an important factor on thestudy of connecting branches, loads, reactive banks, etc.
Switching transient is one of the primary causes of transient
overvoltage and over current in power systems. This report
focuses on a comparative study of the modeling and simulation of
a switching transient response using two simulation tools:
PSCAD/EMTDC and MATLAB (Chenxis code). The
comparative overvoltage transient results during the switching
study are also provided.
I.INTRODUCTIONThe opening or closing of breakers and switches in a powersystem produce switching transients. Those switching
operations are depicted mainly in two categories: i)
energization of a branch1 (main objective of this project) and
ii) de-energization of a branch.
The first category consists of energization of transformers,
reactors, capacitor banks, transmission lines or cables, loads,
and so on. The second category includes load rejections, faults
clearing, shunt reactor banks de-energization, etc.
As a result of the difficulty at the time of representing
mathematically all the elements involved, digital computer
simulations using Electromagnetic Transient Programs
(EMTP) plays an important factor in the analysis of switching
transient. The results from those studies are relevant in the
study of:
a. insulation co-ordination to determine overvoltagesstresses on equipment
b. determining the arrester characteristicsc. determining the transient recovery voltage across
circuit breakers.d. determining the effectiveness and security of a
connection during the re-energization of a system
(black start)
Those factors are currently analyzed by software as
PSCAD/EMTDC, ATP, EMTP-RV, etc. In this document, we
will use the theory developed by H. Dommel [1] during the
transient time to create a program in MATLAB which can
analyzed the voltage and current response to consecutive
1In this document a branch is a power system element as a
transformer, a resistor, an inductor, a capacitor, a line, etc.
connection of branches during the re-energization of a power
system.
To show the results this document it will be divided in threesections. Section I, will describe the models implemented in
MATLAB for the analysis. Section II, provides a model case
along with the comparison switching transient results for both
programs during the energization. Finally, Section III
concludes and exposes the future steps of the study.
II.MODELING REQUIREMENTSWith the use of EMTP representation of each element [1]during transient analysis, this section shows the standard
representation of each element during a switching transient
A.ResistanceFrom [1] the representation of a resistor takes the form of
Figure 1, this is the same as in steady state because there is not
exist any element which stores energy (capacitor or inductor)
R
)(ti
)(tek
)(tem
DATUMDATUM
Figure 1Resistance models
B.InductanceEquation 1, shows the relation between voltage and current in
the inductor
Equation 1In EMTP the model takes the form of
where
-
7/30/2019 Report Transient Analysis2
2/4
)(, ttI mk
t
LR
2
)(,
timk
)(tek
)(tem
DATUMDATUM
Figure 2 Capacitance model for transient analysis
C.CapacitanceEquation 2, shows the relation between voltage and current in
a capacitor: () Equation 2In EMTP the model takes the form of
( ) Where
( ) The representation is homologous to inductor with a variation
in the current source () and the parallel resistor .D.LinesLines are represented using the Bergeron method [1], Figure
3.
Where H is
)(tek )(tem
DATUM
)(, ti mk
)( tIk
Z )( tIm Z
4'
'R
C
LZ
Surge Impedance or
Characteristic Impedance
)(, ti mk
Figure 3 Lines representation for long lines during transient
analysis
E.TransformersTransformers are represented by a combination of a series R-L
branch.
F.SourcesIn switching transient studies, the voltage source is modeled as
an ideal sine-wave source. Generators are modeled as a
voltage behind a (subtransient) Thevenin impedance.However, the simulations up to now used a dc voltage source
to reduce complexity.
III.STUDYCASEThe goal of this energization study case is to compare the
entire voltage wave during the connection of a new branch in
both programs. The comparison includes the settling time and
the maximum amplitude of the waves.
To achieve this objective a small system will be consecutive
energized and the result compared. The power system is
shown in Figure 4, is a 4 buses system 100 KVA and 230kV
with an open ended line at the bus 4. For the analysis thesystem is progressive connected in two steps.
Bus 2Bus 1 Bus 3
Line 1 Line 2TR
Load 1 Load 2VOLTAGE
SOURCE
Bus 4Swt 1 Swt 2
Figure 4 4 buses system example for progressive connections.
A.Step 1 -Voltage Magnitude & Settling time during the firstenergization
First, with transformer connected to the generator and in open
circuit2, the first loaded line at both ends is energized. The
voltage results are shown in Figure 5.
2Transformer saturation is not considered
-
7/30/2019 Report Transient Analysis2
3/4
Figure 5 Result connecting loaded line to a transformer in
open circuit
To compare the error in maximum voltages and settling times
between Matlab code and PSCAD the next formula was used:
| || |
Bus
Name
Maximum voltage
magnitude (PE)
Settling time
(PE)
Bus 2 0.16 % 4.83 %
Bus 3 0.56 % 3.84 %
Table 1 Maximum voltage magnitude and settling time
comparison for the first energization
The second column ofTable 1 shows the result at the time of
comparing the maximum voltage at bus 2 and bus 3. The
results show a good approximation of the modeled system
with Matlab and the simulation in PSCAD. The same criteria
is applied for the settling time where the maximum error is
4.83 %
B.Step 2- Voltage Magnitude & Settling time during thesecond energization
When the steady state is reached the second open ended line is
switched on. The results from MATLAB code and PSCADare compared and the results summarize in Table 2.
Table 2 Maximum voltage magnitude and settling time
comparison for the second energization
Figure 6 Voltage magnitude at all buses when connecting an
open ended line to an already energized and loaded
Figure 6shows the voltage magnitudes in the system when the
second line is connected. The general forms of the waves are
-
7/30/2019 Report Transient Analysis2
4/4
closed but the maximum magnitudes errors in Table 2 diverge
in comparison with the first energization.
.
IV.CONCLUSION AND FUTURE WORKA comparison of the performance of two simulation
environments (PSCAD/EMTDC and Matlab code) has been
demonstrated by modeling the switching overvoltage using a
small system. Both programs produced acceptable voltage
waves in magnitude and settling times during the connection
of new branches.
Future work includes the reduction in error percentage during
the connection of the second branch and the test in a bigger
power system to compare not only the transient response but
also the new steady state after each connection.
REFERENCES
[1] H. W. Dommel, Electromagnetic Transients
Program, 1987.
Bus Name Maximum voltage
magnitude (PE)
Settling time
(PE)
Bus 2 5.42 % 5.13 %
Bus 3 15 % 4.9 %
Bus 4 7.06% 6.19%