Report 1969
-
Upload
raghavendran-raghu -
Category
Documents
-
view
233 -
download
0
description
Transcript of Report 1969
IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, VOL. PAS-88, NO. 6, JUNE 1969
500-kY AC Substation Design Criteria
Summary of Industry PracticesIEEE COMMITTE REPORT
Abstract-In order to determine major trends in 500-kV substationdesign practices, a survey was made of ten major electric utility sys-tems in the United States and Canada. These findings are presentedin tabular form for easy comparison of design features. Majorvariations in data are identified by an asterisk and are explained inthe accompanying discussion following the tabulation. These datashould be invaluable to those companies having 500-kV systemsunder study and will serve as a permanent record of the state-of-the-art. The Working Group has prepared similar data on Hydro Que-bec's 735-kV system and American Electric Power Company's 765-kV system, which will be published in a separate report.
INTRODUCTION AND CONCLUSIONS
THE 1960's will be remembered as the decade that saw the500-kV story unfold in the electric utility industry of the
United States and Canada. The first systems were placed inoperation in 1965, and since that time all ten surveyed have ac-
cumulated sufficient operating experience to confirm the validityof their design in varying degrees of satisfaction. Since the survey
was undertaken, additional systems have been placed in serviceor are in advanced stages of design (Fig. 1).These data generally represent the latest design criteria of the
participating agencies. They do not necessarily mean that allstations constructed by these companies conform to the exactcriteria, since individual circumstances usually require some
design change or modification. Indeed, some companies used morethan one design and changed criteria with experience and to meetspecial conditions.
This design information represents a Herculean effort on thepart of the companies which pioneered in this field; and the suc-
cessful operation of these systems is a tribute to the designers,the constructors, and the equipment manufacturers who partici-pated in this exciting venture. This summary should be an
invaluable reference and guide for the whole industry, and espe-
cially for those companies contemplating 500-kV design. It is notintended, however, that this information be used as a substitutefor an independent engineering study of the total situation in-volved. Although these data reflect the individual design phi-losophies of the ten agencies involved, they could not possiblyshow the alternatives considered or give the reasoning behindthese decisions. Therefore, the committee members cautionprospective designers against the temptation to use this informa-
Paper 69 TP 45-PWR, recommended and approved by the Sub-stations Committee of the IEEE Power Group for presentation atthe IEEE Winter Power Meeting, New York, N. Y., January 26-31,1969. Manuscript submitted September 13, 1968; made available forprinting November 7, 1968.Members of the Working Group of the Transmission Substations
Subcommittee of the IEEE Substations Committee are: Paul R.Dolan, Chairman; L. M. Berry, R. R. Blanchard, 0. R. Compton,C. L. Donaldson, Jr., G. E. Hertig, W. J. Leister, E. R. Taylor, Jr.,J. A. Maneatis, L. M. Gordon, J. B. Oliver, R. J. Perina, E. S. Raila,H. N. Scherer, P. H. Shoun, R. F. Stevens, G. W. Supplee, E. York,and C. E. Zanzie. Former members who contributed are: W. G. Case,H. E. Lokay, D. A. Mitchell, V. P. Rader, and E. R. Snyder.
tion verbatim and out of context with the total design settingfrom which it is taken. Certainly every number listed and ev7eryvalue shown would require an explanation far beyond the scopeof this report. For additional information on the individual systemdesigns, it would be best to first review the supporting bibli-ography referred to and then follow up with the particular com-pany involved.
DISCUSSION OF MAJOR DIFFERENCES IN DESIGNCRITERIA TABULATIONS
Allegheny (by G. B. Hoffman)
Supporting Bibliography:[1] W. C. Guvker, J. E. O'Neil, and A. R. Hileman, "Right-of-
way and conductor selection for the Allegheny power system500-kV transmission system," IEEE Trans. Power Apparatusand Systemns, vol. PAS-85, pp. 624-632, June 1966.
[2] W. C. Guyker, A. R. Hileman, and J. F. Wittibschlager,"Full-scale tests for the Allegheny power system 500-kVtower-insulation system," IEEE Trans. Power Apparatusand Systems, vol. PAS-85, pp. 614-624, June 1966.
[3] A. R. Hileman, W. C. Guyker, R. W. Powell, W. A. Richter,and J. WI. DeSalvo, "Insulation coordination in APS 500-kVstations," IEEE Trans. Power Apparatus and Systems, vol.PAS-86, pp. 655-665, June 1967.
[4] A. R. Hileman, W. C. Guyker, H. M. Smith, and G. E.Grosser, Jr., "Line insulation design for APS 500-kV system,"IEEE Trans. Power Apparatus and Systems, vol. PAS-86,pp. 987-994, August 1967.
[5] G. B. Hoffman, A. R. Hileman, and W. C. Guyker, "Alle-gheny power system 500-kV system design," Proc. 1965American Power Conf., vol. 27, pp. 962-970.
