Report Transient Analysis2

download Report Transient Analysis2

of 4

Transcript of Report Transient Analysis2

  • 7/30/2019 Report Transient Analysis2

    1/4

    Steady State & Electromagnetic Transient Study of a

    Power Grid During Consecutive Branches

    ConnectionDiego Rodrguez

    AbstractSwitching transients are an important factor on thestudy of connecting branches, loads, reactive banks, etc.

    Switching transient is one of the primary causes of transient

    overvoltage and over current in power systems. This report

    focuses on a comparative study of the modeling and simulation of

    a switching transient response using two simulation tools:

    PSCAD/EMTDC and MATLAB (Chenxis code). The

    comparative overvoltage transient results during the switching

    study are also provided.

    I.INTRODUCTIONThe opening or closing of breakers and switches in a powersystem produce switching transients. Those switching

    operations are depicted mainly in two categories: i)

    energization of a branch1 (main objective of this project) and

    ii) de-energization of a branch.

    The first category consists of energization of transformers,

    reactors, capacitor banks, transmission lines or cables, loads,

    and so on. The second category includes load rejections, faults

    clearing, shunt reactor banks de-energization, etc.

    As a result of the difficulty at the time of representing

    mathematically all the elements involved, digital computer

    simulations using Electromagnetic Transient Programs

    (EMTP) plays an important factor in the analysis of switching

    transient. The results from those studies are relevant in the

    study of:

    a. insulation co-ordination to determine overvoltagesstresses on equipment

    b. determining the arrester characteristicsc. determining the transient recovery voltage across

    circuit breakers.d. determining the effectiveness and security of a

    connection during the re-energization of a system

    (black start)

    Those factors are currently analyzed by software as

    PSCAD/EMTDC, ATP, EMTP-RV, etc. In this document, we

    will use the theory developed by H. Dommel [1] during the

    transient time to create a program in MATLAB which can

    analyzed the voltage and current response to consecutive

    1In this document a branch is a power system element as a

    transformer, a resistor, an inductor, a capacitor, a line, etc.

    connection of branches during the re-energization of a power

    system.

    To show the results this document it will be divided in threesections. Section I, will describe the models implemented in

    MATLAB for the analysis. Section II, provides a model case

    along with the comparison switching transient results for both

    programs during the energization. Finally, Section III

    concludes and exposes the future steps of the study.

    II.MODELING REQUIREMENTSWith the use of EMTP representation of each element [1]during transient analysis, this section shows the standard

    representation of each element during a switching transient

    A.ResistanceFrom [1] the representation of a resistor takes the form of

    Figure 1, this is the same as in steady state because there is not

    exist any element which stores energy (capacitor or inductor)

    R

    )(ti

    )(tek

    )(tem

    DATUMDATUM

    Figure 1Resistance models

    B.InductanceEquation 1, shows the relation between voltage and current in

    the inductor

    Equation 1In EMTP the model takes the form of

    where

  • 7/30/2019 Report Transient Analysis2

    2/4

    )(, ttI mk

    t

    LR

    2

    )(,

    timk

    )(tek

    )(tem

    DATUMDATUM

    Figure 2 Capacitance model for transient analysis

    C.CapacitanceEquation 2, shows the relation between voltage and current in

    a capacitor: () Equation 2In EMTP the model takes the form of

    ( ) Where

    ( ) The representation is homologous to inductor with a variation

    in the current source () and the parallel resistor .D.LinesLines are represented using the Bergeron method [1], Figure

    3.

    Where H is

    )(tek )(tem

    DATUM

    )(, ti mk

    )( tIk

    Z )( tIm Z

    4'

    'R

    C

    LZ

    Surge Impedance or

    Characteristic Impedance

    )(, ti mk

    Figure 3 Lines representation for long lines during transient

    analysis

    E.TransformersTransformers are represented by a combination of a series R-L

    branch.

    F.SourcesIn switching transient studies, the voltage source is modeled as

    an ideal sine-wave source. Generators are modeled as a

    voltage behind a (subtransient) Thevenin impedance.However, the simulations up to now used a dc voltage source

    to reduce complexity.

    III.STUDYCASEThe goal of this energization study case is to compare the

    entire voltage wave during the connection of a new branch in

    both programs. The comparison includes the settling time and

    the maximum amplitude of the waves.

    To achieve this objective a small system will be consecutive

    energized and the result compared. The power system is

    shown in Figure 4, is a 4 buses system 100 KVA and 230kV

    with an open ended line at the bus 4. For the analysis thesystem is progressive connected in two steps.

    Bus 2Bus 1 Bus 3

    Line 1 Line 2TR

    Load 1 Load 2VOLTAGE

    SOURCE

    Bus 4Swt 1 Swt 2

    Figure 4 4 buses system example for progressive connections.

    A.Step 1 -Voltage Magnitude & Settling time during the firstenergization

    First, with transformer connected to the generator and in open

    circuit2, the first loaded line at both ends is energized. The

    voltage results are shown in Figure 5.

    2Transformer saturation is not considered

  • 7/30/2019 Report Transient Analysis2

    3/4

    Figure 5 Result connecting loaded line to a transformer in

    open circuit

    To compare the error in maximum voltages and settling times

    between Matlab code and PSCAD the next formula was used:

    | || |

    Bus

    Name

    Maximum voltage

    magnitude (PE)

    Settling time

    (PE)

    Bus 2 0.16 % 4.83 %

    Bus 3 0.56 % 3.84 %

    Table 1 Maximum voltage magnitude and settling time

    comparison for the first energization

    The second column ofTable 1 shows the result at the time of

    comparing the maximum voltage at bus 2 and bus 3. The

    results show a good approximation of the modeled system

    with Matlab and the simulation in PSCAD. The same criteria

    is applied for the settling time where the maximum error is

    4.83 %

    B.Step 2- Voltage Magnitude & Settling time during thesecond energization

    When the steady state is reached the second open ended line is

    switched on. The results from MATLAB code and PSCADare compared and the results summarize in Table 2.

    Table 2 Maximum voltage magnitude and settling time

    comparison for the second energization

    Figure 6 Voltage magnitude at all buses when connecting an

    open ended line to an already energized and loaded

    Figure 6shows the voltage magnitudes in the system when the

    second line is connected. The general forms of the waves are

  • 7/30/2019 Report Transient Analysis2

    4/4

    closed but the maximum magnitudes errors in Table 2 diverge

    in comparison with the first energization.

    .

    IV.CONCLUSION AND FUTURE WORKA comparison of the performance of two simulation

    environments (PSCAD/EMTDC and Matlab code) has been

    demonstrated by modeling the switching overvoltage using a

    small system. Both programs produced acceptable voltage

    waves in magnitude and settling times during the connection

    of new branches.

    Future work includes the reduction in error percentage during

    the connection of the second branch and the test in a bigger

    power system to compare not only the transient response but

    also the new steady state after each connection.

    REFERENCES

    [1] H. W. Dommel, Electromagnetic Transients

    Program, 1987.

    Bus Name Maximum voltage

    magnitude (PE)

    Settling time

    (PE)

    Bus 2 5.42 % 5.13 %

    Bus 3 15 % 4.9 %

    Bus 4 7.06% 6.19%