[6] G. B. Hoffman, J. K. Dillard, and A. R. Hileman, "Selectionof line insulation for APS 500-kV system," CIGRE, Paper410, 1966.
[7] "Report tests on designs for 345 500 735 kV," ElectricalWTlorld, pp. 50-51, 102, November 1, 1965.
American Electric Power Service Corporation (by H. N. Scherer,Jr.)
Equipment:Item C.3: A 1600-ampere disconnecting switch was selected,
since this was greater than the maximum line interchange currentexpected in the future and would also be greater than the maxi-mum installed transformer capacity connected to the 500-kVlines.The 500-kV stations are not really substations but are 500-kVlines feeding 500/345-kV transformers that are then tied to the345-kV station buses.
Item E.1: Lightning arresters were specified on the basis of60-Hz sparkover and seal-off voltages and maximum line dis-charge thermal capacity. 384-kV is above the maximum dynamic60-Hz overvoltage that can occur on this system. It is AEPgeneral practice to select the lowest rating arrester that cani be
854
IEEE COMMITTEE REPORT: 500-KV AC SUBSTATION DESIGN CRITERIA
Fig. 1. 500-kV and above tranismission systems in the Uniited States and Canada, in serviceor to be completed in early 1970's. All lines that are not designated are 500 kV ac.
used on our 60-Hz systems with the aim of achievinig the lowestpossible BIL for the transformer.
Arkansas Power and Light (by R. W. Toler)
Electrical Station Design:Item B.3: This phase spacing was utilizedl to allow the in-
stallation of three 500-kV phase transpositions in the substationl.
Supporting Bibliography:[8] J. T. Henderson and R. W. Toler, "Low profile pedestal bus
design used in SCEC-EHV substations," presented at theIEEE EHV-AC Transmission Conf., Richmond, Va.,October 4-6, 1965.
[9] R. N. Newsom, S. B. Nickelson, R. W. Toler, MI. S. AIerritt,H. A. Riesch, and F. W. Smith, "Staged tests on the TVA-SCEC 500-kV interconnection between Johnsonville andWest Memphis," IEEE Trans. Power Apparatus and Systems,vol. PAS-86, pp. 1389-1399, November 1967.
Bonneville Power Administration (by R. F. Stevens)
Electrical Station Design:Item B.3: The 20-foot phase spacing is electrically adequate
and is adopted for economy of space and, more importantly, tominimize length of crossover buses.
Item B.6.e: The height of the main bus above ground is only23 feet, the same height as the bay bus. This is for reasons of
convenience and economy and also provides a lower profile. Thismakes it necessary to bring two phases of the bay bus "up andover" where they connect to the corresponding phases of the mainbus. It is these crossovers that account for the 41-foot heightshown under item C.4.e.
Supporting Bibliography:[10] R. F. Stevens, I. T. Davies, and M. N. Marjerrison, "BPA
500-kV transmission-line and substation design," IEEETrans. Power Apparatus and Systems, vol. PAS-85, pp.687-695, June 1966.
Keystone Project (by C. E. Zanzie)Electrical Station Design:
Item C.4.a: A bundle of three conductors per phase was usedfor substation bay downeomers to minimize corona in the areawhere conductors run parallel to the leg of the backbone strue-ture.
Ultimate Substation Layout:Item A: The maximum open-line voltage of 650-kV is a cal-
culated value based on the following situation. Since it would bepossible to have two lines connected in series between source andline open end, a figure of 260 miles of 500-kV line was used to cal-culate the maximum open-line voltage. The condition of no loadbetween source and the line open end was used. There are no re-actors in the Keystone 500-kV system.
8.5)
500-
kVSAC
Substa~tion
11lc
Lric
ali
Dcsign
(Cri
teri
a
Alt E1
ItENY
ALEI
ARK.
Pt
L.BP
AKE
YSTO
CON
PD-i
tOI
E3'CR
CO.
TVA
IfP
(Co.
RL
ECSR
ICIA
Si
ESKI
__N_
A.'
Minimum
Clearance
'Transrnession
(Metal
tofe
tal)
Stationsm
(Peners'ting
Stations
1.Phase-to-phase,
ft.
2320
20l(
I2-
PO-20n
2r-a
2.Pi
vse-
Lo--
roun
d,ft.
P115IT,-(1113_______
3.Al
enve
enoiiv
-L'i/
111s
idi
vilvi
lie
Cl______
~~~31
_30
Va
stI'
f)aram
eters
I.0)rireit
rain
me32
0030
336c
3000
OA3%
3--
-IotO
-77-c
4CQ
~~~~~
~Cri
_-O
'4
2.Ty
,pe
(rig
id,
tension)
Rigi
dTensioi-
Rigi
dRi
gid
Rigil--
Pigid
Rigi
d-e
sici
Tension
Tens
ioi
d_
3.Ph
ase
spacing,
ft.
2823
35*
20*
2525
2526
2525
___________________________
25(Rkrs.
______
______
_____
4.Mi
ax.
distance
between seipports,
ft. ~~~~~~~56100
-Sta.
ARi
ng53
43Li7
89
C0
Ea.
57__
5.BIL.
kV18oo
1530
I80
1550
iSOC
180
180
100
i00
2551
_
6i.Co
iidu
ctor
sa.
iiberpe
rph
ase
12
i1
11
13
23
h.Ci
aivi
eter
,in
ches
5'RS
1.65
4,5,
6CR5
5IR
54.5
4-1/
28*
1.762
i.68
ie
c.Ty
pe60
61-1
,620
49mcmii
Altuhe
Altu
he4"
Allute
Altu
beAl
lute
2156
memi
l2,034.5
mcmii
249
nccc
til
AlAl
loy
tube
ACSRE
S____
ched
uie
80AC
SR6"
Allute
5005
AlAlloy
d.Subconductor
spacing,
inches
18
18
431'
12
e.((ieight
shov
egr
ound
ft.
(VSupport)
6029
30V5
~23:_____
4753-/C
6o
_____
___
~~~~~~~~~~~~~~~~~~~
J~~~~~~~~~
saLsics.)~
~~~~~~~~~~
~~~li-v
L-!(-I
.L.ii
rrev
itca
liij~
",2O
(131
01iI30A
C,0
0/40
0__
___0
0119
3C17
'Tv-p
(1ensiot
rigi
d)RIij'Tl
cr7ie
PigiJ
CclooenseioliI
iierirCeso
3.9
1__
_iC
~~~~~~
~~~~~~
~~~~~~
~~~~~~
~-igid
Piii
_____
__
iS*ad
l ay
widt
h.ft.
-90
00__
_10
0___
nL5
0-)
100
4.ayconductors______
-.imPer
-ner
phas
p12rs
__
1.Di
amet
er,
inches
SJPC)C,e
i,
5CR
.P1
__
12I
ui__
~~~~
~~
~~
~~~~~~
~~~~
~~~
~~IRS-_L_
j,5
4.51
c.u25
3-1/
i
Cfe
Co(-il
-1,
2040
1(iw
iA11tile
A1.
iCt91il
Clci
Slib1
1li
345
ii1
Alte-
lbeAC
APAAIA1
A535,0AC11)01
TikI
I:.
IiSiii
Alti
be411063V
d.`J
iitc
ondu
icto
r,spseSci
inclhes
ii11.3
.1
Heig
htat
ove
grosind
ft.
(@Su
ppor
t)S
0315
9~
32_
__~
i1.
10232
D.Pn
suil
ator
s
1.Su
spen
isio
nCon
24Un
its
24un
its
2211nits
25Unitt
26Un
its
30-35
Units
30UnitE
IilE
5-3/
4ii
x10
'5-3/41'
x10
f6-3/411
ail
5-3/4ii
xloll
5-3/411
x10
l5-
3/411
x10"*
3li5-3/411
x10
"
*See
discuission.
H z zrn p H;p ~- CI z
50(-cc\[
ACSubst-tion
Elee
tric
alCDa
esigns
Critit
'ia
ALLE
.JGI
IEAP
Ott'AR
.5.
'5PA
-~,
Sat
.i(
!CC
0".7-.
ipCC.
[1.
"LEtC
-PICA
iTA
10`
DESI
SuIp
port
5Un
it~aper-ds
iTtY
'it,
'apered
IIuniit
')'n
itpi
t'it
ntIC)at
Stat
ion
Post
"L:t
ic'
oat
tant
ion
',os
tatu
rSt
atio
nSt
Citatiosna
'iia
)'tn
atCa
itti
o3.''i"
"'c
lt
,inch
es
33e
3_Sw
itch
int'
a sip
e,tn
-10
15:
'St(In5 IC
kna
',T't
CCII'T
['IL'apM
na.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~)O
. 10
e
i.Tr
ansf
orme
rAr
ea______
1.tI
rans
form
erconnection
Rigi
d_1C-nsi-or
Rgi ot
_Rig
i-d~
Rigi
d-RigidefitenireicRgi
(Tension/Rigid)
___e
nsio
n___
____
sioTenior__igid
2.Me
thod
sofco
nnec
ting
CoSpare
Reno
vei
Sparc
once
,Re
move
IRemoveSpar&
1-sPe
ove&
Reov
eS&r-
IaSparereBPusSSparc-anusSpare
ius
spar
e(no
spare,
spare
Repl
ace
Repince
Replace
3-Nto
Spar
ebus,
remoie
&replace)
3.e.c
rtianry
(ius)
one
None
Rigid
Rigi
dRi
gid
orRi
gid
Rigi
dRi
gid
Rigi
dC~one
(none,
rigid,
tension)
Ins.
Cable
e-rtiary
Reactor,Area
on''__
_one
1,
Reactor
connection
-or-
,eliNonse9
a._Y-pe
(rigid,
Tension
_______
Rigid_______
_______
Rigid
Rigid
Tens
ion
Rigid
___o
ne___
t.
Phase
sp'cing,
ft.
76__
2.1.',inina,m
distanice
f'rorr
reactors
tofe
rrou
snl
ater
iais
,ft
._____
IaT
_______
3.CMethod
ofswitching
AC-
Disc.Sw'sa.
ACe
inACt'
per-
AC"
per
Air
eintt
1i
Reactor
tos.
RCa'
etor
ton.
tin
lay
ing
T.'ype
Directionat
DirectionaT
Diri
ctio
nat
Phas
eCoi'._
Plr.
aonqp.ttri.)
Dire
ctio
naT
Phas
Coat
.th
asr
Corap.
T-Ce
tCt
'tic
Dire
cito
nni
Coinparison
Conp
aris
onCo
nrp'
iris
onPi
stan
nc'i
Pj1Drie.
Pisi
.P
neContactno
n'(P
iidendnt)
n./diar:ct
Sura.
Pir.
Corn
p.t'o'.eparo'.
,tgtRIn
Rita
ysra
a'r
nnid
T'rct'fr
n.i)
e'raisair
crit
Ce
I0
_______________
~~~~ri
-Pcaunt
('-ace
aup)
a'C
i.OR
2.Ch
anne
lPT~
T-TPItC
tPLC'
PT'
"141IC
(tni
ttil
)iT,(
TLC
iCC_,tW
LaC1.
Conm
muni
cati
ons
for
disp
atci
-Ci
lSihield
ieOHC
Shie
id"~P
A',tAtaI
nail
ire
PLC
it''C
iChicl
:PS:',
HShield
Ct'tSttCii
ing
area
load
frej
uenc
y,'
Sire
sand
t%ires
t%irc
tine
C".
'ire.-
administration
Carrier__
1.Control
cabie
Shie
ided
,Gr
d.Unshielded
Unsh
ield
edSh
ieil
den
Shie
Tded
'Tnshielded
tUns
hiel
d-d
Shii
elde
dShielded
(shielded,
unshieaded)
aito
then
-ds
except
for
aud-
den
pressure
rela
ycir
cuit
s~
A.
Transformers_______
i.'Typ
eAuto
Auto
trar
s-Au
totr
ans-
Auto
tra-
ns-
Aato
(2zaics)
Auto
tran
s-A-
uton
tran
s-Autotr
ans-
3Windnie
Auto
tran
s-fo
rmer
former
dorm
er-forner
formic
forn
acr
fors
erS.
311
catin'
,"
A21
0SiC
~~~
~~~~
~~~~
35C2
10'C
/C/i
5/0
90SC279/350
360
118046
00145
046004
75060
/~~
2oo12CC
450/
600/
750
5500
+ti,
1'12
CC3)0/51T
50ST6288360
'CCpC
ollo
CC5eoTDCi
2:TS
Ctt/2c0
3.Vt
olta
ge,
Cck5CC/138
n5o
o/16
1/13
.R,
CC23
0S
CC5o623885.25'
500/
lr1/
13'2
C00/23C
/115
5-'
5CC
/3lt
5/T3
.2~~~~
~~~~~~~5
00/1151/
13.5 2
5/SiT.
1-51/
5CC
230/I3.8
525/
238/
28.2
9'25/23t/a3.8'
D-eita
i'ap
/s5-0/o
/13.8
34_
__._
41.Single
orth
ree
pDhnse
3RlInse
Single
Sing
leSingle
7Ra
niks
ofSi
ngle
"3
t,ia0g
cSi
ngS
Sinigle
Single
&3
Cingle
Phas
e?haie
Phas
e2~
Phas
e_5.
BIL,
klvwinding
&13
CCWi
ndin
g13CC
1425
514
125
S142
5a
55C
1675
Winding
11425
S'indin."
1425
1675
Wind
ing
1300
iWinding
bushing
1550
Rushing
1800
Bushing
iiso
Bush
ing
1590
0'u
shin
g&Ru
shin
gC.
~~~~~criinry
rating,to
neT~~
~~~~~~
~~~~~~
~~~~~~
""""'
~~~~
353O
to13
352
3535
30cT
hra
5CA
35No
ne13.5)
(Rea
ctor
Pond)
Rati
ng)
e.
Circuit
'm-rakers
!one__
I1.mi
n.ratit",
t'J,
A35
,000
________
35,000
35,000
38.0
0030
,000
35,0CC
35,000
-3iCCC0
35,000
2.ISP,
kiC
1OC
1500
155C
aC15
001500
1CC0
1CC
1550
*See
discussion.
I_____I__
g to tI., 0 z t Si)z0
m
Pt Pt PIt 0-3
C.T 00
5(0(-1.1VAC
Substationl
Ele
2t'lic
daD2
eign
Critel
iimi.
AILE
(ill
ENY
ALP
ARK.
P.L.
BPA
KM'-fST0
ELOC'
(DRO
P0
1'Fl
SCPE
COVA
VLP
C(.
3.CuLrrent
Yrat
ing,
A30
0030
0024
0030
002500
3000
3000
3000
2000
x~~
~~00__
4.Sw
itch
iing
sirge
resi
stor
(closinlg)
Yes
Yes
Yes
Yes
a'Ye
sYe
sYes
Yes
C.Di
scon
nect
Swit
ches
1.lorizontal
or
vert
icnl
I"er
tica
lfi
oriz
onta
lVertical
Vertical
'.er
tica
lVe
rtic
alcr
tic
al.e
rtic
alIo
rizo
cnta
l-!l
oriz
onta
:Irenk
Doub
leFr
eak
Hori
zont
alan
dCe
nter
Rota
-Douible
End
Vertical
tion
Treak
Reac
hVe
rtic
alReach
Vert
ical
Freak
2.itL
,kV
T56Y0
1550
1800
1550
1800
1800
1800
1800
1800
1a.
eSwitc
hoen
a5
613,6"
Vert
.15'
i4,-10ol
17'
(Mietal
to17
-1/2
'(2
)9'
-8"
17-1
/2'
clearance
~~~~
~~~~
~~~~
~~~~
~~~~
~~~~
~~~~
~~15
'Vert.
feic
tal)
lforiz.
Reach
17-1
/2'
ci
_~~~
~~~~~~
16,'ertciReachl
3.Cu
rren
trating,A
3000
i6oo0'
_3000
2400
kl25
000_
oo1000
3000
3000
3000
20OIl
4.surge
supp
ress
ing
No.0
.o.o
Provisions
For
.'o.'o
.0To
riZ.
Mc.-
resi
stor
Future
Yes~ Vert.Reach-1l'o
5.~y
peof
oper
ator
3Pole,
3Po
le,
Mlot
or3
Pole,
Motor
3Pole,
Motor
3PloleManual
3Po
le,
Moto
r3l
Poie
,cl
,anu
alSiagle
Pole,
3Pole,
M'ot
or1
3Po
le,
I,anual
'01c
tr3Po
le,M
otor
Mianual
Hydr
auli
cna
eum
atic_
Shun
tReactors
lonJone
one
_one
1.Voltage,
kM50
0&13.8
553p&34.5
________
027
.652
3455n13.40
11.47
_______
2.T4
mind
ing
1STI
,kV
1425
t110
1350
C200
1800
Ic11
01550
511
01550
",110
1(75
~-110
Neutral
3.Singlc
or
mreP
hase
T-ot
hco
thSingle
Single
Sing
lcSingle
'hr
e_E.
Ilig
htni
ngArrester
Ratings__
__
1.Rank
376
384
kV*
410k:
396
kV42
0k.
,44
4k
480
kV,
4311
kM.420
k'.7
44Ick4
1307
-f4f8__
2.Shunt
reac
tor
(_500
k.l')
l4on
e42
0k.
'41
0k.
!lo
ne48
0kV
,43
1k'.
460
k'I4(
6~kV
492kV_____
F.Series
Capa
cito
rs',
one
-lone
None
________
one
None
______
________
n1.
kotae1.00
k.,
525
k'.__
____k___
-2.
BILt
IV__
1800
1800
1600
3.M'
inim
umc
clearance
a.
Phase
to
phase,
ft._
17
22-1
121
b.Ph
ase
toground,
ft.
______
1216.
15_
__
___
______
C.Insulators
a.Cmp
port
SIJ
nit
6Iinit
5ni
Stationi
Lo.t
__
______
Stat
ion
Past
Sta-
tion
ilo
st________
______
t.'S
nium
aleakage
dis-
tance,
inches
350
432'
3O__
Pote
ntia
lTransformers
&Co
upli
ngCouipling
Capa
cito
rCoupling
Coupling
Coui
plin
gCoupling
Couipl
inig
Coupling
Devi
ces
Capa
cito
rCapocitor
Cascade
Pote
ntia
lCapacitor
Capacitor
Capacitor
Capa
cito
r'a
paci
tor-
Capa
cito
rand
Rot.
Tlra
nsfo
rmer
IPotential
Potential
SCascade
Devices
Devices
~~~~~~~Device________
1.',
olta
ge,
kV31
8P
to50
030
0LtoI
500
500
500
525
52300
Lto
N287
LtoS
2.Rinding
FIL,
RI16
751550
1T06
1800
1800
1550
,3.
'shing
'IET,
k.16
001
Cc1800
oclan
lCt25
1800
1100
1800
Rous
ing
'See
discussion.
I's I-0 zx I'd2 z F6- F-i c's q ;D ct:z 35
;rl .r c4 )J2
,
Q512-
zI c.
500-kV
ACSu
bsta
tion
Ultimate
Layo
utand
Envi
roma
lent
alPactors
ALLEGHENY
AEP
ARK.
P.&
L.BPA
KEYS'i'ONE
ON'I
'.HY
DRO
PE
SCE
CO.
TVA
VEP
CO.
I.ULTIMAIE
SUBS
I:AT
ION
IAYO
IJ'T
_A.
H4ig
hVo
ltag
e,kV
Nominal
500
500
500
525
0050
0500
5-25
5Q0
--
Maximum
550
550
550
550
550
550
550
550
550
525
Maximum
Open
Litne
55665
0*55_
05Y
600*
550
L.Low
'oltage,
kVNominal
138
345
161
&11
523
023
023
0220
220
161
Maximum
145
362
51241.5
253
242
230
230
169
C.Ba
sic
Switching
Sche
meRreaker
&1/
2Ri
ngCo
nver
t-Ri
ngCo
nver
t-Straight
Pus
Brea
ker
N1/2
Prea
ker
1/2
Breaker
N1/
2Ring,
Main
&Breaker
&1/2
500
kV&
tibl
eto
tible
toRi
ngBus
Transfer
Zig-
138
kRB_reaker
&1
2Br
eake
r&
1/2
Breaker
&1/
27.,
gD.
No.
and
Capa
city
of4
P2@
1P40
03
P4@
66
44
@2
R2@
Tran
sfor
mer
Bank
s35
0MVA
each
600M
VA/B
ank
1@
800
900M
VA/R
ank
650M
C/A/
Pank
900M
VA/
300I
/A/
750
orlOOMYVA
10OOM'VA/Bank
1200
MVA/
Bank
750M
VA/B
ank
Bank
Bank
per
Hank
E.No
.of
Transmission
500
kV4
210
86
148
G08
88
Lines
Low
Volt
age
10-1
38kV
21
345
12@
161&/or
128
188
1210
122
0kV
16P
161
kV12
11(_
F.Capacity
ofTrans-
500
kV17
0013
001500
1200-1500
2400
2000
2000
2400
(Sum
mer-
1000
2000
1000
mission
Lines,
MVA
'lhe
rmal
)Lo
wVo
ltag
e250
(138
kV)
(345
kV)6
00(161
kV)300
300-400
400
600
600
230
kV-636
800
200
400
(Summer-
_|hermal)
II.
ENVIRONMENTAL
(ACTORS
_A.
Maximum
Elev
atio
n,ft
.11
0012
003000
5400
1000
_2000
2000
4000
1000
3500O
B.Te
mper
atur
eRa
nge
-20
to100OF
-10
to11
0°F
0-1200F
-30
to110°F
-40
to13
0OF
-C0
to10
5°F
0to
115OF
0-110°F
-20
to110°F
-30
to110°F
C.Max.
Desi
gnWind
Vlel
ocit
yNo
100mi/h
Wind
NoNo
100mi
/hWind
Rare
57mi
/hNl
ind
100mi/h
Wind
90mi/h
Wind
100mi/h
Wind
and
Gust
Fact
or1.
3Gust
1.25
Gust
130mi/h
Gust
130mi
/hGust
D.Earthquakes
Noea
rthq
uake
s(To
NoYe
sNo
Mino
rYe
sYe
sLight
(To
but
designud
0.2g
Str.
0.2g
Str.
for
mino
rmin-
Desi
gnDe
sign
ing
falls.
_E.
Degr
eeof
Contamination
Ligh
tto
Mode
rate
toNone
Moderate
-Moderate
Mini
mum
Moderate
toModerate
toLight
toLight
toand
Type
Moderate
(Tea
vy1
-Possible
Heav
yHeavy
Heavy
HTeavy
Indu
stri
alHT
eavy
Cont
ami-
Agri
iclual+l
Agrioiultural
Industrial
niat
ioh
from
Indu
s-tr
ial
Power
Plant
Coastal
Pog
_
*See
discussion.
IEEE TRANSACTIONS ON POWERI APPLTRUlS.ANDI) SYSTEMS, JUNF 1969
The condition of 650-kV at any open-line ternminal will occuronly during the time after closing the line source breaker and be-fore application of load. It is contemplated that the condition willoccur not more than 3 minutes a year, average, with a maximumperiod of 15 minutes, which might occur once every 10 years.
Ontario Hydro (by L. M. Gordon)
Equipment:Item B.4: Ontario Hydro has only a single 500-kV linie;
hence high-speed reclosing cannot be used, and this removes themajor need for closing resistors. The line surge withstand wasdetermined by other factors and is sufficient to enable the line tobe picked up without using closing resistors. The circuit breakershave provi;sion for adding closing resistors if necessary when thesecond line is added and high-speed reclosing is used.
Item E.1: Lightning arresters purchased for protection of the500-kV windings of the Hammer and Kleinburg autotrans-formers have switching surge characteristics designed to protect1675-kV BIL windings. These arresters are constructed with twotaps, rated 480 kV and 432 kV rms, and designed to provide a15-percent margin between the maximum switching surge spark-over and the switching surge strength of the transformer whenconnected on the 480-kV tap (full arrester). The 432-kV tap wasprovided so the protective margin could be increased in thefuture when dynamic over voltages on the 500-kV systems areexpected to reduce.
Pacific Gas and Electric Company (by J. A. Maneatis)
Electrical Station Design:Item A.3: This clearance represents the height of the miiain
buses above grade and is based upon the height of the cross busrunning under and connected to the main bus, plus the nominalphase to phase clearance from the cross bus phases to the mainbus phases (28 ft 6 in + 25 ft + 6 in = 54 ft). Roadways crossunder main buses only and run parallel and between adjacentcross bus bays.
Item B.6.b: The use of 8-inch IPS aluminum tube for themain bus was based upon the requirements for current carryingcapacity (4500 amperes) and mechanical strength and deflectionconsiderations. Because of the bus and bay arrangement, onespan of main bus in each bay is 75 feet between supports. Toeliminate additional supports, meet deflection criteria, and pro-vide margins of safety for short-circuit forces, schedule 40, 8-inchaluminum pipe was selected.
Item C.3: A bay width of 150 feet was utilized to permitsatisfactory termination of multiple parallel 500-kV lines enter-ing the bus from the same direction. Pacific Gas and Electric 500-kV transmission lines are of the single-circuit flat-configurationtype with phase conductors at 43.5- and 50-foot separations. Inpractically all cases these lines enter the station at an angle andterminate on separate lineside dead-end structures.
In addition the 150-foot bay arrangement provides adequateclearances to accommodate 500-kV series capacitor banks locatedat the line terminations.
Item D.1: The use of 30 and 35 insulator units in suspensionand dead-end strings was selected on the basis of adequately with-standing switching surges up to 2.3 per unit under wet or con-taminated conditions. Stations in normal environments, consider-ing the long, dry California seasons in the Pacific Gas and Electricservice area, were equipped with 30 units with provision foradding more. Stations in severe environments, such as is found incoastal plant locations, were equipped with 35 units.
Item D.2: The use of a 6-unit post was selected on the basisof adequately withstanding switching surges of 2.3 per unit underwet or contaminated conditions. This number of units provideda means of obtaining the desirable leakage distance by utilizingthe standard type of units available at the time.Equipment:
Item F.4.a: The use of a 6-unjit post was selected on the basisof adequately withstanding switching surges of 2.3 per unit underwet or contaminated conditions. This number of units provided ameans of obtaining the desirable leakage distance by utilizingthe standard types of units available at the time.
Item F.4.b: Because of the long, dry California seasons in thePacific Gas and Electric service area, deposits of dirt, argiculturalsprays, salt water spray, and other contaminants are not washedoff by nature, except during the rainy season. By experience withour 230-kV and lower voltage systems, it has been necessary toprovide substantially more leakage distance for insulators thanwould normally be required. 432 inches were extrapolated fromour 230-kV system and were considered the minimum for supportinsulators.
Southern California Edison Comparty (by P. R. Dolan)
Electrical Station Design:Item D.1: Thirty 53/4- by 10-inclh insulator uniits per string
were selected for the substation suspension insulators in order tomeet the minimum 60-Hz requirements dictated by the degree ofcontamination in the area. Included in this number are threeunits added to provide the substation with a 10-percent marginabove the transmission lines.
Supporting Bibliography:[11] P. R. Dolan and A. J. Peat, "Desigi; of the first 500-kV
substations on the Southern California Edison Companysystem," IEEE Trans. Power Apparatus and Systems, vol.PAS-86, pp. 531-539, May 1967.
[12] P. R. Dolan and E. W. DuBois, "Design criteria for theSouthern California Edisorn Company 500-kV system,"Proc. 1964 American Power Conf., vol. 26, pp. 844-853.
Tennessee Valley Authority (by Pauil H. Shounl)Electrical Station Design:
Item B.6.d: The two-conductor strain bus supports the fixedcontacts of breaker isolating pantograph switches, and the 3-foot7-inch spacing was required to ensure proper operation of theseswitches under winds up to 90 mi/h or gusts up to 130 mi/h.
Item D.1: At generating stations, 32 units are used invertical insulator strings and 26 units in horizontal strings tocompensate for contamination resulting fromn the large coal-burning power stations.
Equipment:Item C.4: Our main and transfer bus switch scheme required
that long sections of bus be de-energized by means of disconnectswitches; therefore, these bus sectionalizing switches (verticalbreak or center rotational horizontal) are equipped with resistorsto limit switching surges. The vertical reach, breaker-isolatingswitches are not so equipped.
Ultimate Station Layout:Item A: The design level for rmaxirnum open-line voltage is
600 kV at the remote station. The 600 kV include the maximumsource voltage plus the Ferranti effect on the line upon energizing.
860
IEEE COMMITTEE REPORT: 500-KnV Af SUBSTATION DESIGN CRITERIA
Supporting Bibliography:[13] R. M. Milton, H. H. Leech anid R. C. St. Clair, "Tennessee
Valley Authority's 500-kY system-step-down substationdesign," IEEE Trans. Power Apparatus and Systems, vol.PAS-85, Ppl 36-46, Jai-nuary 1966.
[141 T. M. Swingle avid H. I. Dobson, "Tennessee Valley Author-ity's 500-kV systeImi-communications," IEEE Trans.Power Apparatus and Systems, vol. PAS-85, pp. 47-53,January 1966.
[15' A. C. Pfitzer and G.M. VWilhoite, "Tennessee Valley Author-ity's 500-kV systemn transmission line design," IEEETrans. Power Apparatus and Systems, vol. PAS-85, Pl'28-35, January 1966.
[16] F. Chambers, 0. S. C. Hamiimer, and L. Edwards, "Ten-nessee Valley Authority's 500-kV system-system plansand considerationts," IEEE Trans. Power Apparatus andSystems, vol. PAS-85, pp. 22-28, January 1966.
[17] C. McCord, L. R. Sellers, and E. R. Snyder, "TVA'sJohnsonville 500-kV switchyard," Proc. 1964 AmericanPower Conf., vol. 26, pp. 1061-1073.
[18] R. C. St. Clair, "Pantograph disconnects save on 500-kVsystem," Electrical World, pp. 48-49, May 29, 1967.
Virginia Electric and Power Com),pany (by 0. R. Compton)
Equipment:Item B.3: The entire initial 500-kV project was designed oni
the basis of the ultitnate needs. It was decided that 1700 MVAwas the maximum loading of long 500-kV lines without seriescapacitor compensation. Since we were designinig for our ultimateneeds, the 2000-ampere switches are adequate.
Item C.3: Disconinect switch current rating was selected tomatch the associated circuit breaker eurrent ratings.
Supporting Bibliography:[19] C. L. Wagnler, J. AIM. Clayton, F. S. Young, and C. L.
Rudasill, "Insulation levels for VEPCO 500-kV substationequipment," IEEE Trans. Power Apparatus and Systems,v-ol. 83, pp. 236-241, March 1964.
Discussion
Frank W. Smith (Tennessee Valley Authority, Chattanooga, Tenn.):The summary of data presented in this paper will be of lasting interestand value to utility engineers concerned with the design of 500-kVsystems. In preparing this paper. Working Group 64.1 has performeda real service to the industry.
The interest of this paper lies both in the similarity of the pr acticesof the several utilities represented and in the contrasts which appear.Explicit reasons are presented in the text of the paper for many ofthe practices whieh at first glance appear unusual. However, onemust also conclude that basic differences in philosophy are reflectedini some of these contrasts. The spread in basic insulation levels, thedifferences in protective margins, the utilization or nonutilization ofcontrol cable shielding or surge suppression resistors on switchesrepresent degrees of liberalism or conservatism in the engineeringapproach of the several companies. Each of these philosophies servesa useful purpose to the industry as a whole, and we may predict thatas time goes on, extremes will tend to become means as experienceproves wherein the optimum answers lie. This is as it should be.
This paper also provides a dramatic illustration of the vast progressin communication between utilities, both private and public, whichhas been taking place over the past several years. Better transporta-tion and communications facilities are partly responsible, and these,too, are products of engineers. But perhaps we can also assume thatrelations between engineers as human beings are on the upgrade;that we are recognizing more and more that in spite of differences inthe structures of our parent organizations, we are all striving for thesame objective: the betterment of the lives of those in our time and ofour posterity. If this spirit cannot only be continued but lcommu-nicated to other factions of our world community, we shall all bericher for it.
IEEE Working Group: Because of the nature of the working groupassignment covered in this paper, we had not expected formal dis-cussion. However, several verbal and informal discussions were re-ceived; and Mr. Smith has in his prepared discussion summed upvery eloquently most of the discussions received. His comments aremuch appreciated and, we think, quite appropriate. He mentionedthe matter of improved communications and human relations involv-ing engineers having different design philosophies and backgrounds.This is an interesting observation and, in working with this group,one could not help but be intrigued by this truth. Even when we werediscussing extreme variations in design criteria, you never once hearda member of this working group criticize another or his company forthe apparent discrepancies in design philosophy. These engineerswere much aware of the fact that there was more than one good solu-tion to an engineering problem-that there were good men on bothsides of a controversy.The objective of this paper was to record and report design criteria
and not to recommend or propose design. Since the presentation ofthis paper, however, feedback from industry has already indicatedthat some design standards and criteria are being revised. This ap-plies especially to the rating and application of lightning arresters.Some companies have been conservative and reluctant to place muchreliance in arresters as surge-limiting devices, but they are liberaliz-ing their viewpoints as modern arresters prove themselves in service.The matter of surge-suppressing resistors and secondary circuit
shielding remains a very controversial subject; but additional study,experience, and tests should soon provide a better analysis of theseinfluences and their significance. Basic insulation levels and electricalclearances are items that are at present under special study byappropriate technical committees. More uniformity and standardiza-tion are indicated and should result in considerable economies to theindustry; however, standardization has its limitations too, sinceenvironmental factors and system operating requirements will varyconsiderably and necessitate continued variations in design criteria.
Manuscript received Fehruary 18, 1969.
861
Mantiscript received April 2, 1969.